Edoc-Switchgear and Switchboard Inspection and Testing Guide
Edoc-Switchgear and Switchboard Inspection and Testing Guide
Edoc-Switchgear and Switchboard Inspection and Testing Guide
Testing Guide
Switchgear maintenance is essential for continued reliable operation. Photo: Twins Chip Electrical Industry
This guide provides a general overview for the inspection, testing and
maintenance techniques used on switchgear and switchboard assemblies, and
their associated components.
Safety Considerations
Warning: Only qualified electrical personnel familiar with the equipment, its
operation and the associated hazards should be permitted to work on
switchboards and switchgear. Always be certain that the primary and secondary
circuits are de-energized before attempting any testing or maintenance.
Electrical Tests
• Bolted Connection Electrical Tests
• Instrument Transformers
• Cubicle Heaters
• Surge Arresters
2.) The unit should be clean and all shipping braces, loose parts, and
documentation shipped inside the cubicles removed. Keep all documentation in a
safe location for maintenance personnel in the future while loose parts and
switchgear tools should be safely stored outside of the enclosure for easy
access. When performing maintenance programs, clean the assembly
using electircal industry accepted methods of cleaning.
3.) For initial acceptance, verify that fuse and/or circuit breaker sizes, types,
and protective device settings match the project drawings and coordination
study. Circuit breaker's equipped with microprocessor-communication packages
should be programmed with the proper digital address. All instrument transformer
current and voltage ratios should also correspond to project drawings.
2.) All interior and exterior lighting should be checked for proper operation. It is
essential for personnel safety that the area be well lit at all times in case of
emergency response and other security reasons.
1.) Check that all wiring connections are tight and that wiring is secure to prevent
damage during routine operation of moving parts, especially when
removing draw-out circuit breakers or opening and closing cubicle doors. Gently
tug on control wires to ensure a tight connection or use a screwdriver to gently
verify torque on the connection. Infrared scans are also very effective for finding
loose wires in control circuits.
2.) Test key interlock systems by making key exchanges with all devices included
in the interlock scheme as applicable. All of these systems are essential for
safety of both the operator and the equipment.
Inspect the lubrication state of the circuit breaker operating mechanism latch faces and rollers. Photo Credit: ABB
Insulators and Barrier Checks for Switchgear and
Switchboards
Tracking is an electrical discharge phenomenon caused by electrical stress on
insulation. This stress can occur phase-to-phase or phase-to-ground. Although
tracking can occur internally in certain insulating materials, these materials as a
rule are not used in medium- or high-voltage switchgear insulation. Tracking,
when it occurs in switchgear assemblies, normally is found on insulation
surfaces.
Accumulated dirt, oil or grease might require liquid solvents or other alternative methods to be removed. Photo Credit:
Wickens Dry Ice Blasting
2.) Inspect barrier and shutter assemblies for proper installation and operation.
All active components should be exercised, mechanical indicating devices should
be inspected for correct operation.
Example of switchgear shutter operation. Video by Twins Chip Electrical Industry.
3.) Ensure that vents are clear and filters are in place. Screens covering
ventilation openings should be in place to prevent entry of rodents or small
animals.
2.) Verify dual-source switchgear bussing is correct at the tie breaker. Compare
resistance values to values of similar connections and investigate values that
deviate by more than 50 percent of the lowest value.
Example:
2.) Apply test voltage for one minute. If no evidence of distress or insulation
failure is observed by the end of the total time of voltage application, the test
specimen is considered to have passed the test.
Solid-state components could be damaged if not properly isolated before applying test voltage. Photo: Square D.
The procedure for inspecting and testing instrument transformers is beyond the
scope of this guide as each type has its own procedure. Instrument transformers
generally include current transformers, voltage transformers, and control power
transformers. Conduct electrical tests on instrument transformers in accordance
with ANSI/NETA Section 7.10. Where applicable, testing of instrument
transformers generally include:
• Visual/Mechanical Inspection
• Dielectric Withstand
• Excitation Tests
• Burden Test
• Power/Dissipation Factor
It's essential that circuit breakers be tested and maintained to ensure proper operation during electrical faults.
Photo: Vacuum Interrupter Testing
• Visual/Mechanical Inspection
• Insulation Resistance
• Dielectric Withstand
• Contact/Pole Resistance
• Electrical Operations
• Power/Dissipation Factor
Recommended Reading:
2.) Determine the resistance between the main grounding system and all major
electrical equipment frames, system neutral, and derived neutral points by means
of point-to-point testing using a low-resistance ohmmeter. Values which exceed
0.5 ohm should be investigated.
Metering devices are verified using secondary voltage and current levels. Photo: EATON
Metering device inspections and tests are beyond the scope of this guide.
Generally, metering devices are verified using secondary voltage and current
levels supplied by a relay test set or other secondary source.
1.) Perform current-injection tests on the entire current circuit in each section of
switchgear by secondary injection with magnitudes that produce a minimum
current of 1.0 ampere flows in the secondary circuit. Verify correct magnitude of
current at each device in the circuit.
Tip: Infrared cameras are the easiest way to verify heater functionality without
making contact with energized electrical equipment.