20BC0058 Vo #2
20BC0058 Vo #2
20BC0058 Vo #2
ITEM NO. DESCRIPTION UNIT UNIT PRICE in TOTAL ITEM TOTAL QNTY TOTAL QNTY TO
TOTAL APPROVED IN TOTAL QNTY
CONTRACT Php COST THIS DATE
PREVIOUS APPROVED IN
QUANTITY BILLING THIS BILLING
PART B OTHER GENERAL REQUIREMENTS
B.5 Project Billboard/Signboard ea 2.00 3,487.00 6,974.00 1.93 1.93
B.7(2) Occupational Safety and Health Program l.s. 1.00 48,023.00 48,023.00
B.9 Mobilization/Demobilization l.s. 1.00 5,421.17 5,421.17
Err:509 Err:509
PART C EARTHWORKS
101(4)a3 Removal of Actual Structures/Obstruction, 910mmØ RCCP ln.m - - - 0.50 0.50
102(2) Surplus Common Excavation cu.m. - 200.90 -
PART D SUBBASE AND BASE COURSES
200(1) Aggregate Subbase Course cu.m. 825.45 879.00 725,572.30 -
0 TOTAL OF PART D 0 - - - - -
PART E SURFACE COURSES 0 - - - - -
311(1)a Portland Cement Concrete Pavement (Unreinforced), 0.15 m thick sq.m - - - - -
311(1)e1 Portland Cement Concrete Pavement (Unreinforced), 0.28 m thick sq.m 1,970.00 1,656.00 3,262,320.00
0 TOTAL OF PART E 0 - - - - -
PART G DRAINAGE AND SLOPE PROTECTION STRUCTURES 0 - - -
404(1)a Reinforcing Steel (Grade 40) kgs 28,612.92 68.00 1,945,678.60 -
405(1)a3 Structural Concrete, Class A, 20.68MPa at 28 days cu.m. 430.79 7,371.00 3,175,353.09 3,050.00 3,050.00
407(8) Lean Concrete cu.m. - - -
-
500(1)a3 Pipe Culverts, 910mmØ Class B RCCP ln.m - - -
505(2)a Grouted Riprap, Class A cu.m. - - 0.01 -
0 TOTAL OF PART G 0 - - -
0 0 0 - - - 50.00 50.00
0 GRAND TOTAL 0 - - - -
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 -
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 -
Err:509
Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 -
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 -
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509
COST OF THIS
COST TO DATE
BILLING
6,729.91 6,729.91
- -
- -
- -
- -
- -
- -
- -
22,481,550.00 22,481,550.00
- -
- -
- -
- -
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
LORNA B. ASUTEN
District Engineer
DPWH - CAGAYAN 2ND DISTRICT ENGINEERING OFFICE
CONTRACTOR'S STATEMENT OF WORK ACCOMPLISHED
April 9, 2018 to May 31, 2018
ITEM NO. DESCRIPTION UNIT UNIT PRICE in TOTAL ITEM TOTAL QNTY TOTAL QNTY TO
TOTAL APPROVED IN TOTAL QNTY
CONTRACT Php COST THIS DATE
PREVIOUS APPROVED IN
QUANTITY BILLING THIS BILLING
PART A. FACILITIES FOR THE ENGINEER
A.1.4(1) Provision of Progress Photographs mos. 5.63 16,088.50 90,578.26 1.93 1.93
A.1.1(11) Provision of Furnitures/ Fixtures, Equipment & appliances mos. 5.63 1,485.48 8,363.25
PART B. OTHER GENERAL REQUIREMENTS
B.5 Fab./Inst. Of Project Billboard each 4.00 2,325.41 9,301.64 4.00 4.00
B.7 Occupational Safety and Health Program mos. 5.63 27,828.32 156,673.44 1.93 1.93
B.8 Traffic Management mos. 5.63 6,244.05 35,154.00 1.93 1.93
B.9 Mobilization/Demobilization LS 1.00 247,905.58 247,905.58 0.50 0.50
PART C. EARTHWORKS
101(4)a1 Removal of actual Structures/ Obstruction (610mm dia.) cu.m. 28.00 331.00 9,268.00 28.00 28.00
103(1)a Structure Excavation(Common Soil) cu.m. 1,257.00 144.38 181,485.66 300.00 300.00
103(3) Foundation Fill cu.m. 64.00 1,330.36 85,143.04 -
104(1)a Embankment from Roadway Excavation cu.m. 1,338.00 321.50 430,167.00 1,271.10 1,271.10
104(1)b Embankment from Borrow cu.m. 8,630.00 269.70 2,327,511.00 8,198.50 8,198.50
105(1)a Subgrade Preparation-Common Materials sq.m. 14,266.22 18.38 262,213.12 13,552.91 13,552.91
PART D. SUBBASE AND BASE COURSE
200(1) Aggregate Subbase Course (10cm thk) cu.m. 7,385.94 906.48 6,695,206.89 7,016.64 7,016.64
PART E. SURFACE COURSES
311(1)a PCC Pavement (Unreinforced)-150mm thk sq.m. 3,825.00 831.60 3,180,870.00 -
311(1)a3 PCC Pavement (Unreinforced)-230mm thk sq.m. 10,436.22 1,238.90 12,929,432.96 3,050.00 3,050.00
PART F. BRIDFE CONSTRUCTION
404(1)a Reinforcing Steel Bar, Grade 40 (Minor Structures) kg 8,717.80 60.93 531,175.55 -
405(2)a3 Structural Concrete Class A (Minor Structures) cu.m. 250.78 6,833.07 1,713,597.29 -
PART G. DRAINAGE AND SLOPE PROTECTION
500(1)a3 Pipe Culverts, 910MM dia. ln.m. 64.00 4,436.13 283,912.32 50.00 50.00
505(2)a Grouted Riprap (Class A) cu.m. 40.00 4,318.81 172,752.40 -
510(2) Concrete Slope Protection cu.m. 912.51 7,611.56 6,945,624.62 -
PART H. MISCELANNEOUS STRUCTURES
612(1) Reflectorized Thermoplastic Pavement Markings(White) ln.m. 262.66 1,214.95 319,118.77 -
612(2) Reflectorized Thermoplastic Pavement Markings(Yellow) ln.m. 194.81 1,303.12 253,860.81
620(1)a1 Chevron Signs(450mm x 600mm) each 20.00 15,436.35 308,727.00 -
37,178,042.60
COST OF THIS
COST TO DATE
BILLING
31,050.81 31,050.81
9,301.64 9,301.64
53,708.66 53,708.66
12,051.02 12,051.02
123,952.79 123,952.79
9,268.00 9,268.00
43,314.00 43,314.00
- -
408,658.65 408,658.65
2,211,135.45 2,211,135.45
249,102.47 249,102.47
6,360,446.55 6,360,446.55
- -
3,778,645.00 3,778,645.00
- -
- -
221,806.50 221,806.50
- -
- -
- -
-
- -
13,512,441.52 13,512,441.52
LORNA B. ASUTEN
District Engineer
ITEMIZED COST OF REVISION
(Proposed Variation Order No. 2)
Project : 20BC0058: Construction/ Improvement of Access Roads leading to Trades, Industries and Economic Zones - Pacac-Binubungan connecting to Coconut Food Pocessing Area, Allacapan, Cagayan
A.1.4(1) Provision of Progress Photos ea 30.000 100.000 3,000.000 100.0000 3,000.0000 No Change
B.7(2) Occupational Safety and Health Program l.s. 48,023.000 1.000 48,023.000 1.0000 48,023.0000 No Change
B.8(2) Traffic Management l.s. 19,580.000 1.000 19,580.000 1.0000 19,580.0000 No Change
PART C EARTHWORKS
103(1)a Structure Excavation (Common Soil) cu.m. 222.000 504.000 111,888.000 112.7200 25,023.8400 391.2800 86,864.1600 Decreased
103(3) Foundation Fill cu.m. 1,280.000 68.500 87,680.000 20.6200 26,393.6000 47.8800 61,286.4000 Decreased
104(1)a Embankmet from Roadway Exacavation (Common Soil) cu.m. 152.000 58.000 8,816.000 58.0000 8,816.0000 No Change
104(2)a Embankment from Borrow (Common Soil) cu.m. 341.000 935.000 318,835.000 64.9152 22,136.0832 999.9152 340,971.0832 No Change
105(1)a Subgrade Preparation (Common Material) sq.m 20.000 786.000 15,720.000 786.0000 15,720.0000 No Change
200(1) Aggregate Subbase Course cu.m. 879.000 825.452 725,572.308 237.5800 208,832.8200 587.8720 516,739.4880 Decreased
311(1)e1 Portland Cement Concrete Pavement (Unreinforced), 0.28 m thick, 14 days sq.m 1,656.000 1,970.000 3,262,320.000 1,970.0000 3,262,320.0000 No Change
404(1)a Reinforcing Steel (Grade 40) kgs 68.000 28,612.921 1,945,678.602 9,973.7730 678,216.5640 18,639.1476 1,267,462.0380 Decreased
405(1)a3 Structural Concrete, Class A, 20.68MPa at 28 days cu.m. 7,371.000 430.790 3,175,353.090 152.7400 1,125,846.5400 278.0500 2,049,506.5500 Decreased
EXTRA WORK
311(1)a.5 PCC Pavement (Plain) - Conventional Method, 280mm thk. sq.m. 2,183.000 882.0000 1,925,406.0000 1,925,406.0000 New Item
TOTAL AMOUNT 9,800,000.000 1,947,542.0832 2,064,313.3640 9,683,228.7192
Name of Project: 20BC0058: Construction/ Improvement of Access Roads leading to Trades, Industries and Economic Zones - Pacac-Binubungan connecting to Coconut Food
Pocessing Area, Allacapan, Cagayan
Location: Brgy. Binubungan, Allacapan, Cagayan
To: A. NIDUAZA BUILDERS
You are hereby directed to make the herein described changes from the plans and specification, or do the following work not included the plans and specifications.
DELETION OF ITEMS:
NEW ITEM :
311(1)a Portland Cement Concrete Pavement (Unreinforced), 0.15m thk. 534.00 sq.m.
REASON FOR CHANGE: Please see attached detailed technical justifications.
ITEMIZED QUANTITIES AND COST OF REVISION ON THE REVERSE SIDE OF SHEET Original Contract Amount P 9,800,000.00
We the undersigned contractor have given careful consideration to the proposed changes Difference in Cost this Change P (116,771.28)
and hereby agree, if this proposal is approved, that we will provide all equipment, Estimated Revised Contract Amount P 9,683,228.72
furnish all materials except as may otherwise be noted above and perform all Percentage Change in Original Contract Value (+) or (-) -1.19%
services necessary for the work above specified and will accept as full Original Contract Time 115 Calendar Days
payment therefore to the prices shown on the reverse side of the sheet. Proposed Time Extension (T.E.) due to this V.O. 5 Calendar Days
Revised Contract Time (if T.E. is approved) 120 Calendar Days
Effectivity of Contract February 17, 2020
ACCEPTED DATE: ___________________________ Original Expiry Date June 10, 2020
_______________________________ Revised Expiry Date June 15, 2020
ORIGINAL REVISED
ITEM NO. DESCRIPTION UNIT VARIANCE REMARKS
QUANTITY QUANTITY
Prepared by:
JACKYLOU P. TORIDA
Project Engineer
DETAILED UNIT PRICE ANALYSIS (DUPA)
20BC0058: Construction/ Improvement of Access Roads leading to Trades, Industries and Economic Zones - Pacac-Binubungan connecting to Coconut Food
Pocessing Area, Allacapan, Cagayan
Allacapan, Cagayan
Personnel No. of Person/s No. of Hour/s Unit Rate/Hour Total Cost (Pesos)
Equipment (Operated) No. of Unit/s No. of Hours Hourly Rate Total Cost (Pesos)
Material Name and Description Qty Unit Unit Cost Total Cost (Pesos)
Reinforcing Steel Bars (Grade 40) 0.5 441.00 kgs. 120.00 52,920.0000
Asphalt Sealant 0.17 150.00 lit. 150.00 22,500.0000
Sand 0.154 136.00 cu.m. 1,200.00 163,200.0000
Gravel 0.28 247.00 cu.m. 1,200.00 296,400.0000
Cement 2.66 2,347.00 bags 300.00 704,100.0000
Concrete Saw (Diamond blde 14") 0.00015 1.00 pcs 8,000.00 8,000.0000
Pipe Sleeve, 1"Ø 0.008 7.00 ln.m. 850.00 5,950.0000
Grease/Tar 0.002 2.00 lit. 500.00 1,000.0000
Equipment P 258,620.0000
Labor 15,600.0000
Materials 1,254,070.0000
TOTAL DIRECT COST 1,528,290.0000
OCM 183,394.8000
Profit 122,263.2000
VAT 91,697.4000
Total 1,925,645.4000
P 2,183.2714
Adjusted Unit Cost 2,183.0000
Estimated Cost 1,925,406.0000
Name of Project: Construction/Improvement of Access Roads Leading to Declared Tourism Destinations-Jct. Centro Lasam-Sto. Nino-Piat Road Leading to Basilica Minore
of Our Lady of Piat
Location: Brgy. Binubungan, Allacapan, Cagayan
To: DANDEX CONSTRUCTION
You are hereby directed to make the herein described changes from the plans and specification, or do the following work not included the plans and specifications.
DESCRIPTION OF THE WORK TO BE DONE: INCREASED IN QUANTITY OF ITEMS: 104(1)b Embankment from Borrow from 8630.00 cu.m. to 9390.86 cu.m.
311(1)a PCC Pavement (Unreinforced)-150mm thk from 3825.00 sq.m. to 5100.00 sq. m.
510(2) Concrete Slope Protection from 912.51 cu.m. to 921.66 cu.m.
DECREASED IN QUANTITY OF ITEMS: 404(1)a Reinforcing Steel Bar, Grade 40 (Minor Structures) from 8717.80 kg. to 5474.93 kg.
405(2)a3 Structural Concrete Class A(Minor Structures) from 250.78 cu.m. to 155.63 cu.m.
DELETION OF ITEMS: 612(1) Reflectorized Thermoplastic Pavement Markings (White) & 612(2) Reflectorized Thermoplastic
Pavement Markings (Yellow)
NEW ITEM : 600(3) Concrete Curb and Gutter, Type A (Cast in Place) L= 180.00 ln.m.
REASON FOR CHANGE: An increase in quantity of embankment is needed due to change in alignment. The quantity of PCC Pavement is also increased to
offset the decrease in the volume of Lined Canal.
CHANGE REQUESTED BY: Project Engineer
WORK TO BE PERFORMED AT:
ITEMIZED QUANTITIES AND COST OF REVISION ON THE REVERSE SIDE OF SHEET Original Contract Amount P 9,800,000.00
We the undersigned contractor have given careful consideration to the proposed changes Difference in Cost this Change P
and hereby agree, if this proposal is approved, that we will provide all equipment, Estimated Revised Contract Amount P 9,683,228.72
furnish all materials except as may otherwise be noted above and perform all Percentage Change in Original Contract Value (+) or (-) 0.00%
services necessary for the work above specified and will accept as full Original Contract Time 169 Calendar Days
payment therefore to the prices shown on the reverse side of the sheet. Approved Time Suspension
Approved Time Extension due to Rainy days 60 Calendar Days
Revised Contract Time 229 Calendar Days
Effectivity of Contract April 09, 2018
ACCEPTED DATE: ___________________________ Original Expiry Date September 24, 2018
_______________________________ Revised Expiry Date November 23, 2018
A Name and Capacity of Equipment (Operated) No. of Units No. of Hours Hourly Rate Total Cost (Pesos)
A. SUB-TOTAL , EQUIPMENT P -
B Designation of Personnel No. of Person No. of Hours Hourly Rate Total Cost (Pesos)
C. Name and Description Qty Unit Unit Cost Total Cost (Pesos)
SUMMARY:
A Equipment P -
B Labor 1,518.75
C Materials -
D TOTAL DIRECT COST 1,518.75
DIRECT UNIT COST 95.52
E OCM 15% of D 227.81
F Profit 10% of D 151.88
G VAT 5% of (D+E+F) 94.92
H Total Cost (D+E+F+G) 1,993.36
F Unit Cost H/Quantity P 125.37
Prepared by:
JACKYLOU P. TORIDA
Project Engineer
DETAILED UNIT PRICE ANALYSIS (DUPA)
CONTRACT ID: 20BC0058 - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES, PACAC-
BINUBUNGAN CONNECTING TO COCONUT FOOD PROCESSING AREA, ALLACAPAN, CAGAYAN
Item No./Description : 311(1)a PORTLAND CEMENT CONCRETE PAVEMENT (UNREINFORCED) 0.15m THK
Unit of Measurement : Sq.m.
Output per hour : 107.33 Sq.m.
Designation Personnel No. of Men No. of Hours Unit Rate/Hour Total Cost (Pesos)
20BC0058: Construction/ Improvement of Access Roads leading to Trades, Industries and Economic Zones - Pacac-Binubungan connecting to Coconut Food
Pocessing Area, Allacapan, Cagayan
Allacapan, Cagayan
Item No./Description : 311(1)a PORTLAND CEMENT CONCRETE PAVEMENT (UNREINFORCED) 0.15m THK Quantity = 285
Unit = sq.m.
A. Name and Capacity of Equipment (Operated) No. of Units No. of Hours Unit Rate/Hour Total Cost (Pesos)
B. Designation of Personnel No. of Person No. of Hours Hourly Rate Total Cost (Pesos)
C. Name and Description Qty Unit Unit Price Total Cost (Pesos)
SIR:
In connection with your contract for the Construction/Improvement of Access Road leading to Trades, Industries and Economic
Zones - Pacac - Binubungan connecting to Coconut Food Processing Area, Allacapan, Cagayan, you are hereby directed to perform the
following extra work:
TOTAL #NAME?
It is estimated that the work to be performed under this order will cost Two Hundred Ninety Four Thousand Six Hundred Four
& 50/100 (P 294,604.50) as shown in the attached estimates.
By reason of this work, you will be allowed (0) Calendar Days extension of contract time.
Please indicate your agreement to this Extra Work Order by dating, signing and returning
same to this office, detach one (1) copy for your file.
A. NIDUAZA BUILDERS
CONTRACTOR