Heat Exchanger Checklist
Heat Exchanger Checklist
Heat Exchanger Checklist
PROCESS DEPARTMENT
Checklist CL-PC-002
Revision 00
73. Nozzle DP shall not be greater than 20% of the exchanger Increase nozzle size to reduce
DP. the nozzle DP
74. Is tubeside pressure drop not utilized fully and tubeside • Decrease tube OD
heat transfer coefficient is controlling? • Increase tube length
• Increase tube passes
75. Velocity Constraints
Fluid Min. Max.
Cooling Water 1 m/s normal Based on MOC
Residues, Hv Oil 1 m/s turndown
Slurry oil 1.5 m/s turndown 2.3 m/s turnup
Rich amine
VIBRATION CHECKS
76. There are no vibration warning
77. Check exchanger for possible vibration in fouled
condition by blocking leakage stream
78. Unsupported tube length does not exceed TEMA span If TEMA span exceeded:
• Decrease baffle spacing and/or
cross passes
• Provide support at U bend,
floating head, Nozzle inlet &
outlet
• Use double segmental baffles
with closer baffle spacing
• Use NITW with intermediate
support plates
79. Fluid elastic instability ratio exceeded (greater than 0.8) If vibration by these possible:
or Vortex induced vibration or Turbulent buffeting • ‘E’ shell and SS baffles
vibration possible different combinations
• ‘E’ shell and SS baffles,
increased tube pitch ratio
• ‘E’ shell and DS baffles
• ‘J’ shell and SS baffles
• ‘J’ shell and DS baffles
• NTIW
• ‘X’ shell
• Rod baffles
80. Acoustic vibration should not be occurring If acoustic vibration possible:
• Change exciting frequencies
like Vortex and turbulent
buffeting by methods
mentioned above
• Add deresonating baffle
81. Shell entrance and exit velocity should not exceed If exceeded:
critical velocity • Increase height under
inlet/outlet nozzles
• Reduce tube unsupported span
at inlet
• Provide partial support plate
under nozzle
• Use J type shells
• Use NTIW design
• Try using Rod baffles
• Use annular distributor
• Check if removing
impingement would help
Aker Kvaerner CL-PC-002 Rev 00
Check List for Heat
Powergas Exchangers
Page 7 of 9
82. Bundle entrance and/or exit velocity should not exceed • Increase nozzle size
critical velocity • Reduce tube unsupported span
at inlet
• Check if removing
impingement would help
• Use divided flow shells like J
shell
83. Nozzle rho*V2 should not exceed specified limit If exceeded:
• Provide impingement plate if
exceeded
• Increase nozzle size
84. Impingement plate shall be provided for:
• vapor and two phase service
• rho*v2 > 2230 for liquid
• rho*v2 > 740 for saturated liquid
85. Check for possible problems due to presence of
impingement plate
86. Sliding strip near the inlet / outlet nozzles affect the
shell and bundle inlet rho*V2.
OPERATIONAL CHECKS
87. Check calculated tube side pressure drop for fouled Tube side fouling layer
condition when the leakage stream are blocked and there is thickness (mm)
certain fouling layer thickness δ t = 134 * R ft (Rft,
•
tube side fouling factor in
m2*hr*C/kcal)
OR
Based on HTRI fouling layer
thickness curves
88. Also check shellside pressure drop and heat exchanger Shell side fouling layer
performance by: thickness (mm)
• Block A stream option in HTRI δ s = 268 * R fs (Rfs, shell
• Block F stream option in HTRI
• Block E stream option in HTRI side fouling factor in
m2*hr*C/kcal)
And specifying the fouling layer thickness OR
Based on HTRI fouling layer
thickness curves
89. Check effect of overdesign on exchanger performance
during start-up with zero fouling resistance and in
SIMULATION mode. Inform Project Lead Engineer
about possible temperatures rises, especially for column
feed/bottom exchangers and reactor feed/outlet
exchangers.
90. For exchangers with steam condensing, there is a
possibility that steam may condense under vacuum when
exchanger is clean (especially when the design is fouling
factor controlled). In such situation a pumping steam trap
may need to be considered.
To Vessels
91. HTRI tube layout
92. Final results
93. Design Pressure (10/13, utility, steam out)
Design temperature (Based on Max. op. temp.)
MOC of exchanger
Corrosion Allowance
NACE, IBR, HIC
Aker Kvaerner CL-PC-002 Rev 00
Check List for Heat
Powergas Exchangers
Page 8 of 9
Stacking details
Mean metal temperature
Cyclic duty if applicable
Cathodic protection for exchanger
Alt. design condition steam-out, chemical cleaning etc.
Final Actions