SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - Mar 2013) Rev 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Lightning Protection SATIP-P-111-02 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

1.0 DOCUMENT REVIEW

Not applicable
RECEIVING
2.0
INSPECTION

Storage, Handling, and Preservation


2.1
Visual Inspection for Electrical Equipment
SAIC-P-3002 SAIC-P-3002 W S Weekly Inspection by Contractor QA/QC

Storage, Handling, and Preservation


2.2
Visual Inspection for Cable
SAIC-P-3201 SAIC-P-3201 W S Weekly Inspection by Contractor QA/QC

Lightning Protection Equipment


Material Receiving
2.3
Visual Inspection for Lightning Protection
SAIC-P-3750 SAIC-P-3750 H W
Air Terminals

Lightning Protection Equipment


Material Receiving
2.4
Visual Inspection for Lightning Protection
SAIC-P-3751 SAIC-P-3751 H W
Ground Terminals

Lightning Protection Equipment


Material Receiving
2.5
Visual Inspection for Lightning Protection
SAIC-P-3752 SAIC-P-3752 H W
Cable

LP Accessories See GENERAL NOTES for typical accessories.


Material Receiving
2.6
Visual Inspection for Lightning Protection
SAIC-P-3753 SAIC-P-3753 H W Notify SA by RFI on receipt of each listed accessory (by
Accessories type or manufacturer).

3.0 INSTALLATION

Air Terminal Installation


3.1
Visual Inspection
SAIC-P-3754 SAIC-P-3754 H W

Page 1 of 3
03/09/2022 3:40 PM
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - Mar 2013) Rev 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Lightning Protection SATIP-P-111-02 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

Loop and Down Conductor


3.2 Identification and Installation SAIC-P-3756 SAIC-P-3756 H W
Visual Inspection

Ground Terminal Installation


3.3
Visual Inspection
SAIC-P-3755 SAIC-P-3755 H W See also SATIP-P-111-01 Grounding and Bonding

Bonding Conductor Installation


3.4
Visual Inspection
SAIC-P-3756 SAIC-P-3756 H W See also SATIP-P-111-01 Grounding and Bonding

3.5 Conductor Termination SAIC-P-3756 SAIC-P-3756 H W See also SATIP-P-111-01 Grounding and Bonding

4.0 PRE-COMMISSIONING

Ground Terminal System


4.1
Electrode Resistance Testing
SATR-P-3702 SATR-P-3702 H H

Conductor Termination
4.2
Torque Testing
SATR-P-3706 SATR-P-3706 H W

Lightning Protection System


Final Visual Inspection
4.3
for Mechanical Completion for Lightning
SAIC-P-3754 EIL H H
Protection Air Terminals

Lightning Protection System


Final Visual Inspection
4.4
for Mechanical Completion for Lightning
SAIC-P-3756 EIL H H
Protection Conductors

Lightning Protection System


Final Visual Inspection
4.5
for Mechanical Completion for Lightning
SAIC-P-3755 EIL H H
Protection Ground Terminals

Page 2 of 3
03/09/2022 3:40 PM
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - Mar 2013) Rev 7 31-Mar-13

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Lightning Protection SATIP-P-111-02 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

Quality Document Review PMCC


4.6
and Mechanical Completion Certificate
FEIL
MCC
RH RH Review FEIL and all associated Quality Records

GENERAL NOTES

The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the
1
levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
3
organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization
4
representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

Accessories include exothermic welding material and tools, mechanical connectors, hydraulic crimp connectors and tools, conductor clamps and supports, and anchor materials.
6
SA PID by shall be notified on delivery of each Item. (by type or manufacturer).

LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection

Page 3 of 3