Underground Cables 2: Installation of 66Kv To 330Kv Xlpe Insulated Cables
Underground Cables 2: Installation of 66Kv To 330Kv Xlpe Insulated Cables
Underground Cables 2: Installation of 66Kv To 330Kv Xlpe Insulated Cables
INSTALLATION
of
66kV to 330kV XLPE INSULATED CABLES
DMS #7374971
Ref: DMS # 879976 and 1148541
TOPICS
• Main Components
• Rating of cable circuits
• Function of cable sheath
• Sheath standing voltage (SSV)
• Sheath bonding systems
• Earth continuity conductor (ECC)
• Link and sheath voltage limiter boxes
• Sheath voltage limiters (SVL)
• Cable installation
• Cable trench backfill
• Cable installation in air
• Distributed temperature sensing cable (DTS)
• Cable testing
• Work on cables - safety
• Environmental considerations
• Future trends
MAIN COMPONENTS OF CABLES
Conductor
Load Current Rated
Losses in Conductor
Fault Currents Rated
Insulation
Stresses
Semi-conducting Layers
Manufacturing
Sheath
Moisture and Mechanical
Barrier
Fault Current Rated
Sheath Standing Voltages
(SSV)
Earth Bonding Methods
RATING OF CABLE CIRCUITS
S1
1 S1 p .S 3 p 3 S3 p
S E = 2πfI (2.10 −7 )( log e + j log e )
I S2 1 2 S 22 p 2 S1 p
R
3 S
S
1
2
I
Y
2
I S
B 1
P
1
Trefoil Formation
Phase Distances S12=S23=S13 and cable diameter d
1 3 2S
E1 = 2πfI ( 2.10 −7 )(− + j ) log e
2 2 d
2S
E2 = 2πfI (2.10 −7 ) log e
d
1 3 2S
E3 = 2πfI (2.10 −7 )(− − j log e
2 2 d
Flat Formation
Phase spacing S and cable diameter d
1 S 3 4S
E1 = 2πfI (2.10 −7 )(− log e + j log e )
2 d 2 d
2S
E2 = 2πfI (2.10 −7 ) log e
d
1 S 3 4S
E3 = 2πfI (2.10 −7 )(− log e − j log e )
2 d 2 d
Note: All voltages in V/m
SHEATH STANDING VOLTAGES (3)
Trefoil Formation
V2
V1 V3
Flat Formation V2
S
= 1.1
d
V1 V3
V2
S
=4
d
V1 V3
V2
S
= 10
S = Cable Spacing d
d = Cable Diameter
V1 V3
SHEATH BONDING SYSTEMS
a) Solid Bonding
Cable sheath ends are bonded directly to earth
Main Features
Cross Bonding
Requirements:
Link and SVL boxes are installed at the ends of the cable lengths and
connect the sheath to earth
Removable links provide a facility to isolate the sheath from earth for
over sheath insulation test to be carried out
SVLs are installed as required on the earth side of the link
All earth connection cables have to be rated for the system fault
currents and test voltages
The boxes have to be water and corrosion proof and rated for the
system fault currents and test voltages
SHEATH VOLTAGE LIMITERS (SVL)
Function
1. SVL rating >the induced voltage on the sheath caused by the max system
fault current.
2. Calculate the max impulse withstand voltage (8/20 and 4/10 micro sec)
of the cable oversheath. Obtained from cable data multiplied by 0.75 to
allow for ageing, temperature and mechanical damage of the oversheath
3. From SVL data, check that the SVL selected has a residual voltage
(based on the fault current) is less than the calculated withstand voltage
of the sheath.
4. SVL connection surge impedances should be minimise by using short
(less than 10m) concentric leads.
SVL CHARACTERISTICS
CABLE INSTALLATION
For inclines (up and downwards) the angle either adds or subtracts to the tension
Sidewall Pressure
P = T/R kg/m
Side rollers and skid plates can be used as guides but point loads should be avoided.
Minimum bending radius of the cable should not exceeded.
CABLE INSTALLATION
DUCTS
The cable trench may be filled with clean native soil or a special
backfill can be used to significantly improve the rating of the
cable circuit in some cases.
WP uses a 14:1 sand cement mix (by volume) which has a thermal
resistivity of 1.0oC.m/W
The backfill thermal resistivity has to be maintained when dried out (1%
moisture content)
The backfill cross sectional area has to be adequate to ensure that the
50oC isotherm is contained within the backfill
Different mixtures of backfill (clay, sand, gravel) can be developed and
proved for use
The backfill may be installed wet or dry according to the site . All air
voids have to be eliminated.
CABLE INSTALLATION IN AIR
When cables are directly buried in soil or backfill, the forces due
to thermal and loading cycling as well as fault current are
restrained.
Optical fibres either inserted under the cable sheath or laid on top of the
phase cable(s)
DTS cable is usually jointed at the same location as the HV cable
Temperature measurements are taken using optical time domain
reflectrometry (OTDR)
Cable ‘hot spots’ can be detected and preventative action taken to
prevent permanent cable damage
Computer software may be used to predict short term and emergency
ratings
CABLE TESTING
Factory Tests
Cable and accessory tests include type, routine and sample tests according to
various standards
Type tests are most important as is a service history of an identical or similar
installation
Cables above about 300kV should have completed prequalification tests for
one year
HV AC test voltages applied to the cable and accessories (eg 2.5U0 for 30 m)
Mechanical tests such as bending and sheath hardness should be carried
out
Special tests (eg water penetration, fibre optical etc)
CABLE TESTING
Site Tests
Induced Voltages
Cables being installed parallel with overhead or underground electrical
systems carrying high currents are exposed to induced voltages,
especially during system faults.
Transferred Voltages
During earth fault conditions, large currents can flow into the earthing
systems causing a local rise in voltage (EPR). These voltages are
transferred to the cable metallic components if they are connected to
the earthing system.
Elimination of lead
The use of lead is recognised as being detrimental to the environment both during the refining
and the disposal of the metal. Other metallic sheaths are being investigated as possible
alternatives.