Update Main Controller and Display

(Operating concept up to year 2008)

!!! Important !!!


During the complete update the ignition must be on and the engine turned off.
The update software must be installed on your laptop prior to starting the
update.
!!! Important !!!

Tools needed for the update:


• Laptop
• Complete software for display and main controller
• IFM cable
• Cat5 network cable

First the current software version has to be determined


Press F6 in Display Choose system information press F6 to confirm

In the upper third part of the window for system information you can find the software
version of the display (for example 02.00.00).
In the middle third part you can find the software version of the main controler (for
example HV005 SV02.00.01)
Write down both software versions. You need them later on, when the file names/
folder names for the data backup will be created.

Compatibility:
Basically, be aware that the software versions of the display and the main controler
have to match (except the last two numbers).

Software of main
Software of Display Compatible?
controller
02.00.00 02.00.00 Yes
02.00.02 02.00.00 Yes
02.00.00 02.00.03 Yes
02.02.00 02.00.03 No
02.00.00 02.01.03 No
02.00.00 03.00.00 No

The denomination HV… of the main controller, tells what hardware is installed on the
machine (Components like wiring harnesses, switches, sensors..)
An Update to an higher version (for example from HV005 to HV006) is not possible,
or only after consultation with Aftermarket Dept. Terex Fuchs.

After every change of the software version, a report has to be sent to


Aftermarket Dept. Terex Fuchs. Only if we receive information about every
modification, we can guarantee that in case of a replacement of a main
controller or a display the correct software version will be installed!

Update Main Controller and Display, Operating Concept up to year 2008 Page 1 of 25
Update Main controller CR0020
Central electric box

Connection for Display (CR9014) Connection for Main Controller (CR0020)

• CR0020 Main Controller (Central Electric Box)

Update Main Controller and Display, Operating Concept up to year 2008 Page 2 of 25
The connection of the laptop (Normally Com1, serial com port) and the main
controller (IFM Cr0020) must be by special IFM cable, or a standard serial (RS232)
cable with an IFM+ecology+Lenkrechner adapter.

Special IFM Cable

or

Adapter MHF 001 017A

in connection with serial data cable MHF 001 013A

Update Main Controller and Display, Operating Concept up to year 2008 Page 3 of 25
Start the Program “Download IFM” then select RS232 for interface.

Adjust program “Download IFM” Settings:


Select “Interface Parameter” and set the parameters.

Bits per Second @ 57600, Data Bits @ 8, Stop Bits @ 1, Parity @ None,
Com-port @ Com1 (It may be necessary to select alternate com port if not using a
serial port)
Select “OK”

Update Main Controller and Display, Operating Concept up to year 2008 Page 4 of 25
Select File, then from the menu select “File Options”

Only Runtime Systems / Application Program should be check marked,


Then select OK.
Then Select “Get Identity”
Identity: CR0020_Q 041214 is the old software and needs to be updated/patched
before the application program can be updated.

Identity: CR0020_Q 070629 is the New software and the application program can be
updated.

Prior to beginning the update make a data save


(Ignition on, engine off!)

Click “Open File”

Update Main Controller and Display, Operating Concept up to year 2008 Page 5 of 25
Follow the file path as the example shown above. (Note- at “Software Projekte” it is
necessary to select the correct model machine you are updating)

Type the machine model - serial number


and the date in the file name field as
shown

Click on “Open”

Update Main Controller and Display, Operating Concept up to year 2008 Page 6 of 25
The file name will be displayed at the top.

Click “Upload”

A Safety copy of the application program will be saved on your laptop.

will be displayed, click OK

Click “Get Identity” Click “OK”

Update Main Controller and Display, Operating Concept up to year 2008 Page 7 of 25
Click “Run” Click “OK”

Update Directions

To start the application program update,

Click on “Open File”

Follow the file path as the example shown above. (Note- at “Software Projekte” it is
necessary to select the correct model machine you are updating)

Update Main Controller and Display, Operating Concept up to year 2008 Page 8 of 25
Select the file with the same hardware version and
the newest software version

Click “Open”

The correct file will be shown at the top.

Click “Download”

Update Main Controller and Display, Operating Concept up to year 2008 Page 9 of 25
The laptop will begin to download the application program to the main controller.

will be displayed, click OK

Click “Get Identity” Click “OK”

Click “Run” Click “OK”

Click “Exit” And disconnect the cable from the circuit board.

The Update of the main controller is complete.

Update Main Controller and Display, Operating Concept up to year 2008 Page 10 of 25
Update Display CR9014

• CR9014 - Display PDM360

Connect the laptop to the display with the cat5 network cable ( use the Ethernet port
in the central electric box)

Connection in
Central Electric box

Update Main Controller and Display, Operating Concept up to year 2008 Page 11 of 25
Start the program WS_FTP95 LE

This screen will be displayed.

If the “Session Properties” screen matches this, click OK.

Update Main Controller and Display, Operating Concept up to year 2008 Page 12 of 25
If the Profile name displays as “Ipswitch” as shown below, follow the procedures
below;

Push the button ”New” and change to:

Profile Name: IFM Display


Host Name/Address: 10.31.0.248
User ID: root
Password: root

Select “Startup” and type /home/project in the “Initial Remote Site Folder” field

Update Main Controller and Display, Operating Concept up to year 2008 Page 13 of 25
Then click “OK”. Wait for the Lap top to connect with the display.

Connecting.

Update Main Controller and Display, Operating Concept up to year 2008 Page 14 of 25
NOTE: if the lap top will not connect it may be necessary to change the network
connection settings.

When the connection is completed this screen will be displayed.

The left side “Local System” Displays the lap top files

The right side “Remote Site” will show the files on the display when completely
connected.

Update Main Controller and Display, Operating Concept up to year 2008 Page 15 of 25
Make a data save

Double Click to go to “C” drive

Double click on FuchsService

Double click on “Update”

Update Main Controller and Display, Operating Concept up to year 2008 Page 16 of 25
Double click on “SoftwareProjekte”

Select with double click the folder for the machine model you are working on

Update Main Controller and Display, Operating Concept up to year 2008 Page 17 of 25
Double click on “Display”

Click on MkDir (Make Directory)

This screen will display. Enter the Machine Model and serial number and the date
and click “OK”

Update Main Controller and Display, Operating Concept up to year 2008 Page 18 of 25
Double click on the folder you just created.

At the “Remote Site” Highlight from the top file completely to the last file.

Click the arrow to transfer the files from the display to the laptop

Update Main Controller and Display, Operating Concept up to year 2008 Page 19 of 25
When the transfer is complete the screen will have the same files on both sides.

Click on “Delete”, Then click on “Delete All”

After “Delete” the remote site will be blank.

Update Main Controller and Display, Operating Concept up to year 2008 Page 20 of 25
Double click here

Double click on the most current version software

Update Main Controller and Display, Operating Concept up to year 2008 Page 21 of 25
Select all the files from the top to the bottom.

At the bottom DO NOT HIGHLIGHT THE DRIVE FOLDERS AT THE BOTTOM

Click the arrow to transfer the files form the lap top to the remote site.

This will flash during the transfer process

Update Main Controller and Display, Operating Concept up to year 2008 Page 22 of 25
This screen will display when the transfer is complete.

Click on “Exit”

Turn key switch off; disconnect the network cable, Turn Master Battery switch off.

Wait 10 seconds

Turn master switch and then key switch back on.

On the display, Press “F6” (Main Menu)

Update Main Controller and Display, Operating Concept up to year 2008 Page 23 of 25
Select System Information from the main menu

Verify the newest software version is on the display.

Press AND HOLD in this order – “F2” and “F3” and “F1”.

This will begin system initialization. A blue field will be show on the display.
When this is complete you will see the message “initializing variables” “DONE”

Update Main Controller and Display, Operating Concept up to year 2008 Page 24 of 25
Return to the main menu.

Check the machine for proper operation.

The “Update” is complete.

Update Main Controller and Display, Operating Concept up to year 2008 Page 25 of 25
Update main controller and display
(Operating concept from year 2008 and up)

!!! Important !!!


During the complete update: Ignition ON; Engine OFF.
The required data, see:
C:\FuchsService\update\SoftwareProjekte\
!!! Important !!!

Required tools:
• laptop with serial port (RS232)
• data set (C:\FuchsService\update\SoftwareProjekte)
• special data cable (see update main controller CR0020)
• network cable (see update display CR9014)

First, the current software version will be identified


Press F6 on the display Æ choose system information Æ press F6 to confirm

In the upper third of the window “system information”, you see the software version of
the Display (eg. 02.00.00).
In the middle of the screen you see the software version of the main controller.
(eg. HV005 SV02.00.01).
Make a note of the both software versions, you need them later to use as file names
for the data backup.

Compatibility:
Basically it’s important, that the software version of the display and the software
version of the main controller, match up to the last two digits.

Display software main controller software compatibly


02.00.00 02.00.00 yes
02.00.02 02.00.00 yes
02.00.00 02.00.03 yes
02.02.00 02.00.03 no
02.00.00 02.01.00 no
02.00.00 03.00.00 no

The part “HV…” from the software version of the main controller, indentifies the
hardware version.
A update to a another hardware version is not possible, or only after consultation with
the Terex Fuchs Aftermarket Department.

After every change of the software version, a report has to be sent to


Aftermarket Dept. Terex Fuchs. Only if we receive information about every
modification, we can guarantee that in case of a replacement of a main
controller or a display the correct software version will be installed!

Update Main Controller and Display, Operating Concept from 2008 and up Page 1 of 26
Update Main controller CR0020 (new cabin concept)

Central electric box

• CR0020 - main controller (central electric box)

Update Main Controller and Display, Operating Concept from 2008 and up Page 2 of 26
Interface to the main controller (CR0020)

Interface main controller


CR0020
(X22)

Update Main Controller and Display, Operating Concept from 2008 and up Page 3 of 26
Remove the red protection cover from the Sub-D socket (X3), and attach the silver
plug. After the update, remove the plug and replace the protection cover.

Update Main Controller and Display, Operating Concept from 2008 and up Page 4 of 26
The connection of the laptop (normally Com1, serial com port) and the main
controller (IFM Cr0020) must be by special IFM cable, or a standard serial (RS232)
cable with an IFM+ecolog+Lenkrechner adapter.

Special IFM Cable

or

Adapter MHF001017A

in link with a serial data cable MHF001013A

Update Main Controller and Display, Operating Concept from 2008 and up Page 5 of 26
Start the program DOWNLOAD IFM V06.05.05.

Old downloader

New downloader

If you can’t find the icon “Downloader IFM V06.05.05”, you have to create a new
shortcut.

When the new Downloader opens, the following steps between the red bars can be
skipped.

Update Main Controller and Display, Operating Concept from 2008 and up Page 6 of 26
Open “My Computer”

Go to: C:\\FuchsService\CDenglisch\SoftwareEnglish\IFM_Downloader_d_060505

Update Main Controller and Display, Operating Concept from 2008 and up Page 7 of 26
Click with the right hand mouse button on the file “DOWNLOAD.exe” and chose:
Send to Desktop.

You get the following icon on your Desktop:

Click the icon with the right hand mouse button,


to rename the shortcut.

Rename to: DOWNLOAD IFM V06.05.05

Start the program „DOWNLOAD IFM V06.05.05“.

Update Main Controller and Display, Operating Concept from 2008 and up Page 8 of 26
Push the button “Identity”.
If you get an error message, check the Interface settings.
Open “Interface” on the drop down menu, to set the interface parameters.

Click on RS232

Update Main Controller and Display, Operating Concept from 2008 and up Page 9 of 26
Interface parameter menu:

The parameter settings to connect with the main controller:

• 57600 Bits per Second


• Data Bits: 8
• Parity: N
• Stop Bits: 1
• COM-Port: Com1 (serial port on your PC )

If you do not have a serial port on your PC, you need a USB to RS232 adapter.
In this case select the correct COM-Port.

Before you start the data transfer, check the transfer settings:

Open the drop down menu Options and go to File Options.

Update Main Controller and Display, Operating Concept from 2008 and up Page 10 of 26
Only select Runtime System / Application Program”!

Backup from the main controller (Ignition on; Engine off)

Press the button upload.

Go to “C:\FuchsService\backup\main_controler”.
If the path does not exist create a new folder.

Update Main Controller and Display, Operating Concept from 2008 and up Page 11 of 26
Enter file name: (File name:
main_controler_machinetype_serialnumber_date_softwareversion;
e.g. main_controler_MHL320_Sn966_2008_11_5_HV010SV03.12.04)
and press the Button „Save”.

Now a copy of the application program will be stored on your computer.

Update Main Controller and Display, Operating Concept from 2008 and up Page 12 of 26
If you get the message „Upload successful“ the upload was done.
Press „OK“ to confirm.

press Identity Æ

„Status: Running“ Æ main controller is ready Æ press OK

Load the new files into the main controler


Before each update of an application program must be made an update.

press download Æ

Update Main Controller and Display, Operating Concept from 2008 and up Page 13 of 26
Select the path:

e.g.
C:\FuchsService\update\SoftwareProjekte\MHL3xxD_neuesBedienkonzept2008\Hau
ptsteuerung\6738020010_MHL3XX_HAUPTSTEUERUNG_HV010_SV03.12.04.H86

Mark the file and press Open.


„6738020010_MHL3XX_HAUPTSTEUERUNG_HV010_SV03.12.04.H86“

Update Main Controller and Display, Operating Concept from 2008 and up Page 14 of 26
Confirm the massage with yes.

Now the update is running.

If you get the message „Download successful“the update was complete. Press OK.

Press Identity Æ

Status: Not Running“ Æ main controller is stopped Æ Press OK

Update Main Controller and Display, Operating Concept from 2008 and up Page 15 of 26
Press the button Run Æ

„Status: Running“ Æ main controller is ready Æ Press OK

Close the program DOWNLOAD IFM.


Remove the data cable.
The update from the main controller is done.

Finally an initialization of the main controller has to be carried out. (How to do so


please see last page of this manual). If the main controller is updated, we
recommend

Update Main Controller and Display, Operating Concept from 2008 and up Page 16 of 26
Preparations for updating the software on display CR9014.
• CR9014 - Display PDM360

The connection between PC and Display (port ont the central electric board) via a
network cable.

Network cable: MHF001015A

Update Main Controller and Display, Operating Concept from 2008 and up Page 17 of 26
Preparations for updating the software on display CR9014.

Interface for Display (CR9014)

Interface Display CR9014


(X12)

Start the program WS_FTP.

Update Main Controller and Display, Operating Concept from 2008 and up Page 18 of 26
If the connection settings are correct, the Instructions between the two lines can be
skipped.

Enter the following Settings in General:

Profile Name: IFM Display


Host Name: 10.31.0.248
Host Type: Automatic detect
User ID: root
Password: root
Anonymous: not enabled
Save Pwd: enabled

Update Main Controller and Display, Operating Concept from 2008 and up Page 19 of 26
Enter the following Settings in Startup:

Initial Remote Site Folder: /home/project

To update the Display, the Ignition must be on and the engine off!
Press OK to connect.

After a few minutes you see on the Remote Site the files from the Display

Update Main Controller and Display, Operating Concept from 2008 and up Page 20 of 26
It can takes up to 3 minutes to connect with the Display. If you can’t connect to the
display check the Firewall and the LAN settings.

To set the network connections go to:


Start Æ Control Panel Æ Network Connections
Press the right hand mouse button on Local area connection and mark “Internet
Protocol (TCP/IP)”, Press Properties.

Go to Alternative Configuration
Æ User configured
IP-adress: 10.31.0.10
Subnet mask: 255.255.255.0

Update Main Controller and Display, Operating Concept from 2008 and up Page 21 of 26
Backup from the Display
Navigate in the left column to the directory:
C:\FuchsService\backup\display CR9014\.
If the directory doesn’t exist, make a new directory.

Also make a new Directory for the machine.


e.g. \MHL320sn4711

Update Main Controller and Display, Operating Concept from 2008 and up Page 22 of 26
Mark all the files on the Remote Site,
And press the arrow to the left, for uploading the Files from the Display to your PC.

After the upload there is a copy from these files on your hard disk.

Now the window has to look like shown on the following picture.

Update Main Controller and Display, Operating Concept from 2008 and up Page 23 of 26
Downloading the new files to the Display
Before each update to the Display a backup has to be made.

Mark all the files on the Remote Site and delete them

Confirm with „Delete All“.

All Files on the Display in the directory „/home/project“ are deleted


.

Update Main Controller and Display, Operating Concept from 2008 and up Page 24 of 26
!!! Important !!!
In this situation don’t switch off the ignition or the battery switch (data loss).
!!! Important !!!

Navigate in the left column (Local System) to the directory:


C:\FuchsService\update\SoftwareProjekte\MHL3xxD_neuesBedienkonzept2008\
Display

Mark all the new files.

Now press the arrow to the right, to download the files from your PC into the Display.

Update Main Controller and Display, Operating Concept from 2008 and up Page 25 of 26
After the download is complete the window has to look like shown on the following
picture:

Press the button close, to disconnect and then close the program WS_FTP.

Disconnect the network cable Æ ignition off Æ disconnect the battery switch for 10
seconds Æ ignition on Æ check all the functions of the machine.
The update of the display is now complete.

Initializing the main controller

Press F6 Æ go to “system information” Æ press F6 for OK Æ


Press and hold F2, additionally press and hold F3 and then also press F1 Æ
You get a message on the Display „Initialization done“ Æ
Ignition off Æ ignition on

The Initializing is now complete

After every change of the software version, a report has to be sent to


Aftermarket Dept. Terex Fuchs. Only if we receive information about every
modification, we can guarantee that in case of a replacement of a main
controller or a display the correct software version will be installed!

Update Main Controller and Display, Operating Concept from 2008 and up Page 26 of 26

You might also like