Prepared By: Engr. Mark Roger Huberit Ii Riprap Construction
Prepared By: Engr. Mark Roger Huberit Ii Riprap Construction
Prepared By: Engr. Mark Roger Huberit Ii Riprap Construction
Indirect Cost
1. Material Testing (1% of DC) -
2. Contractor's Profit (10% of DC) 592.50
3. Taxes (12% of DC) 711.00
4. Contingency -
Total Indirect Cost P 1,303.50
Total Cost of ITEM I P 10,191.00
Unit Cost 24.26
II STRUCTURE EXCAVATION 72.00 CU.M.
Labor
Equipment Operator 1 2 days 600.00 1,200.00
P 1,200.00
Equipment
1 unit- Backhoe 24 hours 1,400.00 33,600.00
P 33,600.00
Indirect Cost
1. Material Testing (1% of DC) -
2. Contractor's Profit (15% of DC) 5,220.00
3. Taxes (12% of DC) 4,176.00
4. Contingency -
Total Indirect Cost P 9,396.00
Total Cost of ITEM II P 61,596.00
Unit Cost 855.50
Page 1 of 3
PREPARED BY: ENGR. MARK ROGER HUBERIT II RIPRAP CONSTRUCTION
Indirect Cost
1. Material Testing (1% of DC) 2,601.80
2. Contractor's Profit (15% of DC) 39,026.97
3. Taxes (12% of DC) 31,221.58
4. Contingency 26,017.98
Total Indirect Cost P 98,868.32
Total Cost of ITEM III P 361,649.92
Unit Cost 27,435.51
IV STONE MASONRY 120.00 CU.M.
Materials
Portland Cement 240 bags 275.00 66,000.00
Washed Gravel 40 cu.m. 1,500.00 60,000.00
Washed Sand 20 cu.m. 900.00 18,000.00
Boulders 100 cu.m. 900.00 90,000.00
PVC Pipe 2" ø Weep Holes 13 length 265.00 3,445.00
P 237,445.00
Labor
Civil Engineer 1 25 days 600.00 15,000.00
Foreman 1 25 days 550.00 13,750.00
Skilled Worker 2 25 days 450.00 22,500.00
Laborer 6 25 days 300.00 45,000.00
P 96,250.00
Equipment
1 unit- Bagger Mixer 72 hours 172.00 12,384.00
P 12,384.00
Indirect Cost
1. Material Testing (1% of DC) 3,460.79
2. Contractor's Profit (15% of DC) 51,911.85
3. Taxes (12% of DC) 41,529.48
4. Contingency 34,607.90
Total Indirect Cost P 131,510.02
Total Cost of ITEM IV P 481,049.81
Unit Cost 4,008.75
TOTAL PROJECT COST 914,486.73
Page 2 of 3
PREPARED BY: ENGR. MARK ROGER HUBERIT II RIPRAP CONSTRUCTION