Key Plan Showing Dado/ Cladding Tiles Location 1:50
Key Plan Showing Dado/ Cladding Tiles Location 1:50
Key Plan Showing Dado/ Cladding Tiles Location 1:50
790
790
1,200 1,200
1,200
2,200
750
SCREENSHOT OF PROPERTY MANAGER SHOWING FORMULA DERIVED FOR NUMBER OF TILES
750
DADO TILES
BATH BATH BATH BATH KITCHEN KITCHEN KITCHEN WB WB WC WC WC WC
ELEMENT ID
WALL 1 WALL 2 WALL 3 WALL 4 WALL 1 WALL 2 WALL 3 WALL 1 WALL 2 WALL 1 WALL 2 WALL 3 WALL 4
LENGTH OF THE
2,190 1,200 2,190 1,190 790 3,200 790 1,410 1,015 1,200 1,190 1,180 1,200
WALL
HEIGHT OF THE
2,100 2,100 2,100 2,100 2,100 2,100 2,100 2,100 2,100 2,100 2,100 2,100 2,100
WALL
NET TILE AREA 3.05 2.12 4.54 2.48 1.62 5.60 1.66 2.96 1.89 2.52 2.12 2.44 0.95
NO OF TILES 22.00 16.00 34.00 18.00 12.00 40.00 12.00 18.00 14.00 20.00 17.00 19.00 8.00 250.00
VOLUME OF WET
0.03 0.03 0.05 0.02 0.01 0.06 0.01 0.03 0.02 0.03 0.03 0.02 0.01
MORTOR
DRY MORTOR
0.00 0.01 0.02 0.01 0.01 0.02 0.01 0.10 9.00 0.01 0.01 0.02 0.00
VOLUME
TOTAL VOLUME OF
0.05 0.34 0.07 0.04 0.02 0.09 0.02 0.04 0.03 0.04 0.03 0.04 0.02 0.83 m³
MORTOR
NO OF CEMENT
0.36 0.25 0.54 0.29 0.19 0.67 0.19 0.35 0.22 0.30 0.25 0.29 0.11 4.01 m³
BAGS IN CU.M
RATE OF CEMENT
102.31 71.16 152.40 83.26 54.33 188.09 54.33 99.48 63.50 84.60 71.16 81.84 31.75 1,138.21 m³
BAGS
SAND IN CU.M 0.03 0.02 0.05 0.03 0.02 0.07 0.02 0.03 0.02 0.03 0.26 0.03 0.01 0.62 m³
AMOUNT OF
40.66 28.28 60.58 33.09 21.59 74.76 21.59 39.54 25.21 33.65 28.28 32.53 12.62 452.38 m³
SAND REQUIRED
COST OF TILES 1548.68 1077.21 2307.00 1260.30 822.40 2847.13 822.40 1505.96 961.25 1281.66 1077.21 1238.94 480.62 17230.76
WHITE CEMENT
76.13 52.95 113.40 61.95 40.43 139.95 41.48 74.03 47.25 63.00 52.95 60.90 23.63 848.05 m²
REQUIRED
TITLE : NORTH
NAME : PRANITA ATUL ZAMBARE DATE SIGN
SUBJECT : BIM (ARCHICAD) SEM : 1
ESTIMATE FOR DADO TILES IN WC,BATH, WB & KITCHEN AREA M.ARCH (CONST.MGMT), ACOA,PUNE
GSEducationalVersion ROLL NO : 08