Estimate and S Curve - PRACTICE FILES (Abe Ref)
Estimate and S Curve - PRACTICE FILES (Abe Ref)
Estimate and S Curve - PRACTICE FILES (Abe Ref)
Project :
Location :
Owner :
I. GENERAL REQUIREMENTS
1.1 Mobilization and Demobilization 1 lot 20,000.00 20,000.00 20,000.00 20,000.00
1.2 Safety Productive Measures / PPE 1 lot 5,000.00 5,000.00 5,000.00 5,000.00
1.3 Tools & Equipment Support 1 lot 10,000.00 10,000.00 10,000.00 10,000.00
1.4 Temporary Facilities & Utilities 1 lot 30,000.00 30,000.00 30,000.00 30,000.00
a. Temporary Electric power and light
b. Temporary water service and distribution
c. Material Storage & Warehouseman
Sub Total @ item I 65,000.00 65,000.00
V. STRUCTURAL STEEL
5.1 16mm dia x 6mtrs RSB 521.40 kgs 40.00 20,856.00 18.00 9,385.20
5.2 12mm dia x 6mtrs RSB 1,013 kgs 40.00 40,520.00 18.00 18,234.00
5.3 10mm dia x 6mtrs RSB 777.42 kgs 40.00 31,096.80 18.00 13,993.56
5.4 G.I Wire #16 50 kgs 80.00 4,000.00 36.00 1,800.00
Sub Total @ item V 96,472.80 43,412.76
40,000.00
10,000.00
20,000.00
60,000.00
included
included
included
130,000.00
###
###
20,500.00
12,400.00
15,000.00
65,000.00
112,900.00
###
###
52,200.00
69,600.00
30,000.00
4,350.00
156,150.00
###
145,000.00
145,000.00
83,520.00
373,520.00
total
30,241.20
58,754.00
45,090.36
5,800.00
139,885.56
56,840.00
145,000.00
130,500.00
40,774.00
2,900.00
319,174.00
116,000.00
46,400.00
39,150.00
15,660.00
69,600.00
22,968.00
29,580.00
217,021.61
124,012.35
9,688.46
9,688.46
699,768.89
10,000.00
290.00
609.00
9,787.50
2,175.00
4,350.00
2,900.00
4,350.00
2,175.00
7,975.00
7,250.00
17,400.00
34,800.00
30,450.00
8,700.00
2,175.00
14,790.00
2,465.00
70,470.00
11,020.00
3,480.00
44,080.00
14,036.00
6,960.00
7,018.00
3,915.00
5,568.00
5,104.00
1,305.00
1,740.00
145.00
174.00
90,045.00
###
###
572,750.00
75,400.00
174,000.00
28,710.00
5,800.00
13,050.00
17,400.00
26,100.00
8,700.00
978.75
922,888.75
###
###
339,300.00
15,225.00
30,450.00
17,400.00
20,300.00
6,960.00
13,050.00
442,685.00
###
203,000.00
139,200.00
52,200.00
21,750.00
1,740.00
7,250.00
34,800.00
1,522.50
10,875.00
1,740.00
2,610.00
5,672.84
1,470.74
113.56
740.37
635.57
3,001.50
870.00
217.50
7,612.50
7,975.00
2,871.00
3,335.00
1,392.00
8,700.00
3,480.00
7,250.00
783.00
5,800.00
2,320.00
12,180.00
553,108.06
287,000.00
234,000.00
73,600.00
8,200.00
22,000.00
2,700.00
2,800.00
5,600.00
600.00
1,440.00
2,000.00
33,600.00
45,200.00
718,740.00
###
58,000.00
45,675.00
19,575.00
9,135.00
141,737.50
4,350.00
10,150.00
1,305.00
4,712.50
16,240.00
310,880.00
49,300.00
92,800.00
44,660.00
3,480.00
150,249.00
24,940.00
3,915.00
369,344.00
21,750.00
7,250.00
9,425.00
2,537.50
2,610.00
5,000.00
48,572.50
5,387,661.77
808,149.27
538,766.18
646,519.41
7,381,096.62
PROJECT
SCHOOL
LOCATION
SUBJECT
I General Requirements 16 178,100.00 2.28% 0.001423332746064 0.001423332746064 0.001423332746064 0.001423332746064 0.001423332746064 0.001423332746064 0.001423332746064 0.001423332746064 0.001423332746064
III. Forms and Scaffolds 12 213,925.50 2.74% 0.002279522136389 0.002279522136389 0.002279522136389 0.002279522136389 0.002279522136389 0.002279522136389 0.002279522136389 0.002279522136389 0.002279522136389
IV. Structural Concrete 5 511,722.40 6.54% 0.013086603010707 0.013086603010707 0.013086603010707 0.013086603010707 0.013086603010707
VI Masonry & Plastering Works 6 437,268.38 5.59% 0.009318785761894 0.009318785761894 0.009318785761894 0.009318785761894 0.009318785761894 0.009318785761894
VII Doors and Windows 10 958,683.39 12.26% 0.012258510546535 0.012258510546535 0.012258510546535 0.012258510546535 0.012258510546535
70.38%
VIII Electrical Works 15 123,361.65 1.58% 0.001051602027646 0.001051602027646 0.001051602027646 0.001051602027646 0.001051602027646 0.001051602027646 0.001051602027646 0.001051602027646
63.21%
IX Steel Truss 7 1,264,357.59 16.17% 0.023095873034715 0.023095873034715 0.023095873034715 0.023095873034715 0.023095873034715 0.023095873034715 0.023095873034715
53.73%
XI Plumbing Works 15 757,758.05 9.69% 0.006459543139587 0.006459543139587 0.006459543139587 0.006459543139587 0.006459543139587 0.006459543139587 0.006459543139587 0.006459543139587
36.90%
XII Painting Works 14 984,673.80 12.59% 0.008993460904671 0.008993460904671 0.008993460904671 0.008993460904671 0.008993460904671 0.008993460904671 0.008993460904671
29.10%
XIV Tile Works & Concrete Topping 6 425,905.60 5.45% 0.009076629417364 0.009076629417364
14.12%
2ND WEEK 3RD WEEK 4TH WEEK 1ST WEEK 2ND WEEK 3RD WEEK 4TH WEEK
85.16%
77.77%
0.019387324821277