ASSET BUILDERS CORPORATION v. STRONGHOLD INSURANCE COMPANY, INC.
ASSET BUILDERS CORPORATION v. STRONGHOLD INSURANCE COMPANY, INC.
ASSET BUILDERS CORPORATION v. STRONGHOLD INSURANCE COMPANY, INC.
FACTS:
Article 1217 of the New Civil Code acknowledges the right of reimbursement from a co-debtor
(the principal co-debtor, in case of suretyship) in favor of the one who paid (the surety).
(Lucky Star) as part of the completion of its project to construct the ACG Commercial On April
28, 2006, Asset Builders Corporation (ABC) entered into an agreement with Lucky Star Drilling
& Construction Corporation Complex 3 Lucky Star was to supply labor, materials, tools, and
equipment including technical supervision to drill one (1) exploratory production well on the
project site. The total contract price for the said project was P1,150,000.00. To guarantee faithful
compliance with their agreement, Lucky Star engaged respondent Stronghold which issued two
(2) bonds in favor of petitioner. The first, SURETY BOND G(16) No. 141558, dated May 9,
2006, covers the sum of P575,000.004 or the required downpayment for the drilling work. On
May 20, 2006, ABC paid Lucky Star P575,000.00 (with 2% withholding tax) as advance
payment, representing 50% of the contract price. Lucky Star, thereafter, commenced the drilling
work. By July 18, 2006, just a few days before the agreed completion date of 60 calendar days,
Lucky Star managed to accomplish only ten (10) % of the drilling work. On the same date,
petitioner sent a demand letter to Lucky Star for the immediate completion of the drilling work
with a threat to cancel the agreement and forfeit the bonds should it still fail to complete said
project within the agreed period.
On August 3, 2006, ABC sent a Notice of Rescission of Contract with Demand for Damages to
Lucky Star
RULING: Suretyship, in essence, contains two types of relationship – the principal relationship
between the obligee (petitioner) and the obligor (Lucky Star), and the accessory surety
relationship between the principal (Lucky Star) and the surety (respondent). In this arrangement,
the obligee accepts the surety’s solidary undertaking to pay if the obligor does not pay. Such
acceptance, however, does not change in any material way the obligee’s relationship with the
principal obligor. Neither does it make the surety an active party to the principal obligee-obligor
relationship. Thus, the acceptance does not give the surety the right to intervene in the principal
contract. The surety’s role arises only upon the obligor’s default, at which time, it can be directly
held liable by the obligee for payment as a solidary obligor.
In the case at bench, when Lucky Star failed to finish the drilling work within the agreed
time frame despite petitioner’s demand for completion, it was already in delay. Due to this
default, Lucky Star’s liability attached and, as a necessary consequence, respondent’s liability
under the surety agreement arose. In fine, respondent should be answerable to petitioner on
account of Lucky Star’s non-performance of its obligation as guaranteed by the performance
bond.