Project IT Management Questions

1. Approximately what percentage of the world’s gross product is spent on projects?

a. 10 percent

b. 25 percent

c. 50 percent

d. 75 percent

2. Which of the following is not a potential advantage of using good project


management?

a. Shorter development times

b. Higher worker morale

c. Lower cost of capital

d. Higher profit margins

3. A is a temporary endeavor undertaken to create a unique product, service, or result.

a. program

b. process

c. project

d. portfolio

4. Which of the following is not an attribute of a project?

a. projects are unique

b. projects are developed using progressive elaboration

c. projects have a primary customer or sponsor


1
Eng. Hashim Al Atefi
d. projects involve little uncertainty

5. Which of the following is not part of the triple constraint of project management?

a. meeting scope goals

b. meeting time goals

c. meeting communications goals

d. meeting cost goals

6. is the application of knowledge, skills, tools, and techniques to project activities to


meet project requirements.

a. Project management

b. Program management

c. Project portfolio management

d. Requirements management

7. Project portfolio management addresses ………… goals of an organization, while


project management addresses …………… goals.

a. strategic, tactical

b. tactical, strategic

c. internal, external

d. external, internal

8. Several application development projects done for the same functional group might
best be managed as part of a ………………..

a. portfolio

b. program

2
Eng. Hashim Al Atefi
c. investment

d. collaborative

9. Which of the following is not true?

a. Most American companies have a project management office.

b. You can earn an advanced degree in project management from hundreds of


colleges and universities.

c. Employers are looking for project management skills in new graduates.

d. IT hiring managers reported that project management certification did not affect
starting pay.

10. What is the name of one of the popular certifications provided by the Project
Management Institute?

a. Certified Project Manager (CPM)

b. Project Management Professional (PMP)

c. Project Management Expert (PME)

d. Project Management Mentor (PMM)

11. Which of the following is not part of the three-sphere model for systems
management?

a. business

b. information

c. technology

d. organization

3
Eng. Hashim Al Atefi
12. Which of the four frames of organizations addresses how meetings are run, employee
dress codes, and expected work hours?

a. structural

b. human resources

c. political

d. symbolic

13. Personnel in a organizational structure often report to two or more bosses.

a. functional

b. project

c. matrix

d. hybrid

14. Project work is most successful in an organizational culture where all of the following
characteristics are important except .

a. member identity

b. group emphasis

c. risk tolerance

d. control

15. A is a product or service, such as a technical report, a training session, or hard- ware,
produced or provided as part of a project.

a. deliverable

b. product

c. work package

4
Eng. Hashim Al Atefi
d. tangible goal

16. Which of the following statements is false?

a. An analysis project life cycle is a collection of project phases.

b. A product life cycle is the same as a project life cycle.

c. The waterfall approach is an example of a predictive life cycle model.

d. Agile is an example of an adaptive life cycle model.

17. Which of the following terms describes a framework of the phases involved in
developing information systems?

a. systems development life cycle

b. rapid application development

c. predictive life cycle

d. extreme programming

18. The nature of IT projects is different from projects in many other industries because
they are very .

a. expensive

b. technical

c. diverse

d. challenging

19. What term describes an organization’s acquisition of goods and services from an
outside source in another country?

a. globalization

b. offshoring

5
Eng. Hashim Al Atefi
c. exporting

d. global sourcing

20. is the leading agile development method.

a. Extreme programming

b. Sprint c.

Six sigma

d. Scrum

21. A ______ is a series of actions directed toward a particular result.

a. goal

b. process

c. plan

d. project

22. ______ processes include coordinating people and other resources to carry out project
plans and create the products, services, or results of the project or phase.

a. Initiating

b. Planning

c. Executing

d. Monitoring and controlling

e. Closing

23. Which process group normally requires the most resources and time?

a. Initiating

6
Eng. Hashim Al Atefi
b. Planning

c. Executing

d. Monitoring and controlling

e. Closing

24. What methodology was developed in the United Kingdom, defines 45 separate sub-
processes, and organizes them into eight process groups?

a. Six Sigma

b. RUP

c. PMBOK® Guide

d. PRINCE2

25. Which of the following outputs is often completed before initiating a project?

a. stakeholder register

b. business case

c. project charter

d. kick-off meeting

26. A work breakdown structure, project schedule, and cost estimates are outputs of the
______ process.

a. initiating

b. planning

c. executing

d. monitoring and controlling

7
Eng. Hashim Al Atefi
e. closing

27. Initiating involves developing a project charter, which is part of the project ______
management knowledge area.

a. integration

b. scope

c. communications

d. risk

28. ______ involves measuring progress toward project objectives and taking corrective
actions.

a. Initiating

b. Planning

c. Executing

d. Monitoring and controlling

e. Closing

29. Which of the following is not a typical reason that project teams would use a
predictive approach versus an agile approach to managing a project?

a. The project has unclear up-front requirements.

b. The project team is inexperienced and dispersed.

c. Large risks are involved.

d. The completion date is fairly rigid.

30. Many people use ______ to have a standard format for preparing various project
management documents.

8
Eng. Hashim Al Atefi
a. methodologies

b. templates

c. project management software

d. standards

31. Which of the following processes is not part of project integration management?

a. developing the project business case

b. developing the project charter

c. developing the project management plan

d. closing the project or phase

32. What is the last step in the four-stage planning process for selecting IT projects?

a. IT strategy planning

b. business area analysis

c. mind mapping

d. resource allocation

33. Which of the following is not a best practice for new product development projects?

a. aligning projects and resources with business strategy

b. selecting projects that will take less than two years to provide payback

c. focusing on customer needs in identifying projects

d. assigning project managers to lead projects

9
Eng. Hashim Al Atefi
34. A new government law requires an organization to report data in a new way. Which
of the following categories would include a new information system project to provide
this data?

a. problem

b. opportunity

c. directive

d. regulation

35. If estimates for total discounted benefits for a project are $120,000 and total
discounted costs are $100,000, what is the estimated return on investment (ROI)?

a. $20,000

b. $120,000

c. 20 percent

d. 120 percent

36. A is a document that formally recognizes the existence of a project and provides
direction on the project’s objectives and management.

a. project charter

b. contract

c. business case

d. project management plan

37. Which of the following items is not normally included in a project charter?

a. the name of the project manager

b. budget information

10
Eng. Hashim Al Atefi
c. stakeholder signatures

d. a Gantt chart

38 ensures that the descriptions of the project’s products are correct and complete.

a. Configuration management

b. Integrated change control

c. Integration management

d. A change control board

39. Which of the following is not a suggestion for performing integrated change control?

a. use good configuration management

b. minimize change

c. establish a formal change control system

d. view project management as a process of constant communication and negotiation

40. What tool and technique is used for all processes of project integration management?

a. project management software

b. templates

c. expert judgment

d. all of the above

41. ______ refer(s) to all the work involved in creating the products of the project and the

processes used to create them.

a. Deliverables

b. Milestones
11
Eng. Hashim Al Atefi
c. Scope

d. Product development

42. Which tool or technique for collecting requirements is often the most expensive and
time consuming?

a. interviews

b. focus groups

c. surveys

d. observation

43. A ______ is a deliverable-oriented grouping of the work involved in a project that


defines its total scope.

a. scope statement

b. WBS

c. WBS dictionary

d. work package

44. What approach to developing a WBS involves writing down or drawing ideas in a
nonlinear format?

a. top-down

b. bottom-up

c. analogy

d. mind mapping

45. Assume that you have a project with major categories called planning, analysis,
design, and testing. What level of the WBS would these items fall under?

12
Eng. Hashim Al Atefi
a. 0

b. 1

c. 2

d. 3

46. Which of the following is not a best practice that can help in avoiding scope problems
on IT projects?

a. Keep the scope realistic.

b. Use off-the-shelf hardware and software whenever possible.

c. Follow good project management processes.

d. Don’t involve too many users in scope management.

47. Why did McDonald’s terminate a large project after spending $170 million on it?

a. The company found a better technology.

b. The company decided to outsource the work.

c. The scope was too much to handle.

d. The government requirement that prompted the project was repealed.

48. Scope ______ is often achieved by a customer inspection and then sign-off on key
deliverables.

a. acceptance

b. validation

c. completion

d. close-out

13
Eng. Hashim Al Atefi
49. Which of the following is not a suggestion for improving user input?

a. Develop a good project selection process for IT projects.

b. Have users on the project team.

c. Co-locate users with developers.

d. Only have meetings as needed, not on a regular basis.

50. Project management software helps you develop a ______, which serves as a basis for
creating Gantt charts, assigning resources, and allocating costs.

a. project plan

b. schedule

c. WBS

d. deliverable

50. Which of the following processes involves determining the policies, procedures, and
documentation that will be used for planning, executing, and controlling the project
schedule?

a. planning schedule management

b. defining activities

c. estimating activity resources

d. activity sequencing

52. Predecessors, successors, logical relationships, leads and lags, resource requirements,
constraints, imposed dates, and assumptions are all examples of .

a. items in an activity list

b. items on a Gantt chart

14
Eng. Hashim Al Atefi
c. milestone attributes

d. activity attributes

53. As the project manager for a software development project, you are helping to
develop the project schedule. You decide that writing code for a system should not start
until users sign off on the analysis work. What type of dependency is this?

a. technical

b. mandatory

c. discretionary

d. external

54. You cannot start editing a technical report until someone else completes the first
draft. What type of dependency does this represent?

a. finish-to-start

b. start-to-start

c. finish-to-finish

d. start-to-finish

55. Which of the following statements is false?

a. A resource breakdown structure is a hierarchical structure that identifies the


project’s resources by category and type.

b. Duration and effort are synonymous terms.

c. A three-point estimate includes an optimistic, most likely, and pessimistic


estimate.

d. A Gantt chart is a common tool for displaying project schedule information.

15
Eng. Hashim Al Atefi
56. What symbol on a Gantt chart represents a slipped milestone?

a. a black arrow

b. a white arrow

c. a black diamond

d. a white diamond

57. What type of diagram shows planned and actual project schedule information?

a. a network diagram

b. a Gantt chart

c. a Tracking Gantt chart

d. a milestone chart

58. is a network diagramming technique used to predict total project duration.

a. PERT

b. A Gantt chart

c. Critical path method

d. Crashing

59. Which of the following statements is false?

a. Growing grass was on the critical path for a large theme park project.

b. The critical path is the series of activities that determine the earliest time by which
a project can be completed.

c. A forward pass through a project network diagram determines the early start and
early finish dates for each activity.

16
Eng. Hashim Al Atefi
d. Fast tracking is a technique for making cost and schedule trade-offs to obtain the
greatest amount of schedule compression for the least incremental cost.

60. is a method of scheduling that considers limited resources when creating a project
schedule and includes buffers to protect the project completion date.

a. Parkinson’s Law

b. Murphy’s Law

c. Critical path analysis

d. Critical chain scheduling

61. Accountants usually define _________________ as a resource sacrificed or foregone


to achieve a specific objective or something given up in exchange.

a. money

b. liability

c. trade

d. cost

62. What is the main goal of project cost management?

a. to complete a project for as little cost as possible

b. to complete a project within an approved budget

c. to provide truthful and accurate cost information on projects

d. to ensure that an organization’s money is used wisely

63. Which of the following is not an output of the project cost management process called
estimating costs, according to the PMBOK® Guide?

a. activity cost estimates

17
Eng. Hashim Al Atefi
b. a cost baseline

c. basis of estimates

d. project documents updates

64. If a company loses $5 for every $100 in revenue for a certain product, what is the
profit margin for that product?

a. 5 percent b.

5 percent

c. $5

d. $5

65. _________________ reserves allow for future situations that are unpredictable.

a. Contingency

b. Financial

c. Management

d. Baseline

66. You are preparing a cost estimate for a building based on its location, purpose,
number of square feet, and other characteristics. What cost-estimating technique are you
using?

a. parametric

b. analogous

c. bottom-up

d. top-down

18
Eng. Hashim Al Atefi
67. _________________ involves allocating the project cost estimate to individual
material resources or work items over time.

a. Reserve analysis

b. Life cycle costing

c. Project cost budgeting

d. Earned value analysis

68. __________________ is a project performance measurement technique that


integrates scope, time, and cost data.

a. Reserve analysis

b. Life cycle costing

c. Project cost budgeting

d. Earned value management

69. If the actual cost for a WBS item is $1,500 and its earned value is $2,000, what is its
cost variance, and is it under or over budget?

a. The cost variance is $500, which is over budget.

b. The cost variance is $500, which is under budget.

c. The cost variance is $500, which is over budget.

d. The cost variance is $500, which is under budget.

70. If a project is halfway completed, its schedule performance index is 110 percent, and
its cost performance index is 95 percent, how is it progressing?

a. It is ahead of schedule and under budget.

b. It is ahead of schedule and over budget.

19
Eng. Hashim Al Atefi
c. It is behind schedule and under budget.

d. It is behind schedule and over budget.

71. It is a temporary endeavor undertaken to create a unique product, service, or


result.

a. program
b. project
c. policy
d. result

72. A group of related projects managed in a coordinated way to obtain benefits and
control not available from managing them individually.”

a. program
b. project
c. policy
d. result

73. Which is true about scope?

a. Scope affects schedule and cost of the project.


b. Scope aligns IT investments and priorities more closely with the business
c. Scope of project management helps to operate in a broad organizational
environment easily.
d. Scope aligns investments that focus mainly on the direction and control of the
country.

74. Successful project management is obtained through proper planning basically focused
on

a. management success
b. Leadership, organizations and decision rights
c. Limitation, organization and success
d. Scope, time, cost, quality

75. Which is not true about Project Management?

a. Deals the application of knowledge.

20
Eng. Hashim Al Atefi
b. Uses skills to manage it.
c. Tools are used to obtain best result in PM.
d. It doesn’t use techniques to project activities to meet project requirements

76. Which is not part of the 9 knowledge areas of Project management?

a. Human Resources Management


b. Procurement Management
c. Procedure Management
d. Risk Management

77. It is the taking of a holistic view of a project and understanding how it relates to the
larger organization.

a. Project development
b. Project management
c. System Development
e. System Thinking

78. Which is not included as basic organizational structure?

a. Functional
b. Basic
c. Conceptual
d. Matrix

79. Which is true about the task of senior manager?

a. Can encourage the use of standard forms and software for project
management.
b. Can formulate design for food development
c. Can use Spiral Model for managing people.

d. Can produce more output through reading.

80. Which is not true about project executing?

a. The use of ordinary forms and software for project management could
help in the creating of desired output.
b. Project managers must use their leadership skills to handle the many
challenges that occur during project execution.
c. A milestone report can keep the focus on completing major milestones.
d. Project execution usually takes the most time and resources.

81. Write T if the statement is TRUE and F if the statement is False.

21
Eng. Hashim Al Atefi
_______ _ 1. Project closing involves gaining stakeholder and customer acceptance of
the final products and services

____ ___ 2. Most projects also include a final report and presentation to the sponsor or
senior management

___ _____ 3. Definition Phase is the earliest part of a project when the purpose and
requirements are clarified.

__ ______ 4. Scope refers to all the work involved in creating the products of the project
and the processes used to create them.

__ ______ 5. Project management does not include the processes involved in defining
and controlling what is or is not included in a project.

___ _____ 6. A deliverable is a product produced as part of a project, such as hardware or


software, planning documents, or meeting minutes.

____ ____ 7. The scope management plan is the main output of scope planning.

_____ ____ 8. Scope definition is the process of specifying the criteria for determining if
important phases of work and the project have been completed.

______ ___ 9. The project scope statement is a document which specifies the user
acceptance requirements, project objectives, or high-level specifications for the main end-
item and ancillary side items.

____ _____ “Work Breakdown Structure.” a systematic, formal approach is used to to


design a flow chart.

_____ ____ 11. Scope verification involves formal acceptance of the completed project
scope by the stakeholders. This acceptance is often achieved by customer inspection and
then sign-off on key deliverables.

___ ______ 12 A milestone is a significant event that normally has no duration.

22
Eng. Hashim Al Atefi
._____ ____ 13. Many experts believe the underlying causes of many companies’
problems are the structures or staff.

______ ___ 14. Cost is a resource sacrificed or foregone to achieve a specific objective,
or something given up in exchange.

_____ ____ 15. Cost budgeting involves allocating the project cost estimate to individual
work items over time.