Well Completion Course
Well Completion Course
Well Completion Course
SECTION1: Introduction
4.1.Blast joint
4.2 Sliding Sleeves
4.3 Crossover connections
4.4 Double Pin Subs
4.5 Couplings
4.6 Flow Couplings
4.7 FlowTubes
4.8 Pup Joints
4.9 Seal Rings
4.10 Safety subsurface equipment
4.11 Mule Shoes
4.12 Landing Nipples
4.13 BULL PLUGS/BULL CAPS AND OTHERS
4.14 GAS LIFT EQUIPMENT
4.15 Telescopic Subs
4.16 Packers
6.1 GasLift
6.2 Rod Lift System
6.3 PCP
6.4 ESP
6.5 Plunger Lift
1-2 Well Completion
SECTION 1
INTRODUCTION
Section 1 -INTRODUCTION 1-3
SECTION 1 - INTRODUCTION
Wells were made by bailing and pilling until an initial blowout, driving to fast reservoir
gas depletion. The production was gathered by spill pits around the well. Once the
reservoir pressure, dropped, below the hydrostatic pressure it was needed a
production method by the means of artificial lifting techniques (This explain partially
why most old oil wells were equipped at an early stage with beam pumps).
As the demand on the oil market growth, the development of oil industry increased,
at this moment, it was realized that preserving from a fast gas cap pressure draw
down was an efficient, cheap way of keeping a well flowing efficiently. Casing and
tubing concept were introduced for this purpose allowing then to produce wells under
pressure.
1859 First open hole eruptive well driven to 24 meters (Bailing & Piling).
Fast drop of reservoir pressure
Install the first Xmas tree to allow swabbing
Possibility to divert the produced fluid into a storage tank
Install first sucker rod pumping system (Steam driven)
Found that concept of single casing is not suitable for long term.
Install first tubing string as a wear sleeve
Forced to develop wellhead and tubing hanger system
Need to develop junction threads.
Wooden derrick (Drak's yoke) handling capacity still limited the well T.D.
Around a maximum of 100 meters
1910 First open hole gravel pack in open hole unconsolidated reservoirs.
Use of slotted liner associated with liner hanger (Baker oil tools, Brown
oil tools)
1920 First electric line logging with G.R. and C.C.L. allowed to identify more
than one producing zone.
Electric line technique allowed running, correlating and firing explosive
charges to put again the reservoir in communication with production
casing.
To avoid cross flow between two o r more reservoirs, mechanical tubing
set packer were developed.
1924 First P.C.E; equipment was built by Bowen oil tool to allow Wire line
under pressure
Flow control equipment such as Sliding sleeves, plugs, was developed
by many service companies, so that a given zone can be isolated, or
produced commingling or independently.
Section 1 -INTRODUCTION 1-5
1925 GRC company develop the first mechanical down hole recorder
1935 First Water injector wells and dump flood injector wells
Development of permanent packer with PBR (seal bore)
1975 First semi permanent packer able to be retrieved with a retrieving tool
1995 First cemented mono bore well where the tubing is also the production
casing. (Mainly suitable when the reservoirs to produce are marginal)
1-6 Well Completion
1998 Development of the intelligent type completion. (Only suitable for wells
with a production that justifies it).
Figure N° 1-1
Downhole completion examples
Section 1 -INTRODUCTION 1-7
Notes
Section 2 –WELL PRODUCTIVITY FUNDAMENTALS 2-1
SECTION 2
WELL PRODUCTIVITY
FUNDAMENTALS
2-2 Well Completion
The drilling and completion process must be carefully designed to fit the needs of a
given reservoir, taking into count all the characteristics that will determine the life of
your well, all along the time you expect to produce, there are several types of
completion, but those are just guidelines, because each well requires personalizing
according to its own characteristics. Also when selecting down-hole equipment, it’s
very important to do it following a brainstorming process involving all the team.
Thinking ahead in time its very important because as the well produces all those
parameters will change and a good completion must be able to be adapted to new
flow conditions with as few as possible modifications, the completion design must
take into count the different services that a well will require in time, and must ensure
that those services can be done in the best way, and that will be possible to install,
service or retrieve with a suitable mean all down-hole equipment (ex: well deviations
with more than 70 degrees will create potential wire line operation difficulties, so a
well with this deviation must be designed for coiled tubing service),
Modern tools, monobore technology and geochemical fingerprint, now allow better
measurement and control of multiple zones in the same wellbore (Commingled flow)
Also, directional drilling technology allows to obtain a larger drainage than classical
vertical wells (at the same time it makes the well more expensive and risky to drill
and complete)
Section 2 –WELL PRODUCTIVITY FUNDAMENTALS 2-3
Gas in reservoir:
Solution Gas driven Reservoir:
Those are constant volume
reservoir. The production is the
result of the volumetric expansion of
solution gas. Pressure declines are
characteristics of this type of
reservoir, since drive is not achieved
by water encroachment or gas cap
expansion. In addition excessive
drawdown can actually decrease oil
production under some given
conditions.
Figure N° 2-2
Porosity
Figure N° 2-3
Darcy’s law
• Oil properties: several characteristics that can modify the behavior of flow
o Specific Gravity: is a comparison of fluid density to that of water.
o Viscosity: Is the resistance to flow of a fluid
o Bubble point: The temperature and pressure at which gas, held in
solution in crude oil, breaks out as free gas from the solution.
o Oil formation volume factor: this is the ratio of the liquid volume at stock
tank (standard conditions), this ratio is used to convert reservoir barrels
to stock barrels
Figure N° 2-4
Hydrocarbon composition
• Water properties
o Viscosity: in water the viscosity is primarily a function of temperature,
however salinity has a slight influence on it.
o Water formation volume factor: it’s a function of temperature, and
slightly influenced by pressure, the calculation is done by using a
correlation
o Water Compressibility: its an estimated value calculated through
Meehan correlation.
• Gas properties
o Gas formation
Volume Factor:
Z, under typical
conditions
hydrocarbon
gases will
deviate from
the ideal gas
law, thus
requiring a correction factor, this is determined from laboratory
measurement, but it’s a common use to determine it using the Camco
chart
o Gas Viscosity: in natural gas is a proportional function of pressure, as it
decreases, gas viscosity decreases, natural gas viscosity varies from a
range between 0.01 and 0.04 cp
2-6 Well Completion
• Partial penetration effect: this is when only a fractional percentage of the total
productive section is open to the wellbore, this can impact in the following
ways the well production:
• Conning effect: Excessive drawdown when producing a well can create water
or gas cone around the pay zone. This cone eventually will reach the
perforations and affect the oil production by giving priority to water or gas
production.
• Reduced producing rate effect: this refers to the relation between the potential
length of the payzone and the actually perforated interval.
• Reduced bottom hole pressure effect: the bottomhole pressure on a partially
penetrated well is less than would be available under totally penetrating
conditions.
• Skin damage effect: this is defined as a thin layer of impaired permeability
occurring immediately around the well bore and extending vertically over the
entire productive interval penetrated by the well.
• The selection of tubing size is given by the required flowing bottomhole
pressure at various flow rates, depending on the depth of the well. Also there
are certain reservoir variables which must be at least closely approximated in
order to accurately perform tubing sizing calculation:
o Gas Liquid ratio (GLR): the higher the GLR is, the lower the density of
the produced fluid is, thus lower will be the required flowing bottom-hole
pressure.
o Liquid Density: the fluid density has the same effect as GLR, only this
refers to the density on the liquid phase of the fluid.
o Liquid Viscosity: the higher the viscosity the higher that the required
bottomhole flowing pressure will be.
o Liquid surface tension increased the bottomhole required flowing
pressure will be higher.
o Kinetic energy effect will become important in small diameter tubing
with high GLR and low pressure levels
• Surface equipment, the influence of surface equipment in the production
capacity of a well, is given by the pressure losses created by the surface
equipment in order to deliver the production to the separation and storage
facilities, production choke size, Flowline size, production header pressure,
separator pressure, interaction of the network in the header.
Section 2 –WELL PRODUCTIVITY FUNDAMENTALS 2-7
Figure N° 2-5
Temperature Gradient
Figure N° 2-6
Fluid changes from Downhole to surface
2-8 Well Completion
Tertiary stage: Its purpose is to recreate the natural force in the reservoir by
modifying its natural conditions, doing so eruptive production can be achieved again.
For this several techniques have been developed some of them are:
• Injecting water in the reservoir to repressurize it. For this water injection wells
are drilled and compressed water is forced inside the reservoir.
• Injecting gas, air, nitrogen, steam in the reservoir (is different from gas lift) for
this several injection wells are drilled and the fluids ares forced inside the
formation.
• Creating a water drive from several water injection wells around the producing
well, by this is intended to displace the oil in the reservoir to the payzone in the
producing well.
Its important to note that this is only a classification, that varies from company to
company following certain guidelines, and according to internal policies of the
operating companies those stages are applied some times combining two or more of
the thecniques the enhance the production, and the common denominator here is
that no management will wait to reach full depletion before starting an alternate
recovering plan.
Section 2 –WELL PRODUCTIVITY FUNDAMENTALS 2-9
This kind of damage can be the result of inappropriate procedures during the process
of drilling, completion and even during normal operation, to avoid this at each stage
the team must develop procedures that are adequate to the type of formation /
completion in question
During drilling, some preventive procedures can be applied to minimize the risk of
formation damage, like using wide particle size in mud, high bit weight and low rpm,
minimizing barite, mud conditioning, use of low invasion fluids, minimizing drilling
time, low overbalance, matching salinity of formation, among others.
2-10 Well Completion
Reperforation technique is
found to be useful as a
remedy to blocked
perforations because the
detonation of the gun has
a loosening effect on the
blocking materials in the
Figure N° 2-9
formation adjacent to the
Sequence of firing a perforation gun
well and in the previous
perforations.
Figure N° 2-10
2-12 Well Completion
Sand production can produce erosion on both surface and downhole equipment,
flowline deposits can create undesired chokes, and deposits in tanks or separators
can render them to un-operational
The objective of all sand exclusion techniques is to avoid the migration of the
formation sand into the production stream trough the well to the surface.
By restraining production rate of the well, drag forces on the sand grains are
reduced. This is not a efficient approach and its usually used when there’s no sand
control technique on the completion design, but while simple this approach is
uneconomical. Using this technique at the moment of starting the well, by opening
slowly the production choke, and letting the flow stabilize for long periods, contributes
to decrease the initial drawdown of the wellbore and thus Natural sand consolidation
is achieved. This is very important to remember because doing so increases the
chances of long term clean producing wells.
A widely used method is to control the sand through gravel, this can be done by
chemical treatments to consolidate the gravel around the perforations or a physical
screen installed down hole, or in some types of gravel pack the screen is installed
along with resin coated gravel, there are several types but basically can be divided
as follows:
Each method has its own advantages and applications, as they have inconvenients
too, resine coated for example, tends to become unefficient under high water
conditions, because it gets washed from the gravel, losing its controlling properties.
2-14 Well Completion
Figure N° 2-11
Different methods of sand control
Section 2 –WELL PRODUCTIVITY FUNDAMENTALS 2-15
Also the design must be made a way that all the fluid going through the perforations
is in laminar flow.
Some reservoir characteristics play and important role at the moment of selecting the
sand control method:
• Interval length
• Sand Quality
• Reservoir Temperature
• Reservoir pressure
• Reservoir fluid
2-16 Well Completion
2.3.2.1.1. SCREENS:
Other important part of the gravel packing method
is the screen. Its function is to retain the gravel in
an annular region within the wellbore. There are
three types of screen available.
The sand control technique must be designed according to the geometric factors and
completion requirements of a particular well.
Figure N° 2-14
Gravel packing process
2-18 Well Completion
Resin coated Gravel: this consists in consolidating the gravel placed inside and
immediately surrounding the perforation. The gravel is coated with a resin at the
surface and then pumped into the well as slurry. This slurry is then squeezed through
the perforations to fill a region behind the casing. After hardening, the consolidated
gravel prevents formation sand from entering the wellbore. All excess are removed
from inside the casing either drilling or washing. This method is 25% to 50% cheaper
than conventional consolidation treatments or gravel pack, but in despite it has a
relative short lifetime.
Section 2 –WELL PRODUCTIVITY FUNDAMENTALS 2-19
Any fluid flowing in a pipe loses part of its energy, which is absorbed by dissipation in
friction process. This friction can be the result either internal (the fluid viscosity) or
external (the pipe roughness) and even both, also changes in diameter create
pressure losses, and when the change is a restriction to avoid the creation of
turbulences a specially polished piece shall be used immediately after the restriction,
those pieces are called “Flow Coupling” and come in sizes from 2 feet up to 6 feet,
FC has a extremely low roughness 1/1000mm. Pressure losses are expressed by the
difference in the pressure of the fluid between two points of the pipe. And are
modified according to the type of flow laminar or turbulent.
The type of flow is determined by the Reynolds number Re, which is them compared
to a critical value ReC
(Velocity of fluid (m/s) * inner diameter of pipe (inches) * density of fluid (kg/m3))
Dynamic viscosity (pa.s)
Laminar flow is the ideal condition for production, and to determine if this condition is
met, the velocity of flow must be less of equal to critical velocity, which is the flow
velocity at the critical Reynolds number.
So, pressure losses, are determined by several factors, but they can be calculated,
from: critical velocity, critical flow rate, length of the pipe, inner diameter, circulation
velocity, flow rate, dynamic viscosity and the density of fluid.
2-20 Well Completion
Notes
Section 3 –CASING & TUBING 3-1
SECTION 3
Casing and Tubing are key elements on a completion, carefully selection of pipe
properties, according to the characteristic of the well must be done, the basic need of
a casing is to keep the drilled hole in shape, so erosion due to flow doesn’t collapse
the well, in the early days there was only the conductor, that acted as casing,
production casing, tubing, all I one, later when the importance of reservoir gas was
realized, the need to put a production tubing aroused, to act as a velocity string, as a
solution to gas slugging, and also to protect the production casing from erosion due
to flow, the actual process of drilling a well and completion, includes a wide range of
carefully engineering and products to optimize the live of wells in time and efficiency.
Please refer to Well Production Practical handbook for tables (on this section only)
• Steel Grade
• Length range
• Wall thickness
• Manner of manufacture
• Type of joints
Section 3 –CASING & TUBING 3-3
Basically what is taken in account for preventing those problems are the tensile
requirements and Steel grade:
The grade refers to the yield minimal strength of the steel, is expressed in thousands
of PSI, this means, the amount of tensile stress required to produce extension under
load, so, the higher the grade the higher the force coming from the weight of the
tubing string that the tubing can withstand.
And the Tensile strength: which is the maximun amount of tensile stress required to
produce breakdown of a pipe under load.
The type of steel used plays a big role in a completion, it could be: Carbon steel,
stainless steel, titanium, iconel. Each type of steel has a specific application and
special tolerance to certain effects coming from the well or reservoir characteristics.
3-4 Well Completion
3.1.1.2. Hardness
The hardness of a pipe its measured either using the; Rockwell hardness testing
which is an indentation testing method. An indenter is impressed into the test sample
at a prescribed load to measure the material's resistance to deformation. A Rockwell
hardness number is calculated from the depth of permanent deformation of the
sample after application and removal of the test load. Various indenter shapes and
sizes combined with a range of test loads form a matrix of Rockwell hardness scales
that are applicable to a wide variety of materials. Also there is the Brinell Hardness
Test this common standard method of measuring the hardness of materials is done
by subjecting to indentation by a hardened steel ball under pressure the smooth
surface of the metal. The diameter of the indentation, in the material surface, is then
measured by a microscope and the hardness value is read from a chart or
determined by a prescribed formula.
It’s important to try to keep subassemblies within the range of pipe used normally, to
fit the derrick size and the length of the stand of pipe been used.
3.1.5. CONNECTIONS
As new completion techniques demanded stronger steel to reach deeper wells
several types of thread connections were developed to meet the higher
requirements. Now the most common types of tread used for completions are:
UE: API non upset connection is a 10 round thread form cut on the body of the pipe,
it’s not recommended because the joint has less strength than the body.
EUE: API External upset connection, it’s an 8 round thread and the thread area is
wider in the outside to make the joint as stronger as the pipe body is. Also is found
for high pressure service a special long thread form which is 50% longer than the
standard effective thread
3-6 Well Completion
Buttress
Figure N°3-3
Figure N°3-4
Hydrill thread
Section 3 –CASING & TUBING 3-9
Notes
Section 4 –COMPLETION EQUIPMENT 4-1
SECTION 4
COMPLETION EQUIPMENT
4-2 Well Completion
Figure N° 4-1
4.2. SLIDING SLEEVES:
They are completion devices that can
be operated to provide a flow path
between the production conductor and
the annulus. Sliding sleeves incorporate
a system of ports that can be opened or
closed by a sliding component that is
generally controlled and operated by
slickline tool string.
Figure N° 4-2
Sliding sleeve
Section 4 –COMPLETION EQUIPMENT 4-3
Figure N° 4-4
4.7. FLOWTUBES:
Figure N° 4-9Bis
Figure N°4-11
4.12. LANDING NIPPLES:
Those are adaptors to place gas lift valves, the spacing between each SPM, is very
important and it is defined by calculations done determined by the static and dynamic
gradient of the well, and the characteristics of fluids. Gas lift valves are set in place
using wireline, with a Sidekick Tool.
Figure N°4-14.1.1
Kick off tool
Figure N°4-14.1.2
Side Pocket Mandrel
Section 4 –COMPLETION EQUIPMENT 4-9
Figure N° 4-15
4-10 Well Completion
4.16. PACKERS:
There are several types of packer developed to fit different needs, but essentially
them all serve the same basic purpose, create isolation between the tubing and the
production casing so production fluids arrive to surface through the tubing to avoid
gas slugging and don’t loose pressure and velocity because of casing wider
diameters. The rubber in a packer is the real sealing element, and it should be
selected according to the fluid, well and completion characteristics. Rubber comes in
different Although the rubber is what makes the seal, packers are classified
according to the installation method and own characteristics, and today they are so
technified that you could thing that the rubber seal is not important at all. Initially
packers had one single rubber element, now it
is usually three of them stacked, the one in the
center usually the softer one is the actual seal,
the ones on the extremes are made of a harder
rubber and act as backups of the center one
and also help keeping this in place and
untouched by fluids (this makes it last longer)
setting packers is a job that must be carefully
carried out, and after the setting, a test must be
made to ensure there is no leaks, basically a
packer is held in place by a metal cone which
compresses the rubber seal and a set of slips
acting against the cone and the casing, this
principle applies for almost all kind of packers
and comes from the compression packer
design, almost all the other types of packer vary
in the way of setting and the internal equipment
used to hold them in place and made possible
retrieving. The selection of the type of packer to
be installed, is done according to the well
characteristics, the depth, the deviation, the
fluids, ETC. the following are the most
commonly used packers in completions:
Figure N°4-16.2
Hydrolic Packer
4-12 Well Completion
Figure N°4-16.3
Permanent Packer
Section 4 –COMPLETION EQUIPMENT 4-13
They have rings between the rubber elements, and are set applying torque on the
string, the rotation screws the center piece, which compresses the rubber and makes
it fill the gaps in the rings, this type of packer is suitable for DST, but while you avoid
putting weight on the string to set, you put a lot of torque in the string which is not
good for deviated wells because is very difficult to drive the torque through the
deviations without creating damage to the string.
Figure N°4-16.4
Mechanical Packer
4-14 Well Completion
Figure N°4-16.5
Retrivable packer setup / retrieve
Section 4 –COMPLETION EQUIPMENT 4-15
Notes
Section 5 –SURFACE EQUIPMENT 5-1
SECTION 5
SURFACE EQUIPMENT
5-2 Well Completion
Figure N° 5-1
Wellhead
After the choke comes the flowline, which is the pipe that delivers the production of
the well to the separation facilities. Also has a flow line valve normally. All the
equipment after the choke, usually has a lower pressure specifications than the
Xmas tree equipment.
All along the Xmas tree, are measuring points and sampling points, for taking
pressure, temperature and samples of the production.
Section 5 –SURFACE EQUIPMENT 5-5
Notes
Section 6 –ARTIFICIAL LIFT SYSTEMS 6-1
SECTION 6
EQUIPMENT
6-2 Well Completion
There is not artificial method better than the other, all the ones menctioned here,
have been used in the industry since what we could call the early days, and have
suffered modifications and optimizations, sometime to make them more efficient,
some times to reduce costs associated to them. We can say each well has its own
personality and what suit the needs in one case is not necessary the solution for a
well just aside. Normally given the oil characteristics and the reservoir, a method is
selected and applied for several wells in the same field/reservoir, but in this case
each well need that the detailed conditions are selected and adapted to fits its
behaivor and achieves the best benefits.
In this manual the more common methods are summarized and briefly explained, but
to get into the real thing a single book or a whole encyclopaedia will be required, here
is explained the principle of how those methods work, and Gas Lift receives certain
preffrence, because perhaps is the oldest and more common thecnique, and also the
less understood of them all.
Section 6 –ARTIFICIAL LIFT SYSTEMS 6-3
The principle: In a typical gas lift system, compressed gas is injected through gas lift
mandrels and valves into the production string. The injected gas lowers the
hydrostatic pressure in the production string to reestablish the required pressure
differential between the reservoir and wellbore, thus causing the formation fluids to
flow to the surface.
Figure N° 6-1
Tipical Gas lift System
The final consideration is that the injection should be made through the lowest point.
There are two GL techniques, Continuous and intermittent, continuous is used at the
early stages of reservoir natural force depletion, while intermittent is normally the
option when continuous is no longer producing benefits.
6-4 Well Completion
Continuous GL: The technique is based in the principle of lightening the fluid
column along the tubing to drive the fluids to surface, through gas injection inside it.
This is achieved by a fixed orifice, installed in a side pocket mandrel at the deepest
possible level (the closer to the packer the better).
Intermittent GL: in this case, there is a lapse of time, between the action of the
lowest valve (which is a live valve) this lapse, allows fluids to enter from the formation
and create a liquid “plug” in the tubing which is the amount of liquid to be lifted.
Tc = CYCLE TIME = t i + t t + t e
Figure N° 6-2
Intermitent Gas Lift (Standar & Idealized)
Section 6 –ARTIFICIAL LIFT SYSTEMS 6-5
Figure N° 6-4
Typical beampump
Section 6 –ARTIFICIAL LIFT SYSTEMS 6-7
Figure N° 6-7
PCP Completion
6-10 Well Completion
6.3.6. PC PUMPS
There are two basic elements that make up the downhole
Progressing Cavity (PC) Pump – a single helical alloy-steel
rotor connected to a rod string and a double helical Figure N° 6-9
elastomer-lined stator attached to the tubing string. Using the PCP Pump
latest manufacturing technology, rotors are kept to tight
Section 6 –ARTIFICIAL LIFT SYSTEMS 6-11
Figure N° 6-10
Elastometer
Figure N° 6-11
PCP Pump
6-12 Well Completion
Notes