OISD Std-164
OISD Std-164
OISD Std-164
FOR RESTRICTED
CIRCULATION ONLY
FOR RESTRICTED
CIRCULATION ONLY
Prepared by:
Oil Industry in India is more than 100 years old. Over the
years a variety of practices have been in vogue because of
collaboration/ association with different foreign companies and
governments. Standardisation in design, operating and maintenance
practices was hardly in existence at a national level. This lack of
uniformity, coupled with feed back from some serious accidents that
occurred in the recent past in India and abroad, emphasised the
need for the industry to review the existing state of art in designing,
operating and maintaining oil and gas installations.
The present document on Fire Proofing in Oil & Gas Industry was
prepared by the Functional Committee on Fire Proofing. This
document was prepared based on the accumulated knowledge,
experience of industry members and various national/international
codes and practices.
The Coordinator
Functional Committee on Fire Proofing
Oil Industry Safety Directorate
2nd Floor, “Kailash”,
26, Kasturba Gandhi Marg,
NEW DELHI 110 001.
FUNCTIONAL COMMITTEE
ON
FIRE PROOFING IN OIL & GAS INDUSTRY
LEADER
Shri B. K. Raut DGM (SMMS) E.I.L.
MEMBERS
Shri R. P. Saxena DGM (M) MRBC, ONGC
MEMBER COORDINATOR
===================================================================
In addition to the above, several other experts from Industry contributed in the
preparation, review and finalisation of this document.
CONTENTS
SUBJECT
1.0 INTRODUCTION 1
2.0 SCOPE 1
3.0 DEFINITION 1
10.0 REFERENCES 16
ANNEXURE 1 TO III 17
8.7 CURING :
Loss of bonding to the substrate for periodic fire testing over the
seriously affects the material’s expected life of the coating.
performance and may be caused by
moisture, penetration, corrosion, the In the event of a fire, the affected
use of an improper primer on the area of coating should be
substrate, or poor preparation of the thoroughly examined including
substrate before the fireproofing is substrate if required and
applied. necessary jobs carried out.
e) High Rise
Test 1093 (2000) 3.77(50000) .38(5000) 4.15(55000)
(UL1709)
f) ASTM
E-119 538 (1000) 1.125(14900) .11(1400) 1.23(16300)
Test
(UL 263)
(ISO 834)
c) ASTM E- - Atleast 8150 C
1529 after first 3
minutes -- -- 3.77(50000)
- Between 10100
C & 11800 C
after 5 min. at
all times
Pressurised
Propane 1216 (2200) 2.2(29100) 3.2(42400) 5.4(71500)
Burners
contained by 4’
x 8’ x 3’ pit Jet
fire test
Open Pool ** 926 (1700) to 3.40(45000) 0.38(5000) 3.77(50000) to
Fire Test 1260(2300) to to 4.6(61000)
3.85(51000) 0.76(10000)
** - Peak values are largely dependent upon fire size and geometry
ANNEXURE - II
UL 1709 W 10 X49 1093 deg C (2000 Protected steel must High intensity
Column 9” deg F) not exceed or high rise fire
high 538 deg C (1000 deg curve. Gas
F) fired furnace
BAM 90 min. for Horizontal 485 600-900 deg C 250 deg C (482 deg Pressurised
pressurised LPG M3 Tank with (1112 - 1652 deg F) F) maximum wall Propane jets in
tanks (Germany) 6.4 mm wall temperature a series
thickness and measured in the surrounding
50% filled with ullage space not the tank.
Propane adjacent to the
liquid. Maximum
internal pressure of
approximately 20
bars.
GESIP (France) Loaded vessel 1000 deg C Protected steel must Simulated
+ + Flame not exceed 427 deg C Pool fine
impingement 1100 deg C (800 deg F) furnace test
and + Hose H/C
Stream
H.S.E. Loaded vessel Pool fire (H/S) 427 deg C Pool fire
(U.K.) 1100 deg C
CONDENSERS VESSEL
PIPES
NON-LOAD
BEARING BRACINGS
FIRE HAZARDOUS
AREA
Large Pumps
Figure No. 5.4 : Pipe racks with large Fire-Potential Pumps installed below