CALIBRATION OF HM Plant

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 3

PN-40

Improvement to Phaltan, Pusegon , Aundh ,Gopuj , Nimsod ,Mhasurne ,Road SH- 147 KM 0+000 to 89+000 Dist Satara (Part-2 Pusegon to Mhasurne KM
47+000 to 92+670 ) Under Maharashtra Road Improvement Programme -MRIP Under Hybrid Mode

Client Maharashtra PWD

Independent Engineer Unison Consultant-Pune

EPC Contractor Raj path Infracon Pvt. Ltd.

CALIBRATION OF HOT MIX PLANT


Type of Plant : BATCH MIX PLANT Date of Calibration : 15-07-2019

Capacity of Plant : 160 TPH Calibrated by : JOINTLY

Batch Capacity : 1.6 TONNE Next due date of Calibration : 14-01-2020

Location : Base camp Rajpath Infracon Pvt Ltd site

Aggregate Weigher
Display(kg)
Difference in weight
Applied load(kg) Trial -1 Trial -2 Variation (%) Remarks
Average (kg)
Loading Unloading Loading Unloading
0 0 0 0 0 0 0.0 0.00

20 20 20 20 20 20 0.0 0.00

40 40 40 40 40 40 0.0 0.00

60 60 60 60 60 60 0.0 0.00

80 80 80 80 80 80 0.0 0.00

100 100 100 100 100 100 0.0 0.00

120 120 120 120 120 120 0.0 0.00

140 140 140 140 140 140 0.0 0.00

160 160 160 160 160 160 0.0 0.00

180 180 180 180 180 180 0.0 0.00

200 201 201 201 201 201 1.0 0.50

220 220 220 220 220 220 0.0 0.00

240 241 241 241 241 241 1.0 0.42

260 261 261 261 261 261 1.0 0.38

280 281 281 281 281 281 1.0 0.36

300 301 301 301 301 301 1.0 0.33

320 321 321 321 321 321 1.0 0.31

340 341 341 341 341 341 1.0 0.29

360 361 361 361 361 361 1.0 0.28

380 381 381 381 381 381 1.0 0.26

400 401 401 401 401 401 1.0 0.25

Page 1 of 3
PN-40
Improvement to Phaltan, Pusegon , Aundh ,Gopuj , Nimsod ,Mhasurne ,Road SH- 147 KM 0+000 to 89+000 Dist Satara (Part-2 Pusegon to Mhasurne KM
47+000 to 92+670 ) Under Maharashtra Road Improvement Programme -MRIP Under Hybrid Mode

Client Maharashtra PWD

Independent Engineer Unison Consultant-Pune

EPC Contractor Raj path Infracon Pvt. Ltd.

CALIBRATION OF HOT MIX PLANT


Type of Plant : BATCH MIX PLANT Date of Calibration : 15-07-2019

Capacity of Plant : 160 TPH Calibrated by : JOINTLY

Batch Capacity : 1.6 TONNE Next due date of Calibration : 14-01-2020

Location : Base camp Rajpath Infracon Pvt Ltd site

Aggregate Weigher
Display(kg)
Difference in weight
Applied load(kg) Trial -1 Trial -2 Variation (%) Remarks
Average (kg)
Loading Unloading Loading Unloading
420 421 421 421 421 421 1.0 0.24

440 441 441 441 441 441 1.0 0.23

460 462 462 462 462 462 2.0 0.43

480 482 482 482 482 482 2.0 0.42

500 502 502 502 502 502 2.0 0.40

520 523 523 523 523 523 3.0 0.58

540 545 545 545 545 545 5.0 0.93

560 565 565 565 565 565 5.0 0.89

580 585 585 585 585 585 5.0 0.86

600 605 605 605 605 605 5.0 0.83

620 624 624 624 624 624 4.0 0.65

640 645 645 645 645 645 5.0 0.78

660 665 665 665 665 665 5.0 0.76

680 685 685 685 685 685 5.0 0.74

700 705 705 705 705 705 5.0 0.71

720 726 726 726 726 726 6.0 0.83

740 743 743 743 743 743 3.0 0.41

760 764 764 764 764 764 4.0 0.53

780 784 784 784 784 784 4.0 0.51

800 804 804 804 804 804 4.0 0.50

820 824 824 824 824 824 4.0 0.49

840 844 844 844 844 844 4.0 0.48

860 864 864 864 864 864 4.0 0.47

880 884 884 884 884 884 4.0 0.45

900 904 904 904 904 904 4.0 0.44

Maximum Difference (Kg) 6.00


Aggregate Load Cell Variation = = 0.67
Maximum Applied load (Kg) 900.00

For EPC Contractor: For Independent Engineer:

Name: Name:

Designation: Designation:

Date: Date:

Page 2 of 3
Improvement s to Phaltan , Pusegon Aundh , Gopuj Nimsod Mhasurne ,Road SH-147 KM 0+000 to 89+000 Dist Satara (Part-2 Pusegon to Mhasurne KM
PN-40
47+000 to 92+670 ) Under Maharashtra Road Improvement Programme -MRIP Under Hybrid Annuity Mode

Client Maharashtra PWD

Independent Engineer Unison Consultant-Pune

EPC Contractor Raj path Infracon Pvt. Ltd.

CALIBRATION OF HOT MIX PLANT

Type of Plant : BATCH MIX PLANT Date of Calibration : 15-07-2019

Capacity of Plant : 160 TPH Calibrated by : JOINTLY

Batch Capacity : 1.6 TONNE Next due date of Calibration : 14-01-2020

Make of Plant Korian Location: Base Camp Rajpath Infracon Pvt Ltd site

Bitumen Weigher
Display(kg)

Difference in
Applied load(kg) Trial -1 Trial -2 Trial -3 Error (%) Remarks
weight (kg)
Average
Loading Unloading Loading Unloading Loading Unloading

0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

20 20 20 20 20 20 20 20.0 0.0 0.00

40 40 40 40 40 40 40 40.0 0.0 0.00

60 60 60 60 60 60 60 60.0 0.0 0.00

80 80 80 80 80 80 80 80.0 0.0 0.00

100 100 100 100 100 100 100 100.0 0.0 0.00

120 120 120 120 120 120 120 120.0 0.0 0.00

140 140 140 140 140 140 140 140.0 0.0 0.00

160 160 160 160 160 160 160 160.0 0.0 0.00

Maximum Difference (Kg) 0.00


Bitumen Load Cell Variation = = = 0.00
Maximum Applied load (Kg) 160.00

Filler Weigher
Display(kg)

Difference in
Applied load(kg) Trial -1 Trial -2 Trial -3 Error (%) Remarks
weight (kg)
Average
Loading Unloading Loading Unloading Loading Unloading

0 0 0 0 0 0 0 0.0 0.00 0.00

20 20 20 20 20 20 20 20.0 0.00 0.00

40 40 40 40 40 40 40 40.0 0.00 0.00

60 60 60 60 60 60 60 60.0 0.00 0.00

80 80 80 80 80 80 80 80.0 0.00 0.00

100 100 100 100 100 100 100 100.0 0.00 0.00

120 120 120 120 120 120 120 120.0 0.00 0.00

Maximum Difference (Kg) 0.00


Filler Load Cell Variation = = = 0.00
Maximum Applied load (Kg) 50.00

For EPC Contractor: For Independent Engineer


Name: Name
Designation: Designation
Date: Date

Page 3 of 3