Morse Test On Multi Cylinder Petrol Engine
Morse Test On Multi Cylinder Petrol Engine
Morse Test On Multi Cylinder Petrol Engine
(AMBASSADOR ENGINE)
AIM:
To perform the Morse test on the given multi cylinder petrol engine and to
determine the efficiency at the given load
APPARATUS REQUIRED:
1. Multi Cylinder Petrol Engine Test Rig
2. Tachometer
3. Stop watch
SPECIFICATIONS:
Engine : Multi cylinder, ambassador engine
Fuel : Petrol
New No. 3, Old no. 2, S.V . Koil Street, Sekar Nagar, Ashok Nagar, Chennai – 600 083
Phone: +91 (044) 4351 8677 | Cell: (+91) 9789976777
Email: sales@elshaddaiengg.com, support@elshaddaiengg.com www.elshaddaiengg.com
of air tank fitted with an orifice. The air tank is connected with the engine inlet manifold
through a flexible pipe.
BRAKE POWER :
BP = (2πNT) / 60
Where,
T = Brake Torque (W * L)
W – Load in Newton
N - Rpm.
FORMULAE:
Brake power when all cylinders are working, BP 1234 = ( 2πNT1234 )/ (60*1000) KW.
Brake power when first cylinder is cutoff, BP234 = ( 2πNT234) / (60*1000) KW.
Brake power when second cylinder is cutoff, BP134 = ( 2πNT134) / ( 60*1000) KW.
Brake power when third cylinder is cutoff, BP124 = ( 2πNT124) / (60*1000) KW.
Brake power when fourth cylinder is cutoff, BP123 = ( 2πNT123) / (60*1000) KW.
IP1234 = IP1+IP2+IP3+IP4
Mechanical efficiency (ηм) = {( BP1234) / (IP1234)} * 100 %
New No. 3, Old no. 2, S.V . Koil Street, Sekar Nagar, Ashok Nagar, Chennai – 600 083
Phone: +91 (044) 4351 8677 | Cell: (+91) 9789976777
Email: sales@elshaddaiengg.com, support@elshaddaiengg.com www.elshaddaiengg.com
PROCEDURE:
Before starting the engine keep the fuel cut off level in ON position.
Start the engine using starter motor.
Allow the engine to run at no load for about 10 minutes to warm up and attain
steady state condition.
Load the engine to the required level.
When the engine is loaded to the required load adjust the throttle to maintain the
speed of the engine at its rated rpm.
Allow few minutes for the engine attains steady state condition and note down the
load when all the cylinders are developing power.
Cut off cylinder no.1 by lifting the cutoff switch no.1
Bring the engine again to rated speed by adjusting the load on brake drum and not
by adjusting the throttle and note down the corresponding load on the engine.
Similarly cut off the cylinder.2,3,4 and repeat the above procedure to find the load
on the engine for cylinder.
Remove the load from the engine and stop the engine by switching off the ignition
switch.
PRECAUTIONS:
The lubricating oil level should be ensured before starting the engine.
The engine cooling water supply should be ensured before starting the engine.
New No. 3, Old no. 2, S.V . Koil Street, Sekar Nagar, Ashok Nagar, Chennai – 600 083
Phone: +91 (044) 4351 8677 | Cell: (+91) 9789976777
Email: sales@elshaddaiengg.com, support@elshaddaiengg.com www.elshaddaiengg.com
OBSERVATION:
RESULT:
The Morse test on the given 4-stroke engine has been conducted and results are
obtained.
New No. 3, Old no. 2, S.V . Koil Street, Sekar Nagar, Ashok Nagar, Chennai – 600 083
Phone: +91 (044) 4351 8677 | Cell: (+91) 9789976777
Email: sales@elshaddaiengg.com, support@elshaddaiengg.com www.elshaddaiengg.com