Hy-Rib Permanet Formwork - TDS
Hy-Rib Permanet Formwork - TDS
Hy-Rib Permanet Formwork - TDS
HY-RIB
®
User’s Guide
HY-RIB® USER’S GUIDE
INTRODUCTION
INTRODUCTION
For over 80 years Hy-Rib® has been successfully used as permanent formwork on
innumerable building and infrastructure projects, throughout the world.
• Reduced risk of Hand and Arm vibration injury (white finger): product featured
in HSE document - Vibration Solutions Ref HS (G) 170
• Expamet Hy-Rib® joint surfaces require minimal preparation prior to the next
pour, with the exception of the rebar cover zones. It minimises the labour,
mess and disposal requirements associated with scabbling, chemical
retarders and jet washing.
• Hy-Rib reduces the risk of trapped air and voids within the concrete.
• The range of narrower sheet widths improves site productivity and minimises
wastage.
SECTION 1
PRODUCT RANGE
SECTION 2
INSTALLATION ESSENTIALS
SECTION 3
CONCRETE
SECTION 4
DESIGN THEORY
Sheet Identification ID Colour: Red 2811 ID Colour: Green 2611 ID Colour: Yellow 2411
Sheet Identification ID Colour: Blue 2811 S 304 ID Colour: Black 2811 S 316
SHEET WIDTHS
ORDER CODING:
Standard Sheet
Quote Grade and Length
e.g. 26113000
or 28113000S304
CURVED HY-RIB®
Ribs In
Ribs out
ORDER REQUIREMENTS:
Specify
Ribs In or Out
Radius and Arc Length
or
Chord Length and Rise
Dimensions to be given
to concrete face.
HY-RIB® DEFINITIONS
Edge Rib
Tangs
Colour Coding Strip inside the rib
Inner Rib
MEASURING POINTS
Sheet length
SPAN
SPAN
SPAN
Sheet 1 Sheet 1
Sheet 2
Sheet 2
Typical end lapping of Hy-Rib® sheets for wall Small overlap - 25mm - 50mm
stopends and construction joints. Tie sheets tightly together to
minimise gap
Butt ends together: zero overlap Nail or tie Hy-Rib® to supports
25/50
mm
Hy-Rib® must have the same cover as the Temporary timber used to form cover zones
reinforcement and is generally fixed between
the outer layers of reinforcement.
Horizontal
noggins
Eventual
position of seal
1. Leave a gap between adjacent Hy-Rib® sheets in 2. After the first pour, remove the timber support and
line with the edge of the noggins to ensure a flat noggins and fix the seal to the flat concrete surface as
concrete surface where the seal is to be located. per the manufacturer’s instructions.
This section illustrates current best practice for placement and compaction of concrete in proximity to Hy-Rib®
stopends. Further consultation should be taken if there is any uncertainty regarding site conditions - pour shape
and size, concrete mix, type of compaction equipment and the Project Specification.
1.5 - 2m
Use correct length of pipe trunking or tremie tube Don’t dump the concrete from excess height
Place concrete at least 500mm from Hy-Rib® Don’t discharge concrete directly against the
stopend Hy-Rib® stopend
Allow concrete to naturally flow up toward the Don’t allow concrete to pile up against the
Hy-Rib® stopend Hy-Rib® stopend
VIBRATION COMPACTION
Where continuous vibration is used keep Do not use continuous and excessive vibration too
poker about 450mm from the Hy-Rib® close to the Hy-Rib® face. This may result in
In close proximity to Hy-Rib® stopend, vibrate in excessive loss of concrete fines.
5 second bursts until concrete is compacted Do not vibrate the stopend.
Vibrate in this way until cement grout is observed External vibrators are not recommended for
coming through the open mesh use with Hy-Rib®
Highly workability and ‘fluid’ mixes may require Do not vibrate the steel reinforcement
less total vibration effort than ‘stiff’ concrete mixes.
CONCRETE FINISH
Following the placement and compaction guidance Never brush, scrape or jet-wash the fresh
in this document. Do nothing else! concrete/Hy-Rib® face
CLEANING
If excess grout builds up on the walings and Do not disturb the fresh concrete/Hy-Rib® face
supports it is good practice to lightly brush these while removing any overspill and grout build up
clean before the concrete hardens. on the walings.
Never brush, scrape or jet-wash the fresh
CURING concrete/Hy-Rib® face
If curing is needed, use well sealed polythene Do not use curing compounds on any joint or
sheeting pressed over the ends of any projecting Hy-Rib® stopends to which a further pour will be
reinforcement. connected (Many curing agents make excellent
de-bonding agents!)
PREPARING THE JOINT FOR THE NEXT POUR
Remove the timber cover zone strips and prepare Do not remove the Hy-Rib® sheet - it is permanent
the exposed concrete band, being careful not to formwork!
damage the edge corners.
The recommended reduction in design concrete pressure when using Hy-Rib®, compared to the calculated
Construction Industry Research and Information Association (CIRIA) Report 108 values for casting against
impermeable formwork are shown at below. These show that the maximum concrete pressure obtained when
using Hy-Rib® is almost halved for pours up to 3m in height, with an upper limit of 38 kN/m² for walls from 3m
up to 5m in height.
The research work, carried out by the British Cement Association confirmed the significant reduction in the
pressure of concrete placed in vertical sections against Hy-Rib® when compared to the predicted pressure
obtained using the full weight density head of concrete.
The results from five full scale wall pours, each 5m high, are shown plotted below. They were also published in
Concrete magazine. The trials were carried out using concrete with additions and admixtures to provide a very
high workability mix to give extremely fast rates of rise. The CIRIA Report 108 "Concrete pressures on formwork"
categorises these concretes as Group 4, and predicts that at such rates of rise the design maximum pressure
should use the weight density head of concrete. The actual concrete density averaged 23.15 kN/m³ in the
wall trials.
2
Height from
top of CIRIA 108 pressure value
concrete (m) using density of 23.15kN/m2
Maximum design
pressure when using
Hy-Rib is 38kN/m2
4
5
0 20 40 60 80 100 120
Concrete pressure (kN/m2)
The general method of determining the design concrete pressure uses Table 2 from CIRIA Report 108 with a
weight density of 25 kN/m³, and concrete classified into five groups. Although the full scale tests were carried
out on a very fluid group 4 concrete, the BCA are of the opinion that it is reasonable to assume that the pressure
reductions can also be applied when using Hy-Rib® with the stiffer group 1 and 2 concretes using CEM I, CEM I/R
or + SR with or without any admixture. Hy-Rib® is also effective when used with Group 6 and 7 concrete, and has
been used with concrete of slump 180mm.
In addition the BCA have recorded the same reduction of concrete pressure on a very thick section (8m wide)
whilst pouring a 5m high double faced wall using Hy-Rib® to both faces.
Section Modulus
Zjoint mm3/m 1710 1125 952 Rib in tension
Zspan mm3/m 2233 1488 1266 Face in tension
Moment of resistance kNm/m 0.330 0.217 0.184 At supports (rib away from load)
(working) (fZ) kNm/m 0.431 0.287 0.244 At midspan (rib towards load)
Notes:
1. The properties assume that the Hy-Rib® is used with the ribs pointing into the concrete to be placed first and
spanning in the strong direction between supports with the ribs parallel with the span.
2. The Hy-Rib® is considered a single use sacrificial material with a minimum factor of safety of 1.4 on ultimate
failure. The failure stress being the minimum ultimate tensile strength of the Hy-Rib® sheet material.
3. The bending stiffness values should only be used for estimating deflections. They allow for the complex
geometric changes in properties and shape as Hy-Rib® deflects.
Overall
Depth
Notes:
1. The Hy-Rib® is used in horizontal sheets with the ribs pointing into the concrete to be placed, and
spanned in the strong direction between vertical supports.
2. The theoretical maximum pressure is that calculated using Table 2 in CIRIA report 108 with a concrete density
of 25kN/m3, for EITHER a wall, base or column; AND applies to concrete groups 1 to 5 inclusive.
3. The Hy-Rib® pressure diagram up to 3m in height of joint is assumed to be triangular. The permissible spans
calculated from a uniformly applied concrete have been increased by a factor of 1.2 to allow for the triangular
shape of the concrete pressure diagram. The maximum pressure only applies at the very bottom of the joint.
1
THIN WALL CONSTRUCTION JOINTS:
MAXIMUM SPACING ON TIMBER SUPPORTS 2
3
All temporary works must be designed by
4
a competent Temporary Works Designer
5
6
7
8
Centre to centre spacing of the supports (mm) and the approximate height of wall (mm)
Position of the Grade 2811
support Grade 2411 Grade 2611 Grade 2811 S 304
measured from Grade 2811 S 316
the top of the support approximate support approximate support approximate
wall spacing wall height spacing wall height spacing wall height
Load in the
approximately 14.3 kN/m approximately 11.4 kN/m approximately 10.5 kN/m
supports
Notes:
1. The Hy-Rib® is used in vertical sheets with the ribs pointing into the concrete.
2. The value of the support spacing is measured centre to centre of the vertical supports and is NOT the clear distance.
3. The supports to the Hy-Rib® are horizontal and are a minimum of 50mm wide.
4. The approximate load per metre of the supporting members is given as a guide only.
5. It is assumed that the Hy-Rib® is continuous over at least three spans (i.e. over four horizontal supports).
If this is not the case, refer to a designer for the increase in load on the supports.