PREFACE
This Standard details the level of documentation that INTERTECH TECHNOLOGIES PVT.LTD (ITPL) will provide during a
contract for fabricating tank(s) or portable equipment’s. Extensive documentation is required for this system to assist in the
validation of critical services to comply with FDA / EU regulatory authorities. This documentation will be compiled in the
form of a Quality Assurance manual, the format of which is outlined in this specification. It will contain all necessary
information regarding design, construction, installation and validation undertaken by IET.
INTRODUCTION
Document and file:
Brief scope of work / Project Description.
Equipment schedule (including make, model, size, serial numbers)
Tank & Equipment’s i.e. Reactor et . data sheets / specification.
Process & Instrumentation Diagram (If applicable).
Details of any departures from the design specifications at installation including materials of construction and
key equipment.
Functionality Testing reports.
Warranty on parts and workmanship.
QUALITY SYSTEM
The design and fabrication of portable and fixed hygienic tanks will comply with the following standards and
specifications:
Design Specification
Good Engineering Standards
Quality Records
The direct contractor shall operate to a quality system for all works in this contract, inc. Materials and
workmanship. The quality system will comply with cGMP norms or equivalent.
Full details of the Quality System will be submitted to client prior to the commencement of manufacture. A
final and signed copy will be included with the final documentation submission. Throughout the project, IET
will maintain records to verify that quality procedures and standards have been adhered to. Variations or
modifications must be documented and approved by client prior to implementation.
Independent tank inspection reports will also be incorporated into the Quality Assurance manual.
Hold Points
The following designated production hold points shall be incorporated into the Inspection and Test Plan.
The IET shall give client a minimum of 72 hours prior to reaching any hold point inspection stage:
Qualification of weld procedures/operators (WPS, PQR.)
critical Fabrication set up
Assembly stages as approved as per QAP
Hydrostatic test;
Roughness testing for surface finish
Functional trial of equipment as approved in QAP
Will Client waive the right to the nominated inspection IET shall carry out internal checks and document the
same for future verification by the client.
Drawing Approvals
Records of new or modified drawings will be maintained as part of the quality assurance manual. All new
drawings and modifications will be approved by Client prior to distribution or implementation.
Equipment s Construction
Surface Finish
The internal surface of the vessel is to be mechanically polished to a surface finish as per Client
specifications. The surface will be free of surface defects, tarnishing, scuff marks or burrs. Provision
of surface roughness measurements will be at the discretion of the Project engineer pending the
nature of the vessel application.
Test Samples
The Client can request to submit a surface finish sample. The sample shall consist of two pieces of
the vessel material (approx. 6” x 6”), double butt welded and polished on one side to the surface
finish specified.
Site Installation
Any standard procedures followed in order to meet industry / Client standards must be referred to. If
appropriate, Quality Procedures will be incorporated into the quality assurance documentation. Quality
procedures will apply to the following aspects:
Vessel, Jacket & insulation
Welding
Equipment inspection & installation
Cleaning of tanks & fittings
The installation work is to be performed to the best industry standards. Inspections are to be carried out
during installation to ensure that IET is working in accordance with specifications and is performing work to
the best industry practices. Any reports generated from such inspections must be included.
Completion
After delivery on site, documented proof shall be provided to verify that the vessel meets industry & Client
standards. Other documents such as non-conformance report, rectification lists and Handover Inspection
reports will also be incorporated into an appropriate section of the Quality Assurance manual .
MATERIALS OF CONSTRUCTION
Materials of construction will be shown to comply with Client specifications. Evidence in the form of check sheets,
material certificates or letters of conformity, shall be provided for 'critical' materials. i.e. those that impact on the
quality of the final product.
WELDING
The method of welding used to fabricate the tank and associated piping will be clearly stated. Details of
Company Welding Quality systems will also be given. A Welding Quality system will identify the
following areas:
Welding process;
Welding machine;
Grade of material used;
Grade of Welding consumables: used gas, tungsten type and filler type;
Tubing diameter & wall thickness
Weld records (inc. Date, Job No., Drg. No., Operator etc)
Weld Inspection reports
Radiography report for all weld joints (As per approved QAP)
Mechanical
Document and file evidence that the following items have been adequately function tested:
Inlet / outlet valves
drainage
sample ports
jacket services (inc. relief valves & non-return valves)
stirrer / agitator
spray balls
load cells
vent filters (inc. Integrity test reports of Letters of Conformity from manufacturer)
Light glasses etc.
Nozzle end connection fitment
Document and file evidence that the following items have been inspected and shown to meet Client
specifications:
Bearings and seals
Hinges
Gaskets
Insulation & cladding
Baffles, if any
File test certificates for all above mentioned components
File: a calibration report containing details of all findings, adjustments and tolerances, calibration
procedures & records.
AS-BUILT DRAWINGS
The following 'As-built' drawings must be provided in hard copy and as soft copy.
General assembly drawings
Layout drawings
Process & Instrumentation diagram (if applicable)
Records of new & developing or modified drawings shall be maintained as part of this section.
A full drawing register must also be provided as part of this section.
This section will contain a technical description of each component together with all associated maintenance
recommended by the manufacturer or supplier. The following information will be provided.
• Equipment technical data (including manufacturers' literature and suppliers' reference list) of all
components will be provided.
• Complete Operation overview
• If PLC operated system, complete system overview with operation sequencing. Alarm and safety interlock ,
I/O list details covered in Functional design specification(FDS) documents
• Any safety precautions necessary to protect personnel and equipment during maintenance.
• General Cleaning Procedure
• Repair, overhaul, disassembly and reassembly procedures, wear components spare parts, part numbers.
• Clear and specific maintenance instructions with illustrations to explain procedures and showing
replacement parts and quantities required.
• Any special tool requirements necessary tolerance fits, alignments, tensions, adjustments, and testing
procedures if correct settings are not made.
• The expected service life of normal wear items or replacement frequency of services items in operating
hours.
• A recommendation of all spare parts to be maintained at Client.
FORMAT Intertech
Sr. CHARACTERISTIC ACCEPTANCE
ACTIVITIES TYPE OF CHECK OF Agency
NO. OF CHECK STD (AI)
RECORD
Mark Leg
orientation on
(i) Visual Inspection As Approved
cone/shell, Set- Markings of Leg
5 per Drawing Fabrication Report P H/W
up, Welding, locations
(ii) Dimensional check. Drawing
Visual
examination.
AGITATOR ASSEMBLY
i) Drawing approval of Approved
Dimension as per
agitator assembly Fabrication Report P H/W
technical specification
with support Drawing
1 Agitator ii) Drawing approval TC and approval of As per Approved
Report P H/W
of mechanical seal drawing Drawing
ii)Dynamic balancing ISO 1940 Grade Inspection
Balancing P H/W
of agitation shaft 6.3 Report
Alignment Visual
Final Approved Inspection
Final Dimensional Orientation Visual P H/W
Dwg. Report
verification as per Dimensions Measurement
As build drawing Integrity/ HT as per
2 ASME Sec VIII Test
(With All Nozzle Hydro-Testing ASME Sec VIII P H/W
Div 1 reports
Fitment) Div 1 procedure
Leak Testing Leak test as per ASME Soap Bubble Test
P H/W
Sec VIII Div 1 procedure Test reports
Inspection of
surface finish'
(Int./Ext.) before Approved Surface
testing ‘of Visual & Surface Drawing. finish
3 Surface finish P H/W
equipment. roughness meter (RA value inspection
Free from foreign Range) report
particle, rust dust
and grease.
(i)Operating panel
functions
verification
(i)Ensure Operations (ii)Interlock verification Approved
Functionality
4 and functions as per (iii) RPM verification Fabrication FAT report. P H/W
testing
specified requirement (iv)With Load drawing.
functioning trial
(v) Load cell calibration
Pipeline verification
AI Authorized Inspector (From Intertech Technologies Pvt. Ltd )
Agency Customer Authorized Third Party inspection Agency or Customer representative
H (HOLD): Stage of Inspection beyond which work shall not progress unless accepted by AI/Agency
Stage of Inspection for which AI /Agency shall be notified in advance, However work may
W (WITNESS)
proceed with AI's/Agency’s consent if AI is unable to undertake the inspection.
P(Perform) AI to perform the activity, document all results