FSD - Antenna Tower

Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

OPRNS SAUDI ARABIAN OIL COMPANY

WASIT GAS PROGRAM


PMT
CERT

ZHK

TABLE OF CONTENTS
ENG’G

RJV

1.0 GENERAL............................................................................................................... 3
1.1 Scope ...................................................................................................................... 3
1.2 Site and Ambient Conditions................................................................................... 3
DESCRIPTION

1.3 Industry Codes and Standards................................................................................ 3


1.4 Related Drawings.................................................................................................... 4
2.0 OPERATING PHILOSOPHY .................................................................................. 4
3.0 TECHNICAL REQUIREMENTS ............................................................................. 5
Issued for Bid

3.1 Foundations ............................................................................................................ 5


3.2 Structural ................................................................................................................. 5

THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
3.3 Antennas and Mounting .......................................................................................... 6
3.4 Electrical System..................................................................................................... 6
10-00914-0001
JO/EWO NO.

3.5 Fence ...................................................................................................................... 6


3.6 Description Overview .............................................................................................. 7
3.6.1 Painting ................................................................................................................... 7
3.6.2 Design Life .............................................................................................................. 7
3.7 Safety and Security Requirement ........................................................................... 7
DATE

05/27/10

4.0 INSPECTION .......................................................................................................... 8


4.1 Mechanical Completion Certificate (MCC) .............................................................. 8
5.0 DOCUMENTATION ................................................................................................ 8
REV
NO.

5.1 Drawings ................................................................................................................. 9


DRAWN 5.2 Installation Drawings ............................................................................................... 9
DATE 5.3 As-Built Drawings.................................................................................................... 9
CHECKED

BY
DATE

DISCIPLINE
ENGINEER

DATE

PROJECT
ENGINEER

DATE

CERTIFIED

DATE

CONSTRUCTION
AGENCY

DATE

OPERATIONS

DATE

WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED SU&O
FOR
CONSTRUCTION Q75 T PP-418245 2
UNTIL CERTIFIED of 0
AND DATED.
9
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT
CERT

ZHK

1.0 GENERAL
ENG’G

1.1 Scope
RJV

This Functional Specification Document (FSD) describes the technical


requirements for the supply and installation of Antenna Tower to support
the Mobile Antenna System for the Wasit Gas Plant (WGP), under the
Wasit Gas Project (BI-10-00914) and NGL Fractionation Facilities (BI-10-
DESCRIPTION

00302).

The technical requirements for a Antenna Tower shall consist of:


Issued for Bid

‰ Foundations
‰ Structural

THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
‰ Mounting
10-00914-0001
JO/EWO NO.

‰ Electrical System
‰ Fence

1.2 Site and Ambient Conditions


DATE

05/27/10

The equipment is required to operate in an outdoor plant environment. The


project specific ambient conditions shall be based climatic condition of
REV
NO.

Khursaniyah as per SAES-A-112 Saudi Aramco metrological and seismic


0

DRAWN
data.
DATE
1.3 Industry Codes and Standards
CHECKED

BY
DATE The works should conform to the requirements of the latest issues and
most recent revisions of the Saudi Aramco and International Standards
DISCIPLINE
ENGINEER
and Procedures listed below.
DATE

PROJECT
SAES-A-112 Metrological and Seismic Design Data
ENGINEER SAES-B-068 Electrical Area Classification
DATE SAES-T-492 VHF/UHF Land-Mobile and Fixed Radio
SAES-T-744 Design Criteria / Installation of Communication
CERTIFIED
Towers
DATE SAES-T-795 Communications Facility Grounding System
CONSTRUCTION SAES-T-887 Telecommunications: Electrical Coordination -
AGENCY
Protection at Power Plants and Radio Stations
DATE SAES-P-111 Grounding
OPERATIONS
SAES-O-100 General Requirements Safety and Security
SAES-O-101 Standard Security Fence – Category 1
DATE

WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED SU&O
FOR
CONSTRUCTION Q75 T PP-418245 3
UNTIL CERTIFIED of 0
AND DATED. 9
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT

SAES-Q-001 Construction of Concrete Structures


CERT

ZHK

SAES-Q-005 Concrete Foundations


SAES-Q-010 Cement Based, Non-Shrink Grout for
ENG’G

Structural and Equipment Grouting


RJV

SAES-Q-012 Criteria for Design and Construction of Precast


and Prestressed Concrete Structures
SAES-M-001 Structural Design Criteria for non-Building
Structures
SAES-M-006 Saudi Aramco Security and General Purpose
DESCRIPTION

Fencing
SAES-H-100 Coating Materials & Application Requirements
for Industrial Facilities
Issued for Bid

SAES-H-101 Approved Protective Coating Systems for


Industrial Plants & Equipment

THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
ANSI/NFPA-70 National Electrical Code
ETSI TETRA TErrestrial Trunked RAdio
ETSI 300392-2 Air Interface Standard
10-00914-0001
JO/EWO NO.

EIA/TIA 222 Structural Standard for Antenna – Supporting


Structures and Antennas
EIA/TIA 329-B Minimum Standards for Base Station
Antennas
EIA/TIA 329-B-1 Minimum Standards for Vehicular Antennas
DATE

05/27/10

EIA/TIA 603 Land Mobile FM or PM Communications –


Equipment Measurement and Performance
REV
NO.

Standards
0

DRAWN
ITU-T G Transmission Systems and Media, Digital
DATE
Systems and Networks
CHECKED
1.4 Related Drawings
BY
DATE
The following documents and drawings are referenced in this FSD and
DISCIPLINE
ENGINEER
form part of the specification.
DATE
Q76-T-PP-118324 Mobile Radio System Functional Specification
PROJECT
ENGINEER
Q76-T-PP-118035 Mobile Radio System Block Diagram
Q76-T-PP-118040 Communications Grounding Block Diagram
DATE

CERTIFIED 2.0 OPERATING PHILOSOPHY


DATE
The Antenna Tower and foundations is to be installed adjacent to the
CONSTRUCTION
AGENCY Administration Building. The Administration Building and Antenna tower will
DATE
provide a reliable operating environment for communications equipment
and antennas installed at the facility.
OPERATIONS

DATE

WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED SU&O
FOR
CONSTRUCTION Q75 T PP-418245 4
UNTIL CERTIFIED of 0
AND DATED. 9
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT

According to a preliminary Propagation analysis, the required tower height


CERT

ZHK

should be around 30 m in order to cover the desired area. The Radio


Contractor shall supply a complete Radio propagation analysis and also, is
ENG’G

responsible to confirm the height of the tower.


RJV

3.0 TECHNICAL REQUIREMENTS


3.1 Foundations
DESCRIPTION

Foundations design shall be done by the Contractor, foundations and


concrete shall comply with 09-SAMSS-097, SAES-Q-001 and SAES-Q-
005. Contractor shall provide the tower structure loading data, including,
Issued for Bid

but not limited to the following:


‰ Maximum Vertical Force (downward)

THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
‰ Maximum Horizontal Force
‰ Maximum Upward Force (upward)
10-00914-0001
JO/EWO NO.

‰ Dead Load, Live Load, and the Wind Load for above parameters.
Loading Capacity of the tower shall be calculated for the known loading to
be on the tower for its commissioning plus any additional loading expected
to occur within one year after commissioning as per SAES-A-112. Ice
DATE

05/27/10

loading shall not be considered in the tower loading calculations. TSTower


Program (latest Version) shall be used for Tower load Analysis.
REV
NO.

DRAWN 3.2 Structural


DATE

CHECKED
The Antenna Antenna Tower structure is required to be self-supported and
BY
free-standing type. And the material shall be made of steel according to
DATE Saudi Aramco Standard (SAES-T-744).
DISCIPLINE
ENGINEER The Tower structure size, height and locations are selected to provide
DATE
adequate coverage of the site.
PROJECT
ENGINEER The basic wind speed for the location of the tower shall be determined and
DATE
considered from SAES-A-112 and according to EIA /TIA-222-G. 60 miles
per hour shall be the operational wind speed requirements for tower
CERTIFIED structures in Saudi Arabia.
DATE

Cable ladder is required to support power and communication cables going


CONSTRUCTION
AGENCY up the tower.
DATE

OPERATIONS

DATE

WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED SU&O
FOR
CONSTRUCTION Q75 T PP-418245 5
UNTIL CERTIFIED of 0
AND DATED. 9
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT

3.3 Antennas and Mounting


CERT

ZHK

The maximum permissible twist and tilt angle for tower installed antennas
ENG’G

are + 0.5 degrees. Ensure antennas and microwave dish mounting


RJV

brackets comply with the above parameters.

3.4 Electrical System

The Tower Electrical system shall include the following:


DESCRIPTION

‰ Tower lighting including obstacle lights for aircraft safety to meet Saudi
Arabia Government regulations. Lighting of the tower shall comply with
SAES-B-063.
Issued for Bid

‰ Earthing system for the tower, lighting, and transmission lines


components to prevent active electronic equipment against electrical

THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
surges. The tower ground ring shall be bonded:
zTo the grounding plate twice (if one exists)
10-00914-0001
JO/EWO NO.

z To each tower leg


z To the ground rods
z To the building outside ground ring
Grounding system shall be implemented according to SAES-T-887 and
DATE

05/27/10

Standard Drawing AA-036391. The outer ground ring shall be composed a


minimum of #2 AWG (35 mm²) solid tinned copper wire and shall be buried
REV
NO.

not less than 0.8 m (2.5 feet) below grade level and at least 0.6 m (2 feet)
0

DRAWN
outside foundation and tower footings
DATE ‰ Tower lighting protection rod of sufficient length to provide a 45
CHECKED degrees cone of protection to the lower structure including antennas.
BY Also, ensure antennas are insulated and isolated such that operating
DATE
personnel are protected from potential hazards.
DISCIPLINE
ENGINEER
‰ Cable support system to support transmission lines.
DATE
3.5 Fence
PROJECT
ENGINEER
A perimeter fence (20m x 30m) for the tower shall be provided and shall
DATE
meet the requirement for Category I, Security Perimeter Fencing for Saudi
CERTIFIED Aramco's vital industrial facilities and Safety and Security Directive No. 1
DATE
(SSD/1) of the Saudi Arabian Government Supreme Commission for
Industrial Security.
CONSTRUCTION
AGENCY

DATE

OPERATIONS

DATE

WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED SU&O
FOR
CONSTRUCTION Q75 T PP-418245 6
UNTIL CERTIFIED of 0
AND DATED. 9
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT

3.6 Description Overview


CERT

ZHK

3.6.1 Painting
ENG’G

RJV

Quality paint and materials shall be selected to provide extra years of


service. The paint shall be compatible with the surfaces to be painted,
including any previous coatings, and suitable for the environmental
conditions. Painting and protective coatings for steel structures of the
towers shall be in comply with SAES-H-100 and SAES-H-101.
DESCRIPTION

3.6.2 Design Life


Issued for Bid

The Antenna tower and antenna should have a minimum design life of
twenty (20) years. To eliminate corrosion, all anchor rods shall be fusion
bonded epoxy coated. The coating shall be 500 to 625 micrometers (20 to

THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
25 mils) dry film thickness.
10-00914-0001
JO/EWO NO.

3.7 Safety and Security Requirement

Saudi Aramco places a very high onus upon all of its employees and its
contractors and their staff to conduct their business with safety and
security as paramount considerations.
DATE

05/27/10

Ensure safety rail for climbing and maintenance operations, complete with
climbing harness are included.
REV
NO.

DRAWN The equipment supplied shall operate without creating a hazard to the user
DATE directly and/or other third parties.
CHECKED

BY Provide all necessary safety guards around all moving equipment parts to
DATE
protect operating personnel from injury.
DISCIPLINE
ENGINEER Hazard warning labels shall be affixed to the equipment to advise of any
DATE feature of the equipment that may cause potential injury to the user or
PROJECT
maintenance personnel.
ENGINEER

DATE Maintenance manuals and other documentation must highlight any


CERTIFIED
potential dangers that may be encountered during the servicing or repair of
the equipment.
DATE

CONSTRUCTION Contractor shall perform all activities in accordance with Saudi Aramco
AGENCY
safe working procedures.
DATE

OPERATIONS

DATE

WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED SU&O
FOR
CONSTRUCTION Q75 T PP-418245 7
UNTIL CERTIFIED of 0
AND DATED. 9
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT

Contractors shall fully comply with the statutory requirements of the Saudi
CERT

ZHK

Arabian Government Supreme Commission for Industrial Security, Safety


and Security Directives pertaining to communications sites.
ENG’G

RJV

Contractor staff shall obtain clearance to gain entry to all sites and carry
suitable identification at all times.

Many of the Saudi Aramco communications systems are regarded as


critical. Contractor shall take all precautions to avoid disruption to traffic.
DESCRIPTION

4.0 INSPECTION
Issued for Bid

4.1 Mechanical Completion Certificate (MCC)

Mechanical completion is the acceptance that the physical installation

THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
conforms to Saudi Aramco standards, and that all required equipment has
been provided and is plant tagged.
10-00914-0001
JO/EWO NO.

Saudi Aramco inspection shall take place in the presence of Contractor.


The inspector shall prepare an exception list, detailing all violations of the
standards.

Failure to identify any error or omission during inspections made in the


DATE

05/27/10

installation phase, shall not relieve the Contractor of any of the


specification requirements.
REV
NO.

DRAWN
Once the “Yes” exception list is cleared, the Mechanical Completion
DATE
Certificate can be issued and the Commissioning can proceed to the Site
CHECKED
Acceptance Test.
BY
DATE The Antenna system MCC shall be considered complete only when the
SAT approval has been signed-off by a Saudi Aramco representative.
DISCIPLINE
ENGINEER

DATE
5.0 DOCUMENTATION
PROJECT
ENGINEER
As a minimum, the following documents and drawings shall be provided for
DATE
SLI review:
CERTIFIED
‰ Equipment lists indicating manufacturer, type, part numbers, tag
DATE
numbers
CONSTRUCTION
AGENCY ‰ Installation details
DATE Contractor shall submit a complete set of manufacturer books, in electronic
OPERATIONS and hardcopy, in the quantities and formats specified in purchase order
document list.
DATE

WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED SU&O
FOR
CONSTRUCTION Q75 T PP-418245 8
UNTIL CERTIFIED of 0
AND DATED. 9
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT

5.1 Drawings
CERT

ZHK

Complete drawing packages shall be provided. Information contained in


ENG’G

these drawings will be used to update purchaser's drawings.


RJV

5.2 Installation Drawings

Installation drawing details shall be provided.


DESCRIPTION

5.3 As-Built Drawings

Red-lined drawings shall be provided during construction and as-built


drawings shall be submitted prior to project completion.
Issued for Bid

THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
10-00914-0001
JO/EWO NO.
DATE

05/27/10
REV
NO.

DRAWN

DATE

CHECKED

BY
DATE

DISCIPLINE
ENGINEER

DATE

PROJECT
ENGINEER

DATE

CERTIFIED

DATE

CONSTRUCTION
AGENCY

DATE

OPERATIONS

DATE

WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED SU&O
FOR
CONSTRUCTION Q75 T PP-418245 9
UNTIL CERTIFIED of 0
AND DATED. 9
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914-0001