19pf0016 Ccs and Dupa
19pf0016 Ccs and Dupa
19pf0016 Ccs and Dupa
Project Name and: : 19PF0016, CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS
Location: : Mankayan, Benguet
Contracting Parties: : DPWH – BENGUET SECOND DISTRICT ENGINEERING OFFICE (DPWH BSDEO) represented by D.E. RO
ENTERPRISE represented by Mr. BRANDY D. ABEYA
Approved Budget for the Contract : ₱ 77,200,000.00
Contract Cost : ₱ 76,399,788.57
B.4(10) MISCELLANEOUS SURVEY AND STAKING lumpsum 1.00 9,923.50 9,923.50 1.00 40,463.00
B.5 PROJECT BILLBOARD / SIGNBOARD each 3.00 6,554.20 19,662.60 3.00 5,282.00
B.15(1) DETOUR / ACCESS ROAD lumpsum 1.00 379,909.93 379,909.93 1.00 383,284.00
B.17 TEMPORARY DIVERSION OF WATERWAY lumpsum 1.00 104,489.06 104,489.06 1.00 64,518.00
1700(1) CLEARING AND GRUBBING sq.m 5,604.00 20.11 112,696.44 5,604.00 20.00
1702(1)b STRUCTURE EXCAVATION (SOFT ROCK) cu.m 92.77 426.84 39,597.95 92.77 453.00
Page 1 of 33
Project Name and: : 19PF0016, CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS
Location: : Mankayan, Benguet
APPROVED BUDGET FOR THE CONTRACT
CONTRACT COST
Item No. DESCRIPTION Unit
Qty. Unit Cost Total Qty. Unit Cost
EMBANKMENT FROM ROADWAY /
1704(1)a cu.m 411.00 118.00 48,498.00 411.00 139.00
STRUCTURE EXCAVATION
404(1)a REINFORCING STEEL (GRADE 40) kg 198,134.40 68.36 13,544,467.58 198,134.40 65.00
407(8) LEAN CONCRETE, CLASS "B", 16.5 MPa cu.m 51.09 5,597.30 285,966.06 51.09 5,992.00
517(1)b DRAIN PIPE (PVC) li.m 33.75 214.25 7,230.94 33.75 265.00
1710(2)a GROUTED RIPRAP (CLASS "A") cu.m 30.10 2,944.17 88,619.52 30.10 5,233.00
Results of Evaluation:
The Approved Budget for the Contract and Contract Cost were found to be higher than the COA Evaluated Cost by P
Thus, both the ABC and Contract Cost are deemed unreasonable.
Page 2 of 33
IINFRA.TER.OC.WP.CCS
ES SECTOR
ICE
EET
Page 3 of 33
D DRAINAGE SYSTEMS: CONSTRUCTION OF BAGUYOS FLOOD CONTROL
76,399,788.57 74,049,034.30
Reviewed by:
Page 4 of 33
PROJECT NAME: 19PF0016, CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND
DRAINAGE SYSTEMS: CONSTRUCTION OF BAGUYOS FLOOD CONTROL
LOCATION: Mankayan, Benguet
A.1.1(6) PROVISION OF COMBINED FIELD OFFICE, LABORATORY AND LIVING QUARTERS FOR THE ENGINEER
QUANTITY: 6.00 month
MATERIALS
A.1.1(15) OPERATION AND MAINTENANCE OF THE TEMPORARY FIELD OFFICE, LABORATORY AND LIVING
QUARTERS
QUANTITY: 6.00 month
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Laborer 42.91 1,440.00 61,790.40
Sub-total= 61,790.40
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Geodetic Engineer 117.34 24.00 2,816.16
2.00 Rodman 55.46 24.00 2,662.08
1.00 Recorder 55.46 24.00 1,331.04
Sub-total= 6,809.28
EQUIPMENT RENTAL
MONTHLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE MONTHS
1.00 unit Survey Instrument (Total Station) 12,000.00 0.10 1,200.00
Sub-total= 1,200.00
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Construction Foreman 76.56 4.00 306.24
1.00 Skilled Laborers 55.46 4.00 221.84
1.00 Laborers 42.91 4.00 171.64
Sub-total= 699.72
MATERIALS
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Part Time Practitioner 62.50 205.71 12,856.88
1.00 First Aider 35.00 1,440.00 50,400.00
Sub-total= 63,256.88
MATERIALS
EQUIPMENT RENTAL
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 unit Backhoe (0.80 cu.m) to be loaded to lowbed trailer
2.00 unit Dump Truck (10 cu.m) 1,420.00 4.00 11,360.00
1.00 unit Payloader (1.50 cu.m) 1,733.00 4.00 6,932.00
1.00 unit Water Truck / Pump (16,000 L) 2,450.00 4.00 9,800.00
1.00 unit Cargo Truck (10 m.t) 1,212.00 4.00 4,848.00
1.00 unit Lowbed Trailer w/ Prime Mover 2,290.00 4.00 9,160.00
-
Other smaller equipment to be loaded to Dumptrucks and Cargo Trucks
-
Sub-total= 42,100.00
Note: As per DPWH Department Order No. 197, series of 2016, in no case shall mobilization and demobilization exceed 1% of the
Estimated Direct Cost (EDC) of the civil works items:
EDC of civil works items= 59,130,436.42
1% of EDC= 591,304.36
Item cost for mobilization and demobilization < 1% EDC; therefore adopt computed item cost
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Construction Foreman 76.56 48.00 3,674.88
4.00 Laborers 42.91 48.00 8,238.72
Sub-total= 11,913.60
EQUIPMENT RENTAL
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
0.5 1.00 unit Backhoe (0.80 cu.m) 1,537.00 24.00 36,888.00
0.6667 2.00 unit Dump Truck (10 cu.m) 1,420.00 32.00 90,880.00
0.3333 1.00 unit Payloader (1.50 cu.m) 1,733.00 16.00 27,728.00
Minor Tools (5% of Labor Cost) 595.68
Sub-total= 156,091.68
MATERIALS
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Construction Foreman 76.56 120.00 9,187.20
2.00 Laborers 42.91 120.00 10,298.40
Sub-total= 19,485.60
EQUIPMENT RENTAL
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
Submersible Pump (5 HP, diesel driven,
1 2.00 unit 266.25 120.00 63,900.00
12,000.0 Lit/min)
Minor Tools (5% of Labor Cost) 974.28
Sub-total= 64,874.28
MATERIALS
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Construction Foreman 76.56 11.21 858.24
2.00 Laborers 42.91 11.21 962.04
Sub-total= 1,820.28
EQUIPMENT RENTAL
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1 2.00 unit Dump Truck (10 cu.m) 1,420.00 11.21 31,836.40
1 1.00 unit Payloader (1.50 cu.m) 1,733.00 11.21 19,426.93
1 1.00 unit Bulldozer, D6H Series II PSDS/DD 3,379.00 11.21 37,878.59
Sub-total= 89,141.92
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Construction Foreman 76.56 2.73 209.01
1.00 Skilled Laborers 55.46 2.73 151.41
2.00 Laborers 42.91 2.73 234.29
Sub-total= 594.71
EQUIPMENT RENTAL
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1 1.00 unit Backhoe (0.80 cu.m) 1,537.00 2.73 4,196.01
1 1.00 unit Dump Truck (10 cu.m) 1,420.00 2.73 3,876.60
Sub-total= 8,072.61
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Construction Foreman 76.56 40.87 3,129.01
4.00 Laborers 42.91 40.87 7,014.93
Sub-total= 10,143.94
EQUIPMENT RENTAL
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1 1.00 unit Plate Compactor (5 HP) 123.00 40.87 5,027.01
0.01 1.00 unit Water Truck / Pump (16,000 L) 2,450.00 0.41 1,004.50
Minor Tools (10% of Labor Cost) 1,014.39
Sub-total= 7,045.90
MATERIALS
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Construction Foreman 76.56 6.63 507.59
3.00 Laborers 42.91 6.63 853.48
Sub-total= 1,361.07
EQUIPMENT RENTAL
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1 2.00 unit Dump Truck (10.0 cu.m) 1,420.00 6.63 18,829.20
0.5 1.00 unit Backhoe (0.80 cu.m) 1,537.00 3.32 5,102.84
0.5 1.00 unit Backhoe w/ Breaker (0.80 cu.m) 1,998.10 3.32 6,633.69
Minor Tools (10% of Labor Cost) 136.11
Sub-total= 30,701.84
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
B. Spreading and Compaction
1 1.00 Construction Foreman 76.56 8.22 629.32
1 2.00 Laborers 42.91 8.22 705.44
Sub-total= 1,334.76
EQUIPMENT RENTAL
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
B. Spreading and Compaction
1 1.00 unit Motorized Road Grader (140 HP) 2,173.00 8.22 17,862.06
1 1.00 unit Vibratory Roller (10 m.t) 1,846.00 8.22 15,174.12
0.25 1.00 unit Water Truck / Pump (16,000 L) 2,450.00 2.06 5,047.00
Sub-total= 38,083.18
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Construction Foreman 76.56 1,100.75 84,273.42
2.00 Skilled Laborers 55.46 1,100.75 122,095.19
8.00 Laborers 42.91 1,100.75 377,865.46
Sub-total= 584,234.07
EQUIPMENT RENTALS
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
0.15 1.00 unit Cargo Truck (10 m.t) 1,212.00 165.11 200,113.32
0.5 1.00 unit Bar Cutter, Single Phase 219.75 550.38 120,946.01
0.5 1.00 unit Bar Bender 351.50 550.38 193,458.57
Sub-total= 514,517.90
MATERIALS
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Construction Foreman 76.56 3,012.29 230,620.92
4.00 Skilled Laborers 55.46 3,012.29 668,246.41
8.00 Laborers 42.91 3,012.29 1,034,058.91
Installation and Removal of Forms
4.00 Skilled Laborers 55.46 3,012.29 668,246.41
8.00 Laborers 42.91 3,012.29 1,034,058.91
Sub-total= 3,635,231.56
EQUIPMENT RENTALS
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1 1.00 unit One Bagger Mixer 172.00 3,012.29 518,113.88
1 1.00 unit Concrete Vibrator 91.25 3,012.29 274,871.46
0.1 1.00 unit Water Truck/Pump (16,000 L) 2,450.00 301.23 738,013.50
Minor Tools (5% of Labor) 181,761.58
Sub-total= 1,712,760.42
MATERIALS
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Construction Foreman 76.56 31.15 2,384.84
4.00 Skilled Laborers 55.46 31.15 6,910.32
8.00 Laborers 42.91 31.15 10,693.17
Sub-total= 19,988.33
EQUIPMENT RENTALS
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1 1.00 unit One Bagger Mixer 172.00 31.15 5,357.80
1 1.00 unit Concrete Vibrator 91.25 31.15 2,842.44
0.1 1.00 unit Water Truck/Pump (16,000 L) 2,450.00 3.12 7,644.00
Minor Tools (5% of Labor) 999.42
Sub-total= 16,843.66
MATERIALS
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Construction Foreman 76.56 0.14 10.72
2.00 Skilled Laborers 55.46 0.14 15.53
8.00 Laborers 42.91 0.14 48.06
Sub-total= 74.31
EQUIPMENT RENTAL
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
0.25 1.00 unit Cargo Truck (10 m.t) 1,212.00 0.04 48.48
Sub-total= 48.48
MATERIALS
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Construction Foreman 76.56 3.28 251.12
2.00 Skilled Laborers 55.46 3.28 363.82
2.00 Laborers 42.91 3.28 281.49
Sub-total= 896.43
MATERIALS
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Construction Foreman 76.56 4,998.75 382,704.30
2.00 Skilled Laborers 55.46 4,998.75 554,461.35
8.00 Laborers 42.91 4,998.75 1,715,970.90
Sub-total= 2,653,136.55
EQUIPMENT RENTAL
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1 1.00 unit One Bagger Mixer 172.00 4,998.75 859,785.00
0.05 1.00 unit Water Truck/Pump (16,000 L) 2,450.00 249.94 612,353.00
0.1 1.00 unit Backhoe (Wheel Type 0.28 cu.m) 922.00 499.88 460,889.36
Minor Tools (10% of Labor) 265,313.66
Sub-total= 2,198,341.02
MATERIALS
LABOR
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1.00 Construction Foreman 76.56 24.08 1,843.56
2.00 Skilled Laborers 55.46 24.08 2,670.95
8.00 Laborers 42.91 24.08 8,266.18
Sub-total= 12,780.69
EQUIPMENT RENTAL
HOURLY NO. OF
QTY UNIT DESCRIPTION TOTAL COST
RATE HOURS
1 1.00 unit One Bagger Mixer 172.00 24.08 4,141.76
0.05 1.00 unit Water Truck/Pump (16,000 L) 2,450.00 1.20 2,940.00
Minor Tools (5% of Labor) 639.03
Sub-total= 7,720.79
MATERIALS
Prepared by:
A. Loading
Quantity= 10,000.00 bags
Capacity of 1 Cargo Truck: 10,000.00 kgs
No. of bags/CT: 10,000.00 kgs = 250.00 bags
40.00 kg/bag
Loading Time (using 6 10,000.00 kgs x 1.00 man-min x 1.00 = 41.67 mins.
laborers): 40.00 kgs 6.00 lab.
B. Handling
Ave. Hauling Distance 47.73 kms
Paved Road: 46.93 kms; Ave. Loaded Speed: 20.00 km/hr (Mountainous)
Ave. Unloaded Speed: 30.00 km/hr
Loaded Trip: 46.93 kms x 1.00 x 60.00 min = 140.79 mins.
20.00 km/hr 1.00 hr
Unloaded Trip: 46.93 kms x 1.00 x 60.00 min = 93.86 mins.
30.00 km/hr 1.00 hr
Unpaved Road: 0.80 kms; Ave. Loaded Speed: 15.00 km/hr (Mountainous)
Ave. Unloaded Speed: 25.00 km/hr
Loaded Trip: 0.80 kms x 1.00 x 60.00 min = 3.20 mins.
15.00 km/hr 1.00 hr
Unloaded Trip: 0.80 kms x 1.00 x 60.00 min = 1.92 mins.
25.00 km/hr 1.00 hr
1. Equipment Cost
Using: 4.00 Cargo Truck/s *Note: consider 4 units CT to minimize stand-by time of laborers
No. of Days reqd: 10,000.00 bags x 355.41 min/trip x 1.00 trip x 1.00
480.00 min/day 250.00 bags 4.00 CT's
No. of Days reqd: 7.40 day/s
Equipment Cost: 4.00 CT's x 9,696.00 Php/day x 7.40 days = 287,001.60
2. Labor Cost
Employing: 6.00 Laborers
Labor Cost: 6.00 lab x 343.28 Php/day x 7.40 days = 15,241.63
19PF0016 UNIT COST DERIVATION OF CEMENT Page 24 of 33
Cost/bag at source: 249.00
Hauling Cost: 302,243.23
Hauling Unit Cost: 302,243.23 = 30.30 Php/bag
10,000.00
Total Cost/bag= 249.00 Php/bag + 30.30 Php/bag = 279.30 Php/bag
A. Loading
Quantity= 10,000.00 kgs
Capacity of 1 Cargo Truck: 10,000.00 kgs (Assume 1 laborer can carry 40 kgs of RSB)
Loading Time (using 6 10,000.00 kgs x 1.00 man-min x 1.00 = 41.67 mins.
laborers): 40.00 kgs 6.00 lab.
B. Handling
Ave. Hauling Distance 47.73 kms
Paved Road: 46.93 kms; Ave. Loaded Speed: 20.00 km/hr (Mountainous)
Ave. Unloaded Speed: 30.00 km/hr
Loaded Trip: 46.93 kms x 1.00 x 60.00 min = 140.79 mins.
20.00 km/hr 1.00 hr
Unloaded Trip: 46.93 kms x 1.00 x 60.00 min = 93.86 mins.
30.00 km/hr 1.00 hr
Unaved Road: 0.80 kms; Ave. Loaded Speed: 15.00 km/hr (Mountainous)
Ave. Unloaded Speed: 25.00 km/hr
Loaded Trip: 0.80 kms x 1.00 x 60.00 min = 3.20 mins.
15.00 km/hr 1.00 hr
Unloaded Trip: 0.80 kms x 1.00 x 60.00 min = 1.92 mins.
25.00 km/hr 1.00 hr
1. Equipment Cost
Using: 1.00 Cargo Truck/s
No. of Days reqd: 10,000.00 kgs x 355.41 min/trip x 1.00 trip x 1.00
480.00 min/day 10,000.00 kg 1.00 CT's
No. of Days reqd: 0.74 day/s
Equipment Cost: 1.00 CT's x 9,696.00 Php/day x 0.74 days = 7,175.04
2. Labor Cost
Employing: 6.00 Laborers *Consider 25% of equipment duration
Labor Cost: 6.00 lab x 367.12 Php/day x 0.19 days = 418.52
A. Production
Quantity= 1,000.00 cu.m / 30.0% = 3,333.33 cu.m
B. Handling
Paved Road: 4.37 kms; Ave. Loaded Speed: 20.00 km/hr (Mountainous)
Ave. Unloaded Speed: 30.00 km/hr
Loaded Trip: 4.37 kms x 1.00 x 60.00 min = 13.11 mins.
20.00 km/hr 1.00 hr
Unloaded Trip: 4.37 kms x 1.00 x 60.00 min = 8.74 mins.
30.00 km/hr 1.00 hr
Unaved Road: 0.80 kms; Ave. Loaded Speed: 15.00 km/hr (Mountainous)
Ave. Unloaded Speed: 25.00 km/hr
Loaded Trip: 0.80 kms x 1.00 x 60.00 min = 3.20 mins.
15.00 km/hr 1.00 hr
Unloaded Trip: 0.80 kms x 1.00 x 60.00 min = 1.92 mins.
25.00 km/hr 1.00 hr
1. Equipment Cost
Using: 2.00 Dumptrucks
No. of Days reqd: 1,000.00 cu.m x 35.17 min/trip x 1.00 trip x 1.00
480.00 min/day 10.00 cu.m 2.00 DT's
No. of Days reqd: 3.66 day/s
Equipment Cost:
Production 1.00 BD's x 27,032.00 Php/day x 8.33 days = 225,176.56
1.00 PL's x 13,864.00 Php/day x 13.89 days = 192,570.96
2.00 Screen = 40,000.00
Hauling 2.00 DT's x 11,360.00 Php/day x 3.66 days = 83,155.20
1.00 PL's x 13,864.00 Php/day x 1.83 days = 25,371.12
2. Labor Cost
Employing: - Laborers
A. Production
Quantity= 1,000.00 cu.m
B. Handling
Paved Road: 4.37 kms; Ave. Loaded Speed: 20.00 km/hr (Mountainous)
Ave. Unloaded Speed: 30.00 km/hr
Loaded Trip: 4.37 kms x 1.00 x 60.00 min = 13.11 mins.
20.00 km/hr 1.00 hr
Unloaded Trip: 4.37 kms x 1.00 x 60.00 min = 8.74 mins.
30.00 km/hr 1.00 hr
Unaved Road: 0.80 kms; Ave. Loaded Speed: 15.00 km/hr (Mountainous)
Ave. Unloaded Speed: 25.00 km/hr
Loaded Trip: 0.80 kms x 1.00 x 60.00 min = 3.20 mins.
15.00 km/hr 1.00 hr
Unloaded Trip: 0.80 kms x 1.00 x 60.00 min = 1.92 mins.
25.00 km/hr 1.00 hr
1. Equipment Cost
Using: 2.00 Dumptrucks
No. of Days reqd: 1,000.00 cu.m x 35.17 min/trip x 1.00 trip x 1.00
480.00 min/day 10.00 cu.m 2.00 DT's
No. of Days reqd: 3.66 day/s
2. Labor Cost
Employing: 50.00 Laborers
A. Production
Quantity= 1,000.00 cu.m / 30.0% = 3,333.33 cu.m
B. Handling
Paved Road: 4.37 kms; Ave. Loaded Speed: 20.00 km/hr (Mountainous)
Ave. Unloaded Speed: 30.00 km/hr
Loaded Trip: 4.37 kms x 1.00 x 60.00 min = 13.11 mins.
20.00 km/hr 1.00 hr
Unloaded Trip: 4.37 kms x 1.00 x 60.00 min = 8.74 mins.
30.00 km/hr 1.00 hr
Unaved Road: 0.80 kms; Ave. Loaded Speed: 15.00 km/hr (Mountainous)
Ave. Unloaded Speed: 25.00 km/hr
Loaded Trip: 0.80 kms x 1.00 x 60.00 min = 3.20 mins.
15.00 km/hr 1.00 hr
Unloaded Trip: 0.80 kms x 1.00 x 60.00 min = 1.92 mins.
25.00 km/hr 1.00 hr
1. Equipment Cost
Using: 2.00 Dumptrucks
No. of Days reqd: 1,000.00 cu.m x 35.17 min/trip x 1.00 trip x 1.00
480.00 min/day 10.00 cu.m 2.00 DT's
No. of Days reqd: 3.66 day/s
Equipment Cost:
Production 1.00 BD's x 27,032.00 Php/day x 8.33 days = 225,176.56
1.00 PL's x 13,864.00 Php/day x 6.94 days = 96,216.16
1.00 Screen = 20,000.00
Hauling 2.00 DT's x 11,360.00 Php/day x 3.66 days = 83,155.20
1.00 PL's x 13,864.00 Php/day x 1.83 days = 25,371.12
2. Labor Cost
Employing: - Laborers
Base Course Unit Cost= 341.40 Php/cu.m + 108.60 Php/cu.m + 50.00 Php/cu.m
Base Course Unit Cost= 500.00 Php/cu.m