Locational Marginal Price (LMP (
Locational Marginal Price (LMP (
Locational Marginal Price (LMP (
Generator 1
Generator 2
Cost Function
Cost Function
Cost $/h
Cost $/h
MW MW
400 800 200 400
Power flow dispatch
700MW 1 2 200MW
200MW
1 2
500MW
400MW
500MW 400MW
Segment MW Price
A 400 5
Generation dispatch C 200 6.5
B 300 7.5 Clearing Price
If we add one more MW to the load at either bus ,what will be the new dispatch?
Transmission Limits
Suppose now that the transmission line between buses 1 and 2 is limited to a maximum of 100MW.
600MW 1 2 300MW
100MW
1 2
500MW
400MW
500MW 400MW
Segment MW Price
A 400 5
Generation dispatch C 200 6.5
B 200 7.5
D 100 8 Clearing Price
• If we add 1MW of load, it must come from segment B
of generator 1at a cost of 7.5
Bus1 • The LMP for bus 1 then is 7.5
What unit or combination of units should be used to supply this load most economically?
Unit Combinations and Dispatch for 550-MW Load of Example
For restoring frequency and interchanging quickly in the event of a generating-unit outage.
The spinning reserve is the unused capacity which can be activated on decision of the system
operator and which is provided by devices that are synchronized to the network and able to affect
the active power.
Offline Reserve (scheduled reserve)
• Non-Spinning Reserve is off-line generation capacity that can be ramped to capacity and
synchronized to the grid within 10 minutes of a dispatch instruction by the ISO, and that is
capable of maintaining that output for at least two hours.
• Non-Spinning Reserve is needed to maintain system frequency stability during emergency
conditions.
• Non-spinning (unsynchronized) reserves act only after synchronisation.
• Units that can quickly respond to system events (such as the loss of a generator)
Quick-start diesel generating units, gas-turbine units,Hydroelectric power plant, pumped-storage
hydro-unit.
Example
Suppose a power system consisted of two
isolated regions: a western region and an eastern
region. Five units have been committed to
supply 3090 MW.
The two regions are separated by transmission tie
lines that can together transfer a maximum of 550
MW in either direction.
Loss of Unit1?
Loss of Unit4? The tie capacity of only 550 MW limits the transfer
Thermal Unit Constraints
Minimum up time: Once the unit is running, it should not be turned off immediately.
Minimum down time: Once the unit is decommitted, there is a minimum time before it
can be recommitted.
Crew constraints: If a plant consists of two or more units, they cannot both be turned on at
the same time since there are not enough crew members to attend both units while starting
up.
Start-up cost: Before a thermal plant can feed electricity to the grid, it has to be started up,
i.e. ramped up at least to the minimum generation level. This usually comes at a cost
independent of how much output is produced
Two approaches to treating a thermal unit
during its down period.
Start-up procedure of a turbine depends on its casing and rotor temperature.