Sched Log
Sched Log
Sched Log
EXE
=========================================================
Default Project..................................................C00001-2
Projects:
C00001-
2.........................................................CONSTRUCCI�N PLANTA DE
PROCESOS - VIVO
Scheduling/Leveling Settings:
-----------------------------
General
-------
Scheduling ......................................................Yes
Leveling ........................................................No
Ignore relationships to and from other projects .................No
Make open-ended activities critical .............................No
Use Expected Finish Dates .......................................Yes
Schedule automatically when a change affects dates ..............No
Level resources during scheduling ...............................No
Recalculate assignment costs after scheduling ...................No
When scheduling progressed activities use .......................Progress
Override
Calculate start-to-start lag from ...............................Early Start
Define critical activities as Total Float less than or equal to .200
Compute Total Float As ..........................................Finish Float
Calculate float based on finish date of .........................Each project
Calendar for scheduling Relationship Lag ........................Predecessor
Activity Calendar
Advanced
--------
Calculate multiple float paths...................................No
Statistics:
-----------
# Projects.......................................................1
# Activities.....................................................62
# Not Started....................................................53
# In Progress....................................................6
# Completed......................................................3
# Relationships..................................................98
# Activities with Constraint.....................................2
Project: C00001-2 Activity: 0E.4120.N.0050 4120 - DESARROLLO
INGENIERIA ELECTRICIDAD
Project: C00001-2 Activity: 0E.4120.P.0050 4120 - DESARROLLO
INGENIERIA INSTRUMENTACION
Errors:
-------
Warnings:
---------
Activities without predecessors..................................1
Project: C00001-2 Activity: 0H.0000.G.0050 INICIO
Scheduling/Leveling Results:
----------------------------
# Projects Scheduled/Leveled.....................................1
# Activities Scheduled/Leveled...................................59
# Relationships with other projects..............................0
Data Date........................................................01-Jul-18
Earliest Early Start Date........................................01-Jul-18
Latest Early Finish Date.........................................12-Jul-19
Exceptions:
-----------
Critical Activities..............................................20
Project: C00001-2 Activity: 07.4120.J.0050 MONTAJE DE TANQUES
01-4122-TN-001/002
Project: C00001-2 Activity: 07.4120.J.0100 MONTAJE OTROS
EQUIPOS
Project: C00001-2 Activity: 07.4120.J.0150 MONTAJE BOMBAS 01-
4122-BH-003/004 Y 01-4122-BV-001
Project: C00001-2 Activity: 07.4120.M.0050 INSTALACION DE
TUBERIA
Project: C00001-2 Activity: 07.4120.N.0050 INSTALACION DE
CABLES
Project: C00001-2 Activity: 07.4120.N.0100 INSTALACION DE
EQUIPOS ELECTRICOS
Project: C00001-2 Activity: 07.4120.N.0150 INSTALACION
CONDUIT
Project: C00001-2 Activity: 07.4120.N.0200 INSTALACION
LUMINARIAS
Project: C00001-2 Activity: 07.4120.P.0050 INSTALACION DE
INSTRUMENTOS
Project: C00001-2 Activity: 0E.4110.D.0050 4110 - DESARROLLO
INGENIERIA MOVIMIENTO DE TIERRAS
Project: C00001-2 Activity: 0E.4120.D.0050 4120 - DESARROLLO
INGENIERIA MOVIMIENTO DE TIERRAS
Project: C00001-2 Activity: 0E.4120.E.0050 4120 - DESARROLLO
INGENIERIA CONCRETO
Project: C00001-2 Activity: 0E.4120.J.0050 4120 - DESARROLLO
INGENIERIA MECANICA
Project: C00001-2 Activity: 0H.0000.G.0200 ETA LLEGADA
TANQUES
Project: C00001-2 Activity: 0H.0000.G.0250 FIN CONSTRUCCION
Project: C00001-2 Activity: 0H.0000.G.0300 FIN PROYECTO
Project: C00001-2 Activity: 0P.4120.P.0050 4110 - GESTION
PROCURA TANQUES
Project: C00001-2 Activity: 0P.4120.P.0100 4110 - FABRICACION
Y ENTREGA TANQUES
Project: C00001-2 Activity: 0P.4120.P.0150 4110 - ETA
INSTRUMENTOS
Project: C00001-2 Activity: 0R.0000.G.0050 PRECOMISIONADO