GUIDELINES 4 Sediment Basin FINAL PDF
GUIDELINES 4 Sediment Basin FINAL PDF
WSUD Technical Design Guidelines for South East Queensland June 2006
Sediment Basins
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-1
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
Chapter 4
4.1 Introduction ............................................................................................................................................4-3
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-2
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
4.1 Introduction
Reducing sediment loads is an important component of improving stormwater quality. Sedimentation basins
can form an integral component of a stormwater treatment train and are specifically employed to remove
coarse to medium sized sediments by settling them from the water column. Sedimentation basins can take
various forms and can be used as permanent systems integrated into an urban design, or temporary
measures to control sediment discharge during construction. This chapter describes the design and
construction of permanent sedimentation basins (‘wet’ basins) that form part of a treatment train (e.g. an inlet
zone/ pond to a constructed wetland) for operation in the post construction/building phase. For the design
and application of temporary sedimentation (‘dry’) basins to control sediment discharge during the
construction/ building phase, refer to Sediment Basin Design, Construction and Maintenance Guidelines
(BCC 2001).
Sedimentation basins are stormwater detention systems that promote settling of sediments through the
reduction of flow velocities and temporary detention. Key elements include purpose designed inlet and outlet
structures, settling pond, and high flow, overflow structures. The storage volume consists of two
components: the permanent pool settling zone and the sediment storage zone. Access for maintenance
must also be provided. These elements are shown below in Figure 4-1 and Figure 4-2. Key design
parameters are selecting a target sediment size, design discharge, basin area and shape, sediment storage
volume and outlet structures.
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-3
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
Permanent Pool
Sized to remove target sediment
size
The second function is the control or regulation of flows entering the downstream treatment system during
‘design operation’ and ‘above design’ conditions. The outlet structures from the sedimentation basin are
designed such that flows up to the ‘design operation flow’ (typically the 1 year ARI) enter the downstream
treatment system, whereas ‘above design flows’ are bypassed around the downstream treatment system. In
providing this function, the sedimentation basin protects the vegetation in the downstream treatment system
against scour during high flows. The configuration of outlet structures within sedimentation basins depends
on the design flows entering the basin and the type of treatment systems located downstream as described
in Section 4.2.4.
Where the sedimentation basin forms part of a treatment train and when available space is constrained, it is
important to ensure that the size of the sedimentation basin (i.e. inlet zone of a constructed wetland) is not
reduced. This ensures the larger sediments are effectively trapped and prevented from smothering the
downstream treatment system. If the site constrains the total area available for the treatment train, the
downstream treatment system should be reduced accordingly.
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-4
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
Analysis of the characteristics of particulate nutrients and metals indicates that coarse to medium sized
sediments (i.e. > 125 μm) have low concentrations of attached pollutants (e.g. nutrients, heavy metals) when
compared to finer sediment and colloidal particles. Basins sized to target coarse to medium sized sediment
are therefore expected to capture sediment that has low levels of contamination and is unlikely to require
special handling and disposal. Removal of particles < 125 μm is best undertaken by treatment measures
other than sedimentation basins (e.g. constructed wetlands and bioretention systems). Therefore, while a
basin must have adequate size for capturing the target sediment size, they should not be grossly oversized.
Conversely, a sedimentation basin that is too small could have limited effectiveness, resulting in sediment
smothering of downstream treatment measures.
In most cases, the outlet design of a sedimentation basin will consist of a ‘control’ outlet structure and a
‘spillway’ outlet structure:
The ‘control’ outlet can be either an overflow pit/ pipe or weir which delivers flows up to the ‘design
operation flow’ (Section 4.3.1) to the downstream treatment system(s).
The ‘spillway’ outlet structure ensures that flows above the ‘design operation flow’ (Section 4.3.1) are
discharged to a bypass channel or conveyance system. The ‘spillway’ bypass weir level is set above the
‘control’ outlet structure and typically at the top of the extended detention depth of the downstream
treatment system.
Where the sedimentation basin discharges to a conveyance system (e.g. swale or piped system), a ‘control’
outlet may not be required and one outlet can be designed to allow discharge of all flows including flood
flows.
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-5
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
Planting of the shallow marsh zone (to a depth of 0.5 m) and littoral zone around the perimeter of a
sedimentation basin is recommended to bind the bank and reduce erosion at the waters edge. Plant species
should be selected based on the water level regime, soil types of the region, and the life histories,
physiological and structural characteristics, natural distribution, and community groups of the plants.
Appendix A (Plant Selection for WSUD Systems) provides a list of suggested plant species suitable for
sedimentation basins. The planting densities recommended in the list should ensure that 70 – 80 % cover is
achieved after two growing seasons (2 years).
Only the waters edge and batters of sedimentation basins should be planted and care needs to be taken in
species selection to ensure vegetative growth will not spread to cover the deeper water zones. Similarly,
floating or submerged macrophytes should be avoided. A sedimentation basin should primarily consist of
open water to allow for settling of only the target sediments (e.g. > 125 μm) and to permit periodic sediment
removal.
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-6
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
4.2.7 Maintenance
Sedimentation basins are designed with a sediment storage capacity to ensure sediment removal is only
required approximately every 5 years (triggered when sediment accumulates to half the basin depth,
determined from regular monitoring of sediment depth with a measuring post during maintenance visits).
Accessibility for maintenance is an important design consideration. If an excavator is able to reach all parts
of the basin from the top of the batter then an access ramp may not be required; however, an access track
around the perimeter of the basin will be required and will affect the overall landscape design. If sediment
collection requires earthmoving equipment to enter the basin, a stable ramp will be required into the base of
the sedimentation basin (maximum slope 1:10).
It is recommended that a sedimentation basin is constructed with a hard (i.e. rock) bottom (with a bearing
capacity to support maintenance machinery when access is required within the basin). This serves an
important role by allowing excavator operators to detect when they have reached the base of the basin
during desilting operations.
Provision to drain the sedimentation basin of water for maintenance must be considered, or alternatively a
pump can be used to draw down the basin. Approvals must be obtained to discharge flows downstream or
to sewer. Alternatively, a temporary structure (e.g. sand bags) can hold water upstream until maintenance is
complete.
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-7
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-8
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
Two design discharges are required to size sedimentation basins and their structures:
‘Design Operation Flow’ (1 year ARI) for sizing the basin area and to size a ‘control’ outlet structure when
discharging directly into a treatment system (e.g. wetland or bioretention system)
‘Above Design Flow’ for design of the ‘spillway’ outlet structure to allow for bypass of high flows around a
downstream treatment system. Defined by either:
Minor design flow (2 year ARI) – required for situations where only the minor drainage system is
directed to the sedimentation basin. For commercial and industrial areas the design flow
requirement for minor flows is a 5 year ARI event.
Major flood flow (50 year ARI) – required for situations where the major drainage system
discharges into the sedimentation basin.
Where the sedimentation basin discharges to a conveyance system (e.g. open channel flow or piped
drainage system), the ‘Design Operation Flow’ is only required to size the sedimentation basin, not for outlets
from the system.
Sedimentation basins should not be designed to have high flows diverted around them. All flows should be
directed through a sedimentation basin such that some level of sedimentation is achieved even during high
flow conditions.
A range of hydrologic methods can be applied to estimate design flows. With typical catchment areas being
relatively small, the Rational Method design procedure is considered to be the most suitable method. For
sediment basins with large catchments (> 50 ha), a runoff routing model should be used to estimate design
flows.
The performance of typical designs of sedimentation basins can be expected to fall within the shaded curves
shown and they can be used to estimate the size of the proposed sedimentation basin as part of conceptual
design and to verify the size derived as part of Step 3. The volume of a permanent pool in a sedimentation
basin should have sufficient capacity to ensure that desilting of the basin is not more frequent than once
every 5 years. However, sizing of sediment basins should be balanced with practicality and as such,
extravagantly large basins should not be designed based primarily on long term storage of sediment. Design
guidance for this sediment storage is provided in Section 4.3.3 (Step 3).
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-9
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
Figure 4-4: Sedimentation Basin Area vs Design Discharges for Varying Capture Efficiencies of 125 μm Sediment
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-10
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
The required area (A) of a sedimentation basin should be defined through the use of the following expression
(modified version of Fair and Geyer (1954)):
n
1 v (de dp )
R 1 1 s Equation 4.1
*
n Q/A (de d )
d* = depth below the permanent pool level that is sufficient to retain the
The concept design stage will generally guide the selection of the fraction of target sediment removed (R)
and permanent pool depth (dp) depending on water quality objectives and the nature of local soils/
sediments. Table 4.1 lists the typical settling velocities (vs) of sediments under ‘ideal conditions’ (velocity in
standing water).
Equation 4.1 is applied with n being a turbulence parameter that is related to hydraulic efficiency ( ). Figure
4-5 provides guidance on estimating a hydraulic efficiency ( ) value that is then used to calculate an
appropriate n value (according to the configuration of the basin). The shape of a basin has a large impact on
the effectiveness of the basin to retain sediments. Generally, a length to width ratio of at least 3 to 1 should
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-11
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
be achieved. In addition, the location of the inlet and outlet, flow ‘spreaders’ and internal baffles impact the
hydraulic efficiency of the basin for stormwater treatment as the range of values in Figure 4-5 demonstrates.
Figure 4-5 provides some guidance on what is considered to be good basin design, with the higher values
(of ) representing basins with good sediment retention properties. Sedimentation basins should be
designed to have a value of not less than 0.5. If the basin configuration yields a lower value, modification to
the basin configuration should be explored to increase the value (e.g. inclusion of baffles, islands or flow
spreaders).
Consideration of maintenance access to a basin is also required when developing the shape, as this can
impact the allowable width (if access is from the banks) or the shape if access ramps into a basin are
required. An area for sediment dewatering should also be provided, that drains back to the basin. This may
impact on the footprint area required for a sedimentation basin system.
Hydraulic efficiency ranges from 0 to 1, with 1 representing the best hydrodynamic conditions for stormwater
treatment. The o in diagrams O and P represent islands in the waterbody and the double line in diagram Q
represents a weir structure to distribute flows evenly (Persson et al. 1999).
Good practice in the design of sedimentation basins is to include a permanent pool to reduce flow velocities
and provide storage of settled sediment. The presence of a permanent pool reduces flow velocities in the
sedimentation basin and thus increases detention times. With the outlet structure being located some
distance above the bed of a sedimentation basin, it is also not necessary for sediment particles to settle all
the way to the bed of the basin to be effectively retained. It is envisaged that sediments need only settle to an
effective depth (d*) which is less than the depth to the bed of the sedimentation basin. This depth is
considered to be approximately 1.0 m below the permanent pool level.
A further consideration in the design of a sedimentation basin is the provision of adequate storage for settled
sediment to prevent the need for frequent desilting. A desirable frequency of basin desilting is once every five
years (triggered when sediment accumulates to half the basin depth). To ensure this storage zone is
appropriate the following must be met:
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-12
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
Sedimentation Basin Storage Volume (Vs) > Volume of accumulated sediment over 5 yrs (Vs:5yr)
The sedimentation basin storage volume (Vs) is defined as the storage available in the bottom half of the
sedimentation basin permanent pool depth. Vs can be calculated using a product of the sedimentation basin
area (Ab) and half the permanent pool depth (0.5 x dp) and appropriate consideration of the internal batters
(see Internal Batters below).
The volume of accumulated sediments over 5 years (Vs:5yr) is established by gaining an understanding of the
sediment loads entering the sedimentation basin and applying the fraction of target sediment removed (R):
Vs A c R Lo Fc Equation 4.3
A catchment loading rate (Lo) of 1 m3/ha/year for developed catchments is recommended to be used to
estimate the sediment loads entering the basin, based on Figure 8.24, from Australian Runoff Quality
(Engineers Australia, 2006))
In both edge treatments, it is recommended to line the bottom of the basin with rock to prevent vegetation
(particularly weed) growth and to guide extraction depths during sediment removal (see Section 4.2.7).
The safety requirements for individual basins will vary from site to site, and it is recommended that
developers engage an independent safety audit of each design. The Sediment Basin Design, Construction
and Maintenance Guidelines (BCC 2001) requires the following:
For water depths > 150 mm and maximum slope of 5:1 (H:V) or less, no fencing is required.
For water depths > 150 mm and maximum slope > 5:1 (H:V) fencing is required.
Further guidance on landscape and public safety considerations for designing sediment basins is contained
in Section 4.4.
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-13
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
Figure 4-6: Illustration of a Soft Edge Treatment for Open Waterbodies (GBLA 2004)
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-14
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
Additionally, the designs should be verified with the Building Code of Australia for compliance. An alternative
to the adoption of a fence is to provide a 2.4 m ‘safety bench’ that is less than 0.2 m deep below the
permanent pool level around the waterbody.
Design of inlet structures for adequate scour protection is common hydraulic engineering practice and the
reader is referred to standard hydraulic design handbooks for further guidance on design of scour prevention
methods and appropriate sizing of energy dissipation structures (e.g. Henderson 1966; Chow 1959).
If conceptual design of the stormwater system identified the need to remove anthropogenic litter (i.e.
industrial or commercial situations) then some form of gross pollutant trap (GPT) may be required as part of
an inlet structure. The provision of a GPT will depend on catchment activities as well as any upstream
measures in place. There are a number of proprietary products available for removing gross pollutants and
these are discussed in Chapter 7 of Australian Runoff Quality (Engineers Australia 2006). The storage
capacity of gross pollutant traps should be sized to ensure that maintenance (cleanout) frequency is not
greater than once every 3 months.
The ‘control’ outlet can be an overflow pit/ pipe or weir which delivers flows up to the ‘design operation
flow’ (Section 4.3.1) to the downstream treatment systems.
The ‘spillway’ outlet structure ensures that flows above the ‘design operation flow’ (Section 4.3.1) are
discharged to a bypass channel or conveyance system.
Where the sedimentation basin discharges to a conveyance system (e.g. bioretention basin or piped
system), a ‘control’ outlet may not be required and hence one outlet (‘spillway’ outlet) can be designed to
allow discharge of all flows including flood flows.
Where the sedimentation basin is formed by constructing an embankment across a drainage gully (such as
shown on Figure 4-1) it may also be possible to use an overflow pit and pipe outlet and still be able to
discharge to a bioretention surface or wetland macrophyte zone.
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-15
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
4.3.5.1 Design of ‘Control’ Outlet - Overflow Pit and Pipe Outlet Configuration
For sedimentation basins that discharge directly to a treatment system (i.e. constructed wetland or
bioretention basin) and the ‘control’ outlet structure discharging to the treatment system is an overflow pit
and pipe, the following criteria apply:
Ensure that the crest of the overflow pit is set at the permanent pool level of the sedimentation basin
(which is typically a minimum of 0.3 m above the permanent water level of the downstream treatment
system).
The overflow pit is sized to convey the design operational flow (e.g. 1 year ARI). The dimension of an
outlet pit is determined by considering two flow conditions: weir and orifice flow (Equations 4.4 and 4.5
below). Generally, the discharge pipe from the sedimentation basin (and downstream water levels) will
control the maximum flow rate from the basin; it is therefore less critical if the outlet pit is oversized to
allow for blockage.
Plate 4-3: Debris screens in Coorparoo, Mill Park (Victoria) and Herston
Qdes
P Equation 4.4
B Cw h3 / 2
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-16
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
2 Orifice flow conditions – when the inlet pit is completely submerged (corresponding to conditions
associated with larger flood events):
Qdes
Ao Equation 4.5
B Cd 2 g h
It is important that an outlet pit is prevented from blockage by debris. Design consideration needs to include
a means of minimising potential blockage of the outlet structure.
The pipe that connects the sedimentation basin to the downstream treatment system (e.g. macrophyte zone
of a constructed wetland or bioretention system) must have sufficient capacity to convey a 1 year ARI flow,
assuming the downstream treatment system is at the permanent pool level of the sedimentation basin and
without resulting in any flow in the bypass system. This ensures the majority of flows have the opportunity to
enter the downstream treatment system before the bypass system is engaged. An energy dissipater is
usually required at the end of the pipes to reduce velocities and distribute flows into the downstream
treatment system.
If the outlet of the connection pipe is submerged, an energy loss equation can be used to estimate the pipe
velocity using the following:
2 V2
h Equation 4.6
2g
Where: h = head level driving flow through the pipe (defined as the ‘spillway’
outlet level minus the normal water level in the downstream
treatment system)
Note: the coefficient of 2 in the equation is a conservative estimate of the sum of entry and exit loss
coefficients (Kin + Kout).
The area of pipe required to convey the ‘design operation flow’ (1 year ARI) is then calculated by dividing the
above ‘design operation flow’ by the velocity. Alternatively, if the pipe outlet is not fully submerged, the orifice
equation should be used (Equation 4.5) to estimate the size of the connection pipe.
An example configuration of a sedimentation basin ‘control’ overflow pit and pipe outlet to the macrophyte
zone of a constructed wetland is provided in Figure 4-8 (over page).
The required length of the weir for ‘control’ outlet operation can be computed using the weir flow equation
(Equation 4.4) and the ‘design operation flow’ (Section 4.3.1), adopting a blockage factor of 1.0 (as weir is
unlikely to become blocked by debris).
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-17
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
Inlet connection to
Macrophyte Zone macrophyte zone
Inlet Zone
(Sedimentation Basin)
Spillway
Overflow Pit
Energy Dissipater
Connection Pipe(s)
Design Surface
Natural Surface
Figure 4-8: Example layout (top) of sedimentation basin ‘control’ overflow pit and pipe connection to a macrophyte zone and control
overflow pit installation (bottom)
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-18
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
In most applications the ‘spillway’ outlet weir will form part of the high flow bypass system, which protects the
downstream treatment system from scouring during ‘above design’ storm flows. Ideally, the ‘spillway’ outlet
weir level should be set at the top of the extended detention level of the downstream treatment system. This
ensures that a significant proportion of catchment inflow will bypass the downstream treatment system once
the extended detention is filled. The length of the ‘spillway’ outlet weir is to be sized to safely pass the
maximum flow discharged into the downstream treatment system (as defined by the ‘above design flow’ in
Section 4.3.1). The water level above the crest of the bypass weir is 0.3 m below the embankment crest
separating the sedimentation basin and the downstream treatment system.
The required length of the ‘spillway’ outlet weir can be computed using the weir flow equation (Equation 4.4
with blockage factor equal to 1.0) and the ‘above design flow’ (Section 4.3.1). Plate 4-4 shows examples of
‘spillway’ weir outlets. The ‘spillway’ outlet weir should be designed using standard methods to avoid scour
and erosion. Typically, a concrete sill is required with rock protection on the downslope sides of the sill.
Plate 4-4: Spillway outlet weir structure of sedimentation basins at the Gold Coast and Coorparoo
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-19
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
Catchment Characteristics
Residential Ha
Commercial Ha
Roads Ha
Conceptual Design
Time of concentration
Refer to Handbook for Drainage: Design Criteria (TCC 2004) and QUDM minutes
Hydraulic efficiency
Vs > Vs:5yr
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-20
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
Internal batters
Fence required
Weir length m
Weir length m
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-21
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
Within a constructed wetland treatment system, sedimentation basins provide a transition between urbanised
streams – possibly piped or channelized – that may have limited access, and natural wetland systems within
accessible parkland. They are located at the highest point of a constructed wetland and may provide viewing
opportunities across the wetland.
Sedimentation basins are a potential place for community education (through signage and other
interpretative elements) as they are large and visible (and perhaps part of a larger constructed wetland). In
addition, they may be the first place in an urban water catchment where treatment takes place. They
therefore make good locations to tell the story of stormwater treatment processes.
Landscape design has a key role in overcoming negative perceptions that permanent water bodies like
sedimentation basins have in some communities. In the past this may have been due to legitimate pest and
safety concerns that have arisen from poorly designed and/ or managed systems, particularly remnant
swamps and lagoons. Additionally, these older systems may have provided poor amenity values to the
community due to lack of access or industrial scale treatment infrastructure.
4.4.1 Objectives
Landscape design for sedimentation basins has five key objectives:
Addressing stormwater quality objectives by applying adequate edge and littoral zone planting to prevent
scour and erosion of batters while ensuring an unvegetated open water pool is retained.
Addressing public safety issues by ensuring the landscape design and edge treatments restrict public
access to the open water zone and allow egress where appropriate.
Ensuring that the overall landscape design of the sedimentation basin integrates with its host natural and/
or built environment and compliments the landscape design of adjacent treatment measures (e.g.
constructed wetlands or bioretention basins).
Comprehensive site analysis should inform the landscape design as well as road layouts, civil works and
maintenance requirements. Existing site factors such as roads, driveways, buildings, landforms, soils, plants,
microclimates, services and views should be considered. For further guidance refer to the South East
Queensland WSUD Conceptual Design Guidelines (Healthy Waterways Partnership, 2008).
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-22
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
desired functions. Additionally, landscape design to specific elements should aim to create places where
local residents and visitors will come to enjoy and regard as an asset.
Through integrated landscape design, sedimentation basins can become important features within open
space areas. Areas of open water provide passive viewing opportunities for plants and wildlife that have
adapted to the urban lagoon landscapes. By siting basins such that inlet structures create dramatic “water
features” in a highly visible area during high flows, basins can create invigorating large-scale urban
environments (see Figure 4-9). Often the sedimentation basins are part of a broader treatment train and
generally form the first part of wetlands. This allows the integrated landscape design of habitat renewal and
open water vistas with public and recreational areas. This often can be part of broader community education
strategy, for the role of sedimentation basins, through appropriate interpretive signage outlining both the
natural habitat and water quality benefits.
Basins shapes can vary widely and need to be primarily responsive to the hydraulic engineers length to width
ratio, depths and inlet requirements. The landscape designer has the opportunity to shape the basin to
respond to adjacent land uses (i.e. recreational spaces, local landforms and existing features). This often
can result in “natural” informal shapes that provide visually aesthetic landscape outcomes. Embankments
and batter profiles play an important role in providing an interesting and functional water body.
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-23
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
The length to width ratio of the basin should be determined by the hydraulic designer working within the site
constraints (refer to section 4.3.2). Once the overall shape has been determined, one of the first
considerations should be if a formal or informal style is required depending on setting. Figure 4-10 illustrates
formal and informal options for a given length to width ratio.
Figure 4-10: Informal and Formal Basin Configuration Given Length to Width Ratio
Where a natural look is required, the designer should explore opportunities for landform grading to the
embankment to create variation in the slope. Geometric planar batters should be avoided. The grading
approach also creates a diversity of habitat niches along the slope and can assist in reducing erosion. Figure
4-11 illustrates this technique. It is important that shaping to the slope does not allow areas for mosquitoes to
breed such as isolated areas of stagnant water. Designing to avoid mosquitoes is discussed in detail in
Chapter 6 (Section 6.2.8) with respect to constructed wetlands.
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-24
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
In coordination with hydraulic engineers, the landscape design and grading of embankment batters allows a
variety of edge treatments and opportunities.
The edge treatments that maximise natural habitats for flora and fauna can be facilitated by slopes flatter
than 1:5 and often have benched foreshores with shallow standing water levels. This allows for safe egress
from the basin. Rock edges and ‘beaches’ can also provide interest at key viewing areas and aid in
providing further localised habitat and visual interest. This can be seen in Figure 4-6.
For areas where public access is to be restricted, batter slopes can be steeper than 1:5, and require safety
fencing to restrict access. This typical treatment can also include a wall to further maximise deep, clear
water. This can be seen in Figure 4-7.
Planting of sedimentation basin edges requires analysis of several issues including water depths and
variances, soil and basin topsoil types, batter profiles, public access and habitat rehabilitation. For further
information refer Section 4.4.4 Appropriate Plant Selection.
The basin inlet is an important place to experience the confluence of fast flowing water with still water and is
a dynamic place within the local landscape. Designers have scope to approach this element in a variety of
ways provided the hydraulic design is not compromised. Options to consider include:
Using salvaged site rocks or patterned and coloured concrete to emphasise the feature and create niche
habitats.
Enhancing the microclimate created by cool running water by adding shade trees.
Creating places to view running water. Where suitable, this can be achieved with footbridges located
above the water. Such structures should be designed appropriately with consideration of life cycle costs
(i.e. timber piers should not be used where contact with water occurs). Alternatively, views from the side
will provide a different experience. Viewing areas should be located a minimum of 5 m from the open
water body to discourage wildlife feeding.
As part of the siting and layout of sedimentation basins, suitable access from an adjacent roadway needs to
be provided to periodically remove sediment. The landscape design of these access ramps needs to
consider the visual impact created in the landscape and how this can be minimised. Access to the basin
floor to remove sediments requires either the installation of a ramp/ ramps, or an access track around the
perimeter for smaller basins (refer section 4.2.7). These elements are crucial to the operation of a
sedimentation basin, but should be designed sensitively so they do not become visually prominent.
For both ramps and perimeter access tracks, reinforced turfing pavers should be considered as the
pavement to create a green surface that blends with the surrounding plantings. Surfaces of concrete or rock
should be avoided where possible. Consideration must be given to the size and weight of machinery likely to
utilise the access ramp. Reinforced vegetated surfaces should be able to respond to impacts given that
desilting of the basin will only be required approximately every 5 years.
Consider incorporating the sediment removal access into other landscape elements. For example, perimeter
access tracks could also be used as recreational trails (in this case part of the track width could be paved
using reinforced concrete). Investigate if the weir could become part of this access way. Ramps may
potentially be integrated with viewing areas.
Trees and shrubs can be employed to screen these elements. The shadow cast by trees also assists in
breaking up the form of linear structures so that they blend into formally designed landscapes.
Where gates and fences are required, it is important to use materials and styles that are sensitive to the
setting. Products aimed for industrial applications should generally be avoided in parkland spaces, as should
products designed for domestic garden situations.
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-25
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
Grates to overflow pits need to be designed to minimize visual impact on the landscape. The grate above
the overflow pit can become an interesting local landmark, particularly if it is sited within the open water
surface. Provided that the grate performs its intended function of preventing blockages by debris (refer
section 4.3.5) and is structurally sound, there are opportunities for creative design solutions to this
component. An important consideration is to prevent local fauna (e.g. ducks) from entering the overflow pit
and becoming trapped. Investigate installing 200 mm wide perforated plates (holes to 20 mm) or similar at
the base of the grate.
Weir outlets may be large items that can potentially add character to the design. Grouted rock wall or off-
form concrete finishes should be investigated rather than loose dumped rocks, particularly where the weir is
visible. Loose rock fill structures create glare, weed and cane toad issues. Alternatives to consider include
rock pitched concrete with planting pockets to soften the visual impact of reinforces weirs. Refer to for a
typical treatment in Figure 4-12.
In parkland areas, turfed spaces within barrier fencing offer a simple low maintenance solution. Figure 4-13
provides illustrations. Constructed decks may be appropriate in more urbanised areas. Hardwood timber
construction should generally be avoided due to its inherent life-cycle costs.
Viewing areas should be located with a minimum distance of 5 m separating the viewing area from the
waterbody, so that wildlife feeding is discouraged.
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-26
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
Figure 4-13: Turfed Viewing Areas with Barrier Fencing and Planting
4.4.3.9 Fencing
Where fences are required to sedimentation basin embankment edges, layout and design of fencing is
important in creating an overall attractive landscape solution. Fence styles need to respond to functional
requirements but also the contextual setting of the sedimentation basin i.e. if it’s an urban residential or open
space/ parkland area.
If fences are used, consider styles suitable for parkland and urban/ suburban contexts. Products designed
for domestic gardens or industrial applications should generally be avoided. Fence types are similar to
manufactured pool safety fences to relevant Australian standards. By specifying a black finish, and allowing
for a screening garden in front of fences, the visual impact can be greatly reduced. Further safety issues are
discussed in Section 5.4).
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-27
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
All signage and artwork proposed for public information must be approved by Townsville City Council.
Signage is an important part of educating the general public on the positive benefits of WSUD strategies. It
can be based on stormwater quality information but also educate on waterways, habitat created, local fauna
and flora. The following key issues and considerations need to be part of the signage strategy:
Signage where possible should be kept simple and easy to interpret. Detailed design plans and system
flow charts should be avoided, as these are often difficult to understand. Artistic illustrations may be used
to explain processes. Text should be kept to a minimum. Annotated photographs or sketches are a more
effective way of explaining processes;
Signage location should take into account pathway networks, designated feature “people places” and
locality to key areas requiring interpretive signage;
Signage materials need to be low maintenance and durable, resistant to UV and graffiti and be easily
installed.
Plate 4-6: Annotated sketches/ photographs are an effective way of explaining treatment process to the public
Within highly visible parkland and urban settings, investigate the use of interesting forms, patterns and
colours that still achieve the desired function. For example, off-form concrete patterning, artwork to
downstream side, coloured concrete, or organic shapes could be employed.
Fringing vegetation should include Shallow Marsh species planted from design water level to 0.5 m below
(refer to Appendix A for suitable plant species).
Littoral zone planting from design water level to top of batter (refer to Appendix A for suitable plant
species).
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-28
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
Plant selection for sedimentation basin edges need to respond to edge profiles, water depths and
functionality. Dense edge planting should occupy habitat to avoid undesirable plant species establishing
and provide a public safety barrier to the open water. Appendix A provides guidance on selecting suitable
plant species and cultivators that deliver the desired stormwater quality objectives for sedimentation basins.
In general, vegetation should provide:
The battered embankment and fringing vegetation to open space or urban areas is important in providing
soil stability, screening, habitat, visual amenity and interest. Between the marsh zone and the top of the
embankment, trees, shrubs and groundcovers can be selected. Some key consideration when selecting
appropriate sedimentation basin embankment planting include:
Selecting locally endemic groundcovers, particularly for slopes greater than 1 in 3 with erodable soils, with
matting or rhizomataceous root systems to assist in binding the soil surface during the establishment
phase.
Preventing marsh zone plants from being shaded out by planting to ensure an open canopy, minimising
tree densities at the waters edge and choosing species such as Melaleuca that allow sunlight to penetrate
the tree canopy.
Allowing excavators and other vehicles access to the water body for sediment removal purposes (refer to
Section 4.4.3.4 below for further guidance).
Locating and selecting species that in key view areas are below 1.0m high and form a dense habitat to
discourage public access to the water edge.
Screening planting that provides interest in form and colour, screens fences where applicable and are
locally endemic.
Open space vegetation may be of a similar species and layout to visually integrate the sedimentation basin
with its surrounds. Alternatively, vegetation of a contrasting species and/ or layout may be selected to
highlight the water body as a feature within the landscape. Turf is an ideal consideration for accessible open
space.
A wide range of species is at the designer’s disposal depending on the desired scheme. Refer to relevant
local guidelines and Appendix A.
The standard principles of informal surveillance, exclusion of places of concealment and open visible areas
apply to the landscape design of sedimentation basins. Where planting may create places of concealment or
hinder informal surveillance, groundcovers and shrubs should not generally exceed 1 m in height. For
specific guidance on CPTED requirements the designer should refer to relevant guidelines from Townsville
City Council.
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-29
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
Fences or vegetation barriers to restrict access should be incorporated into sediment basin areas,
particularly on top of concrete or stone walls where:
There is risk of serious injury in the event of a fall (over 0.5 m high and too steep to comfortably walk up/
down or the lower surface or has sharp or jagged edges).
There is a high pedestrian or vehicular exposure (on footpaths, near bikeways, near playing/ sporting
fields, near swings and playgrounds etc).
Water ponds to a depth of greater than 300 mm on a constructed surface of concrete or stone. Natural
water features are exempt.
Pool fences in accordance with Australian Standards (for areas adjacent to playgrounds/ sports fields
where a child drowning or infection hazard is present).
Dense vegetation (hedge) at least 2 m wide and 1.2 m high (minimum) may be suitable if vandalism is not a
demonstrated concern (this may be shown during the initial 12 month maintenance period). A temporary
fence (e.g. 1.2 m high silt fence) will be required until the vegetation has established and becomes a
deterrent to pedestrians/ cyclists.
An alternative to the adoption of a barrier/ fence is to provide a 2.4 m ‘safety bench’ that is less than 0.2 m deep
below the permanent pool level around the waterbody. This is discussed in Section 4.3.3 with respect to
appropriate batter slopes.
There exist a number of challenges that must be appropriately considered to ensure successful construction
and establishment of sedimentation basin. These challenges are best described in the context of the typical
phases in the development of a Greenfield or Infill development, namely the Subdivision Construction Phase
and the Building Phase (see Figure 4-14).
Subdivision Construction - Involves the civil works required to create the landforms associated with a
development and install the related services (roads, water, sewerage, power etc.) followed by the
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-30
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
landscape works to create the softscape, streetscape and parkscape features. The risks to successful
construction and establishment of the WSUD systems during this phase of work have generally related to
the following:
Construction traffic and other works can result in damage to the sedimentation basins.
Importantly, all works undertaken during Subdivision Construction are normally ‘controlled’ through the
principle contractor and site manager. This means the risks described above can be readily managed
through appropriate guidance and supervision.
Building Phase - Once the Subdivision Construction works are complete and the development plans are
sealed then the Building Phase can commence (i.e. construction of the houses or built form). This phase
of development is effectively ‘uncontrolled’ due to the number of building contractors and sub-contractors
present on any given allotment. For this reason the Allotment Building Phase represents the greatest risk
to the successful establishment of sedimentation basins.
To overcome the challenges associated within delivering sedimentation basins a Staged Construction and
Establishment Method should be adopted (see Figure 4-14):
Stage 1: Functional Installation - Construction of the functional elements of the sedimentation basin as
part of the Subdivision Construction and allowing the basin to form part of the sediment and erosion
control strategy.
Stage 2: Sediment and Erosion Control – During the Building Phase the sedimentation basin will form part
of the sediment and erosion control strategy to protect downstream aquatic ecosystems.
Stage 3: Operational Establishment - At the completion of the Building Phase, the sedimentation basins
can be desilted to establish the design bathymetry and landscaped.
Sub-division Construction
Civil Works
Landscape Works
Allotment Building
STAGE 1:
Functional Installation
STAGE 2:
Sediment & Erosion Control
Stage 3:
Operational Establishment
Figure 4-14: Staged Construction and Establishment Method
Additionally the bathymetry of the sedimentation basin must ensure appropriate storage is available for
accumulated sediment. In this regarding an earthworks tolerance of plus or minus 25 mm is considered
acceptable.
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-31
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
The installation of horticultural soils should follow environmental best practices and include:
Preparation of soil survey reports including maps and test results at the design phase.
Stripping and stockpiling of existing site topsoils prior to commencement of civil works.
Deep ripping of subsoils using a non-inversion plough.
Reapplication of stockpiled topsoils and, if necessary, remedial works to suit the intended plant species.
Addition where necessary, of imported topsoils (certified to AS 4419-2003).
The following minimum topsoil depths are required:
Timing of vegetation planting is dependent on a suitable time of year (and potential irrigation requirements)
as well as timing in relation to the phases of development. October and November are considered ideal
times to plant vegetation in treatment elements. This allows for adequate establishment/ root growth before
the heavy summer rainfall period but also allows the plants to go through a growth period soon after
planting, resulting in quicker establishment. Planting late in the year also avoids the dry winter months,
reducing maintenance costs associated with watering. Construction planning and phasing should endeavour
to correspond with suitable planting months wherever possible. However, as lead times from earthworks to
planting can often be long, temporary erosion controls (e.g. use of matting or sterile grasses to stabilise
exposed batters) should always be used prior to planting.
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-32
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
To maximise the chances of successful vegetation establishment, the water level of the sedimentation basin
is to be manipulated in the early stages of vegetation growth. When first planted, vegetation in the deep
marsh zones may be too small to be able to exist in their prescribed water depths (depending on the maturity
of the plant stock provided). Macrophytes intended for the deep marsh sections will need to have half of their
form above the water level, which may not be possible if initially planted at their intended depth. Similarly, if
planted too deep, the young submerged plants will not be able to access sufficient light in the open water
zones. Without adequate competition from submerged plants, phytoplankton (algae) may proliferate.
Weed management in sedimentation basins is important to ensure that weeds do not out compete the
species planted for the particular design requirements. This may also include some native species like
Phragmites that naturally can appear in constructed wetlands and out-compete other more important planted
species.
Conventional surface mulching of the wetland littoral berms with organic material like tanbark is not
recommended. Most organic mulch floats and water level fluctuations and runoff typically causes this
material to be washed into the wetland with a risk of causing blockages to outlet structures. Mulch can also
increase the wetland organic load, potentially increasing nutrient concentrations and the risk of algal blooms.
Adopting high planting density rates and if necessary applying a suitable biodegradable erosion control
matting to the wetland batters (where appropriate), will help to combat weed invasion and will reduce
maintenance requirements for weed removal. If the use of mulch on the littoral zones is preferred, it must be
secured in place with appropriate mesh or netting (e.g. jute mesh).
4.5.5.4 Watering
Regular watering of the littoral and ephemeral marsh zone vegetation during the plant establishment phase is
essential for successful establishment and healthy growth. The frequency of watering to achieve successful
plant establishment is dependent upon rainfall, maturity of planting stock and the water level within the
wetland. However, the following watering program is generally adequate but should be adjusted (i.e.
increased) as required to suit site conditions:
After this initial three month period, watering may still be required, particularly during the first winter (dry
period). Watering requirements to sustain healthy vegetation should be determined during ongoing
maintenance site visits.
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-33
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
Inspections of the inlet configuration following storm events should be made soon after construction to
check for erosion. In addition, regular checks of sediment build up will be required as sediment loads
from developing catchments vary significantly. The basins must be cleaned out if more than half full of
accumulated sediment.
Similar to other types of WSUD elements, debris removal is an ongoing maintenance requirement. Debris,
if not removed, can block inlets or outlets, and can be unsightly if deposited in a visible location.
Inspection and removal of debris should be done regularly and debris removed whenever it is observed
on the site.
Routine inspection of inlet and outlet points to identify any areas of scour, litter build up and blockages.
Removal of litter and debris.
Removal and management of invasive weeds (both terrestrial and aquatic).
Periodic (usually every 5 years) draining and desilting, which will require excavation and dewatering of
removed sediment (and disposal to an approved location).
Regular watering of littoral vegetation during plant establishment (refer section 4.4.6).
Replacement of plants that have died (from any cause) with plants of equivalent size and species as
detailed in the planting schedule.
Inspections are also recommended following large storm events to check for scour and damage.
All maintenance activities must be specified in a maintenance plan (and associated maintenance inspection
forms) to be developed as part of the design process (Step 7). Maintenance personnel and asset managers
will use this plan to ensure the sediment basins continue to function as designed.
Inspection Frequency
Maintenance Frequency
Data Collection/ Storage Requirements (i.e. during inspections)
Detailed Clean Out Procedures (main element of the plans) including:
equipment needs
maintenance techniques
public safety
environmental management considerations
access issues
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-34
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
Design Details.
An approved maintenance plan is required prior to asset transfer to Council.
An example operation and maintenance inspection form is included in the checking tools provided in Section
4.7. These forms must be developed on a site specific basis as the configuration and nature of sediment
basins varies significantly.
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-35
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
TREATMENT Y N
BASIN CONFIGURATION Y N
Configuration of basin (aspect, depth and flows) allows settling of particles >125 μm?
Public safety design considerations included in design and safety audit of publicly accessible areas undertaken?
Overall shape, form, edge treatment and planting integrate well (visually) with host landscape?
OUTLET STRUCTURES Y N
Designed to prevent clogging of outlet structures (i.e. provision of appropriate grate structures)?
COMMENTS
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-36
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
Site: Date:
Time:
DURING CONSTRUCTION
A. FUNCTIIONAL INSTALLATION
1. Erosion and sediment control plan adopted 19. No seepage through banks
8. Maintenance access (eg. ramp) installed 26. Weed removal prior to planting
10. Level of base, banks/ spillway as designed 28. Vegetation layout and densities as
designed
13. Location and levels of outlet as designed 30. Stabilisation immediately following
earthworks and planting of terrestrial
landscape around basin
14. Safety protection provided 31. Silt fences and traffic control in place
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-37
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
FINAL INSPECTION
1. Confirm levels of inlets and outlets 8. Check for uneven settling of banks
COMMENTS ON INSPECTION
ACTIONS REQUIRED
1.
2.
3.
4.
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-38
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
Location:
Description:
Litter accumulation?
Replanting required?
COMMENTS
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-39
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
Asset ID:
Asset Location:
Construction by:
'On-maintenance' Period:
TREATMENT Y N
MAINTENANCE Y N
Maintenance plans and indicative maintenance costs provided for each asset?
ASSET INFORMATION Y N
COMMENTS
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-40
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
The site is triangular in shape with a surface area of approximately 7,000 m2 as shown in Figure 4-15. Road
runoff is conveyed by roadside open channels and conventional stormwater pipes (up to the 50 year ARI
event) to a single outfall that discharges to the top apex of the sedimentation basin site as shown in Figure
4-15. Approximately 1.0 km of the freeway, with a total contributing area of 8 ha (90 % impervious),
discharges to the sedimentation basin. The site of the sedimentation basin has a fall of approximately 2 m
(from 5 m AHD to 3 m AHD) towards a watercourse.
The conceptual design process established the following key design elements to ensure effective operation
of the constructed wetland and sedimentation basin:
‘Spillway’ outlet weir set at the top of extended detention for the wetland and 0.3 m above the sediment
basin permanent pool level (4.1 m AHD).
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-41
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
6.0
5.0
4.0
Site of Sedimentation
3.0
Basin & Wetland
55 m System
Creek
150 m
Design Objectives
As the sedimentation basin forms part of a treatment train (with the wetland macrophyte zone downstream)
the design requirements of the sedimentation basin system need to:
Promote sedimentation of particles larger than 125 μm with 90 % capture efficiency for flows up to the
‘design operation flow’ (1 year ARI peak discharge).
Provide for connection to the downstream wetland macrophyte zone with discharge capacity
corresponding to the ‘design operation flow’ (1 year ARI peak discharge).
Provide for bypass of the ‘above design flow’ around the wetland macrophyte zone when the inundation
of the macrophyte zone reaches the design maximum extended detention depth.
As described in Section 4.3.1, the ‘design operation flow’ is defined as the 1 year ARI and provides a basis
for sizing the sedimentation basin area and ‘control’ outlet structure.
Design flows are established using the Rational Method and the procedures provided in QUDM (DNRW,
IPWEA & BCC 1998). The site has one contributing catchment being 8 ha in area, 1 km long (along the
freeway) and drained by roadside open channels and stormwater pipes.
For the purposes of establishing the time of concentration, the flow velocity in the roadside channels and
underground pipes is estimated at 1 m/s. Therefore:
= 1000s
= 17 minutes
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-42
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
The coefficient of runoffs were calculated using the Handbook for Drainage: Design Criteria (TCC, 2004) and
Table 4.05.2 of QUDM (DNRW, IPWEA & BCC 1998) as follows:
C Runoff
ARI 1 10 50
QUDM Factor 0.8 1 1.15
Where: C1 = 0.88
Catchment area = 8 ha
tc = 17 mins
I1 = 74.1 mm/hr
The ‘above design flow’ is used to design the ‘spillway’ outlet structure which forms part of the high flow
bypass around the wetland. In this case, the major flood flow (50 year ARI) enters the sedimentation basin
and thus forms the ‘above design flow’.
Where A = 8 ha
C50 = 1.01
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-43
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
n
1 v (de dp )
R 1 1 s
n Q / A (de d* )
Based on the description of the sedimentation basin and wetland provided in Section 4.8.1, the following
applies:
dp = 2.0 m
d* = 1.0 m
de = 0.3 m
An aspect ratio of approximately 1 (W) to 4 (L) is adopted based on the available space (Figure 4-15). Using
Figure 4-5 (configuration I), the hydraulic efficiency ( ) is estimated to be approximately 0.4. This value is less
than desirable; however, site constraints prevent any other configuration. The turbulence factor (n) is
computed from Equation 4.2 to be 1.67. Thus:
λ = 0.4
n = 1.67
Inserting the above parameters into Equation 4.1, the required sedimentation basin area to achieve a target
sediment (125 μm) capture efficiency of 90 % is 368m2. With an approximate W to L ratio of 1:4, the notional
dimensions of the basin are approximately 9.6 m x 38.3 m.
Sedimentation Basin Storage Volume Vs > Volume of accumulated sediment over 5 years (Vs:5yr)
The sedimentation basin storage volume (Vs) is defined as the storage available in the bottom half of the
sedimentation basin permanent pool depth. Assuming the internal batters of the basin (Section 4.3.3.3) are
2:1 (H:V) below the permanent water level, the area of the basin at 1 m depth is determined to be 300 m2.
Therefore, the sedimentation basin storage volume Vs is 300m3.
The volume of accumulated sediments over 5 years (Vs:5yr) is established using Equation 4.3 (using a
sediment discharge rate (Lo) of 1 m3/ha/yr):
Vs:5 yr A c R Lo Fc
Given Ac = 8 ha
R = 90 %
Lo = 1 m3/ha/year
Fc = 5 years
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-44
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
= 8 x 0.9 x 1 x 5
= 36 m3
Rearranging Equation 4.3, the required clean out frequency (Fc) is estimated to be:
300
Fc =
1 8 0.9
= 41.8 years
Considering the relatively small size of the sedimentation basin (9.6 m width), it is not possible to achieve the
notional permanent pond depth of 2 m using the 5:1 (H:V) required for public safety. Therefore a 4:1 (H:V)
batter is to be adopted for the ground above the permanent pool level and to 0.5 m below permanent pool
level and a 2:1 (H:V) internal batter slope for 0.5 m to 2 m below the permanent pool level. The sedimentation
basin will be fenced around most of its perimeter to ensure public safety.
The base of the sedimentation basin will be lined with rock to prevent vegetation growth and to guide
extraction depths during sediment removal. A summary of the sedimentation basin configuration is as
follows:
Width = 9.6 m
Length = 38.3 m
Storm water
pipe
25 m m dia.
w eephole
W ing W all
C oncrete
outlet apron
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-45
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
4.8.5.1 Design of ‘Control’ Outlet - Overflow Pit and Pipe Outlet Configuration
The ‘control’ outlet structure is to consist of an outlet pit with the crest of the pit set at the permanent pool
level of the sedimentation basin (3.8 m AHD) which is 0.3 m above the permanent water level in the wetland.
The overflow pit is sized to convey the design operational flow (1 year ARI).
According to Section 4.3.5, two possible flow conditions need to be checked, i.e. weir flow conditions (with
extended detention of 0.3 m) and orifice flow conditions.
From Equation 4.4, the required perimeter of the outlet pit to pass 1.45 m3/s with an afflux of 0.3 m can be
calculated assuming 50% blockage:`
Qdes 1.45
P = = 10.6 m
3/ 2
B Cw h 3/2
0.5 1.66 0.3
Qdes 1.45
Ao = = 1.99 m2
B Cd 2 g h 0.5 0.6 2(9.81)(0.3)
In this case, the weir flow condition is limiting. Considering the overflow pit is to convey the ‘design operation
flow’ (1 year ARI) or slightly greater, a 3000 x 3000 mm pit is adopted providing a perimeter of 12 m which is
greater than the 9.2 m calculated using the weir flow equation above. The top of the pit is to be fitted with a
letter box grate. This will ensure large debris does not enter the ‘control’ structure while avoiding grate
blockage by smaller debris.
The size of the connection pipe (i.e. between the sedimentation basin and wetland macrophyte zone) can be
calculated by firstly estimating the velocity in the connection pipe (as the outlet is submerged) using the
following (Equation 4.5):
2 V2
h
2g
Where: h = Head level driving flow through the pipe (defined as the ‘Spillway’
outlet level minus the normal water level in the downstream treatment
system)
The area of pipe required to convey the ‘design operation flow’ (1 year ARI) is then calculated by dividing the
above ‘design operation flow’ by the velocity:
A = 1.45/2.43 = 0.5967 m2
This area is equivalent to a 900 mm reinforced concrete pipe (RCP). The obvert of the pipe is to be set just
below the permanent water level in the wetland macrophyte zone (3.5 m AHD) meaning the invert is at 2.55
m AHD.
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-46
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
Overflow pit = 3000 x 3000 mm with letter box grate set at 3.8 m AHD pipe connection (to wetland) =
900mm RCP at 2.55m AHD
The ‘above design flow’ is to bypass the macrophyte zone of the wetland. This will be provided by a ‘spillway’
outlet weir designed to convey the ‘above design flow’ (100 year ARI) set at 0.3 m above the permanent pool
of the sedimentation basin.
The length of the ‘spillway’ outlet weir determines the afflux for the 50 year ARI peak discharge and sets the
top of embankment of the sedimentation basin. It is common practice to allow for 0.3 m of freeboard above
the afflux level when setting the top of embankment elevation. An afflux of 0.3 m has been adopted in
defining the length of the spillway weir. This value was adopted as a trade off between the bank height and
the width of the weir. A bank height of 0.9 m (0.3 m afflux and 0.3 m freeboard plus 0.3 m extended
detention) above the normal water level was deemed acceptable. The weir length is calculated using the weir
flow equation (Equation 4.4) substituting outlet perimeter P with weir length L and blockage factor B=1 (no
blockage):
Q des 4.42
L = = 16.2 m
3/ 2
Cw h3/2
1.66 0.3
The ‘spillway’ outlet is located adjacent to the inflow culvert to minimise risk of sediment scour.
Top of embankment set at 0.9 m above the permanent pool level (4.7 m AHD)
Planting Density
Zone Plant Species
(plants/m2)
Gahnia siberiana 6
Littoral Zone (edge)
Lomandra longifolia 6
Isolepis inundata 10
Shallow Marsh to a depth of 0.5m
Juncus usitatus 10
Refer to Appendix A for further discussion and guidance on vegetation establishment and maintenance.
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-47
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
Catchment Characteristics
Residential Ha
Commercial Ha
Roads 8 Ha
Conceptual Design
Time of concentration
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-48
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
Internal batters
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-49
Chapter 4 – Sedimentation Basins
WSUD Technical Design Guidelines for South East Queensland June 2006
4.9 References
BCC 2001, Sediment Basin Design, Construction and Maintenance: Guidelines, BCC, Brisbane
BCC 2005, Growing Native Plants in Brisbane, BCC, Brisbane, accessed 25th July
2005,http://www.brisbane.qld.gov.au/
DNRW, IPWEA & BCC (Department of Natural Resources and Water, Institute of Public Works Engineering
Australia – Qld Division & Brisbane City Council) 1998, Queensland Urban Drainage Manual (QUDM) Second
Edition, prepared by Neville Jones & Associates and Australian Water Engineering for DNRW, IPWEA & BCC,
Brisbane.
Fair GM and Geyer JC 1954, Water Supply and Waste Disposal, vol. 2, John Wiley and Sons, New York
GBLA (Graeme Bentley Landscape Architects) 2004, Preliminary drawings for Mernda Wetland, report for
Stockland, GBLA, Victoria
Leinster, S 2006, Delivering the Final Product – Establishing Water Sensitive Urban Design Systems, 7th
International Conference on Urban Drainage Modelling and 4th International Conference on Water Sensitive
Urban Design Book of Proceedings, Volume 2, A Deletic and T Fletcher (eds), Melbourne.
LHCCREMS (Lower Hunter and Central Coast Regional Environmental Management Strategy) 2002, Water
Sensitive Urban Design in the Sydney Region: ‘Practice Note 2 – Site Planning’, LHCCREMS, NSW,
http://www.wsud.org/downloads/Planning%20Guide%20&%20PN%27s/02-Site%20Planning.pdf
Persson J, Somes NLG and Wong THF 1999, ‘Hydraulic efficiency and constructed wetland and ponds’,
Water Science and Technology, vol. 40 no. 3, pp. 291–289
Standards Australia 2003, AS 4419-2003: Soils for landscaping and garden use, Standards Australia
WSUD Technical Design Guidelines for the Coastal Dry Tropics 4-50