Bill of Materials: Project: Location: Owner
Bill of Materials: Project: Location: Owner
Bill of Materials: Project: Location: Owner
2mts height)
LOCATION :
OWNER:
BILL OF MATERIALS
Description Quantity Unit Unit Cost AMOUNT
I. GENERAL REQUIREMENTS
Mobilization 1.00 LOT 2,500.00 2,500.00
Demobilization 1.00 LOT 2,500.00 2,500.00
Performance Bond 1.00 LOT - -
Guarantee Bond 1.00 LOT - -
CARI 1.00 LOT - -
Surety Bond 1.00 LOT - -
Contractor's Tax 1.00 LOT - -
Water/ Power/Overhead 1.00 LOT 3,500.00 3,500.00
Safety Protection 1.00 LOT - -
Transportation 1.00 LOT - -
Permits 1.00 LOT - -
SUB-TOTAL 8,500.00
Project Lay-out:
30 - 2x3x12 Coco Lumber bdft 180.00 25.00 4,500.00 4,500.00
4" Common Wire Nails kgs 3.00 75.00 225.00 225.00
2" Common Wire Nails kgs 1.00 75.00 75.00 75.00
Level Hose 3/8" mts 20.00 10.00 200.00 200.00
No. 16 Nylon String rolls 1.00 50.00 50.00 50.00
Reinforcing Steel Bar:
12 mm dia. X 6 m. RSB pcs 83.00 220.00 18,260.00 18,260.00
10 mm dia. X 6 m. RSB pcs 36.00 130.00 4,680.00 4,680.00
10 mm dia. X 7.5 m. RSB pcs 7.00 184.80 1,293.60 1,293.60
10 mm dia. X 9 m. RSB pcs 11.00 221.76 2,439.36 2,439.36
Hacksaw Handle pcs 2.00 250.00 500.00 500.00
Hacksaw blade pcs 10.00 50.00 500.00 500.00
#16 GI Tie Wire kg. 17.00 63.40 1,077.82 1,077.82
Form Lumber:
1/2" Phenolic Boards pcs 3.00 875.00 2,625.00 2,625.00
2 x 2 x 8 Good Lumber bd.ft 158.00 115.00 18,170.00 18,170.00
#16 GI Tie Wire kg. 1.00 63.40 63.40 63.40
1" Common Wire Nail kgs 1.00 75.00 75.00 75.00
3" Common Wire Nail kgs 1.00 75.00 75.00 75.00
Structural Concrete:
Portland Cement bags 74.00 250.00 18,500.00 18,500.00
Fine Aggregates cu.m 4.00 600.00 2,400.00 2,400.00
Gravel, 3/4" cu.m 8.00 700.00 5,600.00 5,600.00
Stone Masonry:
Portland Cement bags 37.00 250.00 9,250.00 9,250.00
Fine Aggregates cu.m 3.00 600.00 1,800.00 1,800.00
100 mm x 400 mm CHB pcs 900.00 12.00 10,800.00 10,800.00
SUB-TOTAL 103,159.18
SUMMARY
I. GENERAL REQUIREMENTS ₱ 8,500.00
II. DIRECT COST - MATERIAL ₱ 103,159.18
III. TOTAL DIRECT LABOR ₱ 30,800.00
IV. MISCELLANEOUS (5%) ₱ 5,157.96
V. CONTINGENCY (10%) ₱ 14,761.71
TOTAL PROJECT COST ₱ 162,378.85