Bar Chart Project Schedule Rainy Days
Bar Chart Project Schedule Rainy Days
Bar Chart Project Schedule Rainy Days
11 18 20 17 24
11 29 49 66 90
DESCRIPTION UNIT QTY WT% W1 W2 W1 W2 W3 W4 W1 W2 W4 W5 W3 W4 W5 W1 W2 W3 W4
GENERAL REQUIREMENTS
Material Sampling and Testing lot 1.00 0.58% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% ###
As-built Shop Drawings (CAD Generated) lot 1.00 0.78% 0.16% 0.16% 0.16% 0.16% 0.16%
Bonds and Insurances lot 1.00 0.97% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06%
Temporary Facilities lot 1.00 2.62% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15%
Permits and Licenses lot 1.00 1.46% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21% ###
Overhead and Contingency lot 1.00 1.46% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09%
Cleanliness and Waste Disposal lot 1.00 0.49% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03%
Construction Board and Board-Up Barricade lot 1.00 0.58% 0.58% ###
Provision of Temporary Fence lot 1.00 0.97% 0.97% ###
Provision of Bluesack lot 1.00 0.49% 0.49% ###
EARTHWORKS
Clearing and Grubbing m3 15,716.00 4.58% 1.53% 1.53% 1.53% ###
Area Drains set 160.00 0.45% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% ###
Cross Drains lm 630.00 0.66% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% ###
a. 200mm Ø PVC (thru pipe) set 783.00 5.38% 0.90% 0.90% 0.90% 0.90% 0.90% 0.90% ###
Clearing and Grubbing of Storm Drainage m2 9,822.00 2.86% 0.72% 0.72% 0.72% 0.72% ###
Excavation of Storm Drainage m2 9,822.00 2.86% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% ###
ROADWORKS
Subgrade Preparation m2 13,097.00 13.15% 2.19% 2.19% 2.19% 2.19% 2.19% 2.19% ###
Aggregate Sub-base Course (200mm thick) m2 13,097.00 5.26% 0.88% 0.88% 0.88% 0.88% 0.88% 0.88% ###
Aggregate Base Course (150mm thick) m2 13,097.00 3.97% 0.57% 0.57% 0.57% 0.57% 0.57% 0.57% 0.57% ###
ELECTRICAL WORKS
Street Light Connection
Rough-ins lot 1.00 3.88% 0.55% 0.55% 0.55% 0.55% 0.55% 0.55% 0.55% ###
b. 14 sqmm TTHN lm 2,350.00 0.46% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% ###
c. PVC Pipe 25mm Ø lm 2,350.00 0.46% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% ###
LEGEND:
Prepared by: CRITICAL PATH
PARALLEL ACTIVITIES
EDGARDO C. CEREDON JR. WORKING DAYS EXCLUDE ALL SUNDAYS
Project Engineer
JLSR Hauling and General Contractor
jlsr Hauling and General Contractor
PROJECT : DESIGN AND CONSTRUCTION OF PROPOSED SARIAYA RELOCATION SITE DEVELOPMENT
LOCATION : Brgy. Castañas, Sariaya, Quezon
OWNER : Arthocem Concrete Industries Inc.
BAR CHART
MAY 20 - 31, 2019 JUNE 1 - 23, 2019 JULY 1 - 31, 2019 AUGUST 1 - 31, 2019 SEPTEMBER 1-28, 2019
11 18 20 17 24
11 29 49 66 90
DESCRIPTION UNIT QTY WT% W1 W2 W1 W2 W3 W4 W1 W2 W4 W5 W3 W4 W5 W1 W2 W3 W4
GENERAL REQUIREMENTS
Mobilization/Demobilization lot 1.00 13.58% 6.79% 6.79%
Construction Survey, Site Survey and Stake-out lot 1.00 0.97% 0.49% 0.49% ###
Material Sampling and Testing lot 1.00 0.58% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% ###
As-built Shop Drawings (CAD Generated) lot 1.00 0.78% 0.16% 0.16% 0.16% 0.16% 0.16%
Bonds and Insurances lot 1.00 0.97% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06%
Temporary Facilities lot 1.00 2.62% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15%
Permits and Licenses lot 1.00 1.46% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21% ###
Overhead and Contingency lot 1.00 1.46% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09%
Cleanliness and Waste Disposal lot 1.00 0.49% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03%
Construction Board and Board-Up Barricade lot 1.00 0.58% 0.58% ###
Provision of Temporary Fence lot 1.00 0.97% 0.97% ###
Provision of Bluesack lot 1.00 0.49% 0.49% ###
EARTHWORKS
Clearing and Grubbing m3 15,716.00 4.58% 1.53% 1.53% 1.53% ###
Area Drains set 160.00 0.45% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% ###
Cross Drains lm 630.00 0.66% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% ###
a. 200mm Ø PVC (thru pipe) set 783.00 5.38% 0.90% 0.90% 0.90% 0.90% 0.90% 0.90% ###
Clearing and Grubbing of Storm Drainage m2 9,822.00 2.86% 0.72% 0.72% 0.72% 0.72% ###
Excavation of Storm Drainage m2 9,822.00 2.86% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% ###
ROADWORKS
Subgrade Preparation m2 13,097.00 13.15% 2.19% 2.19% 2.19% 2.19% 2.19% 2.19% ###
Aggregate Sub-base Course (200mm thick) m2 13,097.00 5.26% 0.88% 0.88% 0.88% 0.88% 0.88% 0.88% ###
Aggregate Base Course (150mm thick) m2 13,097.00 3.97% 0.57% 0.57% 0.57% 0.57% 0.57% 0.57% 0.57% ###
ELECTRICAL WORKS
Street Light Connection
Rough-ins lot 1.00 3.88% 0.55% 0.55% 0.55% 0.55% 0.55% 0.55% 0.55% ###
b. 14 sqmm TTHN lm 2,350.00 0.46% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% ###
c. PVC Pipe 25mm Ø lm 2,350.00 0.46% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% ###
11 18 20 27 14
11 29 49 76 90
DESCRIPTION UNIT QTY WT% W1 W2 W1 W2 W3 W4 W1 W2 W4 W5 W1 W2 W3 W4 W5 W1 W2
GENERAL REQUIREMENTS
Mobilization/Demobilization lot 1.00 13.58% 6.79% 6.79%
Construction Survey, Site Survey and Stake-out lot 1.00 0.97% 0.49% 0.49% ###
Material Sampling and Testing lot 1.00 0.58% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% ###
As-built Shop Drawings (CAD Generated) lot 1.00 0.78% 0.16% 0.16% 0.16% 0.16% 0.16%
Bonds and Insurances lot 1.00 0.97% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06%
Temporary Facilities lot 1.00 2.62% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15%
Permits and Licenses lot 1.00 1.46% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21% ###
Overhead and Contingency lot 1.00 1.46% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09%
Cleanliness and Waste Disposal lot 1.00 0.49% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03%
Construction Board and Board-Up Barricade lot 1.00 0.58% 0.58% ###
Provision of Temporary Fence lot 1.00 0.97% 0.97% ###
Provision of Bluesack lot 1.00 0.49% 0.49% ###
EARTHWORKS
Clearing and Grubbing m3 15,716.00 4.58% 1.53% 1.53% 1.53% ###
Area Drains set 160.00 0.45% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% 0.05% ###
Cross Drains lm 630.00 0.66% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% ###
a. 200mm Ø PVC (thru pipe) set 783.00 5.38% 0.90% 0.90% 0.90% 0.90% 0.90% 0.90% ###
Clearing and Grubbing of Storm Drainage m2 9,822.00 2.86% 0.72% 0.72% 0.72% 0.72% ###
Excavation of Storm Drainage m2 9,822.00 2.86% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% 0.36% ###
ROADWORKS
Subgrade Preparation m2 13,097.00 13.15% 2.19% 2.19% 2.19% 2.19% 2.19% 2.19% ###
Aggregate Sub-base Course (200mm thick) m2 13,097.00 5.26% 0.88% 0.88% 0.88% 0.88% 0.88% 0.88% ###
Aggregate Base Course (150mm thick) m2 13,097.00 3.97% 0.57% 0.57% 0.57% 0.57% 0.57% 0.57% 0.57% ###
ELECTRICAL WORKS
Street Light Connection
Rough-ins lot 1.00 3.88% 0.55% 0.55% 0.55% 0.55% 0.55% 0.55% 0.55% ###
b. 14 sqmm TTHN lm 2,350.00 0.46% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% ###
c. PVC Pipe 25mm Ø lm 2,350.00 0.46% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% ###
LEGEND:
Prepared by: ACTUALACCOMPLISHMENT
TARGET ACCOMPLISHMENT
EDGARDO C. CEREDON JR. WORKING DAYS EXCLUDE ALL SUNDAYS
Project Engineer
JLSR Hauling and General Contractor
jlsr Hauling and General Contractor
PROJECT : DESIGN AND CONSTRUCTION OF PROPOSED SARIAYA RELOCATION SITE DEVELOPMENT
LOCATION : Brgy. Castañas, Sariaya, Quezon
OWNER : Arthocem Concrete Industries Inc.
SUBJECT : REVISED SCHEDULE
BAR CHART
MAY 20 - 31, 2019 JUNE 1 - 23, 2019 JULY 1 - 31, 2019 AUGUST 1 - 31, 2019 SEPTEMBER 1-28, 2019 OCTOBER 1-31, 2019 NOVEMBER 1-30, 2019 DECEMBER 1-4, 2019
11 18 20 17 24 27 24 4
Construction Survey, Site Survey and Stake-out lot 1.00 0.97% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04%
Material Sampling and Testing lot 1.00 0.58% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03%
As-built Shop Drawings (CAD Generated) lot 1.00 0.78% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11%
Bonds and Insurances lot 1.00 0.97% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06%
Temporary Facilities lot 1.00 2.62% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15%
SUBTOTAL 7.63%
STORM DRAINAGE SYSTEM
Drainage System, Pipelines, 600mm RCP lm 2,585.00 13.26% 1.66% 1.66% 1.66% 1.66% 1.66% 1.66% 1.66% 1.66%
Area Drains set 160.00 0.45% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07%
Cross Drains lm 630.00 0.66% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11%
Clearing and Grubbing of Storm Drainage m2 9,822.00 2.86% 0.72% 0.72% 0.72% 0.72%
Excavation of Storm Drainage m2 9,822.00 2.86% 0.48% 0.48% 0.48% 0.48% 0.48% 0.48%
SUBTOTAL 26.11%
SEWER DRAINAGE SYSTEM
Drainage System Pipelines, 200mm Ø PVC lm 2,100.00 x x x x x x x
SUBTOTAL
ROADWORKS
Subgrade Preparation m2 13,097.00 13.15% 1.88% 1.88% 1.88% 1.88% 1.88% 1.88% 1.88%
Aggregate Sub-base Course (200mm thick) m2 13,097.00 5.26% 0.75% 0.75% 0.75% 0.75% 0.75% 0.75% 0.75%
Aggregate Base Course (150mm thick) m2 13,097.00 3.97% 0.57% 0.57% 0.57% 0.57% 0.57% 0.57% 0.57%
SUBTOTAL 22.38%
WATER SUPPLY SYSTEM
Construction of Over-head Water Tank lot 1.00 13.67% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59%
SUBTOTAL 13.67%
ELECTRICAL WORKS
Street Light Connection
Rough-ins lot 1.00 3.88% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49%
b. 14 sqmm TTHN lm 2,350.00 0.46% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06%
c. PVC Pipe 25mm Ø lm 2,350.00 0.46% 0.66% 0.66% 0.66% 0.66% 0.66% 0.66% 0.66% 0.66%
SUBTOTAL 5.25% 0.66% 0.66% 0.66% 0.66% 0.66% 0.66% 0.66% 0.66%
TOTAL 100.00%
WEEKLY ACCOMPLISHMENT 9.40% 2.69% 3.74% 3.74% 2.21% 1.67% 4.04% 5.02% 5.02% 5.02% 4.31% 3.83% 3.83% 2.64% 0.98% 0.98% 4.78% 5.88% 5.88% 5.88% 5.88% 5.88% 5.88% 4.00% 0.06% 6.79%
ACCUMULATED ACCOMPLISHMENT (TARGET) 0 9.40% 12.10% 15.83% 19.57% 21.78% 23.45% 23.45% 27.49% 32.51% 32.51% 37.54% 42.56% 42.56% 46.87% 50.70% 54.53% 57.17% 58.15% 59.14% 63.91% 69.79% 75.67% 81.55% 87.43% 93.31% 99.19% 103.19% 103.26% 110.05%
ACCUMULATED ACCOMPLISHMENT (ACTUAL) 0 20.26% 21.30% 22.57% 25.00% 27.97% 30.44% 30.44% 32.77% 35.76% 36.92% 37.24% 41.20% 42.07% 45.21% 46.78% 48.70% 51.60% 53.23%
LEGEND:
Prepared by: ADDITIONAL WORK
PARALLEL ACTIVITIES
EDGARDO C. CEREDON JR. WORKING DAYS EXCLUDE ALL SUNDAYS
Project Engineer
JLSR Hauling and General Contractor
jlsr Hauling and General Contractor
PROJECT : DESIGN AND CONSTRUCTION OF PROPOSED SARIAYA RELOCATION SITE DEVELOPMENT
LOCATION : Brgy. Castañas, Sariaya, Quezon
OWNER : Arthocem Concrete Industries Inc.
BAR CHART
MAY 20 - 31, 2019 JUNE 1 - 23, 2019 JULY 1 - 31, 2019 AUGUST 1 - 31, 2019 SEPTEMBER 1-28, 2019 OCTOBER 1-31, 2019 NOVEMBER 1-30, 2019 DECEMBER 1-4, 2019
11 18 20 17 24 27 24 4
Temporary Facilities lot 1.00 2.62% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15%
Permits and Licenses lot 1.00 1.46% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21%
Overhead and Contingency lot 1.00 1.46% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09%
Cleanliness and Waste Disposal lot 1.00 0.49% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03%
Construction Board and Board-Up Barricade lot 1.00 0.58% 0.58%
Area Drains set 160.00 0.45% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07%
Cross Drains lm 630.00 0.66% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11%
a. 200mm Ø PVC (thru pipe) set 783.00 5.38% 0.90% 0.90% 0.90% 0.90% 0.90% 0.90%
Clearing and Grubbing of Storm Drainage m2 9,822.00 2.86% 0.72% 0.72% 0.72% 0.72%
Excavation of Storm Drainage m2 9,822.00 2.86% 0.48% 0.48% 0.48% 0.48% 0.48% 0.48%
ROADWORKS
Subgrade Preparation m2 13,097.00 13.15% 1.88% 1.88% 1.88% 1.88% 1.88% 1.88% 1.88%
Aggregate Sub-base Course (200mm thick) m2 13,097.00 5.26% 0.75% 0.75% 0.75% 0.75% 0.75% 0.75% 0.75%
Aggregate Base Course (150mm thick) m2 13,097.00 3.97% 0.57% 0.57% 0.57% 0.57% 0.57% 0.57% 0.57%
ELECTRICAL WORKS
Street Light Connection
Rough-ins lot 1.00 3.88% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49%
b. 14 sqmm TTHN lm 2,350.00 0.46% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06%
c. PVC Pipe 25mm Ø lm 2,350.00 0.46% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06%
TOTAL 100.00%
WEEKLY ACCOMPLISHMENT 9.40% 2.69% 3.74% 3.74% 2.21% 1.67% 4.04% 5.02% 5.02% 5.02% 4.31% 3.83% 3.83% 2.64% 0.98% 0.98% 3.52% 4.62% 4.62% 4.62% 4.62% 4.62% 4.62% 2.75% 0.06% 6.79%
ACCUMULATED ACCOMPLISHMENT (TARGET) 0 9.40% 12.10% 15.83% 19.57% 21.78% 23.45% 23.45% 27.49% 32.51% 32.51% 37.54% 42.56% 42.56% 46.87% 50.70% 54.53% 57.17% 58.15% 59.14% 62.66% 67.28% 71.90% 76.53% 81.15% 85.78% 90.40% 93.14% 93.21% 100.00%
ACCUMULATED ACCOMPLISHMENT (ACTUAL) 0 20.26% 21.30% 22.57% 25.00% 27.97% 30.44% 30.44% 32.77% 35.76% 36.92% 37.24% 41.20% 42.07% 45.21% 46.78%
LEGEND:
Prepared by: CRITICAL PATH
PARALLEL ACTIVITIES
EDGARDO C. CEREDON JR. WORKING DAYS EXCLUDE ALL SUNDAYS
Project Engineer
JLSR Hauling and General Contractor
jlsr Hauling and General Contractor
PROJECT : DESIGN AND CONSTRUCTION OF PROPOSED SARIAYA RELOCATION SITE DEVELOPMENT
LOCATION : Brgy. Castañas, Sariaya, Quezon
OWNER : Arthocem Concrete Industries Inc.
SUBJECT : REVISED SCHEDULE
BAR CHART
MAY 20 - 31, 2019 JUNE 1 - 23, 2019 JULY 1 - 31, 2019 SEPTEMBER 1-28, 2019 OCTOBER 1-31, 2019 NOVEMBER 1-30, 2019 DECEMBER 1-4, 2019
11 18 20 24 27 24 4
Construction Survey, Site Survey and Stake-out lot 1.00 0.97% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.62% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04% 0.04%
Material Sampling and Testing lot 1.00 0.58% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.35% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03%
As-built Shop Drawings (CAD Generated) lot 1.00 0.78% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11%
Bonds and Insurances lot 1.00 0.97% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.91% 0.06%
Temporary Facilities lot 1.00 2.62% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 0.15% 2.47% 0.15%
Permits and Licenses lot 1.00 1.46% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21% 0.21% 1.46%
Overhead and Contingency lot 1.00 1.46% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 0.09% 1.37% 0.09%
Cleanliness and Waste Disposal lot 1.00 0.49% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.03% 0.46% 0.03%
Construction Board and Board-Up Barricade lot 1.00 0.58% 0.58% 0.58%
Area Drains set 100.00% 160.00 0.45% 0.07% 0.07% 0.07% 0.07% 0.07% 0.07% 0.45%
Cross Drains lm 630.00 0.66% 0.11% 0.11% 0.11% 0.11% 0.11% 0.11% 0.66%
Clearing and Grubbing of Storm Drainage m2 100.00% 9,822.00 2.86% 0.72% 0.72% 0.72% 0.72% 2.86%
Excavation of Storm Drainage m2 100.00% 9,822.00 2.86% 0.48% 0.48% 0.48% 0.48% 0.48% 0.48% 2.86%
SUBTOTAL
ROADWORKS
Subgrade Preparation m2 13,097.00 13.15% 1.88% 1.88% 1.88% 1.88% 1.88% 1.88% 1.88%
Aggregate Sub-base Course (200mm thick) m2 13,097.00 5.26% 0.75% 0.75% 0.75% 0.75% 0.75% 0.75% 0.75%
Aggregate Base Course (150mm thick) m2 13,097.00 3.97% 0.57% 0.57% 0.57% 0.57% 0.57% 0.57% 0.57%
SUBTOTAL 22.38%
WATER SUPPLY SYSTEM
Construction of Over-head Water Tank lot 1.00 13.67% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 8.92% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59% 0.59%
SUBTOTAL 65.22% 13.67% 8.92%
ELECTRICAL WORKS
Street Light Connection
Rough-ins lot 1.00 3.88% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49% 0.49%
b. 14 sqmm TTHN lm 2,350.00 0.46% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06%
c. PVC Pipe 25mm Ø lm 2,350.00 0.46% 0.66% 0.66% 0.66% 0.66% 0.66% 0.66% 0.66% 0.66%
SUBTOTAL 5.25% 0.66% 0.66% 0.66% 0.66% 0.66% 0.66% 0.66% 0.66%
TOTAL 100.00%
WEEKLY ACCOMPLISHMENT 9.40% 2.69% 3.74% 3.74% 2.21% 1.67% 4.04% 5.02% 5.02% 5.02% 4.31% 3.83% 3.83% 2.64% 0.98% 0.98% 4.78% 5.88% 5.88% 5.88% 5.88% 5.88% 5.88% 4.00% 0.06% 6.79%
ACCUMULATED ACCOMPLISHMENT (TARGET) 0 9.40% 12.10% 15.83% 19.57% 21.78% 23.45% 27.49% 32.51% #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
ACCUMULATED ACCOMPLISHMENT (ACTUAL) 0 20.26% 21.30% 22.57% 25.00% 27.97% 30.44% 32.77% 35.76% 37.24% 41.20% 45.21% 46.78% 48.70% 51.60% 53.23%
LEGEND:
Prepared by: ADDITIONAL WORK
PARALLEL ACTIVITIES
EDGARDO C. CEREDON JR. WORKING DAYS EXCLUDE ALL SUNDAYS
Project Engineer
JLSR Hauling and General Contractor