rev02-SEWER LINE WORKS
rev02-SEWER LINE WORKS
rev02-SEWER LINE WORKS
PACKAGE 6
Revision
Remarks Issued Date Return Date
No.
00 Issued For Review 21-APR-2010 29-APR-2010
01 Issued For Acceptance 11-MAY-2010 31-MAY-2010
02 Issued For construction 31-MAY-2010
IMPORTANT:
No part of this publication may be reproduced, stored in a retrieval system, or transmitted in any form, or by means of electronic,
mechanical, photocopying, recording, or otherwise, without the written permission of Rotary Engineering Limited.
REFINERY TANK FARM
PACKAGE 6
Revision History
TABLE OF CONTENTS
1. SCOPE………………………………………………………………………………………….4
2. REFERENCE DOCUMENTS..……………………………………………………………..4-5
3. DEFINITIONS…………………………………………………………………………………..5
4. RESPONSILITIES…………………………………………………………………………..5-6
5. METHODOLOGY…………………………………………………………………………..6-11
6. QUALITY CONTROL AND QUALITY ASSURANCE……………………………………12
8. SAFETY EQUIPMENTS……………………………………………………………………12
01
1. SCOPE
This Scope is to derive the methodology for the sewer line to be performed for the
construction of tank farms for SAUDI ARAMCO TOTAL REFINING &
PETROCHEMICAL COMPANY (SATORP) in package 6 at Al-Jubail, Kingdom of
Saudi Arabia, in order to qualify and comply with all the company standards.
01
2. REFERENCE DOCUMENTS
1.1. Approved IFC Drawings
1.2. Project Quality plan
1.3. Project ITP
1.4. Safety and Medical plan
1.5. Schedule “D” & Sec. 11-2 & 11-14 of JER Construction Safety Manual
1.6. Project Specifications & Standards
1.6.1. JERES-Q-005 Concrete foundations
1.6.2. JERES-Q-006 Asphalt concrete paving
1.6.3. JERES-Q-009 Concrete retaining walls
1.7 Company material specifications
1.7.1 JERMS-H-9016 Epoxy Coating of Steel Reinforcing Bars.
1.7.2 JERMS-M-2007 Fabrication of Structural and Miscellaneous Steel
1.7.3 JERMS-M-2008 Erection of Structural and Miscellaneous Steel
1.7.4 JERMS-Q-9016 Concrete Masonry units and Concrete Building
1.8 American Welding Society (AWS)
1.8.1 AWS D1.1 Structural Welding Code - Steel
1.8.2 AWS D1.4 Structural Welding Code – Reinforcing Steel
1.9 American society for testing and materials
3. DEFINITIONS
All the definitions mentioned in the JER Documents have priority over other
standards and any deviation of these standards shall be brought to attention of the
COMPANY. It means to the company representative for resolution.
All terms used in the development of this procedure are defined below:
COMPANY - SATORP
CONTRACTOR - Petrol Steel Company Ltd / Rotary Engineering Ltd
PSCL - Petrol Steel Company Ltd.
Shall - Indicates a mandatory requirement
Should - Indicates a recommended practice
4. RESPONSIBILITIES:
4.1 The project manager shall ensure that all operations related to sewer line
works have been risk assessed and necessary control measures have been
implemented to carry out the task in a safely manner.
4.2 Contractor shall engage their own surveyor for all the related surveying works.
Contractor shall follow IFC Drawings Coordinates and data, which will be
approved by the company. Contractor shall check and verify the BM before
execution of the works. Any changes and deviation found shall be
01
immediately notified to the company for resolution.
4.3 Contractor’s construction engineer shall review and confirm that all sewer line
works being implemented as per the activities stated in the method statement
and in compliance with the (SATORP) codes, standards and project
specifications.
4.4 Contactor’s supervisor shall supervise all sewer line activities as required by
the project drawings and specifications. He shall prepare all the necessary
permits in advance and get it approved from the company designated
representative for the execution.
4.5 Contractor’s QA/QC Engineer shall closely monitor and assure all sewer line
activities are carried out as per (SATORP) QA/QC requirements and conduct
frequent inspections and maintain all records as required by project QA/QC
Program.
4.6 HSE officer shall monitor the sewer lines works and strictly enforce safety PPE
requirements and HSE plan.
‘5. METHODOLOGY
01
5.1 SETTING OUT
All survey coordinates and datum references shall be based on the JERES –
A –100 specification.
5.3 DEWATERING
Dewatering shall not discharge into open areas without the approval of
the authorities having jurisdiction on the maintenance of the area.
The bottom of the trench shall be dry or sufficient drained so that there
is no standing water before the support and bedding layers are placed
and compacted. The bedding layer must be sufficiently drained so that
there is no standing water on the bedding layer before the pipe is
installed.
5.4 BEDDING
Ground bed shall provide uniform and adequate support and drainage
along the entire length of the piping. Base support layer of crushed
stone base materials 150mm deep is required.
The crushed stone base shall meet the requirements of class B base
materials as defined in JERES-Q-006 Table A, and shall be compacted
to at least 95% of ASTM D698.
Surveyor has to determine the center line of the sewer line for
positioning of RC pipe. Reduce and invert level shall confirm for
achieving the gradient or contour of the sewer line.
From storage yard, RC pipe shall deliver to work site using lorry crane
and unload directly into the trench and laid over to the prepared
bedding for actual positioning.
Sealed the joint gap from inside to outside with approved material and
request with SATORP representative to inspect and get approval for
partial backfilling of sewer lines.
Doc No: Title:
Page 8 of 16
SA-JER-TFAAA-PSCL-508008 Rev.02 METHOD STATEMENT FOR SEWER LINE
WORKS
REFINERY TANK FARM
PACKAGE 6
RTR PIPES
RTR PIPE SCHEDULE
The RTR pipe shall be constructed as per project design and the
approved drawing for construction. Based on the approved drawing,
RTR pipe schedule shall be prepared. The RTR pipe schedule contains
the following details:
The size of RTR pipe, length required, number of pipes (male &
female), number of adhesive kits.
RTR PIPE INSPECTION BEFORE ASSEMBLY
All RTR pipe and fittings shall be visually inspected for scratches,
damage ends, cracks, de-lamination, crushing, weathering and
cracked. Damaged pipe and fittings shall not be installed.
RTR pipes (male & female) shall be cleaned and dried before
installation.
For trenches 2 m deep or less, pipe assembled next to the trench shall
not be moved within three pipe lengths of an uncured joint. The
pipeline shall be lowered into the trench progressively to avoid
excessive joint angular deflection.
for over 600 O.D + 600. The depth of the trench shall be dug deep
enough to provide minimum ground cover above the top of pipe, for
RTR pipe sized under 150mm sized minimum cover is 600mm RTR
pipe sized 150mm and larger is 900.
Piping shall have steel sleeves at road crossing and railroad crossing
in accordance with the Company Standard Drawing.
Fill up of thickness approved fine sand bedding on the trench. After lay-
out / install the pipe and fill with approved soft sand as padding around
the pipes by 200mm.
Pulling up of all timber shoring or sheet piling and transfer it to the next
01 location where sewer line is needed to installed.
Pulling up to all timber shoring or sheet piling and transfer it to the next
location where sewer line is needed to installed.
Effluent velocity within the sewer piping networks shall comply with the
requirements specification. JERES-S-020 Section 5.4.
Sanitary sewer systems shall not be combined with oily water system.
The quality of the works shall be on line with the SATORP standards.
Required tests shall be performed on each stage of sewer line works and the
report shall be prepared and submitted to the company representative for prior
approval.
Man Power
Civil Engineer
Civil Supervisor
Surveyor
Safety Supervisor
Foreman
Lorry / Truck Driver
Operators
Labourer 01
8. SAFETY EQUIPMENTS
Fire extinguisher
Hand-held-sirens
PPE
Warning Signs
The health and safety shall perform a splendid role in all construction activities
to ensure that all the works are being carried out in a safe manner and
creating a healthy environment at site. All works performed by individuals shall
comply with the SATORP health and safety standards
Contractor’s Safety Inspector shall closely monitor and assure that all works
are carried out in highly safe manner, gearing the workers with full strength of
safety protective equipment, preparation of safety barricading and dust control
screening wherever applicable in safe manner, safe workability of equipment
to be used and fulfilling any other additional safety needs as required during
work executions. He shall also check and ensure that only qualified personals
are carrying out the equipment & machinery related works.
Contractors shall appoint their own safety manager and he shall conduct
safety walk around the site in weekly basis and prepare and submit a report to
the company .Any accidents occurred shall be informed immediately to the
company and recorded accordingly.
9.1 A safety officer or a safety coordinator shall be present at site full time
during the execution of works and also to clarify the safety related issues.
9.3 The works shall be risk assessed and proper guidance should be
managed before implementation of every individual activities.
9.7 Man shelters shall be provided to protect the workers from adverse
climatic condition, i.e. sand storm, high temperature.
9.8 Potable water source shall be provided for adequate numbers for
workers.
bucket Barricade
the hoisting area
Personal protective
equipment (eg
Dropping of concrete from
Physical injuries and body irritation safety helmet) NIL
bucket
Barricade the
hoisting
Personal protective
Rotating shift
Pumping Noise from pumping Noise induce hearing lost (NIHL) equipment (eg ear
of workers
5 concrete using plug)
concrete pump Manual handling of concrete Rotating shift
Ergonomics, musculoskeletal NIL
hose of shifting of steel pipes of workers
Personal protective
Noise induce hearing lost (NIHL), Rotating shift
Process of Continuous noise generated equipment (eg ear
NID of workers
6 vibration of plug)
cocnrete Proper
Trip and fall Physical injuries and irritation NIL
housekeeping
01