Part - A 10 X 2 20 Marks Answer All Questions

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 2

Part - A 10 X 2 = 20 Marks

Answer all Questions


Unit 1

1. Mention the key production system characteristics that dictate what type of overall production
approach is most appropriate for any type of product?
2. What are the typical intermediate products for a GT-based shipbuilding approach?
3. Mention the key shops in shipyard layout
4. Draw and mention about friction stir welding
5. Draw and mention various Shipyard Steel Shops
6. What are the typical intermediate products for a GT-based shipbuilding approach?

Unit 2
1. Explain briefly about optical lofting and its requirements
2. What are the steps to carry before prepainting of stockyard steel plate?
3. How shell plate development is carried out by lofts man
4. Brief about different types of shot blasting
5. Explain briefly about compute lofting and its requirements
6. Brief about different types of shot blasting

Unit 3
1. Describe briefly about photo electric and NC controlled devices
2. Describe briefly about plasma cutting
3. What are the steps to carry before pre-painting of stockyard steel plate
4. How steel are stored in shipyard
5. Describe briefly about photo electric and NC controlled devices
6. What are methods of cold forming

Unit 4
1. Describe briefly about welding procedure of ship structure
2. Draw and mention preassembly of double bottom sections
3. Describe briefly about oxygen cutting
4. How photo electric and NC control machines are used in shipyard
5. Write the various uses of robotics in shipyard
6. Draw and mention the use of bilge keel structure

Unit 5
1. What are the methods of quality control in welding process?
2. What are the advantages and disadvantages of preassembly of blocks?
3. Draw and mention side tanks and its bracket
4. Describe briefly about pillar construction in ships
5. Describe briefly about watertight doors
6. Draw and brief about electro slag welding

Part - B 5 X 16 = 80 Marks
Unit 1
1. Describe the principle of flowlines production in shipbuilding mechanism.
2. Explain various layouts of shipyard,area,labour and coastline.
3. Describe the ship production strategies used for Ship building
4. Explain the Relations of shipyard with its various supply industry

Unit 2

1. Explain material handling and storage,transport system in steel stockyard.


2. Explain material preparation flowline devices and their control.
3. Explain how the software system covers all phases of lofting from ship lines to production of
N/C tapes in addition to supplementary design and fabrication.
4. Explain about Data generation for shipbuilding process including generation of hull forms,
generation of frame plan & shell platedevelopment.

Unit 3

1. Explain various cutting process and machines used in shipyard industry.


2. Explain various Bending and machines used in shipyard.
3. Describe about plate and section part preparation and its machineries
4. Describe the general description of the various machines such asphotoelectric and NC-control
devices, edge preparation, problems of accuracy

Unit 4

1. Describe the prefabrication Sub-assemblies of built up T -bars, web frames and flat sections
2. Describe the preassembly of double bottom sections & side tank units and its welding process
3. Explain about transverse & longitudinal framing with neat sketch.
4. Draw and explain general cargo ship midship section.

Unit 5

1. Describe erection of ship hull by general assembly methods.


2. Describe the welding quality control in shipbuilding industry.
3. Describe various methods of Water tightness and structural integrity testing carried out in
compartment testing
4. Explain various handling of preassembled units in the block erecting area