2021.03.25 - Invitation To Tender and Scope of Works - Electrical
2021.03.25 - Invitation To Tender and Scope of Works - Electrical
2021.03.25 - Invitation To Tender and Scope of Works - Electrical
Contents
1. Invitation to Tender (ITT) Introduction .................... 1 9. Project Documentation & Specifications That Form
Part of The Scope of Works: ............................................ 8
2. Tender Invitation Details ......................................... 1
10. Site Specific Requirements – Deliveries, Material
3. Brief Project Description ......................................... 2 Handling, Site Access ...................................................... 9
4. Commercial Terms ................................................. 2 11. Licences Required .................................................. 9
5. Conditions & Rules of Tendering ............................ 3 12. Design Verification & Compliance, Certifications &
6. Is this a Design and Construct Package: ................ 3 Handover Documents .................................................... 10
7. Trade Scope of Works ............................................ 4 13. Safety, Environmental & Quality ........................... 11
This Invitation to Tender (ITT) document outlines VMGs requirements for your organisation’s participation in this tender. The
document has been designed so that the all aspect of the works are clearly defined, risk has been apportioned clearly and
the expectations and contractual requirements have been provided upfront. Feel free to email the project estimator should
you have any queries.
Page 1 of 14
Doc Number: VMG230
Invitation to Tender Project No: 614
Electrical Revision: A
The new amenity building scope includes ground floor change rooms, storage rooms, toilets and provision for officials.
This is the final component of the total Coffs Coast Regional Sports Hub Stage 2 Project to be delivered.
Council and Van Mal Group are is seeking to achieve a quality build with a striking presence, however using traditional
materials and construction methods to ensure cost effective delivery to meet budget.
Excluded form Scope - Two synthetic turf fields, One turf field, Field and car park lighting and electrical works, Network
pathway construction, Southern amenity building extensions
4. Commercial Terms
Proposed Form of Contract
Payment Terms • Progress Claims and all supporting documentation are to be submitted to
accounts@vanmalgroup.com.au on the 25th of each month for works
completed.
• Payment will be made 30 days from end of month, provided that all Supporting
documentation has been provided (Subcontractor Statement, Insurances,
Certifications, Testing & Commissioning documentation).
Bank Guarantee/Retention • Retention will be held at 10% of progress claims until a maximum of 5% of the
contract total is reached including variations.
• Upon practical completion 2.5% will released and the remaining 2.5% to be
retained by VMG for the defect liability period.
• During this period, the subcontract will be required to repair any defects at no
extra charge to VMG.
• Bank Guarantees may be accepted instead of retention.
Minimum Insurance Requirement • Public Liability Insurance to the minimum value of $20 million.
• Workers Compensation Insurance
• Contract Works insurance for 150% of the value of the works and variations,
including coverage for Plant and Equipment, Materials and Tools
• Vehicle Insurance for vehicles involved with the works
• Professional Indemnity Insurance when undertaking Design works
Licensing Requirements Provide evidence of current licences for all Trade related works, High Risk Works
and as required.
Page 2 of 14
Doc Number: VMG230
Invitation to Tender Project No: 614
Electrical Revision: A
Page 3 of 14
Doc Number: VMG230
Invitation to Tender Project No: 614
Electrical Revision: A
a) provide all required Labour and Supervision required to undertake the works (all workers to be English
speaking, licenced and qualified)
b) attend meetings both on site and via video conferencing.
c) supply all plant and equipment to undertake the Scope of Works
d) supply all deliveries, material handling, site access to undertake the Scope of Works
e) undertake and verify all set outs, levels, heights, falls, dimensions, spacings, measurements, calculations,
quantities required to undertake the works. NOTE: Any dimensions, quantities & BOQs provided by VMG to
the Subcontractor are approximates only and must not be relied upon.
f) allow for the staging of works and coordination with other Trades associated with the Project.
g) allow to maintain the project programme and to accelerate programme where required
h) allow for daily site clean and removal of trade waste and spoil generated
i) allow for undertaking Design verification works and Certification of Works
j) provide evidence of all required insurances
k) provide a standard of work that is defect free and fit for handover (final handover that matches the head
contract).
l) sign off on each area after agreement from VMG that the works in the area are complete and defect free
7.1.3. The Subcontractor is to advise the VMG project manager in writing if the proposed works are not full
compliance with relevant Standards and Codes.
7.1.4. Please notify the VMG representative via email if any:
Page 4 of 14
Doc Number: VMG230
Invitation to Tender Project No: 614
Electrical Revision: A
3. External Works
a. Allow for external service connection from the underground main (by client) to the main
distribution board.
4. Power
a. Allow to supply and install all cables, conduits, cable trays from the main distribution board
to all switch boards, panel boards, mechanical switchboards, etc as documented.
b. Supply and install all switchboards, distribution boards, circuits and wiring as documented
and as required to provide a fully functional electrical package.
c. Allowance to supply and install power to hydraulic pumps and hot water units.
d. Supply and install all GPOs and writing as documented.
e. Supply and install power to all electrical kitchen/amenities appliances as required.
f. Allow for isolation switches where required.
6. Induction Loops
a. Supply and install induction loops as documented (assume wire cast in slabs), client to
supply amplifiers, electrician to install, test and commission.
Page 5 of 14
Doc Number: VMG230
Invitation to Tender Project No: 614
Electrical Revision: A
9. MATV
a. Supply MATV as documented.
b. Apply to Foxtel and pay all fees and make provisions for any dish or other cabling required,
plus supply head end equipment.
14. Notes
Page 6 of 14
Doc Number: VMG230
Invitation to Tender Project No: 614
Electrical Revision: A
a. Drawings have been provided for the Lift, Mechanical and Hydraulic to allow you to
coordinate works and identify electrical requirements for those trades.
b. Make sufficient allowance for Notes 1 through to 15 of Electrical Dwg. # E02.
c. Allow for fire rated cabling where specified.
d. All materials should be as per project material schedule & specifications.
Page 7 of 14
Doc Number: VMG230
Invitation to Tender Project No: 614
Electrical Revision: A
Page 8 of 14
Doc Number: VMG230
Invitation to Tender Project No: 614
Electrical Revision: A
Page 9 of 14
Doc Number: VMG230
Invitation to Tender Project No: 614
Electrical Revision: A
a) Allow for all necessary design verification, calculations & measurements to confirm that the provided design
is, error free, fit for purpose and compliant with the design intent, BCA / NCC / Australian Standards.
b) Allow for minor design amendments, updates, modifications and coordination and communication of any
Subcontractor identified design shortcomings and or proposed Subcontractor design changes
c) undertake minor design and verification works Drawings
d) Provision of workshop drawings, and required updates in a timely manner, prior to fabrication, for client
review and approval.
12.1.2. The Subcontractor is to provide the following Documents when requested and at Handover Stage:
Page 10 of 14
Doc Number: VMG230
Invitation to Tender Project No: 614
Electrical Revision: A
13.1. General
13.1.1. Common compliance documents that the works will be managed under:
All documents are available upon request and within the Subcontractor Pack.
13.2. Safety
13.2.1. All works are to be carried out safely, in full compliance with current Work Health and Safety Act and
Regulation, Safe Work NSW Codes of Practice, Client and VMG requirements.
13.2.2. All Subcontractor workers must have:
a) “white card” (general construction induction card) with them when onsite.
b) all licences, training and qualifications for the works they are undertaking
c) completed both the Client and VMG site specific site induction prior to commencing works on site
13.2.3. The Subcontractor is to
13.3. SWMS
13.3.1. The SWMS will:
a) Codes of Practice
b) Safety Legislation
c) Client requirements
d) As stated in your approved Safe Work Method Statement (SWMS)
13.4.2. VMG sites have the following minimum mandatory requirements:
Page 11 of 14
Doc Number: VMG230
Invitation to Tender Project No: 614
Electrical Revision: A
13.4.3. The Subcontractor agrees that should its workers not adhere to the PPE requirements, VMG will
implement a “reminder” campaign that may involve:
a) likelihood of asbestos, lead and other HAZMAT within the building fabric and within the ground
b) slips trips and falls
c) plant and equipment
d) working at heights
e) chemicals on site
f) dust
g) live electrical services overhead, within building fabric and underground
h) underground services – water, gas and communications
i) pedestrians and general public nearby
a) Environmental legislation
b) EPA requirements
c) Local Council requirements
d) Client requirements
e) VMG requirements
f) Waste Transport, Waste Tracking requirements and the Heavy Vehicle National Law
13.6.2. The Subcontractor is to retain all tipping dockets and submit to VMG with their monthly progress claim
for:
a) Scope of Works
b) Project documentation
c) Manufacturers’ guidelines
d) Australian Standards
e) Industry best practice
f) Client requirements
g) VMG requirements.
13.7.2. The Subcontractor is to follow Inspection Test Plans (ITPs) and observe all Hold and Witness Points –
such points are to be factored into the overall programme for the subcontractor package.
13.7.3. The Subcontractor is to conduct material testing, if required, to confirm that any installed materials:
Page 12 of 14
Doc Number: VMG230
Invitation to Tender Project No: 614
Electrical Revision: A
Page 13 of 14
Doc Number: VMG230
Invitation to Tender Project No: 614
Electrical Revision: A
Below is a suggested price breakdown format that we prefer for you to follow. This will assist in the evaluation of your
quotation and may reflect the format in which VMG will provide pricing to the Client.
3. Power: $..........
8. MATV: $..........
14. Additional items required to handover a fully complete and certified trade package: $..........
Page 14 of 14