Sched Log
Sched Log
Sched Log
exe
===============================================
Default Project..................................................NIZ-IZK-3
Projects:
NIZ-IZK-
3........................................................UPGRADING NIZWA GS to 220
kV AND ADDING ONE 500MVA 400/200kV TRANSFORMER AT NEW IZKI GS BL
Scheduling/Leveling Settings:
-----------------------------
General
-------
Scheduling ......................................................Yes
Leveling ........................................................No
Ignore relationships to and from other projects .................No
Make open-ended activities critical .............................No
Use Expected Finish Dates .......................................Yes
Schedule automatically when a change affects dates ..............No
Level resources during scheduling ...............................No
Recalculate assignment costs after scheduling ...................No
When scheduling progressed activities use .......................Retained
Logic
Calculate start-to-start lag from ...............................Early Start
Define critical activities as Total Float less than or equal to .0
Compute Total Float As ..........................................Finish Float
Calculate float based on finish date of .........................Each project
Calendar for scheduling Relationship Lag ........................Predecessor
Activity Calendar
Advanced
--------
Calculate multiple float paths...................................No
Statistics:
-----------
# Projects.......................................................1
# Activities.....................................................360
# Not Started....................................................360
# In Progress....................................................0
# Completed......................................................0
# Relationships..................................................457
# Activities with Constraint.....................................2
Project: NIZ-IZK-3 Activity: NIZ-MS-70 Reciept of Permits for
Izki GS : Excavation / Municipality
Project: NIZ-IZK-3 Activity: NIZ-MS-80 Reciept of Permits for
Nizwa GS : Excavation / Municipality
Errors:
-------
Warnings:
---------
Activities without predecessors..................................4
Project: NIZ-IZK-3 Activity: NIZ-MAS-1 Material Submission for
Structural Works
Project: NIZ-IZK-3 Activity: NIZ-MS-10 Receipt of LOI
Project: NIZ-IZK-3 Activity: NIZ-MS-70 Reciept of Permits for
Izki GS : Excavation / Municipality
Project: NIZ-IZK-3 Activity: NIZ-MS-80 Reciept of Permits for
Nizwa GS : Excavation / Municipality
Out-of-sequence activities.......................................0
Scheduling/Leveling Results:
----------------------------
# Projects Scheduled/Leveled.....................................1
# Activities Scheduled/Leveled...................................360
# Relationships with other projects..............................0
Data Date........................................................15-Jul-21
Earliest Early Start Date........................................15-Jul-21
Latest Early Finish Date.........................................30-Apr-22
Exceptions:
-----------
Critical Activities..............................................47
Project: NIZ-IZK-3 Activity: NIZ-BSM-G13-010 Wall Scaffolding-
External
Project: NIZ-IZK-3 Activity: NIZ-BSM-G13-040 Wall scaffolding
- Internal face
Project: NIZ-IZK-3 Activity: NIZ-BSM-G13-080 Column scaffolding
Project: NIZ-IZK-3 Activity: NIZ-BSM-G13-090 Column
reinforcement
Project: NIZ-IZK-3 Activity: NIZ-BSM-G13-100 Column Shutter
fixing
Project: NIZ-IZK-3 Activity: NIZ-BSM-G13-110 Column Concrete
Project: NIZ-IZK-3 Activity: NIZ-BSM-G13-130 Deshuttering
columns
Project: NIZ-IZK-3 Activity: NIZ-BSM-G13-140 Staging for Beams
and GF slab
Project: NIZ-IZK-3 Activity: NIZ-BSM-G13-150 Shutter fixing for
beam & Slab
Project: NIZ-IZK-3 Activity: NIZ-BSM-G13-160 Reinforcement
fixing for beam and Slab
Project: NIZ-IZK-3 Activity: NIZ-BSM-G13-330 Reinforcement
fixing for beam and Slab
Project: NIZ-IZK-3 Activity: NIZ-BSM-G13-340 Inserts and Box
outs fixing
Project: NIZ-IZK-3 Activity: NIZ-BSM-G13-350 Inspection and
Slab Casting (Grid 1-7)
Project: NIZ-IZK-3 Activity: NIZ-DD-IFC-01 Receipt of
Structural IFC drawings GIS building
Project: NIZ-IZK-3 Activity: NIZ-EXT-DW-010 Installation of
Doors as per schedule
Project: NIZ-IZK-3 Activity: NIZ-EXT-DW-020 Installation of
Rolling Shutter as per schedule
Project: NIZ-IZK-3 Activity: NIZ-EXT-DW-030 Installation of
Windows as per schedule
Project: NIZ-IZK-3 Activity: NIZ-GF-ARCH-WF-010 Blockwork
from GF slab to Roof beam
Project: NIZ-IZK-3 Activity: NIZ-GF-ARCH-WF-280 External
plastering
Project: NIZ-IZK-3 Activity: NIZ-GF-STR-010 Column scaffolding
Project: NIZ-IZK-3 Activity: NIZ-GF-STR-020 Column
reinforcement
Project: NIZ-IZK-3 Activity: NIZ-GF-STR-030 Column Shutter
fixing
Project: NIZ-IZK-3 Activity: NIZ-GF-STR-040 Column Concrete
till roof lvl
Project: NIZ-IZK-3 Activity: NIZ-GF-STR-110 Column scaffolding
Project: NIZ-IZK-3 Activity: NIZ-GF-STR-120 Column
reinforcement
Project: NIZ-IZK-3 Activity: NIZ-GF-STR-130 Column Shutter
fixing
Project: NIZ-IZK-3 Activity: NIZ-GF-STR-140 Column Concrete
till roof lvl
Project: NIZ-IZK-3 Activity: NIZ-GF-STR-150 Staging for Beams
and GF slab
Project: NIZ-IZK-3 Activity: NIZ-GF-STR-160 Shutter fixing for
beam & Slab
Project: NIZ-IZK-3 Activity: NIZ-GF-STR-170 Reinforcement
fixing for beam and Slab
Project: NIZ-IZK-3 Activity: NIZ-GF-STR-180 Inserts and Box
outs fixing
Project: NIZ-IZK-3 Activity: NIZ-GF-STR-190 Inspection and
Clearance
Project: NIZ-IZK-3 Activity: NIZ-GF-STR-200 Roof Slab Concrete
Project: NIZ-IZK-3 Activity: NIZ-GF-STR-220 Deshuttering
Project: NIZ-IZK-3 Activity: NIZ-MS-10 Receipt of LOI
Project: NIZ-IZK-3 Activity: NIZ-MS-70 Reciept of Permits for
Izki GS : Excavation / Municipality
Project: NIZ-IZK-3 Activity: NIZ-MS-80 Reciept of Permits for
Nizwa GS : Excavation / Municipality
Project: NIZ-IZK-3 Activity: NIZ-SNG-01 Snagging & Desnagging-
Nizwa GS
Project: NIZ-IZK-3 Activity: NIZ-STR-010 Excavation & Levelling
Project: NIZ-IZK-3 Activity: NIZ-STR-020 Anti termite
Project: NIZ-IZK-3 Activity: NIZ-STR-030 PCC
Project: NIZ-IZK-3 Activity: NIZ-STR-040 Waterproofing
Project: NIZ-IZK-3 Activity: NIZ-STR-050 Formwork- Raft -Grid 1-3
Project: NIZ-IZK-3 Activity: NIZ-STR-060 Reinforcement - Raft
-Grid 1-3
Project: NIZ-IZK-3 Activity: NIZ-STR-170 Reinforcement - Raft -
Grid 5-7
Project: NIZ-IZK-3 Activity: NIZ-STR-180 Inspection and clearance
Project: NIZ-IZK-3 Activity: NIZ-STR-200 Concrete - Raft