Conduct Loop Check
Conduct Loop Check
The Loop checking is defined as pre-Commissioning activity which is initiated after installat
ion of instruments in the field and carry out the instrument loop checks between installed fi
eld instrument and respective control system i.e. PLC or DCS.
checking is the final process before the commissioning of the processing system. Loop ch
ecking is the process that confirms the components wired correctly and also helps to ensur
e that the system is functioning as designed.The loop checking checks the connection bet
ween each component in the control loop. A control loop consists of transmitter/sensor, pr
ocess controller, final control element.Before start, the loop check include, first list the num
ber of loops, test actions, the procedure for documenting the check and plan should specify
the type and characterization of signal. For example, differential flow meter generates a si
gnal that has a square root relationship between flow rate and differential pressure.
The resistance from any point of the electric installation should be earthed. The resistance
from the earthing electrode to the point where the main earthing conductor is connected to
the neutral conductor of the supply system shall not exceed 5 ohms.
Connect the short lead to the earth electrode and measure the earth resistance of the main
earthing conductor
The resistance shall not exceed 5 ohms for the main earthing conductor
Earth continuity test:
Using the long lead and zeroed meter, measure for each circuit, the earth conductor resista
nce from the circuit extremity to the switchboard.
To confirm the measured values are less than those values as provided by table
This test is applicable to all circuits, including socket outlets circuit, lighting circuits and fix
ed equipment circuits.
Insulation resistance test:
The insulation resistance tests to ensure there is no current flow between conductor and gr
ound or insulation surface. If there is no current flow the wire could prevent electric shock h
azards, fire hazards and equipment damage.
Test procedure:
Test procedure:
Isolate the active conductors by turning the main switch OFF and tagging
Confirm the consumer and sub main cables by simply testing from the point of distribution
board to the main switch board using an ohm meter and long test loads. Test result= 0 oh
ms
Confirm the switching of the active conductors using an ohm meter with the long cable con
nected to the active conductor on the board and the short wire connected to the terminals
of the switch as follows
Switch ON = 0Ώ for both terminals, Switch OFF = 0Ώ for one terminal and infinite for the oth
er terminal.
With the MEN link in place, confirm the polarity of the sockets using a 10Ώ resistor and an o
hm meter. Connect the 10Ώ resistor between the active circuit conductor and the neutral bu
s, then connect the multimeter cable to the ground terminal and the second cable to the act
ive terminal. Test the resistance value for.
Fault loop impedance test:
This test is performed to confirm that the impedance value of the fault loop of each circuit
will be low enough to guarantee the operation of the protection device during a fault.
Test procedure
Loop Check :
An operational check of the field, controller and HMI elements of a control loop. A Loop Ch
eck is intended to ensure the integrity of the following.
The field sensing device is properly installed in accordance with engineering specifications.
The field sensing device is properly connected to it’s communication path to the Distributiv
e Control System Controller. (e.g. Current Loop, Multiple device Bus Communication Protoc
ol, etc.)
The field sensing device develops and transmits a proper analogous signal in response to a
variable impressed upon it or a simulation command issued to it.
The corresponding logic in the DCS Controller is ranged accordingly for the field sensing de
vice analog and engineering units.
The HMI of the DCS Controller accurately displays the engineering unit response to the sign
al of the field sensing device.
Alarm points are properly entered into the logic of the DCS Controller and the HMI displays
and logs these appropriately as they are reached.
Where control functionality is required, that the signal from the field sensing device is recei
ved by the control algorithm and generates the appropriate corrective output signal.
If present, the field control device, (e.g. Control Valve, Variable Speed Control etc.), is prope
rly installed in accordance with engineering specifications.
The field control device is calibrated in accordance with engineering specifications.
The field sensing device is properly connected to it’s communication path to the Distributiv
e Control System Controller. (e.g. Current Loop, Multiple device Bus Communication Protoc
ol, etc.
The Field control device responds appropriately to the corrective signal received from the D
CS Controller and that this action is appropriate to the desire process variable.
Where specified, the response action of the valve is correctly transmitted to the DCS Contro
ller and displayed on the HMI.
SUMMARY
The Loop Check is intended to locate and identify deficiencies in the Field/Controller/HMI i
nterface. This includes, but is not limited to, wiring and cabling issues, engineering issues a
nd mechanical installation issues.
It is not the focus of the Loop Check to correct any deficiencies found. Full information con
cerning the deficiency is captured and passed on to the appropriate parties for correction.
Minor corrections can be accepted, but this should be limited in scope.
Procedure:
A list of Loops is collected and identified by Tag Number.
Loops are grouped by Location, Availability, System, Equipment or other criteria. (Note: Loc
ational Grouping of Loops results in the most efficient execution of Loop Check.
The field team can be routed in a logical geographical progression of one device to another
adjacent device without time loss for accessing different floors, buildings, plant sections et
c.
Loop availability can prevent this. If at all possible, Loop availability should be planned to ac
commodate Locational Grouping)
Each Loop Folder is populated with either a comprehensive Loop Sheet, and/or individual el
ements, consisting of the following
Action
Field Device Accessory List (e.g. Transmitter 3 Valve manifold, Valve Pneumatic Latch etc.)
DCS Parameters
Ranges
Alarm points
DCS HMI Graphics assignments
From the Pending Loops file, the Console Engineer and the Field Technician draw the Loop
Folders to be checked in that time period.
The Console Engineer (or Operator) and the Field Technician review the contents of each L
oop Folder in the group to be checked, comparing parameters for parity and completeness
of data.
The Console Engineer prepares his record keeping tool, tracker, for the loops to be checked
in the agreed upon sequence.
The Field Technician evaluates the test equipment to be used, collects same and proceeds
to the first device to be checked.
The Field Technician communicates to the Console Engineer the Tag of the device he is at
Transmitters
The Field Technician reviews the installation and process connections to ensure they are in
accordance with the specification details and good installation practice.
Either by impressed signal, (“Pump Up”) or Communicator command, the Field Technician
drives the transmitter output signal through it’s range. Slowing at Alarm Points so the Cons
ole Engineer can confirm alarm action.
(NOTE: Common is a 0% 25% 50% 75% 100% Check. This was originally necessary to confir
m the linearity of earlier Pneumatic and ElectroMechanical devices, it no longer is as critical
and becomes a matter of agreed upon preference.)
The Field Technician confirms the process connection line up is as desired. (e.g. For a Diffe
rential Flow Transmitter to be placed in service after check out, the three valve manifold wo
uld have the balance closed and the process ports open)
Control Loops
While the transmitter signal impression is occurring, the Console Engineer will call up the C
ontrol Algorithm faceplate and by placing the control mode (PID Controller) to Auto, determ
ine that the output action is appropriate.
Control Valves
The Field Technician reviews the installation to ensure it is in accordance with the specifica
tion details and good installation practice.
If pneumatic, the Field Technician opens the air source checking for proper pressure adjust
ment and air quality.
The Console Engineer adjusts the output signal to the valve while the Field Technician obse
rves the action of the valve.
Jointly, the Field Technician and the Console Engineer determine if the resultant action is a
ppropriate for the control signal sent and the previously determined action of the control al
gorithm.
Where present, the Console Engineer observes any feedback from the valve to be in agree
ment with the reported position of the valve action by the Field Technician.
Either by Signal Impression, manual toggling, or conductor manipulation, the Field Technici
an causes a change in state of the field device signal.a
The Console Engineer observes the indication of the signal to be in agreement with the phy
sical state as impressed on the device by the Field Technician.
The Console Engineer records the results of the results of the signal impression, alarm poin
ts, ranges, valve actions, etc.
If no deficiencies were noted during the Loop Check, the Loop Folder is placed in the Compl
eted Loops File. At this point, the client signs for the Loop as being complete.?ll
The resolution team draws Kick Back forms from the Active Kick Back file.
Each time the deficiency is addressed, the Kick Back form is submitted to the Console Engi
neer.
Date
Resolving Party
Thorough description of the corrective actions taken
Recommendations for further actions
Responsible party assigned to further actions
When the deficiency is corrected, the Kick Back form is submitted to the Console Engineer.
Date
Loop checking procedure of Instruments
This article is about the loop checking procedure of all instruments like flow transmitter, va
lves, vibration, DCS loop, switchgear loop and ramaining pressure and level types instrumen
ts.
HART Communicator
Dead Weight Tester
Air Compressor
MC5 FF Multifunction Calibratorll
Test Gauges with Ranges per Specification
Absolute Pressure Gauge
Portable 120Vac, 60Hz Gasoline Powered Generator
Pulse/Frequency Generator
DC Power Supply Regulated 24Vdc Variable
Nitrogen Tank w/ High Pressure Regulator
Thermo Bath
Hydrostatic Test Pump
Set of Precision Weights
Digital Thermometer
Glass Thermometer
Potentiometer
Portable Pressure Calibrator (DRUCK)
Process Calibrator
Advanced Temperature Calibrator
RTD Conversion Chart
Circuit Tester
Decade Resistance Box
Digital Manometer (Mercury or Water Manometer)
Mercury and Water Manometer
Hand Pump
Hygrometer (Humidity Tester)
Air Regulator
Pneumatic Comparator
Vacuum Pump
Oscilloscope
Radio Communication Equipment (intrinsically safe as per approved)
Multi meter
Test Bench with clean, dry and oil free instrument air
Set of Tools, Hose & Fittings
Stop Watch
Millivolt/Temperature conversion chart
TK-3 (for checking of vibration element)
Spirit Level
BEAMEX MC5 Calibrator
Others,if any
All tools utilized in a classified area should be intrinsically safe and suitable for hazardous
areas.Resolving Party
Thorough description of the corrective actions taken
iii. If any ESD logic / interlocking are involved in applicable loop, then first normal conditio
n should be prepared by forcing the applicable ESD points on ladder on logic and sam
e procedure to be carried out for DCS logic.
Share this:
Share
Like this:
Tags:Instrumentation Calibration
Reference
Introduction to instrument third edition
The purpose of this document is to assure that all the control loops installed by the contrac
tors are operational and within applicable standards and manufacturer’s tolerances and tha
t systems are installed in accordance with design specifications.
With this method cost and time will be minimized and safety integrity will be maintained.
Loop Checking – is defined as the checking for correct operation of all instrument systems
and loops and the preparation of all instrumentation for commissioning. This includes the o
peration of equipment by means of the plant wide Distributed Control System (DCS), ESD, F
GS and correct operation of the associated graphics on the Man Machine Interface (MMI).
Loop/Function test is divided by a two-group operation. One group to be in the field (Field T
echnician) and the other group to be positioned in the control room or front of local panel
(Operator Station Technician).
TYPES OF LOOPS
There are two types of loops are in the field of instrumentation.
1.Open loop: It has no feed back.
2.Close loop :It has feed back.
In instrumentation a Close loop is consist of 3 basic Parts.
1.Input device (pressure ,level ,flow ,temperature transmitters)
2.Output device (Control valve)
3.Controller (DCS, PLC , etc.)
To minimize overlaps and duplicate efforts, it is very important that the loop check team be
prepared and are aware of their responsibilities
GENERAL REQUIREMENTS
Loop shall be termed ready for testing when all the construction punch list items have bee
n satisfactory closed out.
Factory Acceptance Test (FAT) of DCS, ESD, FGS Systems and all other control panels as
sociated with mechanical and other packages have been successfully concluded.
The appropriate pre-installation instrument calibration/testing has been completed, recor
ded on the Instrument Calibration Record and witnessed/accepted by Owner Representativ
e.
All punch items are completed. All required documentation drawings are assembled withi
n each package.
Loop checking shall be witnessed by QC Group in accordance with approved ITP.
The components within the loop have been installed in accordance with process piping, ins
trument air piping, mounting details and Instrument drawings. All cabling and wiring has be
en installed, tested and labeled, recorded on the Cable Test Report and witnessed/accepted
by Owner Representative.
Digital Multimeter
Current / Voltage Standard Source Instruments
Decade Resistor Box/Millivolt Generator
HART Communicator
Screw driver sets
Allen wrench set
Portable Pressure Calibrator
Hand Pump
Temperature Calibrator
Other Relevant Tools
Test equipments must be calibrated and performing in rated accuracy.
All parties involved in this activity must be familiar with applicable safety practice.
Wearing appropriate PPE’s and use of proper tools in opening the instrument terminals bo
xes must be maintained.
Safety belts will be required in some other areas where the instruments are mounted on hi
gh elevations.
Observed proper polarity connections for electronic instruments and any other instrument
s requiring separate supply.
COMMUNICATION REQUIREMENTS
During early commissioning or pre commissioning activities like flushing and blowing it mu
st be ensured that the (operational) commissioning crew is fully equipped with means of co
mmunication.
PROCEDURE
Verify the feruling (tag) of the wiring on field device, Field junction box, Marshalling panel/
rack and DCS cabinet.
Verify the Tag of Instrument on Operator Console.
Verify the Power requirement of the instrument are correctly configured for the device un
der test.
Verify correct cable termination at both DCS termination points and Device under test.
Verify that HOOK-UP installation has been correct.
Test the wiring termination by doing cold wire test or continuity test end to end from Field
device until Marshalling Panel.
Apply Input Signal through Hand Pump to High Side of Transmitter with 0%,50% and 100%
for Raising or Falling and observe reading on DCS Console.
OR
Verify the ferruling (tag) of the wiring on field device, Field junction box, Marshalling panel
/rack and DCS cabinet.
Verify the Tag of Instrument on Operator Console.
Verify the Power requirement of the instrument are correctly configured for the device un
der test.
Verify correct cable termination at both DCS termination points and Device under test.
Verify that HOOK-UP installation has been correct.
Test the wiring termination by doing cold wire test or continuity test end to end from Field
device until Marshalling Panel.
Check Switch by simulating the signal by actuating the Switch “ON” and “OFF” by hand or
put jumper at switch terminal head.
Check DCS alarms etc. Actuate the switching action and check all the related system suc
h as alarms,trip signal, indicating lamp etc.
SIMPLE LOOP
loop test
loop checking
FLOW LOOP
FLOW LOOP
Verify the ferruling (tag) of the wiring on field device, Field junction box, Marshalling panel
/rack and DCS cabinet.
Verify the Tag of Instrument on Operator Console.
Verify the Power requirement of the instrument are correctly configured for the device un
der test.
Verify correct cable termination at both DCS termination points and Device under test.
Verify that HOOK-UP installation has been correct.
Test the wiring termination by doing cold wire test or continuity test end to end from Field
device until Marshalling Panel.
Apply Input Signal through Hand Pump to High Side of Transmitter with 0%,50% and 100%
for Raising or Falling and observe reading on DCS Console.
Perform simulation using 0%,50%,and 100% of full scale and verify the indication on the D
CS Console and local indicator if provided.
In case of flow loop is having control output element, manually set the output to 0%, 25%,
75% and 100% of the operating signal in the HMI. Check for the valve stroke and tight closin
g of control valve. Check the fail-safe position of the valve after completing the test by rem
oving the air supply to the valve.
PRESSURE LOOP
PRESSURE LOOP
Verify the ferruling (tag) of the wiring on field device, Field junction box, Marshalling panel
/rack and DCS cabinet.
Verify the Tag of Instrument on Operator Console.
Verify the Power requirement of the instrument are correctly configured for the device un
der test.
Verify correct cable termination at both DCS termination points and Device under test.
Verify that HOOK-UP installation has been correct.
Test the wiring termination by doing cold wire test or continuity test end to end from Field
device until Marshalling Panel.
Apply Input Signal through Hand Pump to High Side of Transmitter with 0%,50% and 100%
for Raising or Falling and observe reading on DCS Console.
Perform simulation using 0%, 50%, and 100% of full scale and verify the indication on the
DCS Console and local indicator if provided.
In case of flow loop is having control output element, manually set the output to 0%, 25%,
75% and 100% of the operating signal in the HMI. Check for the valve stroke and tight closin
g of control valve. Check the fail-safe position of the valve after completing the test by rem
oving the air supply to the valve.
LEVEL LOOP
LEVEL LOOP
Verify the ferruling (tag) of the wiring on field device, Field junction box, Marshalling panel
/rack and DCS cabinet.
Verify the Tag of Instrument on Operator Console.
Verify the Power requirement of the instrument are correctly configured for the device un
der test.
Verify correct cable termination at both DCS termination points and Device under test.
Verify that HOOK-UP installation has been correct.
Test the wiring termination by doing cold wire test or continuity test end to end from Field
device until Marshalling Panel.
Apply Input Signal through Hand Pump to High Side of Transmitter with 0%,50% and 100%
for Raising or Falling and observe reading on DCS Console.
Perform simulation using 0%, 50%, and 100% of full scale and verify the indication on the
DCS Console and local indicator if provided.
In case of flow loop is having control output element, manually set the output to 0%, 25%,
75% and 100% of the operating signal in the HMI. Check for the valve stroke and tight closin
g of control valve. Check the fail-safe position of the valve after completing the test by rem
oving the air supply to the valve.
TEMPERATURE LOOP
TEMPERATURE LOOP
Verify the ferruling (tag) of the wiring on field device, Field junction box, Marshalling panel
/rack and DCS cabinet.
Verify the Tag of Instrument on Operator Console.
Verify the Power requirement of the instrument are correctly configured for the device un
der test.
Verify correct cable termination at both DCS termination points and Device under test.
Verify that HOOK-UP installation has been correct.
Test the wiring termination by doing cold wire test or continuity test end to end from Field
device until Marshalling Panel.
For thermocouple input, use a voltage source and deliver input signals corresponding to
0%, 50%, and 100% of the input span of temperature transmitter according to the standard t
able. While in RTD input, connect the decade resistor box in place of RTD and obtain the res
istance values corresponding to 0%, 25%, 50%, 75% and 100% of the span and use the obtai
ned resistance as the input value.
Verify the indication in the DCS indicator and local indicator if provided.
In case of temperature loop is having control output element, manually set the output to
0%, 25%, 75% and 100% of the operating signal in the HMI. Check for the valve stroke and ti
ght closing of control valve. Check the fail-safe position of the valve after completing the te
st by removing the air supply to the valve.
Reassemble the temperature element to the original position
Share this:
Share
Like this:
Visual and Technical Checking of Instrumentation and Control System
This article defines the minimum requirements for initial inspection, loop check, and commi
ssioning of control systems during new plant construction, as well as those inspections, lo
op checks, and commissioning that might be necessary following major revisions/modifica
tions or repair. This document outlines specific steps that need to be taken in the…
Tags:Instrumentation Articles
SHOW COMMENTS
Subscribe Youtube Channel
paktechpoint subscribe