Project IT Management Questions
Project IT Management Questions
Project IT Management Questions
a. 10 percent
b. 25 percent
c. 50 percent
d. 75 percent
a. program
b. process
c. project
d. portfolio
5. Which of the following is not part of the triple constraint of project management?
a. Project management
b. Program management
d. Requirements management
a. strategic, tactical
b. tactical, strategic
c. internal, external
d. external, internal
8. Several application development projects done for the same functional group might
best be managed as part of a ………………..
a. portfolio
b. program
2
Eng. Hashim Al Atefi
c. investment
d. collaborative
d. IT hiring managers reported that project management certification did not affect
starting pay.
10. What is the name of one of the popular certifications provided by the Project
Management Institute?
11. Which of the following is not part of the three-sphere model for systems
management?
a. business
b. information
c. technology
d. organization
3
Eng. Hashim Al Atefi
12. Which of the four frames of organizations addresses how meetings are run, employee
dress codes, and expected work hours?
a. structural
b. human resources
c. political
d. symbolic
a. functional
b. project
c. matrix
d. hybrid
14. Project work is most successful in an organizational culture where all of the following
characteristics are important except .
a. member identity
b. group emphasis
c. risk tolerance
d. control
15. A is a product or service, such as a technical report, a training session, or hard- ware,
produced or provided as part of a project.
a. deliverable
b. product
c. work package
4
Eng. Hashim Al Atefi
d. tangible goal
17. Which of the following terms describes a framework of the phases involved in
developing information systems?
d. extreme programming
18. The nature of IT projects is different from projects in many other industries because
they are very .
a. expensive
b. technical
c. diverse
d. challenging
19. What term describes an organization’s acquisition of goods and services from an
outside source in another country?
a. globalization
b. offshoring
5
Eng. Hashim Al Atefi
c. exporting
d. global sourcing
a. Extreme programming
b. Sprint c.
Six sigma
d. Scrum
a. goal
b. process
c. plan
d. project
22. ______ processes include coordinating people and other resources to carry out project
plans and create the products, services, or results of the project or phase.
a. Initiating
b. Planning
c. Executing
e. Closing
23. Which process group normally requires the most resources and time?
a. Initiating
6
Eng. Hashim Al Atefi
b. Planning
c. Executing
e. Closing
24. What methodology was developed in the United Kingdom, defines 45 separate sub-
processes, and organizes them into eight process groups?
a. Six Sigma
b. RUP
c. PMBOK® Guide
d. PRINCE2
25. Which of the following outputs is often completed before initiating a project?
a. stakeholder register
b. business case
c. project charter
d. kick-off meeting
26. A work breakdown structure, project schedule, and cost estimates are outputs of the
______ process.
a. initiating
b. planning
c. executing
7
Eng. Hashim Al Atefi
e. closing
27. Initiating involves developing a project charter, which is part of the project ______
management knowledge area.
a. integration
b. scope
c. communications
d. risk
28. ______ involves measuring progress toward project objectives and taking corrective
actions.
a. Initiating
b. Planning
c. Executing
e. Closing
29. Which of the following is not a typical reason that project teams would use a
predictive approach versus an agile approach to managing a project?
30. Many people use ______ to have a standard format for preparing various project
management documents.
8
Eng. Hashim Al Atefi
a. methodologies
b. templates
d. standards
31. Which of the following processes is not part of project integration management?
32. What is the last step in the four-stage planning process for selecting IT projects?
a. IT strategy planning
c. mind mapping
d. resource allocation
33. Which of the following is not a best practice for new product development projects?
b. selecting projects that will take less than two years to provide payback
9
Eng. Hashim Al Atefi
34. A new government law requires an organization to report data in a new way. Which
of the following categories would include a new information system project to provide
this data?
a. problem
b. opportunity
c. directive
d. regulation
35. If estimates for total discounted benefits for a project are $120,000 and total
discounted costs are $100,000, what is the estimated return on investment (ROI)?
a. $20,000
b. $120,000
c. 20 percent
d. 120 percent
36. A is a document that formally recognizes the existence of a project and provides
direction on the project’s objectives and management.
a. project charter
b. contract
c. business case
37. Which of the following items is not normally included in a project charter?
b. budget information
10
Eng. Hashim Al Atefi
c. stakeholder signatures
d. a Gantt chart
38 ensures that the descriptions of the project’s products are correct and complete.
a. Configuration management
c. Integration management
39. Which of the following is not a suggestion for performing integrated change control?
b. minimize change
40. What tool and technique is used for all processes of project integration management?
b. templates
c. expert judgment
41. ______ refer(s) to all the work involved in creating the products of the project and the
a. Deliverables
b. Milestones
11
Eng. Hashim Al Atefi
c. Scope
d. Product development
42. Which tool or technique for collecting requirements is often the most expensive and
time consuming?
a. interviews
b. focus groups
c. surveys
d. observation
a. scope statement
b. WBS
c. WBS dictionary
d. work package
44. What approach to developing a WBS involves writing down or drawing ideas in a
nonlinear format?
a. top-down
b. bottom-up
c. analogy
d. mind mapping
45. Assume that you have a project with major categories called planning, analysis,
design, and testing. What level of the WBS would these items fall under?
12
Eng. Hashim Al Atefi
a. 0
b. 1
c. 2
d. 3
46. Which of the following is not a best practice that can help in avoiding scope problems
on IT projects?
47. Why did McDonald’s terminate a large project after spending $170 million on it?
48. Scope ______ is often achieved by a customer inspection and then sign-off on key
deliverables.
a. acceptance
b. validation
c. completion
d. close-out
13
Eng. Hashim Al Atefi
49. Which of the following is not a suggestion for improving user input?
50. Project management software helps you develop a ______, which serves as a basis for
creating Gantt charts, assigning resources, and allocating costs.
a. project plan
b. schedule
c. WBS
d. deliverable
50. Which of the following processes involves determining the policies, procedures, and
documentation that will be used for planning, executing, and controlling the project
schedule?
b. defining activities
d. activity sequencing
52. Predecessors, successors, logical relationships, leads and lags, resource requirements,
constraints, imposed dates, and assumptions are all examples of .
14
Eng. Hashim Al Atefi
c. milestone attributes
d. activity attributes
53. As the project manager for a software development project, you are helping to
develop the project schedule. You decide that writing code for a system should not start
until users sign off on the analysis work. What type of dependency is this?
a. technical
b. mandatory
c. discretionary
d. external
54. You cannot start editing a technical report until someone else completes the first
draft. What type of dependency does this represent?
a. finish-to-start
b. start-to-start
c. finish-to-finish
d. start-to-finish
15
Eng. Hashim Al Atefi
56. What symbol on a Gantt chart represents a slipped milestone?
a. a black arrow
b. a white arrow
c. a black diamond
d. a white diamond
57. What type of diagram shows planned and actual project schedule information?
a. a network diagram
b. a Gantt chart
d. a milestone chart
a. PERT
b. A Gantt chart
d. Crashing
a. Growing grass was on the critical path for a large theme park project.
b. The critical path is the series of activities that determine the earliest time by which
a project can be completed.
c. A forward pass through a project network diagram determines the early start and
early finish dates for each activity.
16
Eng. Hashim Al Atefi
d. Fast tracking is a technique for making cost and schedule trade-offs to obtain the
greatest amount of schedule compression for the least incremental cost.
60. is a method of scheduling that considers limited resources when creating a project
schedule and includes buffers to protect the project completion date.
a. Parkinson’s Law
b. Murphy’s Law
a. money
b. liability
c. trade
d. cost
63. Which of the following is not an output of the project cost management process called
estimating costs, according to the PMBOK® Guide?
17
Eng. Hashim Al Atefi
b. a cost baseline
c. basis of estimates
64. If a company loses $5 for every $100 in revenue for a certain product, what is the
profit margin for that product?
a. 5 percent b.
5 percent
c. $5
d. $5
65. _________________ reserves allow for future situations that are unpredictable.
a. Contingency
b. Financial
c. Management
d. Baseline
66. You are preparing a cost estimate for a building based on its location, purpose,
number of square feet, and other characteristics. What cost-estimating technique are you
using?
a. parametric
b. analogous
c. bottom-up
d. top-down
18
Eng. Hashim Al Atefi
67. _________________ involves allocating the project cost estimate to individual
material resources or work items over time.
a. Reserve analysis
a. Reserve analysis
69. If the actual cost for a WBS item is $1,500 and its earned value is $2,000, what is its
cost variance, and is it under or over budget?
70. If a project is halfway completed, its schedule performance index is 110 percent, and
its cost performance index is 95 percent, how is it progressing?
19
Eng. Hashim Al Atefi
c. It is behind schedule and under budget.
a. program
b. project
c. policy
d. result
72. A group of related projects managed in a coordinated way to obtain benefits and
control not available from managing them individually.”
a. program
b. project
c. policy
d. result
74. Successful project management is obtained through proper planning basically focused
on
a. management success
b. Leadership, organizations and decision rights
c. Limitation, organization and success
d. Scope, time, cost, quality
20
Eng. Hashim Al Atefi
b. Uses skills to manage it.
c. Tools are used to obtain best result in PM.
d. It doesn’t use techniques to project activities to meet project requirements
77. It is the taking of a holistic view of a project and understanding how it relates to the
larger organization.
a. Project development
b. Project management
c. System Development
e. System Thinking
a. Functional
b. Basic
c. Conceptual
d. Matrix
a. Can encourage the use of standard forms and software for project
management.
b. Can formulate design for food development
c. Can use Spiral Model for managing people.
a. The use of ordinary forms and software for project management could
help in the creating of desired output.
b. Project managers must use their leadership skills to handle the many
challenges that occur during project execution.
c. A milestone report can keep the focus on completing major milestones.
d. Project execution usually takes the most time and resources.
21
Eng. Hashim Al Atefi
_______ _ 1. Project closing involves gaining stakeholder and customer acceptance of
the final products and services
____ ___ 2. Most projects also include a final report and presentation to the sponsor or
senior management
___ _____ 3. Definition Phase is the earliest part of a project when the purpose and
requirements are clarified.
__ ______ 4. Scope refers to all the work involved in creating the products of the project
and the processes used to create them.
__ ______ 5. Project management does not include the processes involved in defining
and controlling what is or is not included in a project.
____ ____ 7. The scope management plan is the main output of scope planning.
_____ ____ 8. Scope definition is the process of specifying the criteria for determining if
important phases of work and the project have been completed.
______ ___ 9. The project scope statement is a document which specifies the user
acceptance requirements, project objectives, or high-level specifications for the main end-
item and ancillary side items.
_____ ____ 11. Scope verification involves formal acceptance of the completed project
scope by the stakeholders. This acceptance is often achieved by customer inspection and
then sign-off on key deliverables.
22
Eng. Hashim Al Atefi
._____ ____ 13. Many experts believe the underlying causes of many companies’
problems are the structures or staff.
______ ___ 14. Cost is a resource sacrificed or foregone to achieve a specific objective,
or something given up in exchange.
_____ ____ 15. Cost budgeting involves allocating the project cost estimate to individual
work items over time.
23
Eng. Hashim Al Atefi