Design of Rigid (Concete) Pavement 300
Design of Rigid (Concete) Pavement 300
Design of Rigid (Concete) Pavement 300
for Detail Estimate for Widening & Strengthening of Tarra -Powni -Khauna Road,
Length-10.000 K.M.
(As per IRC:58-2002)
Legal limit on the maximum laden axle loads of commercial vehicles
from 8160 kg to 10200 kg
So design wheel load = 5100 kg
Joint Spacing:-
Joint Width
Allowable expansion in concrete
∂ = 1/2 x 2
Lc = 2xScx104
Wxf
= 2x 0.8 x 104
2400 x 1.5
= 4.444m Say : 4.45 m
Which is less than maximum specified spacing of 4.5 m and hence acceptable
[Table 7, IRC 58-2002]
Therefore, provide contraction joint at 4.50m spacing & Expansion joint at every 7th such joint
1 of 8
i.e. 6 x 4.50 = 27.00 m spacing (instead of 28.57 m)
2 of 8
Design of slab thickness :-
I= [Eh3/12K(1-µ2)]1/4
= [(3x105x203)/12x8(1-0.152]1/4
= 198.86 cm
L = 450
I = 198.86
= 2.26
B 400
I = 198.86
= 2.01
L
I = 2.26
So, C = 0.251
2
= 7.35
a = [0.8521 x P + S P ]
0.5 0.5
qxTT π .5227xq
8xπ π 0.5227x8
= [ 172.91 + 344.61]0.5
= 22.75 cm
q = tyre pressure = 8 kg/cm2
s = c/c distance between two tyres = 31 cm
3 of 8
h2
4 of 8
σ = 0.529 x 5100 [4 log10 (96.38/41.33-0.4048](1+0.54µ)
302
= 15.032 kg/cm2
Total of temperature wraping stress and the sheel load stress
=7.35 + 10.832
= 18.182 kg/cm2
Which is less than (45 kg/cm2) the flexural strength at cement concrete
So the pavement thickness of 30cm is safe under combined action of Wheel load and temperature
Where,
P= 5100 kg
h=30cm
a=22.75cm
I=198.86 cm
Corner Stress = 3 x 5100 [ 1-(22.75 √2/108.2)1.2] 7.59 kg/cm2
(30)2
The Corner Stress is less than the Flexural Stength of the concrete i.e. 45 kg/cm2
So the pavement thickness of 30 cm is safe.
Assumed spacing between the dowel bars = 30cm (From table 8, IRC 58-2002)
First dowel bar in placed at distance = 15 cm From the pavement edge
Dowel bars upto a distance of 1.0 x radius of relative stiffness, from the point of load application are
effective in load transfer
5 of 8
Number of dowel bars participating in load transfer when wheel load is just over dowel bar close to the
edge of the slab
= 1+I/Spacing
= 1 + 198.86/20
=9.99
= 10 dowel bars
Assuming that the load transferred by the first dowel bar 'Pt' and assuming that the load on dowel bar at a
distance of 'I' from the first dowel to tbe zero, the total load transferred by dowel bar system.
= (1+(198.86-30)/198.86+(198.86-60)/198.86+(198.86-
90)/198.86) Pt.
= 3.09 Pt
4x2.0x106x5.15
= 0.2382
Where,
E=modulusof Elasticity of the dowel, kg/cm2
I= moment of Interia of the dowel, cm4
K= modulus of dowel/ concrete interaction (dowel support, kg/cm2/cm)
6 of 8
Spacing and length of plain bar
Area of Steel bar pr meter width of Joint to resist the Frictional force at slab bottom
As = bxfxW
S
Where,
b = lane width in meter
W= weight of slab in kg/m2
S= allowable workig stress of steel in kg/cm2
= (2.75 x 1.75 x 0.20 x 2400)/1250
= 2.35 cm2 /m
= 42.80 +10+5
= 57.80 cm
Say 58.00 cm
[Minimum length of tie bar = 51 cm from table 9, IRC:58 - 2002]
Area of Steel bar per meter width of Joint to resist the Frictional force at slab bottom
As =bxfxW
S
Where,
b = lane width in meter
W= weight of slab in kg/m2
S= allowable working stress of steel in kg/cm2
7 of 8
= (2.75 x 1.75 x 0.20 x 2400)
2000
= 1.47 cm2 /m
Spacing of the tie bars = A
As
= 100 x 1.13
1.47
= 76.87 cm
Provide spacing of 80cm c/c
[Maximum spacing 60 cm, for 30 thick slab & 12mm dia, Deformed bar, as per table 9, IRC : 58- 2002
Length of tie bar,
L= 2 x S x A
B XP
L= 2x2000x1.13
24.6x3.77
Increase length by 10cm for loss of bond due to painting and another 5 cm for tolerance in placement.
Therefore the length is,
= 48.73 + 10 + 5
= 63.73 cm
Say 64 cm
[ Minimum length for 12mm diameter deformed bar & 30 cm thick slab is 60 cm as per table 9, IRC 58-
2002]
So, 64cm long 12 mm diameter deformed bar is provided.
8 of 8