Project Plan For HPCL Visakh Refinery Modernization Project

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Project Plan for HPCL Visakh Refinery Modernization Project

Number
#Sr No. List of Activity Task Owner Responsibility Dependency Remarks
of days

ETAP Model ID ,Substation name and Modelling of


equipments MM, CT, PT and Relay for remaining 6 ETAP Rajkumar
substations

SLE and tag parameters should be checked for Source/


ETAP Rajkumar
Incomer & Load /Outgoing for remaining 6 substations
11

Select unit(MV/kV) for MM at Source/Incomer &


ETAP Rajkumar
Load/Outgoing for remaining 6 substations

Create composite network and fit to page for the


ETAP Rajkumar
remaining 6 Substations
1 Engneering Activity
Interconnectivity of remaining 6 sub stations with
ETAP Vasu 4
Complete ETAP Model (Meter ,CT ,PT , CB-ID ) Testing
1. ETAP has completed the FAT
for sub station N. 82 on 24th
Prepare tag address excel sheet as per the Kepware tag
Rajkumar/vasu Activity will start once Emerson - Nov 2020.
addressing path for Analog Signals & Digital Signals for ETAP 15
/Siddhanth SCADA system is ready
remaining 17 sub stations.
2. No Engineering Activity is
pending for sub station.
Addressing of Tags from excel sheet to SI Database for
Activity will start once Emerson -
Analog Signals (MW, MVAR, Amp,Volt & HZ) & Digital ETAP Rajkumar/Siddhanth 35
SCADA system is ready
Signals for remaining 17 sub stations.
Activity will start once Emerson -
2 Commissioning Activity Console and Server Setup Setup as per the architecture ETAP Rajkumar /Vasu 2
SCADA system is ready
LF,SC,RA,CA,RC and Motor Starting - application Testing
including troubleshooting ETAP Gnanasekar/Vasu 10

Load Flow Result Testing


ETAP Gnanasekar/Vasu
3 Internal Testing Real Time communication testing Gnanasekar/vasu 5
ETAP
/Rajkumar
Software Internal Testing ETAP Rajkumar/vasu
P to P testing ETAP+ Emerson/HPCL Rajkumar /Vasu 10 After SAT Document Approval
1. Based on Number of sub stations
Test plans and
4 Integrated SAT ETAP + Emerson/HPCL Gnanasekar/Sushil required for SAT
procedures
2. SAT document approval
ETAP Training on Real Time Predictive Simulation ETAP Siddanth After SAT & Training Document
5 Training Documents 5
Training Document ETAP Siddanth Approval

6 System Handover System Handover along with User Manual Emerson/HPCL Atul Dwivedi