SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
Boxes (Junction, Terminal, and Pull) Wire Troughs, and Wireways SATIP-P-104-04 30-Apr-13 Electrical
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
Page 1 of 4
03/09/2022 3:37 PM
SAUDI ARAMCO ID/PID - 01/01/09- REV 1 (Standards Cutoff - MARCH 2013) Rev 7 31-Mar-13
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
Boxes (Junction, Terminal, and Pull) Wire Troughs, and Wireways SATIP-P-104-04 30-Apr-13 Electrical
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
3.0 INSTALLATION
Hazardous Location
Hold point includes cable connectors, conduit hubs,
Enclosure Installation
conduit unions, box drainage, and conduit seal fittings
and Identification Numbering
installation.
3.1 Visual Inspection SAIC-P-3016 SAIC-P-3016 H H
(Before Cable Pulling) for Class I, Div 1,
SA PID to be notified on completion of this activity for
Zone 0&1, Hazardous Location
each process system and plant area.
Enclosures (Indoor and Outdoor)
Hazardous Location
Hold point includes cable connectors, conduit hubs,
Enclosure Installation
conduit unions, box drainage, and conduit seal fittings
and Identification Numbering
installation.
3.2 Visual Inspection SAIC-P-3017 SAIC-P-3017 H H
(Before Cable Pulling) for Class I, Div 2,
SA PID to be notified on completion of this activity for
Zone 2, Hazardous Location Enclosures
each process system and plant area.
(Indoor and Outdoor)
Page 2 of 4
03/09/2022 3:37 PM
SAUDI ARAMCO ID/PID - 01/01/09- REV 1 (Standards Cutoff - MARCH 2013) Rev 7 31-Mar-13
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
Boxes (Junction, Terminal, and Pull) Wire Troughs, and Wireways SATIP-P-104-04 30-Apr-13 Electrical
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
4.0 PRE-COMMISSIONING
Hazardous Location Hold point (each enclosure) after fiber damming and prior
4.1 Enclosure Sealing SAIC-P-3209 SAIC-P-3209 H H to cement pouring for conduit hubs, conduit seals, and
Visual Inspection cable seals.
Page 3 of 4
03/09/2022 3:37 PM
SAUDI ARAMCO ID/PID - 01/01/09- REV 1 (Standards Cutoff - MARCH 2013) Rev 7 31-Mar-13
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:
Boxes (Junction, Terminal, and Pull) Wire Troughs, and Wireways SATIP-P-104-04 30-Apr-13 Electrical
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the levels of
1
Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
3
organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization
4
representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
a) Box accessories include mechanical fasteners, gaskets, terminal blocks & points, sub-panels, door/panel hardware, drain fittings, box ID. labels, manufacturer nameplates, terminal block & point labels,
warning signs, external/internal grounding & bonding hardware, and mounting lugs and supplemental supports.
6
b) Wireway accessories include elbows, endplates, hinged / removable covers, couplings, T and X fittings, open adaptors, gaskets and Connectors.
c) Channel and strut materials include all mechanical fasteners, anchors, threaded rods, fittings, and brackets required to provide supplemental supports.
LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection