Sabp y 067
Sabp y 067
Contents
1 Purpose...........................................................2
2 Scope.............................................................. 2
3 Disclaimer....................................................... 2
4 Conflicts with Mandatory Standards............... 2
5 References......................................................3
6 Definitions and Acronyms............................... 4
7 Instructions...................................................... 5
Appendix 1 - Factory/Site Acceptance
Test Procedures and Reporting….... 8
Appendix 2 - Test Records Sheets………...……. 22
Appendix 3 - System Punch List………….….….. 49
Appendix 4 - Test Equipment Calibration
Certificates…….............................. 50
Appendix 5 - Skid Instrument Calibration
Certificates..............................…… 51
1 Purpose
2 Scope
This Best Practice specifies the requirements to FAT and SAT Custody Truck
Bottom Loading and Unloading Metering Systems as specified by 34-SAMSS-167 and
34-SAMSS-168, to demonstrate, to the fullest extent possible at the manufacturer’s
facilities and site location, that the subject Metering Systems meet all requirements of
project Functional Specification Document before being shipped to the site and before
commissioning.
This Best Practice is not applicable to truck loading and unloading metering systems
used for LPG, heavy fuel oil with viscosities greater than 180 cSt, molten sulfur or
asphalt.
3 Disclaimer
This Best Practice is being provided for the general guidance and benefit of Saudi
Aramco engineers conducting FAT and SAT. The use of this Best Practice during
factory acceptance test or site acceptance test; however, does not relieve the
manufacturer from his responsibility or duty to confirm or to verify the accuracy of any
information presented or from his contractual liability to perform an accurate FAT that
conforms to Mandatory Saudi Aramco Engineering Requirements. Moreover, this Best
Practice is intended only to provide guidelines for Saudi Aramco engineers and shall
not be considered as a replacement for the Mandatory Saudi Aramco Engineering
Requirements. Saudi Aramco® is a registered trademark of the Saudi Arabian Oil
Company.
In the event of a conflict between this Best Practice and other Mandatory Saudi Aramco
Engineering Requirement, the Mandatory Saudi Aramco Engineering Requirement shall
govern.
Page 2 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
5 References
Page 3 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Factory Acceptance Test (FAT): A series of tests conducted at the vendor’s plant on
the integrated system to demonstrate compliance of the System with the job
specification requirements, to the maximum extent possible in the Contractor's factory
environment.
Pre-FAT: A comprehensive test, completed by the vendor prior to FAT, which ensures
that the System can be tested according to FAT procedures without unanticipated
delays.
Page 4 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Proponent: The Saudi Aramco organization responsible for signing the Saudi Aramco
Form SA-7213, Mechanical Completion Certificate. In the context of this document,
the Proponent is the Saudi Aramco organization responsible for operating and
maintaining the metering facility.
Project Management Team (PMT): The team of Company individuals who are
assigned the responsibility of managing the project.
Site Acceptance Test (SAT): A series of tests conducted at the site location on the
installed System that demonstrates compliance with all requirements, except
availability.
System: The metering skid system that is procured under the Contract.
Vendor: The party that supplies or sells integrated metering systems, metering
equipment, or components sometimes called Integrator.
7 Instructions
7.1 General
a. The Practice laid out in this procedure are designed to provide a level of
confidence in the truck loading and unloading metering systems. The tests
are not designed to recalibrate individual instruments.
b. The FAT shall be conducted in approved manufacturer plant using flow
media (water or as recommended by the manufacturer) to simulate actual
loading and unloading operation. Vendor shall provide all needed utilities
to perform the FAT.
c. Pre FAT/SAT shall be conducted prior to the official FAT/SAT by
manufacturer to ensure the metering system is ready for the official
FAT/SAT. Pre FAT/SAT report shall be submitted to Operating
Department, PMT and P&CSD/Custody Measurement Unit for review and
comments.
d. Ensure availability, copy, of approved Functional Specification Document
(FSD) and P&ID during the FAT and SAT. Also, a copy of calibration
certificate for all instruments and equipment for review.
e. FAT and SAT requirements are the same with exception that the SAT will
take place under normal operation conditions at the site after skid
installation and commissioning where hydrocarbon will be introduced in the
metering system.
f. FAT and SAT of truck loading metering system and unloading metering
system are the same with exception that additional tests will be required for
Page 5 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
7.2 Pre-requisites
a. Ensure that all parts of the metering system with its components have been
integrated as per 34-SAMSS-167 for truck loading metering system, and
34-SAMSS-168 for truck unloading metering system, and are ready for
FAT/SAT.
b. Ensure that all skid components were purchased from approved Saudi
Aramco suppliers, where specified.
c. All test equipment needed for all aspects of FAT/SAT shall be identified.
Valid calibration certificates of the test equipment shall be available prior to
the start of FAT/SAT.
d. Ensure the Vendor conducted a Pre-FAT/SAT. It is basically a trial run of all
FAT/SAT procedures to identify and correct any deficiencies that could cause
delays during FAT/SAT. The pre-FAT/SAT is carried out without the
presence of Company representatives. The purpose of the pre-FAT/SAT is to
ensure that all hardware, software, and application program deficiencies have
been identified and corrected before the official FAT/SAT. This includes but
not limited to:
Wiring from the test panel to the I/O points
Wiring inside the equipment
I/O modules
e. A formal, signed pre-FAT/SAT report shall be submitted to Saudi Aramco
before commencement of FAT/SAT, the vendor shall complete Pre-FAT/SAT
utilizing the approved FAT/SAT procedure/report.
Page 6 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
7.3.2 All documents referenced in the FAT/SAT Procedure shall be listed with
their revision numbers and publication date. Documentation which is
part of System and/or is needed during FAT/SAT shall be available.
Specific items typically include User's Manuals, Maintenance Manuals,
configuration drawings, connection drawings, database listings, logic
drawings, instrumentation loop drawings (ILD), P&IDs.
7.3.3 Appendices
Appendices 1 to 6 are the FAT and SAT reports that list the required
tests and documents for truck loading metering system and truck
unloading metering systems, when approved by the Company
representatives, these reports shall be used as the certification that the
FAT and SAT has been successfully completed.
Appendix 1 - Factory/Site Acceptance Tests Procedure and Reporting
Appendix 2 - Test Record Sheets
Appendix 3 - System Punch List
Appendix 4 - Test Equipment Calibration Certificates
Appendix 5 - Skid Instruments Calibration Certificates
Revision Summary
22 June 2016 New Saudi Aramco Best Practice that establishes guidelines in conducting Factory Acceptance
Test (FAT) and Site Acceptance Test (SAT) for Custody Truck Bottom Loading and Unloading
Metering Systems.
Page 7 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
1. Introduction
This document is the Factory/Site Acceptance Test (FAT/SAT) Best Practice and
Reporting to inspect and verify the functionality of Truck Loading Metering System,
Truck Unloading Metering System and associated control. This document contains
detailed test procedures with associated lists, tables and a buyer’s comment and sign off
area in order to verify and document that each test has been carried out successfully and in
accordance with the buyer’s specification (FSD).
The Practice laid out in this procedure are designed to provide a level of confidence in the
truck loading and unloading metering systems. The testes are not designed to recalibrate
individual instruments but to demonstrate the functionality of the system and its operation
in accordance with project specification.
The SAT requirements are the same with exception that the SAT will take place under
normal operation conditions at the site after skid installation and commissioning where
hydrocarbon will be introduced in the metering system.
2. Test Overview
The test shall follow a structured plan according to this document. The FAT and SAT shall
begin with a full review of documentation, followed by the inspection of the skid and flow
test. During the flow test the functionality of the instruments shall be verified.
Any test failures shall be fully documented and discussed at the daily review. Failures shall
be evaluated and prioritized according to impact on both further system testing and test
schedule time frame. Test schedule shall be modified to continue testing on the unaffected
part of the system. Low priority failures which cannot be rectified immediately and do not
prevent further testing shall be revisited at the end of the scheduled test period.
Truck Loading Metering System shall be checked against project FSD and 34-SAMSS-167.
Truck Unloading Metering System shall be checked against project FSD and 34-SAMSS-168.
Any deviation from these documents shall be recorded as part of the punch-list and resolved
prior to shipping the metering system to the site.
Page 8 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
3. System Checks
FAT and SAT shall include the following tests, checks, and documents as minimum.
Additional tests may be added and recorded under unstructured/ miscellaneous tests
(Record Sheet # 22):
Table 4.1
Modules BI Number Plant Name Plant # Skid Tag # Service Test Medium
Bottom AA-123456 AAAAAA 123 12-3-45689 Diesel,
Loading Gasoline
Kerosene
Crude Oil or
other
As a minimum, the following documents, Table 5.1, shall be made available prior to
FAT/SAT:
Table 5.1
Title Document # Revision Date
Approved Functional Specification Document
Approved Piping and Instrumentation Diagram
Pre FAT test results
Add Approved GA drawings
Page 9 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
6. Test Equipment
All test equipment needed for all aspects of FAT shall be identified and be made available.
Valid calibration/certification reports of test equipment shall be available (Appendix 4).
As a minimum, the following equipment, Table 6.1, is required:
Table 6.1
Cal.
Description Manufacturer Model S/N
Expiration Date
Digital Multi-meter
Timer Counter
Hart Communicator
Pulse generator
Dead Weight Tester
Page 10 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Cal.
Description Manufacturer Model S/N
Expiration Date
Decade Resistance Box
Digital thermometer
Tape measure
Other as applicable
7. Utility requirements
Table 7.1
Description Rating
Water Pump To accommodate the required flow rate
Water Storage Tank To accommodate the required volume
Control panel power supply To accommodate the required VAC
Hoses and Coupler/adapter To accommodate the required valve sizes
Air Compressor To test operation of Air Eliminator
Check that all system component (listed in Table 8.1) were supplied by approved
manufacturer.
Calibration certificate shall be provided (Appendix 5) for all instruments listed in the
table as applicable.
Table 8.1
Description Manufacturer Model S/N
Preset Controller
Flow Meters
Flow Control Valve
Solenoid valve
RTD/Temperature Transmitter
Pressure Transmitter
Differential Pressure Switch
Ball/Plug Valve
Page 11 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
9. Visual inspection
Visual inspection consists of three sections; Mechanical, Electrical and
Instrumentation.
The tests shall demonstrate and document the satisfaction of all requirements of the
System as stated in the applicable references listed in Section 5. Also, to verify the
skid is in line with relevant P&ID, GA and 34-SAMSS-167 or 34-SAMSS-168.
List of tests and observation shall be Recorded Test Record Sheet # 1 (Appendix 2).
Page 12 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Test Arm 2 Pump Enable by having the unit in ‘Hardware Test Mode’, force the
status of the discrete output and observe change of dry contact status from the
designated terminals at the CJB.
Record observations in Test Record Sheet # 3 (Appendix 2).
Page 13 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
This test to verify the functionality of low and high level switches in the Air
Eliminator and switches set-points (low/high).
The Solenoid will energize (vent open) when liquid is below the low level switch.
The Solenoid will de-energize (vent closed) when liquid covers the high level
switch.
Verify level switches set-points against requirements.
Record observations in Test Record Sheet # 8 (Appendix 2)
Page 14 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
This will bring the controller in to overfill bypass mode. Ground mode
cannot be bypassed.
Ground light BLUE should be go on, RED and GREEN indicators will
be flashing and 5 wire / 2 wire mode indicators will be lit.
The detector will return to normal mode from bypass mode once the test
kit or truck is disconnected.
Record observations in Test Record Sheet # 11 (Appendix 2).
Page 15 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
11.1 General
Flow test at the manufacturer plant shall be wet test/liquid. Flow test during
commissioning shall be actual product.
During FAT, signals from Terminal Management Systems will be simulated,
however, during the SAT all signals will be coming from the TMS and loading
and unloading operations will controlled by the TMS.
Prior to flow test ensure all loading and unloading permissives are contacted from
Truck Grounding, Truck Overfill (loading only), Level Switch, Vapor Switch and
Key lock Override.
Pre-set Controller Arm 1 and Arm 2 Loading/Unloading Permissive shall be
wired.
Pre-set Controller Arm 1 and Arm 2 Pump Enable shall be wired.
Note: For Truck Unloading application, one meter and two unloading arms are
installed per skid.
This test is to demonstrate the functionality of Ramp up, Ramp Down, Start and
Stop loading operation, smooth operation, completion of loading operation.
a. Apply 120 VAC power supply for pre-set Controller, Truck Grounding/Truck
Overfill, Level Switch, and Vapor Switch.
b. Line up truck for loading.
c. Set key lock override position switch if required.
d. Pre-set Controller default display of “Connect Interlock” should change to
“Order number” upon connecting truck grounding/overfill plug to the truck.
e. Pre-set Controller should allow any number to be entered for “Order Number”,
“Driver Number” and “Truck Number” in succession.
Page 16 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
f. Enter ‘Arm 1 Pre-set Quantity followed by start and Arm 1 should start counting
g. Verify that Vapor switch is triggered within 30 seconds after Start button is
pressed for Arm 1.
h. Enter ‘Arm 2 Pre-set Quantity followed by start and Arm 2 should start counting
i. Ramp-up for Slow Start Quantity
Verify Arm 1 and Arm 2 Flow Rate at the Pre-set Controller to be 650L/M when
the delivered quantity is less than 1500L (Slow Start Quantity).
j. Ramp-up after Slow Start Quantity
Verify that the flow rate for arm 1 and 2 ramp up to the configured value
XXXXL/M when the delivered quantity reached the configured value XXXXL.
k. Ramp-down for Pre-stop Quantity
The Pre-set Controller will implement the following (example) ramp down
flow rates:
Remaining (L) Flow Rate (L/M)
900 1125
600 675
400 450
200 225
Note: Remaining and flow rate may vary from system to another system.
Verify that Arm 1 and Arm 2 stops counting when it reaches the “Pre-set
Quantity” for each arm.
Record observations in Test Record Sheet # 17 (Appendix 2)
Page 17 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
d. Truck Overflow
Disconnect one leg of Level Switch indication contact connection at the CJB
and verify that Arm 1 Counter is not incrementing.
e. Faulty Pressure Transmitter
Disconnect one leg of pressure transmitter connection at the EJB and verify that
Arm 1 Counter is not incrementing.
Arm 1 will be rendered unavailable for loading unless the error is corrected.
f. Faulty Temperature Element
Disconnect one leg of Temperature Element connection at the EJB and verify
that:
Arm 1 Counter is not incrementing.
Arm 1 will be rendered unavailable for loading unless the error is corrected.
g. Breached of Level B Pulse Security
Disconnect Arm 1 Pulse A Input connection, during loading operation, at
EJB and verify that Arm 1 Counter is not incrementing. Arm 1 will be
rendered unavailable for loading unless the error is corrected.
Disconnect Arm 1 Pulse B Input connection, during loading operation, at
EJB and verify that Arm 1 Counter is not incrementing. Arm 1 will be
rendered unavailable for loading unless the error is corrected.
Disconnect the wires from pick-up A prior to loading, start the loading
operation the process shall stop after the time set in “Flow Error Delay” and
ensure the error message FLOW ERROR will be displayed.
Disconnect the wires from pick-up B prior to loading, start the loading
operation the process shall stop after the time set in “Flow Error Delay” and
ensure the error message FLOW ERROR will be displayed
Disconnect the wires from pick-up A & B and start the loading process.
Check the response from the Pre-set Controller. The NO FLOW ALARM
shall be raised after the time set in “No Flow Time out”
Reverse the connection to meter pick up A and B (B connected to A and A
connected to B).
Record observations in test Record Sheet # 18 (Appendix 2)
Page 18 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Initiate loading operation for Arm 2 and initiate the following actions.
Repeat tests of a to f for loading Arm 2
Record observations in Test Record Sheet # 18 (Appendix 2)
11.4 Unloading Operation
Unloading skid is equipped with Pump and Adjustable Frequency Drive (AFD).
This test will be for operation of the skid, the pump, and AFD.
11.4.1 AFD Test
Testing of AFD will consist of two tests; at low speed and at high speed.
The sequence will be Low-High-Low (starting of unloading operation-
normal unloading operation-end of unloading operation).
Along with that observing the flow rate at different speed to ensure the
speed of the AFD matching the flow rate (low speed at low flow and
high speed at high flow).
Record observations in Test Record Sheet # 19 (Appendix 2).
11.4.2 Unloading and Pump Operation
Prior to the FAT/SAT the pump shall be pre tested. This include
alignment, free of blockage, free rotation of motor, proper direction of
the pump rotor as explained in Operation Manual and Pump
Manufacturer’s Installation Operation Instructions.
Prior to start up, check that all suction and product delivery valves are
open and control valve have been set for the safe operation of the pump.
Close all vents drain valves on the truck unloading skid and connect
unloading arms.
Start unloading operation by opening isolation of unloading arm and
gravity feed product into the skid.
Once the pump is primed up by looking in the sight glass on both arms,
start the pump from local push button/and or preset controller. This is to
verify correct operation (rotation).
Initiate stop and ensure the pump stops.
Start new unloading operation to end and record your observation on the
following:
o Operation of Air Eliminator (level switches, solenoid valve and vent)
o Pump noise and vibration at the start and end of unloading operation.
o Smoothness of starting and completion of loading operation.
Page 19 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Page 20 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Disconnect the wires from pick-up A & B and start the loading process.
Check the response from the Pre-set Controller. The NO FLOW ALARM
shall be raised after the time set in “No Flow Time out.”
Reverse the connection to meter pick up A and B (B connected to A and A
connected to B).
Record observations in Test Record Sheet # 21 (Appendix 2).
12. Miscellaneous Test
This section is for any additional tests required, that are not detailed in the text of this
document. Record observations in Test Record Sheet # 22 (Appendix 2).
13. Punch List
Truck Loading Metering System shall be checked against project FSD and 34-SAMSS-
167. Truck Unloading Metering System shall be checked against project FSD and
34-SAMSS-168. Any deviation from these documents shall be recorded as part of the
punch-list (Appendix 3) and resolved prior to shipping the metering system to the site.
14. System Acceptance Certificate (Test Record Closure)
Appendix 1 to 6 are the FAT and SAT reports that list the required tests and documents for
truck loading metering system and truck unloading metering systems, when approved by
the Company representatives, these reports shall be used as the certification that the FAT
and SAT has been successfully completed.
Page 21 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Page 22 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Page 23 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Page 24 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Page 25 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Page 26 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Acceptable Yes/No
Date: Location
Tested by: Witnessed by:
On Behalf of: On Behalf of:
Page 27 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Isolation Valve
Other (specify)
Remarks:
Acceptable Yes/No
Date: Location
Tested by: Witnessed by:
On Behalf of: On Behalf of:
Page 28 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Manufacturer: Model:
Start-up
Configuration
Arm 1 Permissive
Arm 2 Permissive
Remarks:
Acceptable Yes/No
Date: Location
Tested by: Witnessed by:
On Behalf of: On Behalf of:
Page 29 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Manufacturer: Model:
Range (mA)
Test Data
% Difference % Difference
Input Pressure Preset
Transmitter Accuracy Accuracy
mA Controller
±0.075% ±0.075%
0% of range
100% of range
Remarks:
Acceptable Yes/No
Date: Location
Tested by: Witnessed by:
On Behalf of: On Behalf of:
Page 30 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Manufacturer: Model:
Range:
Test Data
% Difference
Input Pressure Indicator
±0.5%
0%
25%
50%
75%
100%
Remarks:
Acceptable Yes/No
Date: Location
Tested by: Witnessed by:
On Behalf of: On Behalf of:
Page 31 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Manufacturer: Model:
Test Data
% Difference
Input Resistance (Ohms) Preset Controller (Deg. C)
±0.2%
0% of span
25% of span
50% of span
75% of span
100% of span
Additional Test: Disconnect RTD during loading operation and record observation
Remarks:
Acceptable Yes/No
Date: Location
Tested by: Witnessed by:
On Behalf of: On Behalf of:
Page 32 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Manufacturer: Model:
Test Data
Remarks:
Acceptable Yes/No
Date: Location
Tested by: Witnessed by:
On Behalf of: On Behalf of:
Page 33 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Manufacturer: Model:
Test Data
Description Remarks
Remarks:
Acceptable Yes/No
Date: Location
Tested by: Witnessed by:
On Behalf of: On Behalf of:
Page 34 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Manufacturer: Model:
Test Data
±0.5%
0% of span
25% of span
50% of span
75% of span
100% of span
Remarks:
Acceptable Yes/No
Date: Location
Tested by: Witnessed by:
On Behalf of: On Behalf of:
Page 35 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Manufacturer: Model:
Test Data
Indication
Action Red Light Blue Light
Contact
Apply VAC Power Supply
Probe Connected to
Kit/Dummy
Remarks:
Acceptable Yes/No
Date: Location
Tested by: Witnessed by:
On Behalf of: On Behalf of:
Page 36 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Manufacturer: Model:
Test Data
Indication
Action Green Light Red Light
Contact
Apply VAC Power Supply
Overfill Bypass
Remarks:
Acceptable Yes/No
Date: Location
Tested by: Witnessed by:
On Behalf of: On Behalf of:
Page 37 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Manufacturer: Model:
Test Data
Remarks:
Acceptable Yes/No
Date: Location
Tested by: Witnessed by:
On Behalf of: On Behalf of:
Page 38 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Manufacturer: Model:
Test Data
Remarks:
Acceptable Yes/No
Date: Location
Tested by: Witnessed by:
On Behalf of: On Behalf of:
Page 39 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Manufacturer: Model:
Test Data
Remarks:
Acceptable Yes/No
Date: Location
Tested by: Witnessed by:
On Behalf of: On Behalf of:
Page 40 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Manufacturer: Model:
Test Data
Remarks:
Acceptable Yes/No
Date: Location
Tested by: Witnessed by:
On Behalf of: On Behalf of:
Page 41 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Test Data
Assembly
Movement
Remarks:
Acceptable Yes/No
Date: Location
Tested by: Witnessed by:
On Behalf of: On Behalf of:
Page 42 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Test Result
Remarks:
Acceptable Yes/No
Date: Location
Tested by: Witnessed by:
On Behalf of: On Behalf of:
Page 43 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Test Result
Acceptable Yes/No
Date: Location
Tested by: Witnessed by:
On Behalf of: On Behalf of:
Page 44 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Test Result
Remarks:
Acceptable Yes/No
Date: Location
Tested by: Witnessed by:
On Behalf of: On Behalf of:
Page 45 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Test Result
Description Remarks
Remarks:
Acceptable Yes/No
Date: Location
Tested by: Witnessed by:
On Behalf of: On Behalf of:
Page 46 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Test Result
Acceptable Yes/No
Date: Location
Tested by: Witnessed by:
On Behalf of: On Behalf of:
Page 47 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Test Result
Description Result
Remarks:
Acceptable Yes/No
Date: Location
Tested by: Witnessed by:
On Behalf of: On Behalf of:
Page 48 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Remarks:
Page 49 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Page 50 of 51
Document Responsibility: Custody Measurement Standards Committee SABP-Y-067
Issue Date: 22 June 2016 Factory and Site Acceptance Testing
Next Planned Update: TBD for Truck Bottom Loading and Unloading Metering Systems
Page 51 of 51