Silo Executive Summary (REV 1.0 - Nov 26, 2020)

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Department: Engineering (Planning)

Project: Proposed Twelve Unit Silo Foundation


Location: Lumangog, Ubay, Bohol
Client: Alturas Group of Companies
Date: 26-Nov-20

EXECUTIVE SUMMARY/REV 1.0

Contract Milestone
Planned % Remarks
Planned Start Date 15-Aug-20 Elapsed Days 103

Planned Finish Date 19-Sep-21 Remaining Days 297

Revised Completion Date Calendar Days 400


Scope % wt Planned % Planned Value Actual % Actual Value

GENERAL REQUIREMENTS 2.90% 6.89% 0.20% 10.00% 0.29%

SILO ONE 8.09% 7.27% 0.59% 30.22% 2.45%

SILO TWO 8.09% 4.03% 0.33% 26.32% 2.13%

SILO THREE 8.09% 1.98% 0.16% 25.52% 2.06%

SILO FOUR 8.09% 1.85% 0.15% 25.06% 2.03%

SILO FIVE 8.09% 4.71% 0.38% 24.18% 1.96%

SILO SIX 8.09% 1.88% 0.15% 20.21% 1.64%

SILO SEVEN 8.09% 6.97% 0.56% 27.04% 2.19%

SILO EIGHT 8.09% 6.25% 0.51% 27.68% 2.24%

SILO NINE 8.09% 2.03% 0.16% 25.43% 2.06%

SILO TEN 8.09% 2.03% 0.16% 24.55% 1.99%

SILO ELEVEN 8.09% 1.87% 0.15% 24.31% 1.97%

SILO TWELVE 8.09% 1.87% 0.15% 20.21% 1.64%


Total 100.00% 3.66% 24.62%

Issues and Reminders Variance: 20.97%


1. Steel forms expected to arrive at Dec 6, 2020

Prepared by: Checked by:

Rogemie Cherrehan Tano Hermie Gigtenta


MCBI - Planner MCBI - Project in Charge

Approved by: Noted by:

Urbano Curit Mario Tancinco


MCBI - Project Manager MCBI - Operations Manager