2sty 4CL Esperanza Is
2sty 4CL Esperanza Is
2sty 4CL Esperanza Is
Submitted by:
JONATHAN B. RAMOS
Engineer II
Chief, Planning and Design Section
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
PANGASINAN 3RD
DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE I
Tumana, Rosales, Pangasinan
D.O. No. 05 , Series of 2016
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan
A.1.1(8) Provision of Field Office for the Engineer (Rental Basis) 5.33 month 138,666.67 0.00% 8.00% 8.00% 11,093.33 7,488.00 18,581.33 157,248.00 29,484.00
Project : CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL Appropriation : Php 9,885,491.14
BUILDING Source of Fund : BEFF CY 2017
Project ID : Target Start Date :
Location : Esperanza Integrated School, Sison, Pangasinan Total Project Duration : 160 CD
Project Description : Construction of Two (2) Storey Four (4) Classroom School Building
with Permits and Clearances Cost, Demolition Cost; 9.50m x 23.00m; Floor tiles at 3 CL
Window and Corridor at 2/F Grilles ; Total Floor Area - 437.00m²; 1.00 m Embankment )
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part A Facilities for the Engineer 1.76% 138,666.67
Part B Other General Requirements 3.68% 289,569.02
Part III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
Part A Earthworks 3.85% 303,038.01
Part B Plain and Reinforced Concrete Works (PLS. SEE FORM POW-2015-01C-00) 30.10% 2,369,824.82
Part C Finishing and Other Civil Works 52.36% 4,122,159.69
Part D Electrical Works 2.21% 173,755.21
Part E Mechanical Works 6.03% 475,003.09
Total 100.00% 7,872,016.50
RAMIL S. ISIT JONATHAN B. RAMOS ANDRES M. NICER EMMANUEL W. DIAZ, CESE Atty. DONATO D. BALDERAS, JR.
Architect II Engineer II Engineer IV OIC- Assistant Regional Director Schools Division Superintendent
Planning and Design Section Chief, Planning and Design Section Asst. District Engineer Concurrent District Engineer
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS EVALUATED
PART A FACILITIES FOR THE ENGINEER
A. 1. 1. Offices and Laboratory for the Engineer
5.33 month 138,666.67 26,000.00 29,484.00
A.1.1(8) Provision of Field Office for the Engineer (Rental Basis)
138,666.67
TOTAL OF PART A
PART B OTHER GENERAL REQUIREMENTS
1.00 L.S. 97,635.46 97,635.46 102,517.24
B.3 Permits and Clearances
3.00 each 12,463.86 4,154.62 5,234.82
B.5 Project Billboard/Signboard
5.33 month 123,641.33 23,182.75 26,289.24
B.7 Occupational Safety and Health Program
1.00 L.S. 55,828.36 55,828.36 58,619.77
B.9 Mobilization/Demobilization
289,569.02
TOTAL OF PART B
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
1.00 L.S. 82,851.91 82,851.91 86,994.50
801(1) Removal of Structures and Obstructions
196.98 m³ 45,013.67 228.52 287.93
803(1)a Structure Excavation (Common Soil)
105.37 m³ 15,402.65 146.18 184.18
804(1)a Embankment from Structure Excavation
269.15 m³ 130,181.62 483.68 609.43
804(1)b Embankment from Borrow
33.92 m³ 29,588.16 872.29 1,099.09
804(4) Gravel Fill
303,038.01
TOTAL OF PART A
PART B PLAIN AND REINFORCED CONCRETE WORKS
153.74 m³ 623,046.66 4,052.48 5,106.13
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
28,343.22 kgs. 1,345,236.10 47.46 59.80
902(1)a1 Reinforcing Steel (Deformed, Grade 40)
960.52 m² 401,542.06 418.05 526.74
903(2) Formworks and Falseworks
2,369,824.82
TOTAL OF PART B
PART C FINISHINGS AND OTHER CIVIL WORKS
C.1 Termite Control Works
115.60 lit 42,543.73 368.03 463.71
1000(1) Soil Poisoning
42,543.73
Sub-Total C.1
C.2 Masonry Works
129.91 m² 71,290.63 548.77 691.45
1046(2)a1 CHB Non-Load Bearing (including Reinforcing Steel; 100mm)
450.38 m² 378,378.12 840.13 1,058.56
1046(2)a2 CHB Non-Load Bearing (including Reinforcing Steel; 150mm)
449,668.74
Sub-Total C.2
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS EVALUATED
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS EVALUATED
C.6 Roof Framing and Roofing Works
47.80 m 9,910.85 207.34 261.25
1003(11)a1 Fiber Cement Fascia Board
Prepainted Metal Sheets, Long Span, Corrugated, 0.5mm 315.48 m² 139,248.12 441.38 556.15
1014(1)b1
thk.
23.90 m 5,438.16 227.54 286.70
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll)
26.21 m 5,963.78 227.54 286.70
1013(2)b Fabricated Metal Roofing Accessory (Flashing)
47.80 m 16,029.04 335.34 422.52
1013(2)c Fabricated Metal Roofing Accessory (Gutter)
2,271.38 kg 173,835.90 76.53 96.43
1047(2)a Structural Steel (Trusses)
3,687.15 kg 266,355.37 72.24 91.02
1047(2)b Structural Steel (Purlins)
277.47 kg 19,125.57 68.93 86.85
1047(6) Metal Structure Accessories (Steel Plates)
101.34 kg 4,584.66 45.24 57.00
1047(7)b Metal Structure Accessories (Sagrods)
214.42 kg 11,301.20 52.71 66.41
1047(4) Metal Structure Accessories (Crossbracing)
18.00 pc 3,775.26 209.74 264.27
1047(3)c Metal Structure Accessories (Turnbuckle)
1.00 L.S. 102,789.13 102,789.13 129,514.30
1047(1) Structural Steel (Fire Escape)
758,357.04
Sub-Total C.6
C.7 Sanitary/Plumbing Works
12.00 each 10,620.50 885.04 1,115.15
1001(6)a Catch Basin
1.00 L.S. 23,398.44 23,398.44 29,482.03
1001(8) Sewer Line Works
1.00 L.S. 60,638.99 60,638.99 76,405.12
1001(9) Storm Drainage and Downspout
1.00 L.S. 282,689.16 282,689.16 356,188.34
1002(8) Plumbing Fixtures
1.00 L.S. 4,385.07 4,385.07 5,525.18
1002(28) Cold Water Lines
381,732.15
Sub-Total C.7
4,122,159.69
TOTAL OF PART C
PART D ELECTRICAL WORKS
1.00 L.S. 36,818.79 36,818.79 46,391.67
1100(30) Conduits, Boxes and Fittings
1.00 L.S. 64,679.66 64,679.66 81,496.37
1101(42) Wires and Wiring Devices
1.00 L.S. 25,594.39 25,594.39 32,248.93
1102(27) Panel Load Center, Switch Gear and Panelboards
1.00 L.S. 46,662.37 46,662.37 58,794.59
1103(1) Lighting Fixtures
173,755.21
TOTAL OF PART D
PART E MECHANICAL WORKS
1.00 L.S. 466,684.52 466,684.52 588,022.50
1202(1) Automatic Water Sprinkler System
1.00 L.S. 8,318.56 8,318.56 10,481.39
1208(1) Fire Alarm System
475,003.09
TOTAL OF PART E
7,443,780.82
TOTAL OF PART III
7,872,016.50
GRAND TOTAL
CONSTRUCTION OF TWO (2) STOREY FOUR (4) CLASSROOM SCHOOL BUILDING
Esperanza Integrated School, Sison, Pangasinan
FORM POW-2015-01B-00
FORM POW-2015-01C-00
FORM POW-2015-01C-00
FORM POW-2015-01C-00
D2 - (1 set 0.90 x 2.10m) Hollow core flush door set 1.00 6500.00 6,500.00
on wooden jamb with kick plate (as per plan)
D3 - (6 sets 0.80 x 2.10m) Hollow core flush door
set 6.00 6000.00 36,000.00
on wooden jamb (as per plan)
D4 - (1 set 0.70 x 2.10m) Hollow core flush door
set 1.00 5000.00 5,000.00
on wooden jamb (as per plan)
BD-1 - (5 sets 0.60 x 1.20m) Hollow core flush
set 5.00 4000.00 20,000.00
door on wooden jamb (as per plan)
Consumables (5% of Materials Cost) 6,575.00
Sub-Total for F.1 - As Submitted 138,075.00
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 174,155.66
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 20,898.68
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 13,932.45
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 10,449.34
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 219,436.13
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -
30at, 50af, 2p, 240v, in NEMA 3R enclosure set 2.00 1200.00 2,400.00
20at, 50af, 2p, 240v, in NEMA 3R enclosure set 1.00 1200.00 1,200.00
40at, 50af, 2p, 240v, in NEMA 3R enclosure set 1.00 1200.00 1,200.00
Sub-Total for F.1 - As Submitted 24,259.70
F.2 Materials
-
Sub-Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 25,594.39
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated -
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 12% of G.1 3,071.33
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 12% of G.2 -
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 2,047.55
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 -
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1 + H.1 + I.1) 1,535.66
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2 + H.2 + I.2) -
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 32,248.93
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) -