Professional Documents
Culture Documents
Last Updated: April, 2018 Ed Section Answer
Last Updated: April, 2018 Ed Section Answer
Question 1: Since ASTM A370 covers a series of mechanical tests (including Reply 2: See Reply 1.
impact testing), can this standard be used for all applicable mechanical
tests in 16A?
3rd 8.5.8.7.2 Background: Section 8.5.8.7.2 of API 16A states: “Annular packing units No
shall be tested in two stages. The stage one test shall require pressure
testing on the appropriate size drill pipe in accordance with Table 27. The
Stage two test shall require pressure testing without drill pipe in the
preventer, i.e. on the open hole. The high pressure test for this stage shall
be as specified in 8.5.8.7.1.3, except as a minimum it shall be performed at
50 % of the rated working pressure of the preventer.”
Question: Does it matter in which order the two stages are conducted in?
3rd 8.5.7.6 Does an assembled BOP Stack, during FAT testing, fall under the guidelines The correct reference is section 8.5.8. Section 8.5.8.6.4
of 16A Section 8.5.6.7, Assembled Equipment? The vendor's FAT Hydrostatic proof and hydraulic operating chamber tests states
procedure calls for 5 minute Closed Preventer low pressure hydro testing a minimum 3 minute test followed by a 15 minute test. Section
and 16A calls for 10 minute minimum hold time after stabilization 8.5.8.7 Closed-preventer test outlines test criteria under
sections 8.5.8.7.1.2 and 8.5.8.7.1.3 which confirms the 10
minute hold periods.
3rd Annex C Please give me clarification for the actual number of TJ that should pass Annex C addresses stripping test for Ram and Annular type
thru the Annular BOP for API 16 A certification on the stripping life test. preventers. Section C.2.6 provides guidance for Ram
I’ve listed my concerns below. preventers and states NO tool joints. Section C.3.4 states the
following:
16 A references 5,000 TJ in the description of the test, then references
5,000 cycles in the design procedure of the test. Please clarify that 1 cycle C.3.4.3 For 279 mm (11 in) and larger blowout preventers,
is equal to 1 TJ passing through the QCA. This same reference is in 16RCD install a 127 mm (5 in) OD test mandrel with a simulated 18°
where it says 1,000 TJ in the description of the test, and 5,000cycles in the API 6 3/8-inch tool joint profile; for 228 mm (9 in) and smaller,
procedure of the test. install a 88,9 mm (3 ½ in) OD test mandrel with a simulated 18°
API 5-inch tool joint profile.
C.3.4.4 Close the preventer with the manufacturer's
recommended closing pressure. Apply 6,89 MPa (1 000 psi)
wellbore pressure. Reduce the closing pressure until the
preventer leak rate is less than 4 l/min (1 gal/min) (to wet the
test mandrel wall).
C.3.4.5 Reciprocate the test mandrel at speed of approximately
600 mm/s (2 ft/s), 1500 mm (5 ft) in each direction and at 4
cycles per min. Wellbore pressure should vary no more than ±
10 % during the stripping operation. Increase the closing
pressure, as needed, to maintain only slight lubricating leak.
Continue testing until a leak rate of a 4 l/min (1 gal/min)
develops at the manufacturer's recommended closing
pressure, or 5 000 cycles have been completed.
C.3.4.6 Document any wear on all packer elastomers.
Based on the data above one cycle is the movement of the test
mandrel 1500 mm (5ft) in one direction at 600mm/s (2ft/s).
3rd Marking The Marking requirements in section 9.1 indicates: The designation “BB” is meant for the vertical bore of
All equipment, as listed in clause 1, manufactured in accordance with this equipment. API 16A starts at 7-1/16” in the vertical bore. The
American National Standard shall be marked in accordance with the other sizes referenced, i.e. 1-13/16”, are the horizontal outlet
procedure and requirements of this clause and Table 28. Equipment shall bores and are not included in the PDC.
be stamped on the product with the product description code (PDC) or
alphanumeric code, followed by “ISO 13533” or "API 16A".
However, Table 33 — ISO equipment size designation does not include the
sizes of connections below 7-1/16” for PDC coding.
Section 9.4.2.2 include the Size designation (BB) which are the bore size of
the equipment as given in Table 33 for codification. (For example; Section
5.3.11 for 16A Adapters specifies the End connections shall meet the
requirements of 5.3.1, 5.3.2, 5.3.4, or 5.3.9)
Section 5.3.4 Hubbed end and outlet connections includes 16B and 16BX
and the designated sizes and pressure ranges are as shown in Table 6 of
the spec. which covers 1-13/16” to 21-1/4” for 16BX hubs rated 10,000 PSI.
Question:
Is this an over-interpreting the requirement?
3rd 5.8 1. If a facility designs and manufactures an annular preventer but does not Response: If the manufacturer is claiming conformance to the
manufacture the packer, are they required to perform the tests required in specification for an Annular BOP, then it must complete all of
Clause 5.8? the required testing for the assembly per Spec 16A. So the
manufacturer would need the packer installed and then test
the assembly. As a further note, Spec 16A, Section 5 is titled
“Design requirements” and Section 5.8 is titled “Design
temperature verification testing for non-metallic sealing
materials and moulded sealing Assemblies”. In other words,
this is for product validation/verification. Section 5.8.3 begins
with: “Non-metallic seals and moulded sealing assemblies in
annular blowout preventers shall be tested to verify their
ability to maintain a seal at the extremes of their temperature
classification.” It is straightforward that 5.8.3 cannot be
accomplished without a packer.
3rd 8.5.1.15.1 (8.5.1.15.1) if radiography (or UT) are performed to complete volumetric Response: No Section 8.5.1.15.1 states that, “100 % of all
& examination of welds, is Acoustic Emissions Testing still required on the pressure-containing welds shall be examined by either
8.5.1.15.4 welds as specified in 8.5.1.15.4? The way I interpret this is that if AE radiography, ultrasonic or acoustic emission methods after all
Testing is used for volumetric examination of welds instead of AE, then welding and post-weld heat treatment.” The operative word
8.5.1.15.4 applies. If the welds are inspected using RT or UT, AE is not there is “or” as long as 100% of the pressure-containing welds
required. are examined. They don’t need to do the acoustic emissions if
they do one of the other two methods Most equipment
manufacturers do not use AE at all.
3rd Sections 5 Our organization manufactures an 18-3/4” 10K ram type BOP with API 10K Response: No, The current edition of API 16A requires that a
&6 end connections. This BOP design complies with the API 16A Design material with an API Material Designation of 75K meet a
requirements of Section 5 whether it is manufactured from a 60 KSI or 75 minimum hardness of 197HBW. The document does not
KSI MSYS material specification (design validation testing was conducted provide for an exception based on design criteria.
using 60K material and is available for review). The organization purposely
chose to manufacture the pressure containing members of this BOP from a However if the material meets the exception as stated in Spec
75 KSI MSYS material specification that complies with both API 60K and 16A, Section 8.5.1.4, Paragraph 4 (Hardness measurements on
75K Material designations as they are defined in Tables 19 & 20, Section parts manufactured from carbon low alloy and martensitic
6.3.1, of API 16A, 3rd edition. If the inspected material hardness for the stainless type steels shall exhibit maximum values in
pressure containing component drops below the minimum hardness accordance with NACE MR0175 and minimum values equal to
requirement for an API 75K designation (197 HBW minimum) but above or greater than those specified in Table 24.) and the
the minimum hardness requirement for an API 60K designation (174 HBW subsequent statements, then the value as derived from the
minimum) our Engineering department accepts the deviation on the basis testing and application of the equation [API 16A, Section
that it meets both the internal and API design requirements. Does 8.5.1.4b] may be used.
acceptance of said deviation comply with the intent of API 16A Design and
Material requirements of Section 5 and 6 ?
4th Table 18 Table 18 contains a note "only one test is required for a product family of Response 1: No. Product scaling is not permitted. Sealing
functionally similar design to qualify PR1. characteristic data per 16A, Section 4.7.3.1 may be scaled in
Question 1: Is scaling allowed per product family? order to create needed data for different operator sizes, per
Tables 20 and 21. Furthermore, note (a) of Table 18 only
Quesition 2: If yes, can we say that PR1 is comparable with API 16A 3rd applies to the ram access test (4.7.3.11) for PR1 rams.
edition?
Response 2: No. See above. Furthermore, there is no
expectation that 16A (4th Edition) PR1, is meant to be the
equivalent to 16A (3rd Edition).
4th 5.3.2.2 Question: The sentences in question read "The number and location of Response: Yes. Per the API Style Guide, Table 1, equivalent
both part and environmental thermocouples (with controlling and expressions for statements of requirement that may be in a
monitoring designations) SHALL be clearly identified. Thermocouples document include (but are not limited to) the use of “is
attached to the parts SHALL be used as controlling thermocouples. A required” or any variation. The extracted wording “A
minimum of two part thermocouples are required per heat treat batch." minimum of two part thermocouples are required per heat
There are two clear SHALL statements, but the last statement that "a treat batch.” would clearly meet this criterion and therefore is
minimum of two part thermocouples are required" is not a SHALL deemed a requirement.
statement. Can you confirm the requirement for the number of
thermocouples required
4th 5.3.5.2.3 Question: In section 5.3.5.2.3, figure 9, the second to last note ends with Response: No. The ER does not equal one minus one fourth T;
"...ER = 1 - 1/4 T". All other fractions in the document are shown WITHOUT Yes. The ER equals one and one fourth T (equal to 1.25T)
the dash between unit and fraction, so it is unclear if this is a fraction or a
formula, where the dash indicates subtraction. In 3rd edition, this value
was one fourth (0.25). Is the ER equal to one minus one fourth (equal to
0.75), or is it one and one fourth (equal to 1.25)?
4th 5.3.5.2.3 Question: In 16A 3rd edition, in section 6.3.5.5, figure 8.b, there is a Response: No, the last two lines in Figure 9 are NOT notes,
statement which reads “When all internal and external surfaces during they are part of the overall Figure 9 requirements per API 16A,
heat treatment are not within 13mm (1/2 in) of the final surfaces, then ER Section 5.3.5.2.1. The items cited are statements of fact that
= 2T.” Due to the heat treating process, bolt holes and porting (which may include mathematical expressions. These are to be used along
be considered internal or external surfaces) are machined AFTER the with other applicable sections of the document:
process, which means the ER requirement becomes 2T. In 3rd edition, 1) Use of ER Method in Figure 9 per the ‘shall’ statement in
there was a further statement in section 6.3.5.2.3 which limited the API 16A, Section 5.3.5.2.1, “The dimensions of a QTC for a part
maximum QTC ER to 5 inches. In 4th edition, the limitation of the ER to 5 shall be determined using the following ER method.”
inches has been removed (section 5.3.5.2.3), yet the requirement for 2T 2) “The ER of a part shall be determined using the actual
when finished surfaces are not within ½” remains (section 5.2.5.2.3, figure dimensions…” per API 16A, Section 5.3.5.2.2, with Figure 9
9, last note). For some shapes, this requirement actually requires a QTC illustrating the basic models for determining the ER of simple
larger than the actual part (i.e., even a sacrificial forging is not sufficient to solid and hollowed parts and more complicated equipment.
meet the criteria). This presents a conflict where 5.3.5.2.3 states that “The 3) “The ER of the QTC shall be equal to or greater than…”
ER of the QTC shall be equal to or greater than the dimensions of the part per API 16A, Section 5.3.5.2.3.
it qualifies” and the statement in figure 9 that the ER = 2T which can
require a QTC greater than the part it qualifies. Per section D.3 of the API
Document Format and Style Manual, “Notes to figures shall not contain
requirements or any information considered indispensable for the use of
the document” which indicates the notes in figure 9 are
recommendations, not mandatory requirements. Is the QTC limited to a
maximum of a sacrificial part or does a mandatory requirement exist that
may cause a QTC to be larger than the part it qualifies?
4th 4.7.2.2.1 Question: Section 4.7.2.2.1, “NOTE: Test results may be used to qualify Response: No. Both must be tested. In other words, a pipe
other blind rams and other fixed bore pipe rams of different nominal pipe ram test does not qualify a blind ram. As indicated in Table 20,
sizes, …” I interpret this statement as saying that testing a fixed bore pipe blind rams must be tested for sealing characteristics, fatigue
ram of a particular pipe size will qualify other fixed bore pipe rams of and temperature. It is important to note the restrictions
different nominal pipe sizes as long as the relevant criteria is met. But I following Table 19 (bottom of page 43). For example, the
don’t see any explicit statement that says “Fixed bore pipe rams test change of any essential variable prohibits using the
qualifies blind rams”? qualification of a different product. API 16A, Section 4.5.5 lists
metallic insert design and mold design as essential variables.
4th 8.4.1 Question: I have a question regarding the new requirement for Product Response: No. Since the PR does not apply to some products,
Description Code (PDC) in API Spec 16A, 4th edition. Of the 15-digit one should enter “000” for this code for those products.
number that describes the equipment, the last three digits represent the
performance requirement code (PR-1 or PR-2). However, for equipment
such as Drilling Spools, Spacer Spools, etc. which do not undergo
performance validation testing, what PR code should be stamped; would it
be just PR1?
4th 5.3.2.2 In section 5.3.2.2, there is a requirement that “Thermocouples attached Responsoe: No. The contact thermocouple is used to monitor
to the parts shall be used as controlling thermocouples.” There is no the time during the start and stop time of the soak at
definition provided for a “controlling” thermocouple to identify what temperature. This requirement is clarified in Addendum 1
aspects it controls. In general for an oven, the oven thermocouple (October 2017).
(environmental) controls the oven temperature, thus causing confusion
what the part thermocouple is controlling. Part thermocouples are never
used to control the oven temperature because the part thermocouple lag
time would cause the oven temperature to exceed the set point
temperature and overheat. There is also a requirement that states “The
soak time shall begin once all controlling thermocouples are within +/- 14C
(+/- 25F) of the qualified temperature set point” which seems to indicate
that the “controlling” refers to the duration of the soak time only.
Question: Is the part thermocouple controlling the oven temperature?
4th 3.1.10 Question 1: Some 16A manufacturers use threaded bushings in the 16A Response 1: Yes. The definition in 3.1.10 of bolting would
equipment that make up part of a closure bolting load path. Do these include a threaded bushing.
bushings fall under the group of items defined as bolting?
Question 2: Are they subject to the same 20E/F requirements as Response 2: Yes. The BSL level is according to Table 6
summarized in Table 6?
4th 8.4.2.2 Question: Looking at API 16A 4th edition, Section 8.4 Product Description Response: No. Referring to note (e) at the bottom of Table 41,
Code (PDC), there is no option for size designation (Section 8.4.2.2) for it states "The size designation in the PDC may be replaced by
Clamps used on bore sizes less than 7-1/16”. For example, a Clamp no. 5 is the two-digit clamp number in accordance with Table 16. If the
used on 3-1/16” 10K and 4-1/16” 5K Hub connections. However, there is clamp number is used, the rated working pressure code shall
no PDC size designation for 3-1/16” and 4-1/16” bore sizes. Clamps that be replaced by the letters “CC.” For the example given
are used on bore sizes less than 7-1/16” do not need to be stamped with regarding a #5 clamp, the size designation should be "05" and
PDC? the rated working pressure code would be "CC".
4th 4.7.3.23.2 Question 1: In section 4.7.3.23.2, which covers the annular BOP packer Response 1: Yes
access test for both PR1 and PR2, it states that “The test shall be
conducted on the designated drill pipe sizes; see Table 26” and that “A PR2 Response 2: Yes.
test may use the PR1 test mandrel size.” The purpose of the packer access
test is to “undergo repeated packer changes” which has no relation to the Response 3: Yes.
particular size pipe which is being used. In table 26, for PR1 it lists a
specific size (5” for 18-3/8” BOPs) while for PR2 is says “minimum and NOTE: The maximum number of required access attempts is
maximum.” Because there is an option to test only one pipe (per PR1), it specified in 4.7.3.23.2 c) is 200 unless failure occurs sooner. As
isn’t clear if the test is also acceptable using either only minimum size pipe, specified, 180 of the 200 attempts do not involve the use of a
only maximum size pipe, switching between them or if it would require mandrel. The mandrel is only used to facilitate the pressure
two full tests (one on minimum size and one on maximum size) when NOT test on every 20th cycle. A PR2 test may use the PR1 test
using the PR1 size pipe. The test requires up to 200 times or failure. mandrel size. If this permission is followed, a 5" mandrel is
Would the test meet the criteria if it were performed up to 200 times using used for 11" BOPs and larger for both PR1 and PR2 tests. It is
only the minimum size pipe? generally understood that the size of the mandrel does not
Question 2: Would the test meet the criteria if it were performed up to affect the outcome of this test, if a rated working pressure test
200 times using only the maximum size pipe? is possible.. If the permission referenced above is not used, the
Question 3: Would the test meet the criteria if it were performed up to OEM can choose either size of mandrel listed in the PR2
200 times using a combination of the minimum and the maximum size column of Table 26 for this test.
pipe?
4th 4.7.3.11.2 Question: PR1 testing is supposed to be identical to 3rd edition testing. Response Yes. Repeating the test on a second bonnet/door is
There is confusion between the language in the protocol first paragraph not required. The section allows testing with any sealing ram.
where it refers to bonnets or doors in the plural, and the test protocol The first section in this clause is a general statement with no
where the singular is used. Are access tests that are done on a single requirements. The requirements in a) refer to a singular ram.
bonnet/door sufficient to meet the requirements of PR1?
4th 7.6.5 Question: MDB shall be furnished as per annex C recommendation, except Responsie: Yes. The OEM must deliver an MDB unless the
if Customer doesn't need it. Annex C is only informative, and states that purchaser specifies something different. Annex C provides the
the content should be. I understand that only a COC must be provided to information that the MDB must furnish.
Customer. If MDB is required by PO, we can use annex C for the content
of documents to be supplied, is it correct?
4th 8.3.3 Question: Section 8.3.3 defines how to codify non-metallic components. Response: No. "For PR1, use “G” for continuous elevated
For temperature ratings, PR1 only use low and high, while PR2 use low, temperature”, means just that, for PR1, use “G” for continuous
continuous and high. The codification requires three digits for temperature elevated temperature.
class and the second paragraph of section 8.3.3 states to use “G” to fill the
middle character for PR1 parts. Class ‘G’ per table 4 denotes ‘other’
temperature rating. The PR level is not noted in the codification, so it
makes a PR1 part indistinguishable from a PR2 part with a class ‘G’
continuous rating. The sentence that defines use of the ‘G’ character for
PR1 is neither a SHALL nor a MAY statement, so it is not clear if this is
mandatory or a recommendation. Is it permissible to use a character not
predefined in the temperature table 4 (for example, ‘X’ or ‘0’) as the
middle character for a PR1 code to differentiate PR1 from PR2 parts?
4th 4.7.3.15 Question: The purpose of this test is to determine of the main ram seals Response No. The test protocols are mandatory, as written, in
to 4.7.3.17 can control/contain pressure at the minimum rated temperature of the these sections and all require the opening and closing of the
valve. Based on that being the requirement of the test, and the fact that BOP. Use of a sub is not allowed. A small test fixture would
the BOP should be closed "up to seven times" on the cold test - which can not provide the same heatsink effect, thus the results would
be interpreted as 1 time - it would be reasonable to test these seals in not be comparable to the full-scale test. Furthermore, the
isolation from the rest of the valve (by using a suitably designed sub that effects of thermal expansion on the sealing dimensions would
simulates the forces acting on the seals/rams). The main benefit is the not be validated.
much lower footprint and mass of the test sub, therefore allowing
temperature to be achieved in a much lower time and by using much more
economical test facilities. Can the ram seals be tested outside of the main
BOP using a small representative sub, and the results used as evidence of
compliance with the standard/sections 4.7.3.15 to 4.7.3.17?
4th 4.7.3.11.2 The protocol refers to ram bonnets or doors (plural) in the initial Response: Yes
paragraph, but the actual test steps refer to accessing the ram (singular).
Need clarification as to whether both bonnets need to be opened to fulfil
the requirement of the standard. Is opening one bonnet sufficient to meet
the requirements of the standard?
4th 4.7.3.4.2b Fatigue Test Protocol: Step b) last sentence reads: the operating pressure Response: Yes
for this step shall be consistent until the minimum performance criteria
have been achieved... Need clarification on "for this step". Does "this step"
mean all the tests up through the minimum number of cycles in Table 20
and 21?
4th 4.7.2.1 4.7.3. My company makes Ram Type “U” BOPs Type that are are all basically the
same Ram BOP type design differing in flange size and working pressure
rating only.
Question 1: Does this group of one basis design constitute a “Family” Response 1: Yes
since they are all Type U and based on the same design?
Question 3: Do we only test one BOP from each family or do we test the
smallest and the largest dimensionally, regardless of working pressure Response 3: No. Table 18, note ‘a’ only allows the use of on
rating to satisfy the test requirements? test per product family for PR1 Ram Access and PR1 Ram
Locking tests.
Question 4: Conversely, do we test the lowest and the highest pressure
rating BOP’s and regardless of the dimensional size to satisfy the test
requirements? Response 4: No
Question 3: Will Ram Packer seal replacement during this 200 cycle testing
be allowed or required? Response3: Yes, it is allowed but not required.
Question 4: For the PR1 testing there is a foot note “a” that states, “For
“Ram access” and “Ram Locking”, only one test is required for the product Response 4: No response, the question is not clear
family of functionally similar design to qualify for PR1. We presume from
this that once a “Family” is determined (Ref. Your response to the question
on family . above) that one BOP will be selected to accomplish this? What
about the other PR1 test listed in Table 18 Will the same requirement that
only one of the “Family” be tested prevail for all other PR1 test in Table 18,
or will there be a different requirement and if so what will be those
requirements.
Question 5: What about the PR2 test in Table 18, will the PR1 provision for
“Only one test required for a product family of functionally similar design
be applicable to the PR2 test. Response 5: No
4th 4.7.2.1 Ref.4.7.2.1 Table 18 PR2 Minimum Performance Criteria Fatigue test Response: Yes, 52 pressure cycles is the minimum
indicates 52 pressure cycles, which contradicts Ref.4.7.3.4.2, which requirement of successful tests to achieve PR2. The fatigue test
indicates 78 pressure tests (cycles). Is 52 pressure cycles correct? protocol is to stop when a test fails or 78 pressure cycles have
been reached.
4th 4.7.2.2.1 Ref.4.7.2.2.1 Table 19 states: 5” and one size larger / equal to 10 ¾” for 18 Response: Yes, pipe sizes required to be tested for
¾” BOPs and larger, but the paragraph Ref.4.7.3.6.2, and other places in qualification are listed in Table 19 unless otherwise noted in
the standard refer only to 5” test mandrel. Is the 5” pipe test mandrel size the specified design validation test.
requirement correct for 18 ¾” BOPs and larger?
4th 4.7.2.2.1 Ref.4.7.2.2.1 Table 20 says 500ft for stripping PR2 Minimum performance Response: Yes, 500 feet is the minimum requirement to
criteria, but in 4 Ref..7.3.6.2 Protocol e) it states 10,000ft. Is the 500 ft. achieve PR2. The ram stripping test protocol is to stop when
requirement correct? the leak rate exceeds 3.8 l/min (1.0 gal/min) or an equivalent
of 3,048 m (10,000 ft) of pipe has passed through the packer
seals.
4th 6.3.7 The last paragraph in this section is very confusing: “For welds (excluding Response: Yes
overlays) made on low-alloy steels that are allowed to cool below the
minimum preheat temperature, prior to PWHT, and are made by SMAW,
SAW, or FCAW processes, after completion of welding and without
allowing the weldment to cool below the minimum preheat temperature,
the temperature of the weldment shall be raised to a temperature
between 232 °C (450 °F) and 399 °C (750 °F) for a minimum period of two
hours.”
4th 5.3.2.2 Polymer quenchants are typically water-based solutions. In section 5.3.2.2, Response: No
it has requirements for water quenching, which includes “water-based”
quenching and for “oil quenching/polymer”. Under “Oil
quenching/polymer”, it uses the phrase “oil/polymer-quenching medium”
which is unclear if it is referring to either oil or polymer quenching medium
separately or an oil-polymer mix. The requirements for the quenchant
temperatures are different. Should a water based polymer quenchant
follow the temperature requirements for 5.3.2.2.a?
4th 4.7.3.30.2.h In step ‘g’ of the low temperature drift characteristics test, it says to “Pass Response: Yes
a drift mandrel through the bore of the assembly after all pressure
testing…” and then in step ‘h’ it further clarifies that the drift must pass
“after all pressure testing is complete (e.g. after BOP operator is opened)”.
In the FAT drift test (section 7.5.7.4.2) it states the drift must pass “after
the pressure has been removed”. Does the drift test timing start when
operator closing pressure is vented?
4th 7.5.7 7.5.7 Is titled "Assembled Equipment Factory Acceptance Test (FAT)".
Section 7.5.7.7 is titled "Closed-preventer Test". This section has low and
high-pressure tests for both Ram and Annular BOP assemblies (not for
individual components) and is routinely followed by OEMs in the FATs.
Section 7.5.7.7.2 specifies the two pressure tests that are specifically for
Annular BOPs (7.5.7.7.3, .4 and .5 covers pressure tests, shearing test, and
locking device test for Ram assemblies; 7.5.7.7.8 covers pressure tests for
Hydraulic Connectors). The tests for Annular BOPs include testing in two
stages: the first stage requires sealing on a mandrel in the Annular bore,
the other has no mandrel in the bore and the annular packer must seal the
wellbore with no mandrel installed. This second stage is called Complete
Shut-Off or CSO and is only required for packers that are designed for CSO
operations. Note: prior to the 4th edition, all annular packers were
required to CSO, that is no longer required in 4th edition. Manufacturers
typically performs certain tests of the packers at the elastomer
manufacturing facility (their own facility or at a subcontractor). In addition
to the above referenced ABOP assembly FATs, all annular packers that are
sold separately (packer only, not ABOP assembly) must be tested
according to section 7.5.7.7.2 (see 7.5.5) which is typically done in the test
fixture (ABOP) at the elastomer plant.
4th 4.7.2.2.1 Table 19 provides a range of 5 and one size greater than or equal to 10 Response: No
3/4. Our product range is 9 5/8 max. Can a smaller range be qualified
between 5 and 9 5/8?
4th 3.1.63 3.1.63
3.1.64 pressure-controlling bolting
Bolting used to assemble or join pressure-controlling part(s)
3.1.64
pressure-controlling part
Part intended to control or regulate the movement of wellbore fluids
NOTE Examples include packing elements, rams, and replaceable seats
within a pressure-containing part
Question 1: Are studs or bolts within a BOP operator used to fasten parts Response 1: Yes
of a two-part piston together (a piston that operates a ram or annular
closed) pressure controlling bolting when they are not exposed do sea
water or wellbore fluids?
Question 2: Are studs or bolts within a BOP operator used to fasten a Response 2: Yes
piston to a rod, or a rod extension to another rod that connects to a BOP
ram considered pressure controlling bolting?
Question 3: Are studs or bolts that hold a ram locking device and its Response 3: Yes
housing onto a BOP operator considered pressure controlling bolting?
Question 4: Are suds or bolts that fasten parts of a locking device together
within a BOP operator considered pressure controlling bolting? Response 4: Yes
4th 7.5.7.8.5 The procedure section of the hydraulic connector testing (7.5.7.8.5) lists Response: Yes
stage one and stage two and then has a requirement for lock/unlock
cycles. The last sentence of the fourth (last) paragraph states that the
purpose of this test is to determine if any of the seals were damaged
during installation. This type of function testing would normally be
performed prior to pressure testing to ensure proper operation of the
equipment. This section does not indicate whether the lock/unlock cycles
are to be performed after stage one and stage two, or if it may be
performed at any time, including prior to the pressure testing. May the
lock and unlock cycle testing be performed at any time in the sequence of
required testing?
4th 4.7.3.14 The locking test protocol is very vague and only requires performing a low Response: No
and high-pressure test. It does not specify the need to cycle the locks or
define any other requirements. In the documentation section, it makes a
reference to the number of “locking cycles” but there is no definition or
indication what constitutes a locking cycle. The locking test is allowed to
be performed in conjunction with a fatigue test in which it is clear how to
proceed, but when done independently, there is no further guidance other
than perform low and high-pressure tests. When performing a locking
test, are the locks required to be functioned in between pressure tests?
4th Table 18 Ram BOP (Assembly) PR1 Qualification per API 16A 4th Edition. Table 18. Response: No
4.7.3.13
4.7.3.15 Ram Access: Only 1 qualification test required per Product Family. Note:
A Product Family is described in 3.1.69 – Model or Type of Specific
Equipment per Section 1 (Scope). Therefore a RAM BOP is defined as a
Product Family.
Fatigue (per 4.7.3.3) – Reportable (No minimum cycles). Note: One test
will qualify other BOPs that use the same cavity and ram geometry.
Low Temperature (per 4.7.3.15) – 3 pressure cycles. Note: One test will
qualify other BOPs that use the same cavity and ram geometry.
Extreme High Temperature (per 4.7.3.17) – 1 hour hold time (One pressure
cycle). Note: One test will qualify other BOPs that use the same cavity and
ram geometry
Providing the ram and cavity geometry rule is adhered to, in API’s opinion,
must separate qualification tests be performed on EVERY bonnet assembly
available? Ie. Standard Bonnets, Large Bore Bonnets and Large bore with
Tandem Boosters (where the only difference is piston closing Area)?