Capacity Planning: Problems 1, 3, 7, 11, 15
Capacity Planning: Problems 1, 3, 7, 11, 15
MBAN-1302
b. A furnace repair team that services an average of four furnaces a day if the design
capacity is six furnaces a day and the effective capacity is five furnaces a day.
c. Would you say that systems that have higher efficiency ratios than other systems will
always have higher utilization ratios than those other systems? Explain.
No because the efficiency will depend on the design capacity of the system.
P+FC 16,000+9200
Q = = = 126,000 units
R-v .90-.70
11. a.
Total Processing Time by Machine
Machine
Product A B C Processing Time Needed
Units of Capacity Needed=
1 48,000 64,000 32,000 Processing Time Capacity Per Unit
2 48,000 48,000 36,000
3 30,000 36,000 24,000 Processing Time Capacit per Unit = *600 mins a day x 250 days a year =
4 60,000 60,000 30,000 *10 hrs x 60 mins = 600 minutes 150,000 minutes
Total 186,000 208,000 122,000
Units of Capacity Needed for 186,000
= = 1.24 = 2 machines
Machine A= 150,000
Units of Capacity Needed for 208,000
= = 1.39 = 2 machines
Machine B= 150,000
Units of Capacity Needed for 122,000
= = 0.81 = 1 machine
Machine C= 150,000
Option 1: 2 A machines x $40,000 = $80,000 Machine B has lowest total cost of
Option 2: 2 B machines x $30,000 = $60,000 $60,000 in which you can purchase 2
Option 3: 1 C machine x $80,000 = $80,000 machines.
CASTILLO, QUEENIE MARIE A.
MBAN-1302
b. Machine A (2 units): 186,000 min./60 min. = 3,100 hrs. x $10 = $31,000
$31,000 + $80,000 = $111,000
Machine B (2 units):208,000 min./60 min. = 3,466.67 hrs. x $11 = $38,133.37
$38,133.37 + $60,000 = $98,133.37
Machine C (1 unit): 122,000 min./60 min. = 2,033.33 hrs. x $12 = $24,399.96
$24,399.96 + $80,000 = $104,399.96
Revised Station
# Following Positional Time Assign
Workstation Eligible Time Idle
Task Time Remaining Task
Task Weight Remaining Time
1.8 a,b a(1.4) 0.4
a 1.4 7 6 1
0.4 none - - 0.4
b 0.5 6 4.6 1.8 b b(.5) 1.3
c 0.6 2 1.6 2 1.3 c,d,e e(.8) 0.5
d 0.7 2 2.2 0.5 none - - 0.5
1.8 c,d d(.7) 1.1
e 0.8 2 2.3
3 1.1 c c(.6) 0.5
f 0.5 1 1 0.5 f,g f(.5) 0 0
g 1 1 1.5 1.8 g g(1) 0.8
h 0.5 0 0.5 4 0.8 h h(.5) 0.3
0.3 none - - 0.3
1.2
CASTILLO, QUEENIE MARIE A.
MBAN-1302
b. In order of greatest positional weight. Tiebreaker: most following tasks.
Revised Station
Time Assign
Workstation Eligible Will Fit Time Idle
Remaining Task/Time
Remaining Time
4. a. 1
# Following Positional
a.2 Task Time
Task Weight
a 0.2 4 3.4
b 0.4 3 3.2
c 0.3 3 3.1
d 1.3 2 2.8
e 0.1 3 2.4
f 0.8 2 2.3
g 0.3 1 1.5
h 1.2 0 1.2
CASTILLO, QUEENIE MARIE A.
MBAN-1302
a.2 Revised Station
Time Assign
Workstation Eligible Time Idle
Remaining Task
Remaining Time
1.3 a a(.2) 1.1
1.1 b,c,e b(.4) 0.7
1 0.7 c,e c(.3) 0.4
0.4 e e(.1) 0.3
0.3 none - - 0.3
2 1.3 d,f d(1.3) 0 0
1.3 f f(.8) 0.5
3 0.5 g g(.3) 0.2
0.2 none - - 0.2
1.3 h h(1.2) 0.1
4
0.1 none - - 0.1
0.6
a.3 Percentage of Idle Time=(Idle time per cycle/ N actual X Cycle time) x100
= (.6)/(4x1.30) x 100
11.54%
a.4
Desired Output Operating Time 420
= = = 323.08 units
Cycle Time 1.3
4. b.1 Cycle Time = ∑ task time/Workstation = 4.6/2 = 2.3; shortest cycle time feasible
Revised
Time Assign Station
Workstation Eligible Time
Remaining Task Idle Time
Remaining
2.3 a a(.2) 2.1
2.1 b,c,e b(.4) 1.7
1 1.7 c,e c(.3) 1.4
1.4 e e(.1) 1.3
1.3 d,f d(1.3) 0 0
2.3 f f(.8) 1.5
2 1.5 g g(.3) 1.2
1.2 h h(1.2) 0 0
0
CASTILLO, QUEENIE MARIE A.
MBAN-1302
b.2 The time is fully utilized, therefore no idle time.
b.3
Desired Output Operating Time 420
= = = 182.61 units
Cycle Time 2.3
b.4
Desired Output Operating Time 420
= = = 91.30 units
Cycle Time 4.6
8. a.
Revised Station
Time Assign
Workstation Eligible Time Idle
Remaining Task
Remaining Time
2 a a(.5) 1.5
1 1.5 b,c b(1.4) 0.1
0.1 none - - 0.1
2 c c(1.2) 0.8
2 0.8 d,e d(.7) 0.1
0.1 none - - 0.1
3 2 e e(.5) 1.5
1.5 f f(1) 0.5
0.5 g,i i(.5) 0 0
2 g g(.4) 1.6
1.6 h,j h(.3) 1.3
4
1.3 j j(.8) 0.5
0.5 none - - 0.5
2 k k(.9) 1.1
5 1.1 m m(.3) 0.8
0.8 none - - 0.8
1.5
CASTILLO, QUEENIE MARIE A.
MBAN-1302
c. Revised Station
Time Assign
Workstation Eligible Time Idle
Remaining Task
Remaining Time
2 a a(.5) 1.5
1 1.5 b,c b(1.4) 0.1
0.1 none - - 0.1
2 c c(1.2) 0.8
2 0.8 d,e d(.7) 0.1
0.1 none - - 0.1
3 2 e,f f(1) 1
1 e e(.5) 0.5
0.5 i i(.5) 0 0
2 g,h,j j(.8) 1.2
1.2 g,h g(.4) 0.8
4
0.8 h h(.3) 0.5
0.5 none - - 0.5
2 k k(.9) 1.1
5 1.1 m m(.3) 0.8
0.8 none - - 0.8
1.5
d. Balance delay is also the idle time which is 1.5 minutes
Percentage of Idle Time= (Idle time per cycle/ N actual X Cycle time) x100
= (1.5)/(5x2) x 100
15.00%
13. Arrange the departments so they satisfy the conditions shown in the following
rating grid into a 3 × 3 format. Place department 5 in the lower left corner of the 3 × 3
grid.
3 1 8
9 7 4
5 2 6
CASTILLO, QUEENIE MARIE A.
MBAN-1302
15. a.
Department Workflow Department Workflow
The possible reason for the increased cost of repairs is because the shop
increases its repair staff thus the salary cost for all staffs would also increase in
which the shop will obtain from the additional repair costs. In order to
contemplate for the complaints on length of time, the manager may train the
employees to improve their skills and in order for them to finish their work
efficiently with the shortest time possible. On the other hand, to reduce cost of
repairs, the manager may look for lower cost items used in repairing computer,
but he should make sure that it has good quality.
2. As a manager, how would you deal with the possibility that customer satisfaction
does not always lead to customer retention?
Customer satisfaction has a very broad meaning since each customer have
different perspective of what satisfies them. As a manager, I would be optimistic
in dealing with my customers. It is a well-known fact that even if the customer is
satisfied from the company’s product, he/she may or may not patronize the
product again. In order to address this, I would attract customers with special
offers such as discounts and promos. I would also reward loyal customers so
they would feel that the management is thanking them for supporting our
products and by doing this, that customer might also attract additional
customers through word of mouth.
different sets of people who can manage the process. But it is more costly and
maintaining consistency in products is usually a problem. Compared to
decentralized processing, a single processing facility would require more
transportation to and from so more chances for contamination as well as higher
transportation costs.
Example 1: Claiming that the parts used in replacing damaged part of a car is a
new stock from supplier but it turns out it’s just a fixed part from previously
repaired car. It violated the Rights Principle because the firm is taking advantage
of its customers by using repaired part which might affect the quality of the final
product.
Example 2: Putting false labels on packaging like the ICC Stickers and DTI
inspection but when the customer try the product (i.e. Christmas Lights), it
causes fire or it doesn’t work at all. It violated the Utilitarian Principle since the
product of inaction of the service might cause harm to the user
Example 3: Using substandard raw materials for the production. It violated the
Fairness Principle because maybe the customers will pay a higher price for a
poorly done product.
CASTILLO, QUEENIE MARIE A.
MBAN-1302
10. Define and contrast control limits, specifications, and process variability.
Control limits are lines between random and nonrandom deviations from
the mean of the distribution. It is set in order to see what the acceptable values
within the process are and it helps to identify in which part does the process
became out of control. The firm will manually calculate control limits.
Specifications are range of acceptable values in which individual units of output
CASTILLO, QUEENIE MARIE A.
MBAN-1302
12. A new order has come into your department. The capability of the process used for
this type of work will enable virtually all of the output to be well within the specs. (See
Figure 10.15B.)
a. What benefits might be derived from this situation?
b. What alternatives might be considered by the manager?
a. If all output are well within specifications, it reduce scrap, rework, and
warranty claims, it maximizes productivity, improve resource utilization,
reduce cost, improved client satisfaction and overall increase in operation
efficiency.
b. The manager must be mindful about the variability of the process and
carefully look for errors in the process. The production should be extra
careful because even though outputs are within specifications, there might
be underlying problems that the manager didn’t foresee. They could also
research improve the process in order to get higher efficiency and
utilization.