Interview Questions
Interview Questions
Interview Questions
Can you perform calculations for Voltage Drop, Power Factor corrections?
Did you work on Transformers designing and substation design according to Saudi specification.
SEC standards?
Our project has major items like Transformers, generators, UPS and data systems. Did you have
experience on these items in design.
Did you perform any FAT test? For which items you performed FAT? Factory Acceptance Test
Generators, Panel boards, UPS, Cables,
Following questions, what things you do during Fat test?
The Factory Acceptance Test (FAT) is a process that evaluates the equipment during and after the
assembly process by verifying that it is built and operating in accordance with design specifications. FAT
ensures that the components and controls are working properly according to the functionality of the
equipment itself. As the name suggests, this testing is performed at the factory.
FAT is typically conducted in order to assess any discrepancies and non-conformities, as well as develop
a process for how they are to be handled. Deviations or abnormalities observed during testing are
documented in a problem report and corrected prior to shipment.
The used equipment is according to the specification eg, compatible HardWare and SW versions
The used equipment are installed according to manufacturer’s specification
The input and the outputs are connected according to the drawings
The calibration of the equipment are correct
The trip points operate according to the requirements in the Service Record Schedule ( SRS).
The associated software operate according to the requirements in the SRS the outputs and their actions
behave according to the SRS
The reset functions operate according to the SRS
The alarms operate according to the SRS
The operator functions operate according to the SRS
The bypass functions operate according to the SRS
The manual shutdown functions operate according to the SRS
The diagnostic alarm functions operate according to the SRS
A load bank test is used to test the UPS and generator which is under load conditions to ensure that
they are working optimally. This method is a way of validating the true operational performance as
well as the battery autonomy used in UPS and Generator system.
Following question,
Resistive Load Banks: The most common type, resistive load banks mimic the operational load that
a power source will see in actual use. They convert electrical energy (current) into heat using power
resistors and dissipate the heat using air or water. Examples of resistive loads include incandescent
lightbulbs and devices with heating elements, such as space heaters and hot plates.
Reactive Load Banks: These solutions are used to simulate systems affected by electric motors or
other electromagnetic devices on a power network. In general, equipment that requires reactive
power compensation are motor-driven devices, transformers and capacitors.
Reactive load banks can simulate either an inductive or capacitive load depending on the type of load
expected on the power system. A reactive/inductive load converts current into a magnetic field. It
resists the change to voltage, causing the circuit current to lead voltage. Examples of devices
producing reactive/inductive loads include motors, transformers and chokes.
Reactive/capacitive load charges and releases energy. It resists the change to voltage, causing the
circuit current to lead voltage. Reactive/capacitive load bank testing is often conducted in
telecommunications, solar, manufacturing and mining applications.
Resistive/Reactive Load Banks – These solutions combine both resistive and reactive elements in
one load bank package. Resistive/reactive loads are able to mimic motor loads and electromagnetic
devices within a power system, as well as provide purely resistive loads by allowing to set a specific
power factor.
What is the procedure to design Electrical Earthing System?
Step 2 With the results do the calculation to achieve minimum required resistivity in OHMS( less
than 5 ohms)
Step 3 design the building or Site accordingly adding number of Earth Pits and Cables around
building after the calculations.
Ans. Usually Power factor is taken as 0.8.PF of 1 is in ideal condition when there is no drop or any
electrical loss.
Power-factor correction increases the power factor of a load, improving efficiency for the
distribution system to which it is attached. Linear loads with low power factor (such as induction
motors) can be corrected with a passive network of capacitors or inductors. Non-linear loads, such
as rectifiers, distort the current drawn from the system. In such cases, active or passive power factor
correction may be used to counteract the distortion and raise the power factor. The devices for
correction of the power factor may be at a central substation, spread out over a distribution system,
or built into power-consuming equipment.
The National Electrical Code establishes that if a conduit only contains 1 wire, the max fill
percentage is 53%. If it contains 2 wires, the max fill percentage is 31%. And if it contains 3 or
more wires, the max fill percentage is 40%.
What is the difference between MCB & MCCB, Where it can be used?
MCB is miniature circuit breaker which is thermal operated and use for short circuit protection in small
current rating circuit.
Normally it is used where normal current is less than 100A.
MCCB moulded case circuit breaker and is thermal operated for over load current and magnetic operation
for instant trip in short circuit condition. Under voltage and under frequency may be inbuilt.
Normally it is used where normal current is more than 100A.
What are the points to be considered for MCB (miniature circuit breaker selection)?
I(L)x1.25=I(MAX) maximum current. Mcb specification is done on maximum current flow in circuit.
Why we do two types of earthing on transformer (Body earthing & neutral earthing)
The two types of earthing are Familiar as Equipment earthing and system earthing.
In Equipment earthing: body (non conducting part) of the equipment should be earthed to safeguard the
human beings.
The System Earthing: In this neutral of the supply source (Transformer or Generator) should be grounded.
With this, in case of unbalanced loading neutral will not be shifted. So that unbalanced voltages will not arise. We
can protect the equipment also. With size of the equipment (transformer or alternator) and selection of relying
system earthing will be further classified into directly earthed, Impedance earthing, resistive (NGRs) earthing.