Procurement Plan: Al-Janadriyah Exhibition Facility, Ar-Riyadh
Procurement Plan: Al-Janadriyah Exhibition Facility, Ar-Riyadh
Procurement Plan: Al-Janadriyah Exhibition Facility, Ar-Riyadh
:
AL JANADRIYAH EXHIBITION AJEF-DOC-004/PrP
FACILITY, AR-RIYADH Rev. No. R01
EASTERN TRADING & CONT. EST. Date: 18/05/2015
PROCUREMENT PLAN
Req. No. 3000613310
PROCUREMENT PLAN
Page 1 of 11
Doc. No.:
AL JANADRIYAH EXHIBITION AJEF- DOC-004/PrP
FACILITY, AR-RIYADH Rev. No. R01
EASTERN TRADING & CONT. EST. Date: 18/05/2015
PROCUREMENT PLAN
Req. No. 3000613310
B. REFERENCE
The procurement procedures described in this plan shall be implemented in
conjunction and/or referred in the following procedures/documents.
COMPANY Contract Schedules
Contract Schedules
Contract Documents, Specifications & Drawings, Codes & Standards.
Procurement Schedule
Procurement Schedule
D. CONTRACTOR RESPONSIBILITIES
a) Engineering Department Manager
As technical support to procurement functions, his main responsibilities are:
Reviews the Contract/Bid Documents comprising CONTRACTOR’s
materials supply portion and generate a Master List of these items for
issue to Site Technical Support Services Unit as base reference in the
preparation of Materials Requisitions, and required Material Technical
Submittals to the CLIENT.
Assists Procurement Manager in Technical evaluation of Vendor’s bid
proposal and soliciting the required Non-Material Requirements (NMRs) i.e.
Product Technical Data Sheet / Brochures, Catalogue Cuts, Material Test
Certificates, etc.
Reviews and checks the final packaging of the Purchase Requisition
Submittal prepared by Discipline Engineer/Technical Support Services
Supervisor for endorsement to the CLIENT through CONTRACTOR Site
Management and ensures appropriate approval is obtained prior to
procurement. Ensure that the Material Technical Submittals had completed
the acceptance criteria (applicable specifications, standards, IFC Drawing,
Codes and other regulatory requirements) complete CONTRACTOR with
required NMRs and Inspection & Test Requirements (S.A. Form 175s).
Reviews and checks the Material Requisition (MR) prepared by
disciplined Engineer/Technical Support Services Supervisor approved by
the CLIENT.
Doc. No.:
AL JANADRIYAH EXHIBITION AJEF- DOC-004/PrP
FACILITY, AR-RIYADH Rev. No. R01
EASTERN TRADING & CONT. EST. Date: 18/05/2015
PROCUREMENT PLAN
Req. No. 3000613310
d) Site/Construction Manager
CONTRACTOR designated Site/Construction Manager for this contract job shall
be responsible to oversee that the administration of this Procurement Plan is
implemented in collaboration with the Engineering Manager, Procurement
Manager and Corporate QA/QC Manager.
He sees to it that the necessary planned resources and actions to effectively
implement this procurement plan are provided and continuously supported by
t h e CONTRACTOR T o p M anagement.
Doc. No.:
AL JANADRIYAH EXHIBITION AJEF- DOC-004/PrP
FACILITY, AR-RIYADH Rev. No. R01
EASTERN TRADING & CONT. EST. Date: 18/05/2015
PROCUREMENT PLAN
Req. No. 3000613310
e) Procurement QC Supervisor
Procurement QC Supervisor (based in CO NTRACTO R H.O.) shall report to t he
Corporate QA/QC Manager and responsible for random review of materials
requisitions and Purchase Orders for compliance with applicable
specification/standards. Depending on the necessity, he organizes and
established the agenda for pre-inspection meetings, issuance of source
inspection assignments and review of Vendors Quality Plan / ITP.
Procurement QC Supervisor will coordinate with Vendor Inspection with technical
assistance through CONTRACTOR pool of Discipline QC Inspectors or by a
Commissioned Third Party Agency Inspector if ever necessitates performing
Vendor Inspection.
E. PROCUREMENT PROCEDURE
1) General
CONTRACTOR shall be governed by the Contract Provisions on “Contractor’s
Procurement Responsibility” as described in Project Quality Management
System (QMS)-Requirements, ISO 9001:2000/2008, and other requirements
set forth therein in the Contract Agreement.
2) Material Requirement Identification
CONTRACTOR Engineering Department shall identify, take off and prepare a
list of all the materials and equipment required as per the Contract Scope of
Work, which shall be referred to the approved, and Issued for Construction
Drawings. This list shall contain the following information as minimum:
Item Description
Location of use
Quantity
Saudi Aramco Engineering Standards (applicable to the material)
Saudi Aramco Material Supply (SAMSS) stock number (if applicable)
Compliance to specific International Codes/Standards
Recommendation for capital spare parts (may not be applicable for
CONTRACTOR scope since no parent equipment is included in its
supply scope)
Commodity Code Classification number assigned by THE CLIENT for
the Material/Equipment item.
CONTRACTOR’s Procurement Department shall use this list as the master
guideline for the Procurement of all the items as indicated on the list. CLIENT
shall provide t h e CONTRACTOR f or the formats for the Purchase Order
Control Log and Material Technical Submittals as may be appropriate.
8) Expediting
CONTRACTOR shall ensure that the Inspectors and/or expediters and/or those
appointed by them shall have free access to CONTRACTOR’s and its Vendor’s
offices and works.
During expediting, CONTRACTOR shall be responsible for giving complete and
reliable information on the purchase order status. The information will include
shipping schedule, issuance and progress status of any orders, critical orders
and the expected arrival dates.
CONTRACTOR Expediters shall prepare and forward at regular intervals to
Procurement Department, an up-to-date status report of Vendors.
Doc. No.:
AL JANADRIYAH EXHIBITION AJEF- DOC-004/PrP
FACILITY, AR-RIYADH Rev. No. R01
EASTERN TRADING & CONT. EST. Date: 18/05/2015
PROCUREMENT PLAN
Req. No. 3000613310
F. APPENDICES
1. Material Receiving Report - Form No. WF-10
2. Material Inspection Report - Form No. Q-006
3. Non-Conformance Report - Form No. Q-005
4. Inventory Stock Card - Form No. WF-11
5. Issue Voucher - Form No. WF-07