SAUDI ARAMCO ID/PID - 01/01/09- REV 1 (Standards Cutoff - MARCH 2013) Rev 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Boxes (Junction, Terminal, and Pull) Wire Troughs, and Wireways SATIP-P-104-04 30-Apr-13 Electrical
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

1.0 DOCUMENT REVIEW

Cable and Conduit Seal


To be Reviewed and Approved Prior to Electrical Work at
1.1 Installation Procedure SAIC-P-3004 SAIC-P-3004 RH R Jobsite.
Document Review

2.0 RECEIVING INSPECTION

Enclosure Storage, Handling,


2.1
and Preservation Visual Inspection
See Remarks See Remarks W S Weekly Inspection by Contractor QC

Boxes, Enclosures, and Accessories


Material Receiving
2.2
Visual Inspection for Channel and Strut
SAIC-P-3005 SAIC-P-3005 H W See GENERAL NOTES for typical accessories.
Materials & Accessories

Boxes, Enclosures, and Accessories


Material Receiving
2.3
Visual Inspection for Boxes, Enclosures
SAIC-P-3007 SAIC-P-3007 H W See GENERAL NOTES for typical accessories.
and Accessories

Boxes, Enclosures, and Accessories


Material Receiving
2.4
Visual Inspection for Metallic Wireways
SAIC-P-3008 SAIC-P-3008 H W See GENERAL NOTES for typical accessories.
and Accessories

Boxes, Enclosures, and Accessories


Material Receiving
2.5
Visual Inspection for Non-metallic
SAIC-P-3009 SAIC-P-3009 H W See GENERAL NOTES for typical accessories.
Wireways and Accessories

Boxes, Enclosures, and Accessories


Material Receiving
2.6 Visual Inspection for Pushbutton, SAIC-P-3010 SAIC-P-3010 H W See GENERAL NOTES for typical accessories.
Pilot Light Control Stations and
Accessories

Page 1 of 4
03/09/2022 3:37 PM
SAUDI ARAMCO ID/PID - 01/01/09- REV 1 (Standards Cutoff - MARCH 2013) Rev 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Boxes (Junction, Terminal, and Pull) Wire Troughs, and Wireways SATIP-P-104-04 30-Apr-13 Electrical
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

3.0 INSTALLATION

Hazardous Location
Hold point includes cable connectors, conduit hubs,
Enclosure Installation
conduit unions, box drainage, and conduit seal fittings
and Identification Numbering
installation.
3.1 Visual Inspection SAIC-P-3016 SAIC-P-3016 H H
(Before Cable Pulling) for Class I, Div 1,
SA PID to be notified on completion of this activity for
Zone 0&1, Hazardous Location
each process system and plant area.
Enclosures (Indoor and Outdoor)

Hazardous Location
Hold point includes cable connectors, conduit hubs,
Enclosure Installation
conduit unions, box drainage, and conduit seal fittings
and Identification Numbering
installation.
3.2 Visual Inspection SAIC-P-3017 SAIC-P-3017 H H
(Before Cable Pulling) for Class I, Div 2,
SA PID to be notified on completion of this activity for
Zone 2, Hazardous Location Enclosures
each process system and plant area.
(Indoor and Outdoor)

Non-Hazardous Location Hold point includes cable connectors, conduit hubs,


Enclosure Installation conduit unions, box drainage, conduit seal fittings, and
and Identification Numbering cable tray interface installation.
3.3
Visual Inspection
SAIC-P-3014 SAIC-P-3014 H W
(Before Cable Pulling) for SA PID to be notified on start of this activity for each
Non-Hazardous Indoor Enclosures process system and plant area.

Non-Hazardous Location Hold point includes cable connectors, conduit hubs,


Enclosure Installation conduit unions, box drainage, conduit seal fittings, and
and Identification Numbering cable tray interface installation.
3.4
Visual Inspection
SAIC-P-3015 SAIC-P-3015 H W
(Before Cable Pulling) for SA PID to be notified on start of this activity for each
Non-Hazardous Outdoor Enclosures process system and plant area.

Activity for enclosures with cable connectors. Hold point


Enclosure Cable Gland Installation
after cable pulling and prior to cable dressing and
Visual Inspection
termination.
3.5 (Before Cable Termination) for Class I, SAIC-P-3017 SAIC-P-3017 H W
Div 2, Zone 2, Hazardous Location
SA PID to be notified on start of this activity for each
Enclosures
process system and plant area.

Activity for enclosures with cable connectors. Hold point


Enclosure Cable Gland Installation after cable pulling and prior to cable dressing and
Visual Inspection termination.
3.6
(Before Cable Termination) for
SAIC-P-3014 SAIC-P-3014 H W
Non-Hazardous Indoor Enclosures SA PID to be notified on start of this activity for each
process system and plant area.

Page 2 of 4
03/09/2022 3:37 PM
SAUDI ARAMCO ID/PID - 01/01/09- REV 1 (Standards Cutoff - MARCH 2013) Rev 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Boxes (Junction, Terminal, and Pull) Wire Troughs, and Wireways SATIP-P-104-04 30-Apr-13 Electrical
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

Activity for enclosures with cable connectors. Hold point


Enclosure Cable Gland Installation after cable pulling and prior to cable dressing and
Visual Inspection termination.
3.7
(Before Cable Termination) for
SAIC-P-3015 SAIC-P-3015 H W
Non-Hazardous Outdoor Enclosures SA PID to be notified on start of this activity for each
process system and plant area.

4.0 PRE-COMMISSIONING

Hazardous Location Hold point (each enclosure) after fiber damming and prior
4.1 Enclosure Sealing SAIC-P-3209 SAIC-P-3209 H H to cement pouring for conduit hubs, conduit seals, and
Visual Inspection cable seals.

Enclosure Final Hold point includes inspection of installed weather-proof


Visual Inspection sealing.
4.2 (Before Energization) for Class I, Div 1, SAIC-P-3016 SAIC-P-3016 H W
Zone 0&1, Hazardous Location SA PID to be notified on start of this activity for each
Enclosures process system and plant area.

Hold point includes inspection of installed weather-proof


Enclosure Final
sealing.
Visual Inspection
4.3
(Before Energization) for Class I, Div 2,
SAIC-P-3017 SAIC-P-3017 H W
SA PID to be notified on start of this activity for each
Zone 2, Hazardous Location Enclosures
process system and plant area.

Hold point includes inspection of installed weather-proof


Enclosure Final
sealing.
Visual Inspection
4.4
(Before Energization) for
SAIC-P-3014 SAIC-P-3014 H W
SA PID to be notified on start of this activity for each
Non-Hazardous Indoor Enclosures
process system and plant area.

Hold point includes inspection of installed weather-proof


Enclosure Final
sealing.
Visual Inspection
4.5
(Before Energization) for
SAIC-P-3015 SAIC-P-3015 H W
SA PID to be notified on start of this activity for each
Non-Hazardous Outdoor Enclosures
process system and plant area.

Page 3 of 4
03/09/2022 3:37 PM
SAUDI ARAMCO ID/PID - 01/01/09- REV 1 (Standards Cutoff - MARCH 2013) Rev 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Boxes (Junction, Terminal, and Pull) Wire Troughs, and Wireways SATIP-P-104-04 30-Apr-13 Electrical
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

GENERAL NOTES

The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the levels of
1
Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
3
organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization
4
representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

a) Box accessories include mechanical fasteners, gaskets, terminal blocks & points, sub-panels, door/panel hardware, drain fittings, box ID. labels, manufacturer nameplates, terminal block & point labels,
warning signs, external/internal grounding & bonding hardware, and mounting lugs and supplemental supports.
6
b) Wireway accessories include elbows, endplates, hinged / removable covers, couplings, T and X fittings, open adaptors, gaskets and Connectors.
c) Channel and strut materials include all mechanical fasteners, anchors, threaded rods, fittings, and brackets required to provide supplemental supports.

LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection

Page 4 of 4