Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

12.0 Conclusion

Download as pdf or txt
Download as pdf or txt
You are on page 1of 13

12.

0 CONCLUSION

In addressing the quality of education for architectural and engineering degrees, it is


important for students adhere to the highest professional standards. It seeks to protect the
excellence that marks the building professions and the skills required to meet the challenges of
an increasingly complex future through the investment in educating professionals for that
future. Most of the students have problem to understand the design and the construction
process. Thus, in Integrated Design Project will encourage students to explore the inception
and conceptual planning stage of a civil engineering development project. The subject focuses
on basic civil engineering infrastructure design of a mixed development project given to
students, working in groups.

Based on that, HBR Consultant have been assigned to design five storey buildings.
Each part of the building such as foundation, slab, beam, and column need to be design. The
usage of software such as Esteem, AutoCAD and StaadPro is very important in a way to define
the suitable design for each part of the building. Although calculation for loading or bending
can be achieve by using software such as StaadPro can be gathered, manual calculation will be
also,need to be done to make sure that the calculation between manual calculation and software
calculation is tally. Some problems have been faced in designing the building that is some
measurement is not suitable and may result as fail. The problem is faced by seeking reference
and make a group discussion with group member and lecturer. Thus, some changes for the
measurement need to be done after done the group discussion. It is important for each group
member to give tolerance, communicate and work together to achieve the success for the
project. In a nutshell, from this project, each group member had gain new knowledge in termof
using technology, know how to design building and allocate budget for the project.
11.0 QUANTITY SURVEYING / BILL QUANTITY

ITEM DESCRIPTION UNIT RATE AMOUNT


NO. (RM)
1 PRELIMINARIES AND GENERAL Lump sum

2 SITE CLEARANCE WORKS (ALL


PROVISIONAL)

The work included in this section Lump sum


comprises surveying the whole of the site
by a licensed land surveyor to the approval
of the S.O.
3
PRESTRESSED CONCRETE SPUN PILE

Allow for the protection, maintenance and Lump sum


removal of all existing services, walls,
pipes, underground and overhead cables,
street lights etc. during the execution of the
Works.

Allow for the provision of all necessary Lump sum


piling equipment, plant, tools and
4 ancillaries, assembling and erecting and
dismantling and removal off site upon
completion

Lean concrete Grade 30 as described:- Refer table


below
50mm Thick blinding spread and levelled M3
5 under under pile cap
Refer table
Ditto under ground beam. M2 below

Vibrated reinforced concrete Grade 30 as


described in:-

6 Pile cap M3 Refer table


below
Column stump (provisional). M3
Vibrated reinforced concrete Grade 30 as
described in:-

300mm x 600mm Ground beam M3

350mm x 600mm Ground beam M3


Refer table
7 125mm Thick ground slab. M3 below

125mm Thick ground slab. M3

Sawn formwork as described:-

To sides of pile cap. M2

8 Ditto of column stump (provisional) M2 Refer table


below
Ditto of beam. M2

BUILDING STRUCTURE DETAIL:-

Level mezzanine, first floor, second floor


and third floor

Roof structure
9
Allow detail as describe in table below for ITEM
every level including roof. Refer table
below
RECTIFICATION WORKS

Based on determination on site condition


during the Site Visit, the Tenderer shall :- -

Inside Building:-

To make good existing 2 point of cracked ITEM -


brickwall/column at Inside Building
(approximately 1 meter long crack)

To make good existing 2 point of ITEM -


horizontal cracked brickwall/column at the
corner side of the office
To make good existing gap between ITEM -
wall/column at the side of office room

To make good existing crack at upper side ITEM -

To make good existing horizontal cracked ITEM - Refer table


brickwall/column along lab store below

To make good existing cracked wall at ITEM -


meeting room. To make sure door can be
closed properly. (approximately 2 meters
long crack)

Other works

Make good work which are not described


above but shown on the drawings and are
deemed necessary for the proper
completion of the rectification works (to be
detailed up by the Tenderer)
7.0 COSTING FOR SLAB

Slab Formwork and Concrete Costing Tables

Concrete Volume and Cost


Floor Grade Volume (m³) Raw (RM) Placement (RM)
RF 30 0.000 0.00 0.00
4F 30 84.885 12,732.75 21,221.25
3F 30 107.917 16,187.55 26,979.25
2F 30 107.917 16,187.55 26,979.25
1F 30 107.917 16,187.55 26,979.25
GF 30 111.823 16,773.45 27,955.75
Total 520.459 78,068.85 130,114.75

Lean Concrete Volume and Cost


Floor Lean Concrete (m³) Raw (RM) Placement (RM)
RF 0.000 0.00 0.00
4F 0.000 0.00 0.00
3F 0.000 0.00 0.00
2F 0.000 0.00 0.00
1F 0.000 0.00 0.00
GF 0.000 0.00 0.00
Total 0.000 0.00 0.00

Formwork Area and Cost


Floor Formwork Area (m²) Raw (RM) Placement (RM)
RF 0.000 0.00 0.00
4F 679.062 13,581.24 20,371.86
3F 863.297 17,265.94 25,898.91
2F 863.297 17,265.94 25,898.91
1F 863.297 17,265.94 25,898.91
GF 894.691 17,893.82 26,840.73
Total 4,163.644 83,272.88 124,909.32

Slab Reinforcement Costing Tables

Bottom Bar and Cost


Floor Diameter Weight (kg) Raw (RM) Placement (RM)
4F H10 4,842.556 9,685.11 12,106.39
3F H10 6,211.212 12,422.42 15,528.03
2F H10 6,211.212 12,422.42 15,528.03
1F H10 6,211.212 12,422.42 15,528.03
GF H10 6,323.789 12,647.58 15,809.47
Total 29,799.980 59,599.96 74,499.95

License Number: Timer-SN111-C0-1


1/2
Top Bar (Middle + Distribution) and Cost
Floor Diameter Weight (kg) Raw (RM) Placement (RM)
4F H10 1,386.764 2,773.53 3,466.91
3F H10 1,914.752 3,829.50 4,786.88
2F H10 1,914.752 3,829.50 4,786.88
1F H10 1,914.752 3,829.50 4,786.88
GF H10 1,977.238 3,954.48 4,943.09
Total 9,108.259 18,216.52 22,770.65

Top Bar (Support) and Cost


Floor Diameter Weight (kg) Raw (RM) Placement (RM)
4F H10 2,943.365 5,886.73 7,358.41
3F H10 3,905.895 7,811.79 9,764.74
2F H10 3,905.895 7,811.79 9,764.74
1F H10 3,905.895 7,811.79 9,764.74
GF H10 4,181.499 8,363.00 10,453.75
Total 18,842.549 37,685.10 47,106.37

License Number: Timer-SN111-C0-1


2/2
8.0 COSTING FOR BEAM
Beam Formwork and Concrete Costing Tables
Concrete Volume and Cost
Floor Grade Volume (m³) Raw (RM) Placement (RM)
RF 25 57.534 8,630.10 14,383.50
4F 25 101.162 15,174.30 25,290.50
3F 25 101.162 15,174.30 25,290.50
2F 25 101.162 15,174.30 25,290.50
1F 25 101.162 15,174.30 25,290.50
GF 25 106.090 15,913.50 26,522.50
Total 568.272 85,240.80 142,068.00

Lean Concrete Volume and Cost


Floor Lean Concrete (m³) Raw (RM) Placement (RM)
RF 0.000 0.00 0.00
4F 0.000 0.00 0.00
3F 0.000 0.00 0.00
2F 0.000 0.00 0.00
1F 0.000 0.00 0.00
GF 0.000 0.00 0.00
Total 0.000 0.00 0.00

Formwork Area and Cost


Floor Formwork Area (m²) Raw (RM) Placement (RM)
RF 498.530 12,463.25 14,955.90
4F 876.634 21,915.85 26,299.02
3F 876.634 21,915.85 26,299.02
2F 876.634 21,915.85 26,299.02
1F 876.634 21,915.85 26,299.02
GF 919.421 22,985.53 27,582.63
Total 4,924.487 123,112.18 147,734.61

Beam Reinforcement Costing Tables


Bottom Bar and Cost
Floor Diameter Weight (kg) Raw (RM) Placement (RM)
RF H12 1,114.757 2,229.51 2,786.89
H12 1,383.744 2,767.49 3,459.36
H16 710.369 1,420.74 1,775.92
4F
H20 461.095 922.19 1,152.74
H25 410.976 821.95 1,027.44
H12 1,455.067 2,910.13 3,637.67
H16 723.297 1,446.59 1,808.24
3F
H20 293.491 586.98 733.73
H25 417.677 835.35 1,044.19
H12 1,457.468 2,914.94 3,643.67
H16 753.264 1,506.53 1,883.16
2F
H20 249.576 499.15 623.94
H25 417.677 835.35 1,044.19
H12 1,432.800 2,865.60 3,582.00
H16 783.042 1,566.08 1,957.61
1F
H20 300.160 600.32 750.40
H25 419.413 838.83 1,048.53
License Number: Timer-SN111-C0-1
1/2
H12 1,241.016 2,482.03 3,102.54
H16 951.893 1,903.79 2,379.73
GF
H20 759.158 1,518.32 1,897.89
H25 646.293 1,292.59 1,615.73
Total 16,382.231 32,764.46 40,955.58

Top Bar and Cost


Floor Diameter Weight (kg) Raw (RM) Placement (RM)
RF H12 1,139.564 2,279.13 2,848.91
H12 1,697.239 3,394.48 4,243.10
H16 299.037 598.07 747.59
4F H20 501.602 1,003.20 1,254.01
H25 141.502 283.00 353.76
H32 77.753 155.51 194.38
H12 1,563.919 3,127.84 3,909.80
H16 635.295 1,270.59 1,588.24
3F
H20 509.504 1,019.01 1,273.76
H25 272.587 545.17 681.47
H12 1,627.587 3,255.17 4,068.97
H16 644.056 1,288.11 1,610.14
2F
H20 417.646 835.29 1,044.12
H25 272.587 545.17 681.47
H12 1,539.249 3,078.50 3,848.12
H16 792.372 1,584.74 1,980.93
1F
H20 423.449 846.90 1,058.62
H25 232.075 464.15 580.19
H12 1,425.969 2,851.94 3,564.92
H16 649.220 1,298.44 1,623.05
GF H20 791.853 1,583.71 1,979.63
H25 827.145 1,654.29 2,067.86
H32 77.753 155.51 194.38
Total 16,558.961 33,117.92 41,397.40

Side Bar and Cost


Floor Diameter Weight (kg) Raw (RM) Placement (RM)
4F H12 66.650 133.30 166.62
3F H12 160.538 321.08 401.35
2F H12 114.448 228.90 286.12
1F H12 130.858 261.72 327.15
GF H12 231.970 463.94 579.93
Total 704.464 1,408.93 1,761.16

Stirrup Bar and Cost


Floor Diameter Weight (kg) Raw (RM) Placement (RM)
RF H10 1,484.615 2,969.23 3,711.54
4F H10 2,624.317 5,248.63 6,560.79
3F H10 2,609.872 5,219.74 6,524.68
2F H10 2,582.771 5,165.54 6,456.93
1F H10 2,588.065 5,176.13 6,470.16
GF H10 2,933.411 5,866.82 7,333.53
Total 14,823.051 29,646.10 37,057.63

License Number: Timer-SN111-C0-1


2/2
9.0 COSTING FOR COLUMN

Column Formwork and Concrete Costing Tables

Concrete Volume and Cost


Floor Grade Volume (m³) Raw (RM) Placement (RM)
RF 25 12.150 1,822.50 3,037.50
4F 25 37.440 5,616.00 9,360.00
3F 25 37.440 5,616.00 9,360.00
2F 25 37.440 5,616.00 9,360.00
1F 25 37.440 5,616.00 9,360.00
GF 25 18.720 2,808.00 4,680.00
Total 180.630 27,094.50 45,157.50

Formwork Area and Cost


Floor Formwork Area (m²) Raw (RM) Placement (RM)
RF 162.000 4,050.00 4,860.00
4F 374.400 9,360.00 11,232.00
3F 374.400 9,360.00 11,232.00
2F 374.400 9,360.00 11,232.00
1F 374.400 9,360.00 11,232.00
GF 187.200 4,680.00 5,616.00
Total 1,846.800 46,170.00 55,404.00

Column Reinforcement Costing Tables

Main Bar and Cost


Floor Diameter Weight (kg) Raw (RM) Placement (RM)
H12 458.696 917.39 1,146.74
RF
H16 37.928 75.86 94.82
H12 1,829.364 3,658.73 4,573.41
4F
H16 183.822 367.64 459.55
3F H12 1,928.249 3,856.50 4,820.62
H12 1,903.528 3,807.06 4,758.82
2F
H16 45.955 91.91 114.89
H12 1,764.801 3,529.60 4,412.00
H16 229.777 459.55 574.44
1F
H20 74.941 149.88 187.35
H25 123.220 246.44 308.05
H12 861.735 1,723.47 2,154.34
H16 26.991 53.98 67.48
GF H20 135.929 271.86 339.82
H25 538.443 1,076.89 1,346.11
H32 700.370 1,400.74 1,750.92
Total 10,843.749 21,687.50 27,109.37

License Number: Timer-SN111-C0-1


1/2
Link Bar and Cost
Floor Diameter Weight (kg) Raw (RM) Placement (RM)
RF H10 772.966 1,545.93 1,932.41
4F H10 3,180.479 6,360.96 7,951.20
3F H10 3,220.111 6,440.22 8,050.28
2F H10 3,210.203 6,420.41 8,025.51
1F H10 3,160.663 6,321.33 7,901.66
GF H10 1,469.861 2,939.72 3,674.65
Total 15,014.282 30,028.56 37,535.71

License Number: Timer-SN111-C0-1


2/2
10.0 COSTING FOR PILE

Pile Footing Formwork and Concrete Costing Tables

Concrete Volume and Cost


Mark Quantity Grade Volume (m³) Raw (RM) Placement (RM)
P1 4 30 0.756 113.40 189.00
P2 13 30 3.380 507.00 845.00
P3 19 30 5.396 809.40 1,349.00
P4 5 30 3.025 453.75 756.25
P5 1 30 0.605 90.75 151.25
P6 9 30 7.110 1,066.50 1,777.50
P7 4 30 3.292 493.80 823.00
P8 4 30 4.052 607.80 1,013.00
P9 5 30 6.835 1,025.25 1,708.75
P10 2 30 2.694 404.10 673.50
P11 6 30 10.800 1,620.00 2,700.00
P12 2 30 4.132 619.80 1,033.00
P13 2 30 4.460 669.00 1,115.00
P14 2 30 5.508 826.20 1,377.00
Total 62.045 9,306.75 15,511.25

Formwork Area and Cost


Mark Quantity Formwork Area (m²) Raw (RM) Placement (RM)
P1 4 3.840 96.00 115.20
P2 13 15.288 382.20 458.64
P3 19 23.940 598.50 718.20
P4 5 11.000 275.00 330.00
P5 1 2.200 55.00 66.00
P6 9 26.325 658.13 789.75
P7 4 10.356 258.90 310.68
P8 4 12.480 312.00 374.40
P9 5 20.250 506.25 607.50
P10 2 7.300 182.50 219.00
P11 6 29.280 732.00 878.40
P12 2 10.710 267.75 321.30
P13 2 11.006 275.15 330.18
P14 2 12.600 315.00 378.00
Total 196.575 4,914.38 5,897.25

Lean Concrete Volume and Cost


Mark Quantity Lean Concrete (m³) Raw (RM) Placement (RM)
P1 4 0.126 1.89 3.15
P2 13 0.588 8.82 14.71
P3 19 0.770 11.54 19.24
P4 5 0.303 4.54 7.56
P5 1 0.061 0.91 1.51
P6 9 0.547 8.20 13.67
P7 4 0.332 4.98 8.30
P8 4 0.338 5.06 8.44
P9 5 0.456 6.84 11.39
P10 2 0.221 3.32 5.53
License Number: Timer-SN111-C0-1
1/3
P11 6 0.675 10.13 16.88
P12 2 0.243 3.65 6.08
P13 2 0.277 4.15 6.92
P14 2 0.306 4.59 7.65
Total 5.241 78.61 131.02

Earth Excavation Costing Table

Earth Excavation Volume and Cost


Mark Quantity Earth Excavation (m³) Placement (RM)
P1 4 4.664 69.96
P2 13 22.347 335.21
P3 19 29.241 438.62
P4 5 12.405 186.08
P5 1 2.481 37.22
P6 9 24.057 360.86
P7 4 14.272 214.08
P8 4 14.512 217.68
P9 5 20.960 314.40
P10 2 9.958 149.37
P11 6 31.728 475.92
P12 2 11.664 174.96
P13 2 13.554 203.31
P14 2 14.994 224.91
Total 226.837 3,402.56

Pile Footing Reinforcement Costing Tables

Bottom Bar and Cost


Floor Quantity Diameter Weight (kg) Raw (RM) Placement (RM)
P1 4 H10 37.780 75.56 94.45
P2 13 H10 185.557 371.11 463.89
P3 19 H10 300.266 600.53 750.66
H12 93.339 186.68 233.35
P4 5
H16 99.562 199.12 248.90
H12 18.668 37.34 46.67
P5 1
H16 19.912 39.82 49.78
P6 9 H16 576.748 1,153.50 1,441.87
P7 4 H16 282.530 565.06 706.32
P8 4 H16 284.462 568.92 711.16
P9 5 H16 540.479 1,080.96 1,351.20
P10 2 H16 217.493 434.99 543.73
P11 6 H16 846.276 1,692.55 2,115.69
P12 2 H20 336.318 672.64 840.79
P13 2 H20 419.388 838.78 1,048.47
P14 2 H20 438.052 876.10 1,095.13
Total 4,696.829 9,393.66 11,742.07

License Number: Timer-SN111-C0-1


2/3
Side Bar and Cost
Floor Quantity Diameter Weight (kg) Raw (RM) Placement (RM)
P1 4 R6 5.689 11.38 14.22
P2 13 R6 19.407 38.81 48.52
P3 19 R6 45.603 91.21 114.01
P4 5 R6 19.557 39.11 48.89
P5 1 R6 3.911 7.82 9.78
P6 9 R6 45.003 90.01 112.51
P7 4 R6 19.176 38.35 47.94
P8 4 R6 23.113 46.23 57.78
P9 5 R6 36.002 72.00 90.01
P10 2 R6 13.906 27.81 34.76
P11 6 R6 56.937 113.87 142.34
P12 2 R6 19.601 39.20 49.00
P13 2 R6 21.741 43.48 54.35
P14 2 R6 24.890 49.78 62.23
Total 354.537 709.07 886.34

License Number: Timer-SN111-C0-1


3/3

You might also like