POW N ABC
POW N ABC
POW N ABC
2), LIBERTAD
CENTRAL ELEMENTARY SCHOOL
EXECUTIVE SUMMARY
(Detailed Program of Works)
5.1) Project Description : Complete construction of 2-Storey 10-Classroom School Buidling (with
parapet, stairwall 5m width, steel casement windowat rear portion with
security grills for the front jalousie windows, fire protection system,
overhead tank and cistern)
( 9.5m x 55.00m )
5.5) Limits :
6.) REMARKS
6.1) Prices and Unit Costs used in the Detailed Unit Price Analysis (DUPA) were Based
on the approved Price Monitoring Committee for the 3rd Quarter C.Y. 2019
6.2) The authority to approved this program of work is in accordance with the provision
and guidelines of D.O. # 20 series of 2018.
In view of the foregoing, this program of work is respectfully recommended for your
Consideration and Approval.
LEOPOLDO A. LOMONSOD
Engineer III
Chief, Planning & Design Section
Republic of the Philippines
Department of Public Works and Highways
Caraga, Region XIII ANNEX A
*
Butuan City District Engineering Office
Butuan City
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL
Project : ELEMENTARY SCHOOL Appropriation : 28,792,843.61
( 9.5m x 55.00m ) Source of Fund : BEFF 2020
Project ID : Target Start Date : Upon Availability of Funds
Location : Butuan City, Agusan del Norte Total Project Duration : 205 C.D
Project Description : Complete construction of 2-Storey 10-Classroom School Buidling (with parapet, stairwall 5m width, steel casement window No. of Pre-determined : 26 C.D
at rear portion with security grills for the front jalousie windows, fire protection system, overhead tank and cistern) Unworkable Days
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 0.79% 176,800.00
Part II Other General Requirements 1.99% 448,089.64
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 2.83% 637,712.75
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 42.85% 9,645,903.72
PART C FINISHING WORKS 36.80% 8,283,898.31
PART D PLUMBING/SANITARY WORKS 7.53% 1,694,636.90
PART E ELECTRICAL WORKS 2.64% 594,613.32
PART F MECHANICAL WORKS 4.57% 1,029,386.21
Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:
GINALYN L. CULTURA RONELO ANTHONY P. SARCEDA LEOPOLDO A. LOMONSOD ERVIN P. SALANG JOSE CAESAR A. RADAZA
Engineer II Engineer II Engineer III Asst. District Engineer District Engineer
Planning & Design Section Planning & Design Section Planning & Design Section
Concurred:
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 176,800.00
Part II Other General Requirements 448,089.64
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 637,712.75
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 9,645,903.72
PART C FINISHING WORKS 8,283,898.31
PART D PLUMBING/SANITARY WORKS 1,694,636.90
PART E ELECTRICAL WORKS 594,613.32
Total
Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:
Name & Signature Name & Signature Name & Signature Name & Signature Name & Signature
Position Title Position Title Position Title Position Title Position Title
Planning/Const. Section/Division/Consultant Planning/Const. Section/Division/UPMO Planning/Construction Division/BOC
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL ELEMENTARY SCHOOL , Butuan City, Agusan del Norte
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
TOTAL UNIT COST (DIRECT+INDIRECT)
ITEM NO. DESCRIPTION UNIT
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
A.1.1 (8) Provision of Field Office for the Engineer (Rental Basis) 6.80 mo 176,800.00 26,000.00 30,030.00 0.79
B.3 Permits and Clearances 1.00 l.s. 139,150.65 139,150.65 146,108.18 0.62
B.5 Project Billboard/ Sign Board 1.00 ea 4,553.88 4,553.88 5,833.52 0.02
B.7 (2) Occupational Safety and Health Program 1.00 l.s. 85,523.92 85,523.92 98,780.13 0.38
Project ID
PART A EARTHWORKS
801(1) Removal of Structure and Obstruction 1.00 l.s. 106,452.50 106,452.50 136,365.65 0.47
803(1)a Structure Excavation (Common Soil) 469.24 m3 108,776.68 231.81 296.95 0.48
804(1)a Embankment from Structure Excavation 383.40 m3 58,612.35 152.88 195.83 0.26
900(1)c1 Structural Concrete, Class A, 28 days (4000 psi) 391.83 m3 2,521,055.99 6,434.06 8,242.03 11.20
900(1)c2 Structural Concrete, Class A, 28 days (Slab on Fill, 2500 psi) 56.28 m3 319,723.83 5,680.95 7,277.30 1.42
903(2) Formworks and Falseworks 1.00 l.s. 694,658.49 694,658.49 889,857.53 3.09
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
TOTAL UNIT COST (DIRECT+INDIRECT)
ITEM NO. DESCRIPTION UNIT
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
PART C FINISHING
1046(2)a1 CHB Non Load Bearing Wall (including Reinforcing Steel), 100 mm 219.20 m2 135,361.64 617.53 791.05 0.60
1046(2)a2 CHB Non Load Bearing Wall (including Reinforcing Steel), 150 mm 1,073.91 m2 1,036,363.81 965.04 1,236.21 4.60
1003(17) Carpentry and Joinery Works (Blackboard) 1.00 l.s. 38,879.52 38,879.52 49,804.66 0.17
1005(5) Steel Window (Window Grills) 1.00 l.s 56,735.57 56,735.57 72,678.27 0.25
1006(6) Steel Doors and Frames 1.00 l.s. 23,819.77 23,819.77 30,513.13 0.11
1008(1)c Aluminum Glass Window (Awning Type) 2.16 m2 6,041.59 2,797.03 3,583.00 0.03
1003(1)a1 Ceiling (4.5mm Fiber Cement Board on Metal Frame) 649.00 m2 547,199.99 843.14 1,080.07 2.43
1018(1) Glazed Tiles and Trims 118.51 m2 144,670.10 1,220.74 1,563.77 0.64
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
TOTAL UNIT COST (DIRECT+INDIRECT)
ITEM NO. DESCRIPTION UNIT
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.4 mm thk 572.00 m2 407,974.16 713.24 913.66 1.81
1013(2)a1 Fabricated Metal Roofing Accessory (Ridge Roll, 0.5 mm thk.) 55.80 l.m. 17,959.35 321.85 412.29 0.08
1013(2)a2 Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk.) 22.80 l.m. 10,913.67 478.67 613.18 0.05
1013(2)b1 Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk.) 10.00 l.m. 6,114.31 611.43 783.24 0.03
1047(6) Metal Structure Accessories (Steel Plates) 1,678.59 kg 119,345.31 71.10 91.08 0.53
1047(7)b Metal Structure Accessories (Sagrods) 235.00 kg 15,104.28 64.27 82.33 0.07
1047(4) Metal Structure Accessories (Cross Bracing) 520.85 kg 34,215.18 65.69 84.15 0.15
1047(3)c Metal Structure Accessories (Turnbuckle) 44.00 ea. 9,688.65 220.20 282.07 0.04
1001(8) Sewer Line Works 1.00 l.s. 137,752.26 137,752.26 176,460.65 0.61
1001(9) Storm Drainage and Downspout 1.00 l.s. 237,258.38 237,258.38 303,927.98 1.05
1002(24) Cold Water Lines 1.00 l.s. 65,128.16 65,128.16 83,429.18 0.29
FORM POW-2015-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
TOTAL UNIT COST (DIRECT+INDIRECT)
ITEM NO. DESCRIPTION UNIT
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
PART E ELECTRICAL
1100(10) Conduits, Boxes, and Fittings 1.00 l.s. 88,354.64 88,354.64 113,182.29 0.39
1101(33) Wires and Wiring Devices 1.00 l.s. 307,416.21 307,416.21 393,800.17 1.37
1102(1) Panel Boards with Main and Branch Breakers 1.00 l.s. 99,407.50 99,407.50 127,341.01 0.44
1103(1) Lighting Fixtures and Lamps 1.00 l.s. 99,434.97 99,434.97 127,376.19 0.44
PART F MECHANICAL - - - - - -
1202(1) Fire Protection System 1.00 l.s. 329,752.83 329,752.83 422,413.37 1.46
1201(1) Water Pumping System 1.00 l.s. 451,002.09 451,002.09 577,733.68 2.00
FORM POW-2015-01B-00
MINIMUM EQUIPMENT REQUIREMENT
Number of Number of
No. Equipment Description Capacity No. Equipment Description Capacity
Equipment Equipment
1 Dump Truck 12 yd3 2 20
2 Plate Compactor 5 hp 1 21
3 Concrete Vibrator 5 amp 1 22
4 One Bagger Mixer 4 - 6 ft3/min 1 23
5 Bar Cutter 1 24
6 Bar Bender 1 25
7 Welding Machine 500 amp 2 26
8 Cutting Outfit 1 27
9 Set of Minimum Material Testing Equipment 1 28
10 29
11 30
12 31
13 32
14 33
15 34
16 35
17 36
18 37
19 38
,
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL ELEMENTARY SCHOOL , Butuan City, Agusan del Norte
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
A.1.1 Offices and Laboratory for the Engineer
Provision of Field Office for the Engineer As Submitted 0.79 6.80 mo - - 176,800.00 26,000.00 176,800.00 10% 17,680.00 9,724.00 204,204.00
A.1.1 (8)
(Rental Basis) As Evaluated
As Submitted - - 176,800.00 176,800.00 17,680.00 9,724.00 204,204.00
TOTAL OF PART A
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted 0.62 1.00 l.s. 139,150.65 - - 139,150.65 139,150.65 0% - 6,957.53 146,108.18
B.3 Permits and Clearances
As Evaluated
As Submitted 0.02 1.00 ea 3,669.00 804.44 80.44 4,553.88 4,553.88 22% 1,001.85 277.79 5,833.52
B.5 Project Billboard/ Sign Board
As Evaluated
As Submitted 0.38 1.00 l.s. 78,379.44 7,144.48 - 85,523.92 85,523.92 10% 8,552.39 4,703.82 98,780.13
B.7 (2) Occupational Safety and Health Program
As Evaluated
As Submitted 0.97 1.00 l.s. - - 218,861.19 218,861.19 218,861.19 0% - 10,943.06 229,804.25
B.9 Mobilization/Demobilization
As Evaluated
As Submitted 229,148.01 7,948.92 218,941.63 448,089.64 9,554.24 22,882.20 480,526.08
TOTAL OF PART B
As Evaluated
(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted 0.47 1.00 l.s. 2,374.40 5,595.60 98,482.50 106,452.50 106,452.50 22% 23,419.55 6,493.60 136,365.65
801(1) Removal of Structure and Obstruction
As Evaluated
As Submitted 0.48 469.24 m3 - 5,530.46 103,246.22 231.81 108,776.68 22% 23,930.87 6,635.38 139,342.93
803(1)a Structure Excavation (Common Soil)
As Evaluated
As Submitted 0.26 383.40 m3 - 9,184.46 49,427.90 152.88 58,612.35 22% 12,894.72 3,575.35 75,082.42
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted 0.98 240.04 m3 183,630.60 5,750.23 30,945.94 917.88 220,326.76 22% 48,471.89 13,439.93 282,238.58
804(1)b Embankment (Borrow)
As Evaluated
As Submitted 0.64 98.95 m3 117,092.48 19,437.08 7,014.90 1,450.68 143,544.46 22% 31,579.78 8,756.21 183,880.45
804(4) Gravel Fill
As Evaluated
As Submitted 303,097.48 45,497.82 289,117.45 637,712.75 140,296.81 38,900.47 816,910.03
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WO
As Submitted 11.20 391.83 m3 1,765,390.07 506,055.70 249,610.22 6,434.06 2,521,055.99 22% 554,632.32 153,784.42 3,229,472.73
900(1)c1 Structural Concrete, Class A, 28 days (4000 psi)
As Evaluated
Structural Concrete, Class A, 28 days (Slab on As Submitted 1.42 56.28 m3 232,138.12 54,973.11 32,612.60 5,680.95 319,723.83 22% 70,339.24 19,503.15 409,566.22
900(1)c2
Fill, 2500 psi) As Evaluated
As Submitted 8.98 34,876.10 kg 1,686,346.63 235,009.92 100,665.59 57.98 2,022,022.13 22% 444,844.87 123,343.35 2,590,210.35
902(1)a Reinforcing Steel, Grade 40
As Evaluated
As Submitted 18.16 70,518.00 kg 3,409,721.60 475,180.12 203,541.56 57.98 4,088,443.28 22% 899,457.52 249,395.04 5,237,295.84
902(1)b Reinforcing Steel, Grade 60
As Evaluated
As Submitted 3.09 1.00 l.s. 325,201.80 332,907.37 36,549.31 694,658.49 694,658.49 22% 152,824.87 42,374.17 889,857.53
903(2) Formworks and Falseworks
As Evaluated
As Submitted 7,418,798.20 1,604,126.23 622,979.28 9,645,903.72 2,122,098.82 588,400.13 12,356,402.67
TOTAL OF PART B
As Evaluated
,
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL ELEMENTARY SCHOOL , Butuan City, Agusan del Norte
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE
PART C FINISHING
C.1 Termite Control Works
As Submitted 0.29 170.17 L 56,156.10 7,888.01 788.80 380.99 64,832.91 22% 14,263.24 3,954.81 83,050.96
1000(1) Soil Poisoning
As Evaluated
As Submitted 56,156.10 7,888.01 788.80 64,832.91 14,263.24 3,954.81 83,050.96
Sub - Total C.1
As Evaluated
C.2. Masonry Works
CHB Non Load Bearing Wall (including As Submitted 0.60 219.20 m2 102,603.14 20,819.70 11,938.81 617.53 135,361.64 22% 29,779.56 8,257.06 173,398.26
1046(2)a1
Reinforcing Steel), 100 mm As Evaluated
CHB Non Load Bearing Wall (including As Submitted 4.60 1,073.91 m2 843,320.04 122,689.15 70,354.61 965.04 1,036,363.81 22% 228,000.04 63,218.19 1,327,582.04
1046(2)a2
Reinforcing Steel), 150 mm As Evaluated
As Submitted 945,923.18 143,508.85 82,293.42 1,171,725.45 257,779.60 71,475.25 1,500,980.30
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted 0.17 1.00 l.s. 31,000.00 7,163.20 716.32 38,879.52 38,879.52 22% 8,553.49 2,371.65 49,804.66
1003(17) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 0.24 1.00 l.s 54,600.00 - - 54,600.00 54,600.00 22% 12,012.00 3,330.60 69,942.60
1004(2) Finishing Hardware
As Evaluated
As Submitted 1.71 108.00 m2 212,058.00 103,566.00 69,006.60 3,561.39 384,630.60 22% 84,618.73 23,462.47 492,711.80
1005(1) Casement Steel Window
As Evaluated
As Submitted 0.25 1.00 l.s 44,534.93 7,692.46 4,508.18 56,735.57 56,735.57 22% 12,481.83 3,460.87 72,678.27
1005(5) Steel Window (Window Grills)
As Evaluated
As Submitted 0.11 1.00 l.s. 22,050.00 1,608.88 160.89 23,819.77 23,819.77 22% 5,240.35 1,453.01 30,513.13
1006(6) Steel Doors and Frames
As Evaluated
As Submitted 0.03 2.16 m2 4,127.76 1,206.66 707.17 2,797.03 6,041.59 22% 1,329.15 368.54 7,739.28
1008(1)c Aluminum Glass Window (Awning Type)
As Evaluated
As Submitted 0.32 48.00 m2 33,619.20 35,752.89 3,575.29 1,519.74 72,947.38 22% 16,048.42 4,449.79 93,445.59
1009(1)a Jalousie Window (Glass)
As Evaluated
As Submitted 1.63 1.00 l.s. 295,521.00 64,355.20 6,435.52 366,311.72 366,311.72 22% 80,588.58 22,345.02 469,245.32
1010(4) Wooden Doors
As Evaluated
As Submitted 697,510.89 221,345.29 85,109.97 1,003,966.15 220,872.55 61,241.95 1,286,080.65
Sub-Total C.3
As Evaluated
C.4 Finishing Works
Ceiling (4.5mm Fiber Cement Board on Metal As Submitted 2.43 649.00 m2 403,437.87 130,692.83 13,069.28 843.14 547,199.99 22% 120,384.00 33,379.20 700,963.19
1003(1)a1
Frame) As Evaluated
As Submitted 0.28 265.60 m. 50,464.00 12,104.19 - 235.57 62,568.19 22% 13,765.00 3,816.66 80,149.85
1003(15)c Moulding (Pre-cast)
As Evaluated
As Submitted 0.46 183.00 m. 84,161.70 19,628.34 - 567.16 103,790.04 22% 22,833.81 6,331.19 132,955.04
1016(1)a Waterproofing (Cement-Base)
As Evaluated
As Submitted 0.64 118.51 m2 82,300.24 56,699.87 5,669.99 1,220.74 144,670.10 22% 31,827.42 8,824.88 185,322.40
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted 0.23 49.28 m2 33,514.82 16,504.25 1,650.43 1,048.49 51,669.50 22% 11,367.29 3,151.84 66,188.63
1018(2) Unglazed Tiles
As Evaluated
As Submitted 1.97 2,443.24 m2 286,964.65 141,450.74 14,145.07 181.14 442,560.46 22% 97,363.30 26,996.19 566,919.95
1027(1) Cement Plaster Finish
As Evaluated
As Submitted 0.44 516.15 m2 73,164.26 23,236.96 2,323.70 191.27 98,724.92 22% 21,719.48 6,022.22 126,466.62
1038(1) Reflective Insulation
As Evaluated
As Submitted 0.99 1.00 l.s. 203,697.43 7,887.27 10,386.20 221,970.90 221,970.90 22% 48,833.60 13,540.23 284,344.73
1051(6) Railings
As Evaluated
As Submitted 1,217,704.97 408,204.45 47,244.67 1,673,154.10 368,093.90 102,062.41 2,143,310.41
Sub-Total C.4
As Evaluated
,
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL ELEMENTARY SCHOOL , Butuan City, Agusan del Norte
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE
C.5 Painting Works
As Submitted 4.74 3,446.00 m2 587,776.91 434,688.29 43,468.83 309.33 1,065,934.03 22% 234,505.49 65,021.98 1,365,461.50
1032(1)a Painting Works (Masonry/Concrete)
As Evaluated
As Submitted 0.25 209.08 m2 23,081.80 29,304.39 2,930.44 264.57 55,316.63 22% 12,169.66 3,374.31 70,860.60
1032(1)b Painting Works (Wood)
As Evaluated
As Submitted 0.19 143.65 m2 22,137.69 19,026.44 1,902.64 299.80 43,066.77 22% 9,474.69 2,627.07 55,168.53
1032(1)c Painting Works (Steel)
As Evaluated
As Submitted 632,996.41 483,019.12 48,301.91 1,164,317.43 256,149.84 71,023.36 1,491,490.63
Sub-Total C.5
As Evaluated
Prepainted Metal Sheets, Long Span, As Submitted 1.81 572.00 m2 332,109.49 68,967.88 6,896.79 713.24 407,974.16 22% 89,754.32 24,886.42 522,614.90
1014(1)b1
Corrugated, 0.4 mm thk As Evaluated
Fabricated Metal Roofing Accessory (Ridge As Submitted 0.08 55.80 l.m. 16,724.93 1,122.19 112.22 321.85 17,959.35 22% 3,951.06 1,095.52 23,005.93
1013(2)a1
Roll, 0.5 mm thk.) As Evaluated
Fabricated Metal Roofing Accessory (Flashing, As Submitted 0.05 22.80 l.m. 10,409.28 458.53 45.85 478.67 10,913.67 22% 2,401.01 665.73 13,980.41
1013(2)a2
0.6 mm thk.) As Evaluated
Fabricated Metal Roofing Accessory (Gutter, As Submitted 0.03 10.00 l.m. 5,953.40 146.28 14.63 611.43 6,114.31 22% 1,345.15 372.97 7,832.43
1013(2)b1
0.6 mm thk.) As Evaluated
As Submitted 4.13 10,076.43 kg 831,204.71 57,327.18 40,065.19 92.16 928,597.08 22% 204,291.36 56,644.42 1,189,532.86
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted 7.28 17,209.50 kg 1,410,318.53 78,484.45 149,025.33 95.17 1,637,828.31 22% 360,322.23 99,907.53 2,098,058.07
1047(2)b Structural Steel Purlins
As Evaluated
As Submitted 0.08 107.10 kg 15,422.40 2,736.83 2.74 169.58 18,161.97 22% 3,995.63 1,107.88 23,265.48
1047(3)a Bolts
As Evaluated
As Submitted 0.53 1,678.59 kg 90,769.75 25,977.78 2,597.78 71.10 119,345.31 22% 26,255.97 7,280.06 152,881.34
1047(6) Metal Structure Accessories (Steel Plates)
As Evaluated
As Submitted 0.07 235.00 kg 11,103.75 3,636.85 363.68 64.27 15,104.28 22% 3,322.94 921.36 19,348.58
1047(7)b Metal Structure Accessories (Sagrods)
As Evaluated
As Submitted 0.15 520.85 kg 25,348.47 8,060.65 806.06 65.69 34,215.18 22% 7,527.34 2,087.13 43,829.65
1047(4) Metal Structure Accessories (Cross Bracing)
As Evaluated
As Submitted 0.04 44.00 ea. 8,360.00 1,327.33 1.33 220.20 9,688.65 22% 2,131.50 591.01 12,411.16
1047(3)c Metal Structure Accessories (Turnbuckle)
As Evaluated
As Submitted 2,757,724.72 248,245.96 199,931.60 3,205,902.27 705,298.51 195,560.03 4,106,760.81
Sub-Total C.6
As Evaluated
As Submitted 6,308,016.26 1,512,211.67 463,670.36 8,283,898.31 1,822,457.64 505,317.81 10,611,673.76
TOTAL OF PART C
As Evaluated
,
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL ELEMENTARY SCHOOL , Butuan City, Agusan del Norte
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE
PART D PLUMBING/SANITARY WORKS
As Submitted 0.28 28.00 ea 55,576.15 6,588.36 658.84 2,243.69 62,823.35 22% 13,821.14 3,832.22 80,476.71
1001(5)a Catch Basin
As Evaluated
As Submitted 0.61 1.00 l.s. 120,681.12 15,519.22 1,551.92 137,752.26 137,752.26 22% 30,305.50 8,402.89 176,460.65
1001(8) Sewer Line Works
As Evaluated
As Submitted 1.05 1.00 l.s. 182,354.63 49,912.50 4,991.25 237,258.38 237,258.38 22% 52,196.84 14,472.76 303,927.98
1001(9) Storm Drainage and Downspout
As Evaluated
As Submitted 0.86 1.00 l.s. 140,829.14 48,719.19 4,871.92 194,420.25 194,420.25 22% 42,772.46 11,859.64 249,052.35
1001(11) Septic Vault
As Evaluated
As Submitted 1.05 1.00 l.s. 200,877.35 32,831.21 3,283.12 236,991.68 236,991.68 22% 52,138.17 14,456.49 303,586.34
1002(4) Plumbing Fixtures
As Evaluated
As Submitted 0.29 1.00 l.s. 53,013.16 11,013.64 1,101.36 65,128.16 65,128.16 22% 14,328.20 3,972.82 83,429.18
1002(24) Cold Water Lines
As Evaluated
As Submitted 3.38 1.00 l.s 669,413.99 82,589.84 8,258.98 760,262.82 760,262.82 22% 167,257.82 46,376.03 973,896.67
1002(26) Cistern
As Evaluated
As Submitted 1,422,745.52 247,173.97 24,717.40 1,694,636.90 372,820.13 103,372.85 2,170,829.88
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted 0.39 1.00 l.s. 79,504.10 8,045.94 804.59 88,354.64 88,354.64 22% 19,438.02 5,389.63 113,182.29
1100(10) Conduits, Boxes, and Fittings
As Evaluated
As Submitted 1.37 1.00 l.s. 289,348.50 16,425.19 1,642.52 307,416.21 307,416.21 22% 67,631.57 18,752.39 393,800.17
1101(33) Wires and Wiring Devices
As Evaluated
As Submitted 0.44 1.00 l.s. 93,350.00 5,506.82 550.68 99,407.50 99,407.50 22% 21,869.65 6,063.86 127,341.01
1102(1) Panel Boards with Main and Branch Breakers
As Evaluated
As Submitted 0.44 1.00 l.s. 88,208.00 10,206.33 1,020.63 99,434.97 99,434.97 22% 21,875.69 6,065.53 127,376.19
1103(1) Lighting Fixtures and Lamps
As Evaluated
As Submitted 550,410.60 40,184.28 4,018.43 594,613.32 130,814.93 36,271.41 761,699.66
TOTAL OF PART E
As Evaluated
PART F MECHANICAL
As Submitted 1.46 1.00 l.s. 282,957.90 42,540.84 4,254.08 329,752.83 329,752.83 22% 72,545.62 20,114.92 422,413.37
1202(1) Fire Protection System
As Evaluated
As Submitted 2.00 1.00 l.s. 429,599.00 19,457.35 1,945.74 451,002.09 451,002.09 22% 99,220.46 27,511.13 577,733.68
1201(1) Water Pumping System
As Evaluated
As Submitted 1.10 1.00 l.s. 208,160.00 36,792.08 3,679.21 248,631.29 248,631.29 22% 54,698.88 15,166.51 318,496.68
1200(14) Ventilation
As Evaluated
As Submitted 920,716.90 108,669.30 9,879.03 1,029,386.21 226,464.96 62,792.56 1,318,643.73
TOTAL OF PART F
As Evaluated
As Submitted 16,923,784.97 3,557,863.27 1,414,381.95 21,886,151.21 4,814,953.29 1,335,055.23 28,036,159.73
TOTAL OF PART III
As Evaluated
As Submitted 16,923,784.97 3,557,863.27 1,414,381.95 21,886,151.21 4,814,953.29 1,335,055.23 28,036,159.73
TOTAL OF (Project ID)
As Evaluated
As Submitted 17,152,932.98 3,565,812.19 1,810,123.59 22,511,040.85 4,842,187.53 1,367,661.43 28,720,889.81
GRAND TOTAL
As Evaluated
Republic of the Philippines
Department of Public Works and Highways
Caraga, Region XIII
*
Butuan City District Engineering Office
Butuan City
FORM ABC-2015-02-00
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL ELEMENTARY SCHOOL , Butuan City, Agusan del Norte
(Project ID)
(Project Component ID - Description)
Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:
RYAN JOY L. BASCO LAARNI D. DE LOS SANTOS TERESITA D. LOON ERVIN P. SALANG JOSE CAESAR A, RADAZA
Engineer II Engineer II Engineer III Asst. District Engineer District Engineer
Planning & Design Section Quality Assurance Section Chief, Construction Section Chairman
Member Member
Republic of the Philippines
Department of Public Works and Highways
Caraga, Region XIII
*
Butuan City District Engineering Office
Butuan City
FORM ABC-2015-02A-00
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL ELEMENTARY SCHOOL , Butuan City, Agusan del Norte
AS SUBMITTED 1.00 l.s. 85,523.92 10% 8,552.39 4,703.79 13,256.18 98,780.10 98,780.10
B.7 (2) Occupational Safety and Health Program
AS EVALUATED
(Project ID)
(Project Component ID - Description)
PART A EARTHWORKS
AS SUBMITTED 1.00 l.s. 106,452.50 22% 23,419.55 6,492.95 29,912.50 136,365.00 136,365.00
801(1) Removal of Structure and Obstruction
AS EVALUATED
FORM ABC-2015-02A-00
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL ELEMENTARY SCHOOL , Butuan City, Agusan del Norte
AS SUBMITTED 1.00 l.s. 694,658.49 22% 152,824.87 42,373.64 195,198.51 889,857.00 889,857.00
903(2) Formworks and Falseworks
AS EVALUATED
CHB Non Load Bearing Wall (including Reinforcing Steel), AS SUBMITTED 219.20 m2 135,361.64 22% 29,779.56 8,246.00 38,025.56 173,387.20 791.00
1046(2)a1
100 mm AS EVALUATED
CHB Non Load Bearing Wall (including Reinforcing Steel), AS SUBMITTED 1,073.91 m2 1,036,363.81 22% 228,000.04 62,988.91 290,988.95 1,327,352.76 1,236.00
1046(2)a2
150 mm AS EVALUATED
AS SUBMITTED 1.00 l.s. 38,879.52 22% 8,553.49 2,370.99 10,924.48 49,804.00 49,804.00
1003(17) Carpentry and Joinery Works (Blackboard)
AS EVALUATED
AS SUBMITTED 1.00 l.s 54,600.00 22% 12,012.00 3,330.00 15,342.00 69,942.00 69,942.00
1004(2) Finishing Hardware
AS EVALUATED
AS SUBMITTED 1.00 l.s 56,735.57 22% 12,481.83 3,460.60 15,942.43 72,678.00 72,678.00
1005(5) Steel Window (Window Grills)
AS EVALUATED
AS SUBMITTED 1.00 l.s. 23,819.77 22% 5,240.35 1,453.01 6,693.36 30,513.13 30,513.13
1006(6) Steel Doors and Frames
AS EVALUATED
FORM ABC-2015-02A-00
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL ELEMENTARY SCHOOL , Butuan City, Agusan del Norte
AS SUBMITTED 1.00 l.s. 221,970.90 22% 48,833.60 13,539.50 62,373.10 284,344.00 284,344.00
1051(6) Railings
AS EVALUATED
AS SUBMITTED 55.80 l.m. 17,959.35 22% 3,951.06 1,079.19 5,030.25 22,989.60 412.00
1013(2)a1 Fabricated Metal Roofing Accessory (Ridge Roll, 0.5 mm thk.)
AS EVALUATED
AS SUBMITTED 22.80 l.m. 10,913.67 22% 2,401.01 661.72 3,062.73 13,976.40 613.00
1013(2)a2 Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk.)
AS EVALUATED
AS SUBMITTED 10.00 l.m. 6,114.31 22% 1,345.15 370.54 1,715.69 7,830.00 783.00
1013(2)b1 Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk.)
AS EVALUATED
FORM ABC-2015-02A-00
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL ELEMENTARY SCHOOL , Butuan City, Agusan del Norte
AS SUBMITTED 44.00 ea. 9,688.65 22% 2,131.50 590.93 2,722.43 12,411.08 282.07
1047(3)c Metal Structure Accessories (Turnbuckle)
AS EVALUATED
AS SUBMITTED 1.00 l.s. 236,991.68 22% 52,138.17 14,456.15 66,594.32 303,586.00 303,586.00
1002(4) Plumbing Fixtures
AS EVALUATED
AS SUBMITTED 1.00 l.s. 65,128.16 22% 14,328.20 3,972.64 18,300.84 83,429.00 83,429.00
1002(24) Cold Water Lines
AS EVALUATED
AS SUBMITTED 1.00 l.s 760,262.82 22% 167,257.82 46,375.36 213,633.18 973,896.00 973,896.00
1002(26) Cistern
AS EVALUATED
FORM ABC-2015-02A-00
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL ELEMENTARY SCHOOL , Butuan City, Agusan del Norte
Contract ID:
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL
Contract Name:
ELEMENTARY SCHOOL
Contract Location: Butuan City, Agusan del Norte
---------------------------------------------------------------------------
SUMMARY OF BID PRICES
(All Parts of Bill of Quantities)
1. Part No. – Enter the “Part No.” for each section of the BOQ where unit prices are entered.
2. Part Description – Enter the “Part Description” corresponding to the “Part No.”
3. Total Amount – Enter the “Total Amount” in Pesos for all pages having the same “Part Description”
Total of Amounts
Total of All Amounts in words
Pesos
_____________________________________________________________________________________
________
and ___________________________________ centavos__________________________
Contract ID:
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL
Contract Name:
ELEMENTARY SCHOOL
Contract Location: Butuan City, Agusan del Norte
---------------------------------------------------------------------------------
BILL OF QUANTITIES
Contract ID:
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL
Contract Name:
ELEMENTARY SCHOOL
Contract Location: Butuan City, Agusan del Norte
---------------------------------------------------------------------------------
BILL OF QUANTITIES
Php
Php
Department of Public Works and Highways (DPWH)
Contract ID:
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL
Contract Name:
ELEMENTARY SCHOOL
Contract Location: Butuan City, Agusan del Norte
---------------------------------------------------------------------------------
BILL OF QUANTITIES
Php
Department of Public Works and Highways (DPWH)
Contract ID:
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL
Contract Name:
ELEMENTARY SCHOOL
Contract Location: Butuan City, Agusan del Norte
---------------------------------------------------------------------------------
BILL OF QUANTITIES
Contract ID:
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL
Contract Name:
ELEMENTARY SCHOOL
Contract Location: Butuan City, Agusan del Norte
---------------------------------------------------------------------------------
BILL OF QUANTITIES
Php
Php
Department of Public Works and Highways (DPWH)
Contract ID:
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL
Contract Name:
ELEMENTARY SCHOOL
Contract Location: Butuan City, Agusan del Norte
---------------------------------------------------------------------------------
BILL OF QUANTITIES
Contract ID:
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL
Contract Name:
ELEMENTARY SCHOOL
Contract Location: Butuan City, Agusan del Norte
---------------------------------------------------------------------------------
BILL OF QUANTITIES
Php
Department of Public Works and Highways (DPWH)
Contract ID:
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL
Contract Name:
ELEMENTARY SCHOOL
Contract Location: Butuan City, Agusan del Norte
---------------------------------------------------------------------------------
BILL OF QUANTITIES
Contract ID:
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL
Contract Name:
ELEMENTARY SCHOOL
Contract Location: Butuan City, Agusan del Norte
---------------------------------------------------------------------------------
BILL OF QUANTITIES
Php
Php
Eligibility Requirements
1c(1)
The ABC for this contract AS stated clearly at Invitation to Bid.
1c(1)
The prospective bidder must possess a valid license issued by the Philippine Contractors’ Accreditation B
(PCAB) in accordance with the provisions of RA 4566, for the specific category indicated in the Eligibility D
Sheet (EDS), out of the following PCAB categories:
1c(2) (1) The following are the “Major Categories of Works” involved in the contract to be bid: (see sample based o
139, S-2016)
a. BICWOPLC Buildings: Construction - without pile - low rise - concrete frame
(2) The following are the “Similar Categories of Works” that shall be considered in the evaluation of the w
experience required for the contract to be bid:
Must
have done a Single Largest Completed Contract for a Major/Similar Category of Works whose total cost is at least 5
a.
Approved Budget of the Contract to be bid
ation to Bid.
ow table)
Allowable Range of
No limit
Up to PhP300M
Up to PhP200M
Up to PhP100M
Up to PhP15M
Up to PhP500,000
rks” involved in the contract to be bid: (see sample based on D.O. No.
is contract:
for a Major/Similar Category of Works whose total cost is at least 50% of the
ement.
STANDARD FORMAT
BID DATA SHEET
ITB Clause
1.1 The Procuring Entity is DPWH - Butuan City District Engineering Office.
The scope of the Works under this Contract is stated in the Invitation to Bid.
5 The similar work category and qualifier must be met by the eligible bidder as per Department
Order No. 139, S-2016.
8.1 Insert any exceptions, e.g., provisions of approved loan agreement for a foreign-assisted
project pertaining to sub-contracting.
8.3
Insert any limitation on the extent of the portions of the Works that may sub- contracted.
9.1 The date and time of the Pre-Bid Conference are [ as indicated at IB]
The Pledged Equipment shall ne listed in complete by using the Attached Form at PBD
Annex to include the brand, capacity, engine, chassis and serial number and its
present location ready for the inspection during the Post-Qualification Stage.
Failure of the prospective bidders to state a technical description of the Pledge
Equipment and the specific loacation, whether owned, leased or under Purchased
Agreement shall result the bidder automatic post disqualification for award and
forfeiture of its Bid Security as per D.O 58 Series of 2012.
If WB, state: Subject to prior concurrence by the World Bank, for foreign- funded
procurement, a ceiling may be applied to bid prices provided the conditions in ITB 14.3b are
met.
17.1 Bids shall be valid until [unless renewed not later than one hundred twenty (120) days
from the date set for bid opening].
18.2 The Bid Security shall be valid until [unless renewed not later than one hundred twenty
(120) days from the date set for bid opening].
19.1
Select one, delete the other:
PROJECT :
CONSTRUCTION OF TWO STOREY TEN CLASSROOMS (2STY10CL Bldg. 2), LIBERTAD CENTRAL
ELEMENTARY SCHOOL , Butuan City, Agusan del Norte
DURATION : 205
ABC : PhP 28,687,461.58
SUMMARY OF QUANTITIES
:
ITEM NO. DESCRIPTION QTY. UNIT
PART I FACILITIES FOR THE ENGINEER
A.1.1 (8) Provision of Field Office for the Engineer (Rental Basis) 6.80 mo
PART II OTHER GENERAL REQUIREMENTS
B.3 Permits and Clearances 1.00 l.s.
B.5 Project Billboard/ Sign Board 1.00 ea
B.7 (2) Occupational Safety and Health Program 1.00 l.s.
B.9 Mobilization/Demobilization 1.00 l.s.
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
801(1) Removal of Structure and Obstruction 1.00 l.s.
803(1)a Structure Excavation (Common Soil) 469.24 m3
804(1)a Embankment from Structure Excavation 383.40 m3
804(1)b Embankment (Borrow) 240.04 m3
804(4) Gravel Fill 98.95 m3
PART B PLAIN AND REINFORCED CONCRETE WORKS
900(1)c1 Structural Concrete, Class A, 28 days (4000 psi) 391.83 m3
900(1)c2 Structural Concrete, Class A, 28 days (Slab on Fill, 2500 psi) 56.28 m3
902(1)a Reinforcing Steel, Grade 40 34,876.10 kg
902(1)b Reinforcing Steel, Grade 60 70,518.00 kg
903(2) Formworks and Falseworks 1.00 l.s.
PART C FINISHING WORKS
1000(1) Soil Poisoning 170.17 L
1046(2)a1 CHB Non Load Bearing Wall (including Reinforcing Steel), 100 mm 219.20 m2
1046(2)a2 CHB Non Load Bearing Wall (including Reinforcing Steel), 150 mm 1,073.91 m2
1003(17) Carpentry and Joinery Works (Blackboard) 1.00 l.s.
1004(2) Finishing Hardware 1.00 l.s
1005(1) Casement Steel Window 108.00 m2
1005(5) Steel Window (Window Grills) 1.00 l.s
1006(6) Steel Doors and Frames 1.00 l.s.
1008(1)c Aluminum Glass Window (Awning Type) 2.16 m2
1009(1)a Jalousie Window (Glass) 48.00 m2
1010(4) Wooden Doors 1.00 l.s.
1003(1)a1 Ceiling (4.5mm Fiber Cement Board on Metal Frame) 649.00 m2
1003(15)c Moulding (Pre-cast) 265.60 m.
1016(1)a Waterproofing (Cement-Base) 183.00 m.
1018(1) Glazed Tiles and Trims 118.51 m2
1018(2) Unglazed Tiles 49.28 m2
38 of 72
1027(1) Cement Plaster Finish 2,443.24 m2
1038(1) Reflective Insulation 516.15 m2
1051(6) Railings 1.00 l.s.
1032(1)a Painting Works (Masonry/Concrete) 3,446.00 m2
1032(1)b Painting Works (Wood) 209.08 m2
1032(1)c Painting Works (Steel) 143.65 m2
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.4 mm thk 572.00 m2
1013(2)a1 Fabricated Metal Roofing Accessory (Ridge Roll, 0.5 mm thk.) 55.80 l.m.
1013(2)a2 Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk.) 22.80 l.m.
1013(2)b1 Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk.) 10.00 l.m.
1047(2)a Structural Steel, Trusses 10,076.43 kg
1047(2)b Structural Steel Purlins 17,209.50 kg
1047(3)a Bolts 107.10 kg
1047(6) Metal Structure Accessories (Steel Plates) 1,678.59 kg
1047(7)b Metal Structure Accessories (Sagrods) 235.00 kg
1047(4) Metal Structure Accessories (Cross Bracing) 520.85 kg
1047(3)c Metal Structure Accessories (Turnbuckle) 44.00 ea.
PART D PLUMBING/SANITARY WORKS
1001(5)a Catch Basin 28.00 ea
1001(8) Sewer Line Works 1.00 l.s.
1001(9) Storm Drainage and Downspout 1.00 l.s.
1001(11) Septic Vault 1.00 l.s.
1002(4) Plumbing Fixtures 1.00 l.s.
1002(24) Cold Water Lines 1.00 l.s.
1002(26) Cistern 1.00 l.s
PART E ELECTRICAL WORKS
1100(10) Conduits, Boxes, and Fittings 1.00 l.s.
1101(33) Wires and Wiring Devices 1.00 l.s.
1102(1) Panel Boards with Main and Branch Breakers 1.00 l.s.
1103(1) Lighting Fixtures and Lamps 1.00 l.s.
PART F MECHANICAL WORKS
1202(1) Fire Protection System 1.00 l.s.
1201(1) Water Pumping System 1.00 l.s.
1200(14) Ventilation 1.00 l.s.
EQUIPMENT REQUIREMENTS:
39 of 72
ANNEX A
BUREAU OF CONSTRUCTION
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 0.89% 156,000.00
Part II Other General Requirements 1.58% 275,814.08
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 2.28% 396,833.63
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 34.33% 5,988,000.95
PART C FINISHING WORKS 46.10% 8,041,232.82
PART D PLUMBING/SANITARY WORKS 10.45% 1,823,557.12
PART E ELECTRICAL WORKS 4.36% 760,618.07
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted #REF! 6.00 mo - - 156,000.00 156,000.00 8% 12,480.00 20,217.60 188,697.60
#REF! Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 156,000.00 156,000.00 12,480.00 20,217.60 188,697.60
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted #REF! 1.00 ea 3,182.34 918.56 91.86 4,192.76 20% 838.55 603.76 5,635.07
#REF! Project Billboard/ Sign Board
As Evaluated
As Submitted #REF! 1.00 lot 137,035.54 7,008.96 - 144,044.50 8% 11,523.56 18,668.17 174,236.23
#REF! Occupational Safety and Health
As Evaluated
As Submitted #REF! 1.00 l.s. - - 127,576.82 127,576.82 8% 10,206.15 16,533.96 154,316.93
#REF! Mobilization/ Demobilization
As Evaluated
As Submitted 140,217.88 7,927.52 127,668.68 275,814.08 22,568.26 35,805.89 334,188.23
TOTAL OF PART II
As Evaluated
(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted #REF! 413.71 m3 - 5,567.92 91,097.23 96,665.14 20% 19,333.03 13,919.78 129,917.95
#REF! Structure Excavation
As Evaluated
As Submitted #REF! 257.76 m3 - 7,050.94 33,318.02 40,368.96 20% 8,073.79 5,813.13 54,255.88
#REF! Embankment from Structure Excavation
As Evaluated
As Submitted #REF! 335.90 m3 122,028.27 9,188.44 43,418.39 174,635.09 20% 34,927.02 25,147.45 234,709.56
#REF! Embankment from Borrow
As Evaluated
As Submitted #REF! 90.34 m3 58,244.10 20,264.01 6,656.33 85,164.44 20% 17,032.89 12,263.68 114,461.01
#REF! Gravel Fill
As Evaluated
As Submitted 180,272.37 42,071.31 174,489.96 396,833.63 79,366.73 57,144.04 533,344.40
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted #REF! 384.71 m3 1,263,772.35 60,395.33 82,880.19 1,407,047.87 20% 281,409.57 202,614.89 1,891,072.33
#REF! Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted #REF! 68,853.89 kg 2,542,851.62 530,498.28 205,391.47 3,278,741.37 20% 655,748.27 472,138.76 4,406,628.40
#REF! Reinforcing Steel, Grade 40
As Evaluated
As Submitted #REF! 2,577.60 m2 504,369.13 558,645.42 239,197.16 1,302,211.71 20% 260,442.34 187,518.49 1,750,172.54
#REF! Forms and Falseworks
As Evaluated
As Submitted 4,310,993.10 1,149,539.04 527,468.81 5,988,000.95 1,197,600.18 862,272.14 8,047,873.27
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted #REF! 300.27 L 96,086.40 15,898.18 1,589.82 113,574.40 20% 22,714.88 16,354.71 152,643.99
#REF! Soil Poisoning
As Evaluated
As Submitted 96,086.40 15,898.18 1,589.82 113,574.40 22,714.88 16,354.71 152,643.99
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted #REF! 285.37 m2 99,856.73 30,975.89 15,929.91 146,762.53 20% 29,352.51 21,133.80 197,248.84
#REF! 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted #REF! 961.80 m2 561,645.73 125,575.39 64,579.43 751,800.54 20% 150,360.11 108,259.28 1,010,419.93
#REF! 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 661,502.46 156,551.28 80,509.34 898,563.07 179,712.62 129,393.08 1,207,668.77
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted #REF! 1.00 l.s 343,872.83 66,595.60 45.93 410,514.36 20% 82,102.87 59,114.07 551,731.30
1010(4) Wooden Doors
As Evaluated
As Submitted #REF! 70.87 m2 47,447.47 60,276.25 6,027.62 113,751.34 20% 22,750.27 16,380.19 152,881.80
#REF! Jalousie Window
As Evaluated
As Submitted #REF! 146.88 m2 272,857.73 187,386.24 98,502.62 558,746.59 20% 111,749.32 80,459.51 750,955.42
1005(1) Steel Casement Window
As Evaluated
As Submitted #REF! 65.28 m2 56,433.61 9,369.31 4,925.13 70,728.06 20% 14,145.61 10,184.84 95,058.51
1005(5) Window Grilles
As Evaluated
As Submitted #REF! 43.00 set 64,500.00 - - 64,500.00 20% 12,900.00 9,288.00 86,688.00
#REF! Locksets
As Evaluated
As Submitted #REF! 172.00 pc 11,398.44 - - 11,398.44 20% 2,279.69 1,641.38 15,319.51
#REF! Hinges
As Evaluated
As Submitted #REF! 1.00 l.s. 37,200.00 9,818.40 981.84 48,000.24 20% 9,600.05 6,912.03 64,512.32
#REF! Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 833,710.08 333,445.80 110,483.15 1,277,639.03 255,527.81 183,980.02 1,717,146.86
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted #REF! 1,161.01 m2 221,432.06 66,768.81 6,676.88 294,877.75 20% 58,975.55 42,462.40 396,315.70
#REF! Plain Cement Finish with floor hardener
As Evaluated
As Submitted #REF! 4,355.83 m 2
355,282.82 288,224.51 28,822.45 672,329.77 20% 134,465.95 96,815.49 903,611.21
#REF! Plain Cement Plaster Finish
As Evaluated
As Submitted #REF! 66.00 m 19,940.06 3,016.80 3,515.82 26,472.68 20% 5,294.54 3,812.07 35,579.29
#REF! 38 mm dia. G.I. Pipe Railings
As Evaluated
As Submitted #REF! 144.00 m 243,681.41 6,582.10 7,670.87 257,934.38 20% 51,586.88 37,142.55 346,663.81
#REF! 50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar stiffener
As Evaluated
As Submitted #REF! 661.00 m 2
410,897.43 152,040.64 15,204.06 578,142.13 20% 115,628.43 83,252.47 777,023.03
#REF! Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted #REF! 841.24 m 2
119,245.77 43,258.80 4,325.88 166,830.45 20% 33,366.09 24,023.58 224,220.12
#REF! Reflective Insulation
As Evaluated
As Submitted #REF! 115.51 m 2
109,975.18 63,190.67 6,319.07 179,484.91 20% 35,896.98 25,845.83 241,227.72
#REF! Glazed Tiles and Trims
As Evaluated
As Submitted #REF! 50.68 m 2
53,656.17 19,408.10 1,940.81 75,005.08 20% 15,001.02 10,800.73 100,806.83
#REF! Unglazed Tiles
As Evaluated
As Submitted 1,534,110.90 642,490.41 74,475.84 2,251,077.15 450,215.44 324,155.12 3,025,447.71
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted #REF! 4,943.76 m2 674,852.31 712,489.98 71,249.00 1,458,591.29 20% 291,718.26 210,037.15 1,960,346.70
#REF! Masonry/Concrete Painting
As Evaluated
As Submitted #REF! 247.39 m 2
19,362.81 39,615.12 3,961.51 62,939.45 20% 12,587.89 9,063.28 84,590.62
#REF! Wood Painting
As Evaluated
As Submitted #REF! 125.09 m 2
17,234.96 18,929.24 1,892.92 38,057.13 20% 7,611.43 5,480.23 51,148.79
#REF! Metal Painting
As Evaluated
As Submitted 711,450.08 771,034.35 77,103.44 1,559,587.87 311,917.58 224,580.66 2,096,086.11
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted #REF! 841.24 m2 347,086.71 115,856.97 11,585.70 474,529.38 20% 94,905.88 68,332.23 637,767.49
#REF! Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted #REF! 64.20 m 13,549.22 1,474.29 147.43 15,170.94 20% 3,034.19 2,184.62 20,389.75
#REF! Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted #REF! 26.21 m 5,530.88 601.81 60.18 6,192.88 20% 1,238.58 891.78 8,323.24
#REF! Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
As Submitted #REF! 128.40 m 41,262.62 2,498.79 249.88 44,011.30 20% 8,802.26 6,337.63 59,151.19
#REF! Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (12 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted #REF! 7,703.59 kg 428,855.23 49,752.65 103,653.95 582,261.83 20% 116,452.37 83,845.70 782,559.90
#REF! Structural Steel, Trusses
As Evaluated
As Submitted #REF! 10,028.53 kg 564,929.01 52,272.53 87,495.57 704,697.11 20% 140,939.42 101,476.38 947,112.91
#REF! Structural Steel, Purlins
As Evaluated
As Submitted #REF! 128.40 m 24,402.42 3,091.77 309.18 27,803.36 20% 5,560.67 4,003.68 37,367.71
#REF! Fascia Board
As Evaluated
As Submitted #REF! 277.47 kg 15,049.29 4,903.31 490.33 20,442.94 20% 4,088.59 2,943.78 27,475.31
#REF! Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted #REF! 293.65 kg 11,679.64 5,189.21 518.92 17,387.77 20% 3,477.55 2,503.84 23,369.16
#REF! Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted #REF! 628.56 kg 25,750.36 11,107.54 1,110.75 37,968.65 20% 7,593.73 5,467.49 51,029.87
#REF! Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted #REF! 52.00 pc 8,532.16 1,791.19 1.79 10,325.14 20% 2,065.03 1,486.82 13,876.99
#REF! Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted 1,486,627.54 248,540.08 205,623.68 1,940,791.30 388,158.27 279,473.95 2,608,423.52
Sub-Total C.6
As Evaluated
As Submitted 5,323,487.45 2,167,960.10 549,785.26 8,041,232.82 1,608,246.60 1,157,937.54 10,807,416.96
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted #REF! 1.00 l.s. 45,831.25 10,578.67 1,057.87 57,467.79 20% 11,493.56 8,275.36 77,236.71
#REF! Sewer Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 31,668.25 7,362.18 736.22 39,766.65 20% 7,953.33 5,726.40 53,446.38
#REF! Cold Water Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 193,090.94 44,552.97 4,455.30 242,099.20 20% 48,419.84 34,862.28 325,381.32
#REF! Downspout/Storm Drain
As Evaluated
As Submitted #REF! 1.00 l.s. 326,472.09 37,833.19 3,783.32 368,088.60 20% 73,617.72 53,004.76 494,711.08
#REF! Sanitary/Plumbing Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 84,458.63 20,979.97 2,098.00 107,536.59 20% 21,507.32 15,485.27 144,529.18
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted #REF! 30.00 units 18,201.24 6,889.20 12,023.04 37,113.48 20% 7,422.70 5,344.34 49,880.52
#REF! Catch basin
As Evaluated
As Submitted #REF! 1.00 lot 875,153.75 87,573.70 8,757.37 971,484.81 20% 194,296.96 139,893.81 1,305,675.58
SPL-2 Fire Protection System
As Evaluated
As Submitted 1,574,876.14 215,769.88 32,911.11 1,823,557.12 364,711.43 262,592.22 2,450,860.77
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted #REF! 1.00 l.s. 90,605.14 17,183.92 1,718.39 109,507.45 20% 21,901.49 15,769.07 147,178.01
#REF! Conduits, Boxes, and Fittings
As Evaluated
As Submitted #REF! 1.00 l.s. 212,531.55 20,038.24 2,003.82 234,573.61 20% 46,914.72 33,778.60 315,266.93
#REF! Wires and Wiring Devices
As Evaluated
As Submitted #REF! 1.00 l.s. 251,941.00 4,288.65 428.87 256,658.52 20% 51,331.70 36,958.83 344,949.05
#REF! Panel Board
As Evaluated
As Submitted #REF! 1.00 l.s. 120,058.00 10,292.76 1,029.28 131,380.04 20% 26,276.01 18,918.73 176,574.78
#REF! Lighting Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 24,090.00 4,007.68 400.77 28,498.45 20% 5,699.69 4,103.78 38,301.92
#REF! Fire Alarm System
As Evaluated
As Submitted 699,225.69 55,811.25 5,581.13 760,618.070 152,123.610 109,529.010 1,022,270.690
TOTAL OF PART E
As Evaluated
As Submitted 12,088,854.75 3,631,151.57 1,290,236.27 17,010,242.590 3,402,048.550 2,449,474.950 22,861,766.090
TOTAL OF PART III
As Evaluated
As Submitted 12,229,072.63 3,639,079.09 1,573,904.94 17,442,056.670 3,437,096.810 2,505,498.440 23,384,651.920
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 0.99% 151,666.67
Part II Other General Requirements 1.61% 247,792.58
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 2.24% 343,879.89
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 33.84% 5,205,623.63
PART C FINISHING WORKS 45.48% 6,995,668.73
PART D PLUMBING/SANITARY WORKS 11.25% 1,729,864.72
PART E ELECTRICAL WORKS 4.61% 708,793.02
`
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted #REF! 5.83 mo - - 151,666.67 151,666.67 8% 12,133.33 19,656.00 183,456.00
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 151,666.67 151,666.67 12,133.33 19,656.00 183,456.00
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted #REF! 1.00 ea 3,182.34 918.56 91.86 4,192.76 20% 838.55 603.76 5,635.07
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted #REF! 1.00 L.S. 124,212.14 7,008.96 - 131,221.10 8% 10,497.69 17,006.25 158,725.04
II.7 Occupational Safety and Health
As Evaluated
As Submitted #REF! 1.00 l.s. - - 112,378.72 112,378.72 8% 8,990.30 14,564.28 135,933.30
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 127,394.48 7,927.52 112,470.58 247,792.58 20,326.54 32,174.29 300,293.41
TOTAL OF PART II
As Evaluated
(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted #REF! 365.45 m3 - 4,918.41 80,470.57 85,388.98 20% 17,077.80 12,296.01 114,762.79
803(1)a Structure Excavation
As Evaluated
804(1)a As Submitted #REF! 223.43 m3 - 6,111.85 28,880.53 34,992.39 20% 6,998.48 5,038.90 47,029.77
Embankment from Structure Excavation
As Evaluated
As Submitted #REF! 288.09 m3 104,659.50 7,880.61 37,238.47 149,778.58 20% 29,955.72 21,568.12 201,302.42
804(1)b Embankment from Borrow
As Evaluated
As Submitted #REF! 78.20 m3 50,417.18 17,540.91 5,761.84 73,719.94 20% 14,743.99 10,615.67 99,079.60
804(4) Gravel Fill
As Evaluated
As Submitted 155,076.68 36,451.78 152,351.42 343,879.89 68,775.99 49,518.70 462,174.58
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted #REF! 335.41 m3 1,101,821.85 52,655.76 72,259.22 1,226,736.83 20% 245,347.37 176,650.10 1,648,734.30
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted #REF! 59,947.73 kg 2,213,937.11 461,879.02 178,824.36 2,854,640.49 20% 570,928.10 411,068.23 3,836,636.82
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted #REF! 2,225.34 m2 435,440.05 482,298.73 206,507.53 1,124,246.31 20% 224,849.26 161,891.47 1,510,987.04
903(2) Forms and Falseworks
As Evaluated
As Submitted 3,751,199.01 996,833.52 457,591.10 5,205,623.63 1,041,124.73 749,609.80 6,996,358.16
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted #REF! 259.98 L 83,193.60 13,764.98 1,376.50 98,335.08 20% 19,667.02 14,160.25 132,162.35
1000(1) Soil Poisoning
As Evaluated
As Submitted 83,193.60 13,764.98 1,376.50 98,335.08 19,667.02 14,160.25 132,162.35
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted #REF! 267.94 m2 93,757.62 29,083.92 14,956.94 137,798.48 20% 27,559.70 19,842.98 185,201.16
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted #REF! 838.99 m2 489,930.49 109,540.96 56,333.43 655,804.88 20% 131,160.98 94,435.90 881,401.76
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted 583,688.12 138,624.89 71,290.37 793,603.36 158,720.68 114,278.88 1,066,602.92
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted #REF! 1.00 l.s. 296,777.99 59,706.40 5,970.64 362,455.03 20% 72,491.01 52,193.52 487,139.56
1010(4) Wooden Doors
As Evaluated
As Submitted #REF! 59.98 m2 40,156.61 51,014.10 5,101.41 96,272.12 20% 19,254.42 13,863.18 129,389.72
1009(1)a Jalousie Window
As Evaluated
As Submitted #REF! 122.40 m2 227,381.44 156,155.20 82,085.52 465,622.16 20% 93,124.43 67,049.59 625,796.18
1005(1) Steel Casement Window
As Evaluated
As Submitted #REF! 54.40 m 2
47,028.01 7,807.76 4,104.28 58,940.05 20% 11,788.01 8,487.37 79,215.43
1005(5) Window Grills
As Evaluated
As Submitted #REF! 39.00 set 58,500.00 - - 58,500.00 20% 11,700.00 8,424.00 78,624.00
1004(2)a Locksets
As Evaluated
As Submitted #REF! 156.00 pc 10,338.12 - - 10,338.12 20% 2,067.62 1,488.69 13,894.43
1004(2)g Hinges
As Evaluated
As Submitted #REF! 1.00 l.s. 31,000.00 8,182.00 818.20 40,000.20 20% 8,000.04 5,760.03 53,760.27
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 711,182.17 282,865.46 98,080.05 1,092,127.68 218,425.53 157,266.38 1,467,819.59
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted #REF! 1,000.20 m2 190,761.79 57,520.75 5,752.07 254,034.61 20% 50,806.92 36,580.98 341,422.51
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted #REF! 3,825.21 m2 312,002.85 253,113.47 25,311.35 590,427.67 20% 118,085.53 85,021.58 793,534.78
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted #REF! 66.00 m 19,940.06 3,016.80 3,515.82 26,472.68 20% 5,294.54 3,812.07 35,579.29
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar As Submitted #REF! 127.60 m 215,928.80 5,832.47 6,797.24 228,558.52 20% 45,711.70 32,912.43 307,182.65
1053(3)a2
stiffener As Evaluated
As Submitted #REF! 565.91 m 2
351,786.63 130,168.41 13,016.84 494,971.88 20% 98,994.38 71,275.95 665,242.21
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted #REF! 723.31 m2 102,529.19 37,194.53 3,719.45 143,443.17 20% 28,688.63 20,655.82 192,787.62
1038(1) Reflective Insulation
As Evaluated
As Submitted #REF! 115.51 m2 109,975.18 63,190.67 6,319.07 179,484.91 20% 35,896.98 25,845.83 241,227.72
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted #REF! 50.68 m2 53,656.17 19,408.10 1,940.81 75,005.08 20% 15,001.02 10,800.73 100,806.83
1018(2) Unglazed Tiles
As Evaluated
As Submitted 1,356,580.68 569,445.19 66,372.65 1,992,398.52 398,479.70 286,905.39 2,677,783.61
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted #REF! 4,336.71 m2 591,986.41 625,002.52 62,500.25 1,279,489.18 20% 255,897.84 184,246.44 1,719,633.46
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted #REF! 218.61 m2 17,110.25 35,006.52 3,500.65 55,617.42 20% 11,123.48 8,008.91 74,749.81
1032(1)b Wood Painting
As Evaluated
As Submitted #REF! 112.50 m2 15,500.30 17,024.06 1,702.41 34,226.77 20% 6,845.35 4,928.65 46,000.77
1032(1)c Metal Painting
As Evaluated
As Submitted 624,596.97 677,033.09 67,703.31 1,369,333.37 273,866.67 197,184.00 1,840,384.04
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted #REF! 723.31 m2 298,429.70 99,615.34 9,961.53 408,006.57 20% 81,601.31 58,752.95 548,360.83
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted #REF! 55.20 m 11,649.79 1,267.61 126.76 13,044.17 20% 2,608.83 1,878.36 17,531.36
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted #REF! 26.21 m 5,530.88 601.81 60.18 6,192.88 20% 1,238.58 891.78 8,323.24
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
As Submitted #REF! 110.40 m 35,478.14 2,148.50 214.85 37,841.49 20% 7,568.30 5,449.17 50,858.96
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted #REF! 6,440.06 kg 358,515.11 41,592.30 86,652.80 486,760.21 20% 97,352.04 70,093.47 654,205.72
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted #REF! 8,515.07 kg 479,672.50 44,383.80 74,291.14 598,347.44 20% 119,669.49 86,162.03 804,178.96
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted #REF! 110.40 m 20,981.52 2,658.34 265.83 23,905.69 20% 4,781.14 3,442.42 32,129.25
1003(11) Fascia Board
As Evaluated
As Submitted #REF! 277.47 kg 15,049.29 4,903.31 490.33 20,442.94 20% 4,088.59 2,943.78 27,475.31
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted #REF! 248.16 kg 9,870.32 4,385.34 438.53 14,694.19 20% 2,938.84 2,115.96 19,748.99
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted #REF! 528.07 kg 21,633.56 9,331.74 933.17 31,898.48 20% 6,379.70 4,593.38 42,871.56
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted #REF! 44.00 pc 7,219.52 1,515.62 1.52 8,736.66 20% 1,747.33 1,258.08 11,742.07
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted 1,264,030.33 212,403.73 173,436.65 1,649,870.72 329,974.15 237,581.38 2,217,426.25
Sub-Total C.6
As Evaluated
As Submitted 4,623,271.86 1,894,137.33 478,259.53 6,995,668.73 1,399,133.75 1,007,376.28 9,402,178.76
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted #REF! 1.00 l.s. 43,151.00 10,006.85 1,000.69 54,158.54 20% 10,831.71 7,798.83 72,789.08
1001(8) Sewer Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 29,320.77 6,790.36 679.04 36,790.16 20% 7,358.03 5,297.78 49,445.97
1002(6) Cold Water Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 172,839.11 39,956.24 3,995.62 216,790.97 20% 43,358.19 31,217.90 291,367.06
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted #REF! 1.00 l.s. 325,296.09 37,660.96 3,766.10 366,723.15 20% 73,344.63 52,808.13 492,875.91
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 71,748.04 18,033.35 1,803.33 91,584.71 20% 18,316.94 13,188.20 123,089.85
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted #REF! 26.00 units 15,774.41 5,970.64 597.06 22,342.11 20% 4,468.42 3,217.26 30,027.79
1001(6)b1 Catch basin
As Evaluated
As Submitted #REF! 1.00 lot 848,514.95 84,509.21 8,450.92 941,475.08 20% 188,295.02 135,572.41 1,265,342.51
SPL-2 Fire Protection System
As Evaluated
As Submitted 1,506,644.36 202,927.60 20,292.76 1,729,864.72 345,972.94 249,100.51 2,324,938.17
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted #REF! 1.00 l.s. 80,540.14 14,241.12 1,424.11 96,205.37 20% 19,241.07 13,853.57 129,300.01
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted #REF! 1.00 l.s. 202,341.55 17,124.36 1,712.44 221,178.35 20% 44,235.67 31,849.68 297,263.70
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted #REF! 1.00 l.s. 244,155.30 6,861.84 686.18 251,703.32 20% 50,340.66 36,245.28 338,289.26
1102(21) Panel Board
As Evaluated
As Submitted #REF! 1.00 l.s. 101,458.00 8,863.21 886.32 111,207.53 20% 22,241.51 16,013.88 149,462.92
1003(1) Lighting Fixtures
STANDARD TWO-STOREY (10 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
1003(1) Lighting Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 24,090.00 4,007.68 400.77 28,498.45 20% 5,699.69 4,103.78 38,301.92
1208(1) Fire Alarm System
As Evaluated
As Submitted 652,584.99 51,098.21 5,109.82 708,793.020 141,758.600 102,066.190 952,617.810
TOTAL OF PART E
As Evaluated
As Submitted 10,688,776.91 3,181,448.45 1,113,604.62 14,983,829.990 2,996,766.010 2,157,671.480 20,138,267.480
TOTAL OF PART III
As Evaluated
As Submitted 10,816,171.39 3,189,375.97 1,377,741.87 15,383,289.240 3,029,225.880 2,209,501.770 20,622,016.890
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 0.98% 130,000.00
Part II Other General Requirements 1.66% 218,951.28
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 2.19% 289,618.72
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 33.44% 4,423,246.32
PART C FINISHING WORKS 44.93% 5,943,512.95
PART D PLUMBING/SANITARY WORKS 12.17% 1,609,931.08
PART E ELECTRICAL WORKS 4.63% 612,125.66
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted 0.79 5.00 mo - - 130,000.00 130,000.00 8% 10,400.00 16,848.00 157,248.00
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 130,000.00 130,000.00 10,400.00 16,848.00 157,248.00
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted 0.02 1.00 ea 3,182.34 918.56 91.86 4,192.76 20% 838.55 603.76 5,635.07
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted 0.38 1.00 l.s. 112,329.46 5,840.80 - 118,170.26 8% 9,453.62 15,314.87 142,938.75
II.7 Occupational Safety and Health
As Evaluated
As Submitted 0.97 1.00 l.s. - - 96,588.26 96,588.26 8% 7,727.06 12,517.84 116,833.16
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 115,511.80 6,759.36 96,680.12 218,951.28 18,019.23 28,436.47 265,406.98
TOTAL OF PART II
As Evaluated
(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted 0.48 313.84 m3 - 4,223.82 69,106.27 73,330.08 20% 14,666.02 10,559.53 98,555.63
803(1)a Structure Excavation
As Evaluated
As Submitted 0.26 185.75 m3 - 5,081.13 24,010.02 29,091.15 20% 5,818.23 4,189.13 39,098.51
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted 0.98 240.28 m3 87,290.72 6,572.78 31,058.56 124,922.06 20% 24,984.41 17,988.78 167,895.25
804(1)b Embankment from Borrow
As Evaluated
As Submitted 0.64 66.06 m3 42,590.27 14,817.81 4,867.36 62,275.43 20% 12,455.09 8,967.66 83,698.18
804(4) Gravel Fill
As Evaluated
As Submitted 129,880.99 30,695.54 129,042.20 289,618.72 57,923.75 41,705.10 389,247.57
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted 11.20 286.11 m3 939,871.35 44,916.19 61,638.25 1,046,425.79 20% 209,285.16 150,685.31 1,406,396.26
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted 8.98 51,041.57 kg 1,885,022.60 393,259.77 152,257.24 2,430,539.61 20% 486,107.92 349,997.70 3,266,645.23
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted 3.09 1,873.07 m2 366,510.97 405,952.04 173,817.90 946,280.92 20% 189,256.18 136,264.45 1,271,801.55
903(2) Forms and Falseworks
As Evaluated
As Submitted 3,191,404.93 844,128.01 387,713.39 4,423,246.32 884,649.26 636,947.46 5,944,843.04
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted 0.29 219.68 L 70,297.60 11,631.24 1,163.12 83,091.97 20% 16,618.39 11,965.24 111,675.60
1000(1) Soil Poisoning
As Evaluated
As Submitted 70,297.60 11,631.24 1,163.12 83,091.97 16,618.39 11,965.24 111,675.60
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted Err:509 250.52 m2 87,662.01 27,193.05 13,984.52 128,839.58 20% 25,767.92 18,552.90 173,160.40
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 4.60 716.18 m2 418,215.26 93,506.53 48,087.43 559,809.22 20% 111,961.84 80,612.53 752,383.59
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 505,877.27 120,699.58 62,071.95 688,648.80 137,729.76 99,165.43 925,543.99
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted 1.63 1.00 l.s. 249,683.14 52,817.20 5,281.72 307,782.06 20% 61,556.41 44,320.62 413,659.09
1010(4) Wooden Doors
As Evaluated
As Submitted 0.32 49.10 m 2
32,872.45 41,760.46 4,176.05 78,808.96 20% 15,761.79 11,348.49 105,919.24
1009(1)a Jalousie Window
As Evaluated
As Submitted Err:509 97.92 m 2
181,905.15 124,924.16 65,668.42 372,497.73 20% 74,499.55 53,639.67 500,636.95
1005 (1) Steel Casement Window
As Evaluated
As Submitted 0.25 43.52 m 2
37,622.41 6,246.21 3,283.42 47,152.04 20% 9,430.41 6,789.89 63,372.34
1005 (5) Window Grills
As Evaluated
As Submitted 0.24 35.00 set 52,500.00 - - 52,500.00 20% 10,500.00 7,560.00 70,560.00
1004(2)a Locksets
As Evaluated
As Submitted Err:509 140.00 pc 9,277.80 - - 9,277.80 20% 1,855.56 1,336.00 12,469.36
1004(2)g Hinges
As Evaluated
As Submitted 0.17 1.00 l.s. 24,800.00 6,545.60 654.56 32,000.16 20% 6,400.03 4,608.02 43,008.21
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 588,660.95 232,293.63 79,064.16 900,018.75 180,003.75 129,602.69 1,209,625.19
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted Err:509 839.37 m2 160,087.71 48,271.53 4,827.15 213,186.40 20% 42,637.28 30,698.84 286,522.52
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted 1.97 3,294.60 m 2
268,723.70 218,003.10 21,800.31 508,527.12 20% 101,705.42 73,227.90 683,460.44
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted 0.99 66.00 m 19,940.06 3,016.80 3,515.82 26,472.68 20% 5,294.54 3,812.07 35,579.29
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar As Submitted Err:509 111.20 m 188,176.20 5,082.84 5,923.62 199,182.66 20% 39,836.53 28,682.30 267,701.49
1053(3)a2
stiffener As Evaluated
As Submitted 2.43 470.83 m2 292,682.05 108,298.48 10,829.85 411,810.38 20% 82,362.08 59,300.70 553,473.16
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted Err:509 605.38 m2 85,812.62 31,130.25 3,113.03 120,055.89 20% 24,011.18 17,288.05 161,355.12
1038(1) Reflective Insulation
As Evaluated
As Submitted 0.64 115.51 m2 109,975.18 63,190.67 6,319.07 179,484.91 20% 35,896.98 25,845.83 241,227.72
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted 0.23 50.68 m 2
53,656.17 19,408.10 1,940.81 75,005.08 20% 15,001.02 10,800.73 100,806.83
1018(2) Unglazed Tiles
As Evaluated
As Submitted 1,179,053.69 496,401.77 58,269.65 1,733,725.12 346,745.03 249,656.42 2,330,126.57
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted 4.74 3,729.66 m2 509,120.52 537,515.05 53,751.50 1,100,387.07 20% 220,077.41 158,455.74 1,478,920.22
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted 0.25 189.83 m2 14,857.68 30,397.91 3,039.79 48,295.38 20% 9,659.08 6,954.54 64,909.00
1032(1)b Wood Painting
As Evaluated
As Submitted 0.19 99.91 m2 13,765.65 15,118.88 1,511.89 30,396.42 20% 6,079.28 4,377.08 40,852.78
1032(1)c Metal Painting
As Evaluated
As Submitted 537,743.85 583,031.84 58,303.18 1,179,078.87 235,815.77 169,787.36 1,584,682.00
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted 1.81 605.38 m2 249,772.68 83,373.71 8,337.37 341,483.76 20% 68,296.75 49,173.66 458,954.17
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted 0.08 46.20 m 9,750.37 1,060.94 106.09 10,917.40 20% 2,183.48 1,572.11 14,672.99
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted 0.05 26.21 m 5,530.88 601.81 60.18 6,192.88 20% 1,238.58 891.78 8,323.24
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted Err:509 92.40 m 29,693.66 1,798.20 179.82 31,671.68 20% 6,334.34 4,560.72 42,566.74
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted 4.13 5,176.53 kg 288,174.99 33,431.96 69,651.65 391,258.60 20% 78,251.72 56,341.24 525,851.56
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted 7.28 7,001.60 kg 394,415.43 36,495.02 61,086.62 491,997.06 20% 98,399.41 70,847.58 661,244.05
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted 0.08 92.40 m 17,560.62 2,224.92 222.49 20,008.03 20% 4,001.61 2,881.16 26,890.80
1003(11) Fascia Board
As Evaluated
As Submitted 0.53 277.47 kg 15,049.29 4,903.31 490.33 20,442.94 20% 4,088.59 2,943.78 27,475.31
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted 0.07 202.67 kg 8,061.00 3,581.47 358.15 12,000.61 20% 2,400.12 1,728.09 16,128.82
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted 0.15 427.58 kg 17,516.76 7,555.94 755.59 25,828.30 20% 5,165.66 3,719.28 34,713.24
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted 0.04 36.00 pc 5,906.88 1,240.06 1.24 7,148.18 20% 1,429.64 1,029.34 9,607.16
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted 1,041,432.57 176,267.32 141,249.54 1,358,949.44 271,789.90 195,688.74 1,826,428.08
Sub-Total C.6
As Evaluated
As Submitted 3,923,065.93 1,620,325.38 400,121.61 5,943,512.95 1,188,702.60 855,865.88 7,988,081.43
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted 0.61 1.00 l.s. 39,506.00 9,149.12 914.91 49,570.03 20% 9,914.01 7,138.08 66,622.12
1001(8) Sewer Line Works
As Evaluated
As Submitted 0.29 1.00 l.s. 25,799.54 6,004.11 600.41 32,404.06 20% 6,480.81 4,666.18 43,551.05
1002(6) Cold Water Line Works
As Evaluated
As Submitted Err:509 1.00 l.s. 147,422.78 34,062.99 3,406.30 184,892.07 20% 36,978.41 26,624.46 248,494.94
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted 1.05 1.00 l.s. 323,532.09 37,488.73 3,748.87 364,769.69 20% 72,953.94 52,526.84 490,250.47
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted 0.86 1.00 l.s. 65,879.25 16,383.24 1,638.32 83,900.81 20% 16,780.16 12,081.72 112,762.69
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted Err:509 20.00 units 12,134.16 4,592.80 459.28 17,186.24 20% 3,437.25 2,474.82 23,098.31
1001(6)b1 Catch basin
As Evaluated
As Submitted Err:509 1.00 lot 792,545.75 76,965.85 7,696.58 877,208.18 20% 175,441.64 126,317.98 1,178,967.80
SPL-2 Fire Protection System
As Evaluated
As Submitted 1,406,819.57 184,646.83 18,464.68 1,609,931.08 321,986.22 231,830.08 2,163,747.38
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted 0.39 1.00 l.s. 73,453.64 12,805.44 1,280.54 87,539.62 20% 17,507.92 12,605.70 117,653.24
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted 1.37 1.00 l.s. 141,968.40 12,919.40 1,291.94 156,179.74 20% 31,235.95 22,489.88 209,905.57
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted 0.44 1.00 l.s. 244,155.30 4,288.65 428.87 248,872.82 20% 49,774.56 35,837.69 334,485.07
1102(21) Panel Board
As Evaluated
As Submitted 0.44 1.00 l.s. 82,858.00 7,433.66 743.37 91,035.03 20% 18,207.01 13,109.04 122,351.08
1003(1) Lighting Fixtures
As Evaluated
As Submitted Err:509 1.00 l.s. 24,090.00 4,007.68 400.77 28,498.45 20% 5,699.69 4,103.78 38,301.92
1208(1) Fire Alarm System
As Evaluated
As Submitted 566,525.34 41,454.83 4,145.48 612,125.660 122,425.130 88,146.090 822,696.880
TOTAL OF PART E
As Evaluated
As Submitted 9,217,696.75 2,721,250.58 939,487.36 12,878,434.730 2,575,686.960 1,854,494.610 17,308,616.300
TOTAL OF PART III
As Evaluated
As Submitted 9,333,208.55 2,728,009.94 1,166,167.47 13,227,386.010 2,604,106.190 1,899,779.080 17,731,271.280
GRAND TOTAL
STANDARD TWO-STOREY (8 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 1.34% 121,333.33
Part II Other General Requirements 1.83% 165,697.10
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 2.26% 205,356.87
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 34.42% 3,120,847.89
PART C FINISHING WORKS 47.32% 4,290,596.84
PART D PLUMBING/SANITARY WORKS 10.15% 920,631.76
PART E ELECTRICAL WORKS 2.68% 242,990.66
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted #REF! 4.67 mo - - 121,333.33 121,333.33 8% 9,706.67 15,724.80 146,764.80
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 121,333.33 121,333.33 9,706.67 15,724.80 146,764.80
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted #REF! 1.00 ea 3,182.34 918.56 91.86 4,192.76 20% 838.55 603.76 5,635.07
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted #REF! 1.00 l.s. 89,810.36 5,840.80 - 95,651.16 8% 7,652.09 12,396.39 115,699.64
II.7 Occupational Safety and Health
As Evaluated
As Submitted #REF! 1.00 l.s. - - 65,853.18 65,853.18 8% 5,268.25 8,534.57 79,656.00
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 92,992.70 6,759.36 65,945.04 165,697.10 13,758.89 21,534.72 200,990.71
TOTAL OF PART II
As Evaluated
(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted #REF! 244.62 m3 - 3,292.22 53,864.31 57,156.53 20% 11,431.31 8,230.54 76,818.38
803(1)a Structure Excavation
As Evaluated
As Submitted #REF! 139.08 m3 - 3,804.49 17,977.46 21,781.95 20% 4,356.39 3,136.60 29,274.94
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted #REF! 159.64 m3 57,995.22 4,366.90 20,635.04 82,997.16 20% 16,599.43 11,951.59 111,548.18
804(1)b Embankment from Borrow
As Evaluated
As Submitted #REF! 46.06 m3 29,695.85 10,331.64 3,393.74 43,421.23 20% 8,684.25 6,252.66 58,358.14
804(4) Gravel Fill
As Evaluated
As Submitted 87,691.07 21,795.25 95,870.55 205,356.87 41,071.38 29,571.39 275,999.64
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted #REF! 201.23 m3 661,040.55 31,590.95 43,352.08 735,983.58 20% 147,196.72 105,981.64 989,161.94
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted #REF! 36,154.58 kg 1,335,229.31 278,560.04 107,849.28 1,721,638.63 20% 344,327.73 247,915.96 2,313,882.32
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted #REF! 1,312.79 m2 256,878.78 284,522.09 121,824.81 663,225.68 20% 132,645.14 95,504.50 891,375.32
903(2) Forms and Falseworks
As Evaluated
As Submitted 2,253,148.65 594,673.07 273,026.17 3,120,847.89 624,169.59 449,402.10 4,194,419.58
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted #REF! 159.89 L 51,164.80 8,465.58 846.56 60,476.94 20% 12,095.39 8,708.68 81,281.01
1000(1) Soil Poisoning
As Evaluated
As Submitted 51,164.80 8,465.58 846.56 60,476.94 12,095.39 8,708.68 81,281.01
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted #REF! 147.30 m2 51,543.25 15,988.89 8,222.57 75,754.71 20% 15,150.94 10,908.68 101,814.33
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted #REF! 522.79 m2 305,284.64 68,256.97 35,102.39 408,644.01 20% 81,728.80 58,844.74 549,217.55
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 356,827.89 84,245.86 43,324.96 484,398.72 96,879.74 69,753.42 651,031.88
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted #REF! 1.00 l.s. 180,165.84 34,446.00 3,444.60 218,056.44 20% 43,611.29 31,400.13 293,067.86
1010(4) Wooden Dooor
As Evaluated
As Submitted #REF! 34.93 m2 23,385.64 29,708.61 2,970.86 56,065.11 20% 11,213.02 8,073.38 75,351.51
1009(1)a Jalousie Window
As Evaluated
As Submitted #REF! 73.44 m2 136,428.86 93,693.12 49,251.31 279,373.30 20% 55,874.66 40,229.76 375,477.72
1005 (1) Steel Casement Window
As Evaluated
As Submitted #REF! 32.64 m2 28,216.81 4,684.66 2,462.57 35,364.03 20% 7,072.81 5,092.42 47,529.26
1005(5) Window Grill
As Evaluated
As Submitted #REF! 24.00 set 36,000.00 - - 36,000.00 20% 7,200.00 5,184.00 48,384.00
1004(2)a Locksets
As Evaluated
As Submitted #REF! 96.00 pc 6,361.92 - - 6,361.92 20% 1,272.38 916.12 8,550.42
1004(2)g Hinges
As Evaluated
As Submitted #REF! 1.00 l.s. 18,600.00 4,909.20 490.92 24,000.12 20% 4,800.02 3,456.02 32,256.16
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 429,159.07 167,441.59 58,620.26 655,220.92 131,044.18 94,351.83 880,616.93
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted #REF! 584.99 m2 111,571.43 33,642.33 3,364.23 148,577.99 20% 29,715.60 21,395.23 199,688.82
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted #REF! 2,313.83 m2 188,727.30 153,105.73 15,310.57 357,143.60 20% 71,428.72 51,428.68 480,001.00
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted #REF! 33.00 m 9,970.03 1,508.40 1,757.91 13,236.34 20% 2,647.27 1,906.03 17,789.64
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
As Submitted #REF! 92.12 m 155,888.41 4,210.72 4,907.23 165,006.35 20% 33,001.27 23,760.91 221,768.53
1053(3)a2 50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar stiffener
As Evaluated
As Submitted #REF! 332.94 m2 206,965.49 76,581.56 7,658.16 291,205.20 20% 58,241.04 41,933.55 391,379.79
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted #REF! 434.28 m 2
61,559.19 22,331.83 2,233.18 86,124.21 20% 17,224.84 12,401.89 115,750.94
1038(1) Reflective Insulation
As Evaluated
As Submitted #REF! 71.55 m 2
68,123.94 39,143.35 3,914.34 111,181.63 20% 22,236.33 16,010.16 149,428.12
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted #REF! 20.05 m 2
21,227.43 7,678.22 767.82 29,673.48 20% 5,934.70 4,272.98 39,881.16
1018(2) Unglazed Tiles
As Evaluated
As Submitted 824,033.23 338,202.14 39,913.44 1,202,148.80 240,429.77 173,109.43 1,615,688.00
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted #REF! 2,553.91 m2 348,623.73 368,067.08 36,806.71 753,497.52 20% 150,699.50 108,503.64 1,012,700.66
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted #REF! 133.27 m 2
10,430.83 21,340.83 2,134.08 33,905.74 20% 6,781.15 4,882.43 45,569.32
1032(1)b Wood Painting
As Evaluated
As Submitted #REF! 62.73 m 2
8,642.97 9,492.62 949.26 19,084.85 20% 3,816.97 2,748.22 25,650.04
1032(1)c Metal Painting
As Evaluated
As Submitted 367,697.53 398,900.52 39,890.05 806,488.11 161,297.62 116,134.29 1,083,920.02
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted #REF! 434.28 m2 179,179.22 59,809.73 5,980.97 244,969.92 20% 48,993.98 35,275.67 329,239.57
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted #REF! 32.90 m 6,943.45 755.52 75.55 7,774.51 20% 1,554.90 1,119.53 10,448.94
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted #REF! 26.21 m 5,531.54 601.89 60.19 6,193.62 20% 1,238.72 891.88 8,324.22
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted #REF! 65.80 m 21,145.49 1,280.53 128.05 22,554.08 20% 4,510.82 3,247.79 30,312.69
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted #REF! 3,535.91 kg 196,842.45 22,836.22 47,576.65 267,255.32 20% 53,451.06 38,484.77 359,191.15
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted #REF! 5,170.61 kg 291,271.76 26,951.20 45,111.84 363,334.80 20% 72,666.96 52,320.21 488,321.97
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted #REF! 65.80 m 12,505.29 1,584.41 158.44 14,248.14 20% 2,849.63 2,051.73 19,149.50
1003(11) Fascia Board
As Evaluated
As Submitted #REF! 277.47 kg 15,049.20 4,903.29 490.33 20,442.82 20% 4,088.56 2,943.77 27,475.15
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted #REF! 146.82 kg 5,839.62 2,594.52 259.45 8,693.59 20% 1,738.72 1,251.88 11,684.19
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted #REF! 314.91 kg 12,900.99 5,564.90 556.49 19,022.38 20% 3,804.48 2,739.22 25,566.08
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted #REF! 26.00 pc 4,266.08 895.60 0.90 5,162.57 20% 1,032.51 743.41 6,938.49
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted #REF! 1.00 l.s. 58,008.08 16,893.68 27,309.85 102,211.60 20% 20,442.32 14,718.47 137,372.39
1047(6)-1 Metal Structure Accessories, Fire Escape
As Evaluated
As Submitted 809,483.16 144,671.47 127,708.72 1,081,863.35 216,372.66 155,788.33 1,454,024.34
Sub-Total C.6
As Evaluated
As Submitted 2,838,365.67 1,141,927.17 310,303.99 4,290,596.84 858,119.36 617,845.98 5,766,562.18
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted #REF! 1.00 l.s. 18,531.75 4,288.65 428.87 23,249.27 20% 4,649.85 3,347.89 31,247.01
1001(8) Sewer Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 5,799.74 1,358.07 135.81 7,293.62 20% 1,458.72 1,050.28 9,802.62
1002(6) Cold Water Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 70,144.32 16,265.37 1,626.54 88,036.22 20% 17,607.24 12,677.22 118,320.68
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted #REF! 1.00 l.s. 162,352.47 18,830.48 1,883.05 183,066.00 20% 36,613.20 26,361.50 246,040.70
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 56,067.25 14,143.80 1,414.38 71,625.43 20% 14,325.09 10,314.06 96,264.58
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted #REF! 16.00 units 9,707.33 3,674.24 367.42 13,748.99 20% 2,749.80 1,979.85 18,478.64
1001(6)b1 Catch basin
As Evaluated
As Submitted #REF! 1.00 lot 479,028.95 49,621.17 4,962.12 533,612.23 20% 106,722.45 76,840.16 717,174.84
SPL-2 Fire Protection System
As Evaluated
As Submitted 801,631.80 108,181.78 10,818.18 920,631.76 184,126.35 132,570.96 1,237,329.07
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted #REF! 1.00 l.s. 30,928.20 9,663.64 966.36 41,558.20 20% 8,311.64 5,984.38 55,854.22
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted #REF! 1.00 l.s. 63,995.82 7,780.56 778.06 72,554.44 20% 14,510.89 10,447.84 97,513.17
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted #REF! 1.00 l.s. 36,455.00 3,145.01 314.50 39,914.51 20% 7,982.90 5,747.69 53,645.10
1102(21) Panel Board
As Evaluated
As Submitted #REF! 1.00 l.s. 60,585.00 5,432.29 543.23 66,560.52 20% 13,312.10 9,584.71 89,457.33
1003(1) Lighting Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 18,990.00 3,102.72 310.27 22,402.99 20% 4,480.60 3,226.03 30,109.62
1208(1) Fire Alarm System
As Evaluated
As Submitted 210,954.02 29,124.22 2,912.42 242,990.660 48,598.130 34,990.650 326,579.440
TOTAL OF PART E
As Evaluated
As Submitted 6,191,791.20 1,895,701.49 692,931.31 8,780,424.020 1,756,084.810 1,264,381.080 11,800,889.910
TOTAL OF PART III
As Evaluated
STANDARD TWO-STOREY (6 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 6,284,783.90 1,902,460.85 880,209.68 9,067,454.450 1,779,550.370 1,301,640.600 12,148,645.420
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 1.50% 104,000.00
Part II Other General Requirements 1.96% 135,880.93
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 2.20% 152,645.07
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 33.68% 2,338,468.06
PART C FINISHING WORKS 46.56% 3,232,938.03
PART D PLUMBING/SANITARY WORKS 11.38% 790,140.37
PART E ELECTRICAL WORKS 2.74% 189,943.30
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted #REF! 4.00 mo - - 104,000.00 104,000.00 8% 8,320.00 13,478.40 125,798.40
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 104,000.00 104,000.00 8,320.00 13,478.40 125,798.40
TOTAL OF PART I
As Evaluated
PART II OTHER GENERAL REQUIREMENTS
As Submitted #REF! 1.00 ea 3,182.34 918.56 91.86 4,192.76 20% 838.55 603.76 5,635.07
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted #REF! 1.00 l.s. 76,734.52 4,672.64 - 81,407.16 8% 6,512.57 10,550.37 98,470.10
II.7 Occupational Safety and Health
As Evaluated
As Submitted #REF! 1.00 l.s. - - 50,281.01 50,281.01 8% 4,022.48 6,516.42 60,819.91
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 79,916.86 5,591.20 50,372.87 135,880.93 11,373.60 17,670.55 164,925.08
TOTAL OF PART II
As Evaluated
(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted #REF! 196.98 m3 - 2,651.06 43,374.18 46,025.23 20% 9,205.05 6,627.63 61,857.91
803(1)a Structure Excavation
As Evaluated
As Submitted #REF! 105.37 m3 - 2,882.36 13,620.11 16,502.47 20% 3,300.49 2,376.36 22,179.32
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted #REF! 111.83 m3 40,626.44 3,059.07 14,455.13 58,140.64 20% 11,628.13 8,372.25 78,141.02
804(1)b Embankment from Borrow
As Evaluated
As Submitted #REF! 33.92 m3 21,868.94 7,608.54 2,499.25 31,976.73 20% 6,395.35 4,604.65 42,976.73
804(4) Gravel Fill
As Evaluated
As Submitted 62,495.38 16,201.03 73,948.67 152,645.07 30,529.02 21,980.89 205,154.98
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted #REF! 151.93 m3 499,090.05 23,851.38 32,731.11 555,672.54 20% 111,134.51 80,016.85 746,823.90
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted #REF! 27,248.42 kg 1,006,314.81 209,940.79 81,282.16 1,297,537.76 20% 259,507.55 186,845.44 1,743,890.75
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted #REF! 960.52 m2 187,948.73 208,174.31 89,134.72 485,257.76 20% 97,051.55 69,877.12 652,186.43
903(2) Forms and Falseworks
As Evaluated
As Submitted 1,693,353.58 441,966.47 203,148.00 2,338,468.06 467,693.61 336,739.41 3,142,901.08
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted #REF! 115.60 L 36,992.00 6,120.59 612.06 43,724.65 20% 8,744.93 6,296.35 58,765.93
1000(1) Soil Poisoning
As Evaluated
As Submitted 36,992.00 6,120.59 612.06 43,724.65 8,744.93 6,296.35 58,765.93
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted #REF! 129.91 m2 45,458.14 14,101.26 7,251.83 66,811.23 20% 13,362.25 9,620.82 89,794.30
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted #REF! 399.98 m2 233,569.41 52,222.55 26,856.39 312,648.35 20% 62,529.67 45,021.36 420,199.38
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 279,027.54 66,323.81 34,108.22 379,459.58 75,891.92 54,642.18 509,993.68
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted #REF! 1.00 l.s. 133,071.00 26,408.60 2,640.86 162,120.46 20% 32,424.09 23,345.35 217,889.90
1010(4) Wooden Doors
As Evaluated
As Submitted #REF! 24.05 m2 16,101.48 20,454.97 2,045.50 38,601.94 20% 7,720.39 5,558.68 51,881.01
1009(1)a Jalousie Window
As Evaluated
As Submitted #REF! 48.96 m2 90,952.58 62,462.08 32,834.21 186,248.86 20% 37,249.77 26,819.84 250,318.47
1005 (1) Steel Casement Window
As Evaluated
As Submitted #REF! 21.76 m2 18,811.20 3,123.10 1,641.71 23,576.02 20% 4,715.20 3,394.95 31,686.17
1005(5) Window Grill
As Evaluated
As Submitted #REF! 20.00 set 30,000.00 - - 30,000.00 20% 6,000.00 4,320.00 40,320.00
1004(2)a Locksets
As Evaluated
As Submitted #REF! 80.00 pc 5,301.60 - - 5,301.60 20% 1,060.32 763.43 7,125.35
1004(2)g Hinges
As Evaluated
As Submitted #REF! 1.00 l.s. 12,400.00 3,272.80 327.28 16,000.08 20% 3,200.02 2,304.01 21,504.11
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 306,637.85 115,721.55 39,489.56 461,848.96 92,369.79 66,506.26 620,725.01
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted #REF! 424.17 m2 80,899.25 24,393.70 2,439.37 107,732.32 20% 21,546.46 15,513.45 144,792.23
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted #REF! 1,783.22 m2 145,448.15 117,995.35 11,799.54 275,243.04 20% 55,048.61 39,635.00 369,926.65
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted #REF! 33.00 m 9,970.03 1,508.40 1,757.91 13,236.34 20% 2,647.27 1,906.03 17,789.64
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar As Submitted #REF! 73.42 m 124,243.67 3,355.96 3,911.08 131,510.71 20% 26,302.14 18,937.54 176,750.39
1053(3)a2
stiffener As Evaluated
As Submitted #REF! 237.86 m2 147,860.91 54,711.63 5,471.16 208,043.70 20% 41,608.74 29,958.29 279,610.73
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted #REF! 315.48 m 2
44,719.29 16,222.82 1,622.28 62,564.39 20% 12,512.88 9,009.27 84,086.54
1038(1) Reflective Insulation
As Evaluated
As Submitted #REF! 71.55 m 2
68,123.94 39,143.35 3,914.34 111,181.63 20% 22,236.33 16,010.16 149,428.12
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted #REF! 20.05 m 2
21,227.43 7,678.22 767.82 29,673.48 20% 5,934.70 4,272.98 39,881.16
1018(2) Unglazed Tiles
As Evaluated
As Submitted 642,492.68 265,009.43 31,683.50 939,185.61 187,837.13 135,242.72 1,262,265.46
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted #REF! 1,946.86 m2 265,757.84 280,579.61 28,057.96 574,395.41 20% 114,879.08 82,712.94 771,987.43
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted #REF! 104.49 m 2
8,178.26 16,732.22 1,673.22 26,583.71 20% 5,316.74 3,828.05 35,728.50
1032(1)b Wood Painting
As Evaluated
As Submitted #REF! 50.14 m 2
6,908.31 7,587.44 758.74 15,254.49 20% 3,050.90 2,196.65 20,502.04
1032(1)c Metal Painting
As Evaluated
As Submitted 280,844.41 304,899.27 30,489.93 616,233.61 123,246.72 88,737.64 828,217.97
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted #REF! 315.48 m2 130,163.63 43,448.40 4,344.84 177,956.87 20% 35,591.37 25,625.79 239,174.03
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted #REF! 23.90 m 5,044.02 548.84 54.88 5,647.75 20% 1,129.55 813.28 7,590.58
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted #REF! 26.21 m 5,531.54 601.89 60.19 6,193.62 20% 1,238.72 891.88 8,324.22
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted #REF! 47.80 m 15,361.01 930.24 93.02 16,384.27 20% 3,276.85 2,359.33 22,020.45
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted #REF! 2,271.38 kg 126,446.66 14,669.42 30,562.05 171,678.12 20% 34,335.62 24,721.65 230,735.39
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted #REF! 3,687.15 kg 207,705.22 19,218.84 32,169.15 259,093.20 20% 51,818.64 37,309.42 348,221.26
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted #REF! 47.80 m 9,084.39 1,150.98 115.10 10,350.47 20% 2,070.09 1,490.47 13,911.03
1003(11) Fascia Board
As Evaluated
As Submitted #REF! 277.47 kg 15,049.20 4,903.29 490.33 20,442.82 20% 4,088.56 2,943.77 27,475.15
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted #REF! 101.34 kg 4,030.70 1,790.82 179.08 6,000.60 20% 1,200.12 864.09 8,064.81
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted #REF! 214.42 kg 8,784.19 3,789.10 378.91 12,952.21 20% 2,590.44 1,865.12 17,407.77
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted #REF! 18.00 pc 2,953.44 620.03 0.62 3,574.09 20% 714.82 514.67 4,803.58
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted #REF! 1.00 l.s. 58,008.08 16,893.68 27,309.85 102,211.60 20% 20,442.32 14,718.47 137,372.39
1047(6)-1 Metal Structure Accessories, Fire Escape
As Evaluated
As Submitted 588,162.07 108,565.52 95,758.02 792,485.62 158,497.10 114,117.94 1,065,100.66
Sub-Total C.6
As Evaluated s
As Submitted 2,134,156.56 866,640.17 232,141.28 3,232,938.03 646,587.59 465,543.09 4,345,068.71
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted #REF! 1.00 l.s. 18,103.75 4,217.17 421.72 22,742.64 20% 4,548.53 3,274.94 30,566.11
1001(8) Sewer Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 5,799.74 1,358.07 135.81 7,293.62 20% 1,458.72 1,050.28 9,802.62
1002(6) Cold Water Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 62,014.42 14,379.53 1,437.95 77,831.90 20% 15,566.38 11,207.79 104,606.07
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted #REF! 1.00 l.s. 161,176.47 18,715.66 1,871.57 181,763.70 20% 36,352.74 26,173.97 244,290.41
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 46,716.75 12,022.23 1,202.22 59,941.20 20% 11,988.24 8,631.53 80,560.97
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted #REF! 12.00 units 7,280.50 2,755.68 275.57 10,311.74 20% 2,062.35 1,484.89 13,858.98
1001(6)b1 Catch basin
As Evaluated
As Submitted #REF! 1.00 lot 385,396.15 40,781.29 4,078.13 430,255.57 20% 86,051.11 61,956.80 578,263.48
SPL-2 Fire Protection System
As Evaluated
As Submitted 686,487.77 94,229.64 9,422.96 790,140.37 158,028.07 113,780.20 1,061,948.64
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted #REF! 1.00 l.s. 25,137.80 8,457.60 845.76 34,441.16 20% 6,888.23 4,959.53 46,288.92
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted #REF! 1.00 l.s. 52,894.17 6,115.24 611.52 59,620.93 20% 11,924.19 8,585.41 80,130.53
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted #REF! 1.00 l.s. 24,259.70 2,573.19 257.32 27,090.21 20% 5,418.04 3,900.99 36,409.24
1102(21) Panel Board
As Evaluated
As Submitted #REF! 1.00 l.s. 41,985.00 4,002.74 400.27 46,388.01 20% 9,277.60 6,679.87 62,345.48
1003(1) Lighting Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 18,990.00 3,102.72 310.27 22,402.99 20% 4,480.60 3,226.03 30,109.62
1208(1) Fire Alarm System
As Evaluated
As Submitted 163,266.67 24,251.49 2,425.15 189,943.300 37,988.660 27,351.830 255,283.790
TOTAL OF PART E
As Evaluated
As Submitted 4,739,759.96 1,443,288.80 521,086.07 6,704,134.830 1,340,826.950 965,395.420 9,010,357.200
TOTAL OF PART III
As Evaluated
STANDARD TWO-STOREY (4 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 4,819,676.82 1,448,880.00 675,458.93 6,944,015.760 1,360,520.550 996,544.370 9,301,080.680
GRAND TOTAL
As Evaluated
ANNEX A
BUREAU OF CONSTRUCTION
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 2.05% 99,666.67
Part II Other General Requirements 2.20% 107,225.89
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 2.01% 97,854.73
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 31.95% 1,556,092.30
PART C FINISHING WORKS 43.89% 2,137,714.37
PART D PLUMBING/SANITARY WORKS 15.19% 739,573.28
PART E ELECTRICAL WORKS 2.71% 132,171.50
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted #REF! 3.83 mo - - 99,666.67 99,666.67 8% 7,973.33 12,916.80 120,556.80
I.1.1 (1) Provision of field Office for the Engineer (Rental Basis)
As Evaluated
As Submitted - - 99,666.67 99,666.67 7,973.33 12,916.80 120,556.80
TOTAL OF PART I
As Evalauted
PART II OTHER GENERAL REQUIREMENTS
As Submitted #REF! 1.00 ea 3,182.34 918.56 91.86 4,192.76 20% 838.55 603.76 5,635.07
II.5 Project Billboard/ Sign Board
As Evaluated
As Submitted #REF! 1.00 l.s. 63,384.94 4,672.64 - 68,057.58 8% 5,444.61 8,820.26 82,322.45
II.7 Occupational Safety and Health
As Evaluated
As Submitted #REF! 1.00 l.s. - - 34,975.55 34,975.55 8% 2,798.04 4,532.83 42,306.42
II.9 Mobilization/ Demobilization
As Evaluated
As Submitted 66,567.28 5,591.20 35,067.40 107,225.89 9,081.20 13,956.85 130,263.94
TOTAL OF PART II
As Evaluated
(Project ID)
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
As Submitted #REF! 144.01 m3 - 1,938.16 31,710.40 33,648.56 20% 6,729.71 4,845.39 45,223.66
803(1)a Structure Excavation
As Evaluated
As Submitted #REF! 66.34 m3 - 1,814.71 8,575.10 10,389.81 20% 2,077.96 1,496.13 13,963.90
804(1)a Embankment from Structure Excavation
As Evaluated
As Submitted #REF! 64.02 m3 23,257.67 1,751.25 8,275.22 33,284.13 20% 6,656.83 4,792.92 44,733.88
804(1)b Embankment from Borrow
As Evaluated
As Submitted #REF! 21.78 m3 14,042.02 4,885.44 1,604.77 20,532.23 20% 4,106.45 2,956.64 27,595.32
804(4) Gravel Fill
As Evaluated
As Submitted 37,299.69 10,389.55 50,165.49 97,854.73 19,570.95 14,091.08 131,516.76
TOTAL OF PART A
As Evaluated
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted #REF! 102.63 m3 337,139.55 16,111.81 22,110.14 375,361.50 20% 75,072.30 54,052.06 504,485.86
900(1)c1 Structural Concrete (Ready Mix, Class A, 28 days)
As Evaluated
As Submitted #REF! 18,342.24 kg 677,399.56 141,321.38 54,714.99 873,435.92 20% 174,687.18 125,774.77 1,173,897.87
902(1)a1 Reinforcing Steel, Grade 40
As Evaluated
As Submitted #REF! 608.26 m2 119,020.63 131,828.70 56,445.55 307,294.88 20% 61,458.98 44,250.46 413,004.32
903(2) Forms and Falseworks
As Evaluated
As Submitted 1,133,559.73 289,261.89 133,270.69 1,556,092.30 311,218.46 224,077.29 2,091,388.05
TOTAL OF PART B
As Evaluated
PART C FINISHING
C.1 Termite Control Works
As Submitted #REF! 75.31 L 24,099.20 3,987.39 398.74 28,485.32 20% 5,697.06 4,101.89 38,284.27
1000(1) Soil Poisoning
As Evaluated
As Submitted 24,099.20 3,987.39 398.74 28,485.32 5,697.06 4,101.89 38,284.27
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted #REF! 112.48 m2 39,359.03 12,209.30 6,278.85 57,847.18 20% 11,569.44 8,329.99 77,746.61
1046(2)a1 100 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
As Submitted #REF! 227.17 m2 132,656.54 29,659.97 15,253.18 177,569.69 20% 35,513.94 25,570.04 238,653.67
1046(2)a2 150 mm CHB Non Load Bearing Wall (including Reinforcing Steel)
As Evaluated
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted 172,015.57 41,869.27 21,532.03 235,416.87 47,083.38 33,900.03 316,400.28
Sub - Total C.2
As Evaluated
C.3 Fabricated Materials
As Submitted #REF! 1.00 l.s. 85,976.15 19,519.40 1,951.94 107,447.49 20% 21,489.50 15,472.44 144,409.43
1010(4) Wooden Doors
As Evaluated
As Submitted #REF! 13.71 m2 9,178.85 11,660.61 1,166.06 22,005.51 20% 4,401.10 3,168.79 29,575.40
1009(1)a Jalousie Window
As Evaluated
As Submitted #REF! 24.48 m2 45,476.29 31,231.04 16,417.10 93,124.43 20% 18,624.89 13,409.92 125,159.24
1005 (1) Steel Casement Window
As Evaluated
As Submitted #REF! 10.88 m2 9,405.60 1,561.55 820.86 11,788.01 20% 2,357.60 1,697.47 15,843.08
1005 (5) Window Grill
As Evaluated
As Submitted #REF! 16.00 set 24,000.00 - - 24,000.00 20% 4,800.00 3,456.00 32,256.00
1004(2)a Locksets
As Evaluated
As Submitted #REF! 64.00 pc 4,241.28 - - 4,241.28 20% 848.26 610.74 5,700.28
1004(2)g Hinges
As Evaluated
As Submitted #REF! 1.00 l.s. 6,200.00 1,636.40 163.64 8,000.04 20% 1,600.01 1,152.01 10,752.06
1003(9) Carpentry and Joinery Works (Blackboard)
As Evaluated
As Submitted 184,478.17 65,609.00 20,519.60 270,606.76 54,121.36 38,967.37 363,695.49
Sub-Total C.3
As Evaluated
C.4 Finishing Works
As Submitted #REF! 263.35 m2 50,227.07 15,145.06 1,514.51 66,886.64 20% 13,377.33 9,631.68 89,895.65
1021(1)c Plain Cement Finish with floor hardener
As Evaluated
As Submitted #REF! 1,252.61 m 2
102,169.00 82,884.98 8,288.50 193,342.49 20% 38,668.50 27,841.32 259,852.31
1027(1) Plain Cement Plaster Finish
As Evaluated
As Submitted #REF! 33.00 m 9,970.03 1,508.40 1,757.91 13,236.34 20% 2,647.27 1,906.03 17,789.64
1053(3)a1 38 mm dia. G.I. Pipe Railings
As Evaluated
As Submitted #REF! 55.82 m 94,460.39 2,551.48 2,973.53 99,985.40 20% 19,997.08 14,397.90 134,380.38
1053(3)a2 50 mm Ø G.I. Pipe Handrail Fully Welded on vertical Railing on 19 mm bar stiffener
As Evaluated
As Submitted #REF! 142.77 m 2
88,750.12 32,839.40 3,283.94 124,873.45 20% 24,974.69 17,981.78 167,829.92
1003(1)a1 Fiber Cement Board Ceiling on Metal Frame
As Evaluated
As Submitted #REF! 196.68 m 2
27,879.39 10,113.81 1,011.38 39,004.58 20% 7,800.92 5,616.66 52,422.16
1038(1) Reflective Insulation
As Evaluated
As Submitted #REF! 71.55 m 2
68,123.94 39,143.35 3,914.34 111,181.63 20% 22,236.33 16,010.16 149,428.12
1018(1) Glazed Tiles and Trims
As Evaluated
As Submitted #REF! 20.05 m 2
21,227.43 7,678.22 767.82 29,673.48 20% 5,934.70 4,272.98 39,881.16
1018(2) Unglazed Tiles
As Evaluated
As Submitted 462,807.37 191,864.70 23,511.92 678,184.01 135,636.82 97,658.51 911,479.34
Sub-Total C.4
As Evaluated
C.5 Painting Works
As Submitted #REF! 1,339.81 m2 182,891.94 193,092.14 19,309.21 395,293.30 20% 79,058.66 56,922.24 531,274.20
1032(1)a Masonry/Concrete Painting
As Evaluated
As Submitted #REF! 75.71 m 2
5,925.70 12,123.61 1,212.36 19,261.67 20% 3,852.33 2,773.68 25,887.68
1032(1)b Wood Painting
As Evaluated
As Submitted #REF! 37.55 m 2
5,173.66 5,682.25 568.23 11,424.14 20% 2,284.83 1,645.08 15,354.05
1032(1)c Metal Painting
As Evaluated
As Submitted 193,991.30 210,898.01 21,089.80 425,979.11 85,195.82 61,341.00 572,515.93
Sub-Total C.5
As Evaluated
C.6 Roof Framing and Roofing Works
As Submitted #REF! 196.68 m2 81,148.04 27,087.08 2,708.71 110,943.82 20% 22,188.76 15,975.91 149,108.49
1014(1)b1 Prepainted Metal Sheets, Long Span, Corrugated, 0.5 mm thk
As Evaluated
As Submitted #REF! 14.90 m 3,144.60 342.16 34.22 3,520.98 20% 704.20 507.02 4,732.20
1013(2)a Fabricated Metal Roofing Accessory (Ridge Roll, 0.6 mm thk)
As Evaluated
As Submitted #REF! 26.21 m 5,531.54 601.89 60.19 6,193.62 20% 1,238.72 891.88 8,324.22
1013(2)b Fabricated Metal Roofing Accessory (Flashing, 0.6 mm thk)
As Evaluated
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
As Submitted #REF! 29.80 m 9,576.53 579.94 57.99 10,214.46 20% 2,042.89 1,470.88 13,728.23
1013(2)c Fabricated Metal Roofing Accessory (Gutter, 0.6 mm thk)
As Evaluated
As Submitted #REF! 1,008.85 kg 56,162.21 6,515.53 13,574.36 76,252.09 20% 15,250.42 10,980.30 102,482.81
1047(2)a Structural Steel, Trusses
As Evaluated
As Submitted #REF! 2,143.69 kg 120,758.74 11,173.73 18,702.98 150,635.45 20% 30,127.09 21,691.50 202,454.04
1047(2)b Structural Steel, Purlins
As Evaluated
As Submitted #REF! 29.80 m 5,663.49 717.56 71.76 6,452.81 20% 1,290.56 929.20 8,672.57
1003(11) Fascia Board
As Evaluated
As Submitted #REF! 277.47 kg 15,049.20 4,903.29 490.33 20,442.82 20% 4,088.56 2,943.77 27,475.15
1047(6) Metal Structure Accessories, Steel Plates
As Evaluated
As Submitted #REF! 55.85 kg 2,221.38 986.95 98.69 3,307.02 20% 661.40 476.21 4,444.63
1047(7)b Metal Structure Accessories, Sag Rods
As Evaluated
As Submitted #REF! 113.93 kg 4,667.40 2,013.30 201.33 6,882.03 20% 1,376.41 991.01 9,249.45
1047(4) Metal Structure Accessories, Cross Bracing
As Evaluated
As Submitted #REF! 10.00 pc 1,640.80 344.46 0.34 1,985.60 20% 397.12 285.93 2,668.65
1047(3)c Metal Structure Accessories, Turn Buckle
As Evaluated
As Submitted #REF! 1.00 l.s. 58,008.08 16,893.68 27,309.85 102,211.60 20% 20,442.32 14,718.47 137,372.39
1047(6)-1 Metal Structure Accessories, Fire Escape
As Evaluated
As Submitted 363,572.00 72,159.56 63,310.74 499,042.30 99,808.45 71,862.08 670,712.83
Sub-Total C.6
As Evaluated
As Submitted 1,400,963.60 586,387.94 150,362.84 2,137,714.37 427,542.89 307,830.88 2,873,088.14
TOTAL OF PART C
As Evaluated
PART D PLUMBING/SANITARY WORKS
As Submitted #REF! 1.00 l.s. 17,675.75 3,788.31 378.83 21,842.89 20% 4,368.58 3,145.38 29,356.85
1001(8) Sewer Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 5,799.74 1,358.07 135.81 7,293.62 20% 1,458.72 1,050.28 9,802.62
1002(6) Cold Water Line Works
As Evaluated
As Submitted #REF! 1.00 l.s. 53,018.02 12,257.96 1,225.80 66,501.77 20% 13,300.35 9,576.25 89,378.37
1001(9) Downspout/Storm Drain
As Evaluated
As Submitted #REF! 1.00 l.s. 160,000.47 18,543.43 1,854.34 180,398.24 20% 36,079.65 25,977.35 242,455.24
1002(5) Sanitary/Plumbing Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 32,018.30 8,368.42 836.84 41,223.55 20% 8,244.71 5,936.19 55,404.45
SPL-1 Septic Vault "Type E"
As Evaluated
As Submitted #REF! 8.00 units 4,853.66 1,837.12 183.71 6,874.50 20% 1,374.90 989.93 9,239.33
1001(6)b1 Catch basin
As Evaluated
As Submitted #REF! 1.00 lot 371,746.15 39,720.51 3,972.05 415,438.71 20% 83,087.74 59,823.17 558,349.62
SPL-2 Fire Protection System
As Evaluated
As Submitted 645,112.09 85,873.81 8,587.38 739,573.28 147,914.65 106,498.55 993,986.48
TOTAL OF PART D
As Evaluated
PART E ELECTRICAL
As Submitted #REF! 1.00 l.s. 19,023.20 2,325.32 232.53 21,581.05 20% 4,316.21 3,107.67 29,004.93
1100(19) Conduits, Boxes, and Fittings
As Evaluated
As Submitted #REF! 1.00 l.s. 37,258.20 3,747.40 374.74 41,380.34 20% 8,276.07 5,958.77 55,615.18
1101(18) Wires and Wiring Devices
As Evaluated
As Submitted #REF! 1.00 l.s. 18,390.10 2,001.37 200.14 20,591.61 20% 4,118.32 2,965.19 27,675.12
1102(21) Panel Board
As Evaluated
As Submitted #REF! 1.00 l.s. 23,385.00 2,573.19 257.32 26,215.51 20% 5,243.10 3,775.03 35,233.64
1003(1) Lighting Fixtures
As Evaluated
As Submitted #REF! 1.00 l.s. 18,990.00 3,102.72 310.27 22,402.99 20% 4,480.60 3,226.03 30,109.62
1208(1) Fire Alarm System
As Evaluated
As Submitted 117,046.50 13,750.00 1,375.00 132,171.500 26,434.300 19,032.690 177,638.490
TOTAL OF PART E
As Evaluated
As Submitted 3,333,981.62 985,663.18 343,761.39 4,663,406.180 932,681.250 671,530.490 6,267,617.920
TOTAL OF PART III
As Evaluated
As Submitted 3,333,981.62 985,663.18 343,761.39 4,663,406.180 932,681.250 671,530.490 6,267,617.920
TOTAL OF (Project ID)
STANDARD TWO-STOREY (2 CLASSROOMS) SCHOOL BUILDING
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 12% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
TOTAL OF (Project ID)
As Evaluated
As Submitted 3,400,548.90 991,254.38 478,495.46 4,870,298.740 949,735.780 698,404.140 6,518,438.660
GRAND TOTAL
As Evaluated