FSD - Mobile Radio System
FSD - Mobile Radio System
FSD - Mobile Radio System
TABLE OF CONTENTS
ZHK
ENG’G
RJV
1.0 GENERAL............................................................................................................... 4
1.1 Scope ...................................................................................................................... 4
1.2 Site and Ambient Conditions................................................................................... 5
1.3 Industry Codes and Standards................................................................................ 5
1.4 Related Drawings.................................................................................................... 5
DESCRIPTION
THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
2.2.4 Dispatcher Consoles ............................................................................................... 7
10-00914/302-0001
05/27/10
3.7.1 Transceivers.......................................................................................................... 10
0
DRAWN
3.7.2 Base Station Controller ......................................................................................... 11
DATE 3.7.3 RF Distribution System ......................................................................................... 12
CHECKED 3.8 Dispatcher Console............................................................................................... 15
BY
DATE
3.9 Logging Recorder.................................................................................................. 16
3.10 Radio Specifications.............................................................................................. 16
3.10.1 Fixed Desktop Radios ........................................................................................... 17
DISCIPLINE
ENGINEER 3.10.2 Vehicle-Mounted Mobile Radios ........................................................................... 18
DATE
3.10.3 Hand-held Radios ................................................................................................. 19
3.11 System Monitoring ................................................................................................ 20
PROJECT
ENGINEER
4.0 INSTALLATION .................................................................................................... 20
DATE
4.1 General.................................................................................................................. 20
4.2 Safety and Security Requirement ......................................................................... 22
CERTIFIED 4.3 Material Included................................................................................................... 22
DATE 4.4 Plant Tagging ........................................................................................................ 23
5.0 INSPECTION AND TESTING............................................................................... 23
CONSTRUCTION
AGENCY 5.1 General.................................................................................................................. 23
DATE 5.2 QA/QC Requirements ........................................................................................... 24
5.3 Commissioning...................................................................................................... 25
OPERATIONS
5.4 Factory Acceptance Testing (FAT) ....................................................................... 25
DATE
WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED All Program
FOR
CONSTRUCTION Q76 T PP-118324 2
0
UNTIL CERTIFIED of
AND DATED.
29
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914/302-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT
ZHK
RJV
THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
10-00914/302-0001
JO/EWO NO.
DATE
05/27/10
REV
NO.
DRAWN
DATE
CHECKED
BY
DATE
DISCIPLINE
ENGINEER
DATE
PROJECT
ENGINEER
DATE
CERTIFIED
DATE
CONSTRUCTION
AGENCY
DATE
OPERATIONS
DATE
WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED All Program
FOR
CONSTRUCTION Q76 T PP-118324 3
0
UNTIL CERTIFIED of
AND DATED.
29
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914/302-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT
1.0 GENERAL
CERT
ZHK
1.1 Scope
ENG’G
RJV
THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
Base Station controller and transceivers
10-00914/302-0001
JO/EWO NO.
05/27/10
12 desktop radios: 6 for CCR consoles, 1 for DCC console, 1 for Fire
0
DRAWN
Station console, 1 for the Sulphur Loading Monitoring Building console,
DATE
1 for the Main Gatehouse, 1 for the Computer Gatehouse, and 1 for the
CHECKED
Sulphur Loading Area Gatehouse
BY
DATE
2 dispatcher console radios: 1 for the CCR, and 1 for the DCC
36 RF signal enhancers. Refer to Section 3.7.3.2 for a full list of
DISCIPLINE
ENGINEER buildings with signal enhancers
DATE
Ethernet LAN switches and media converters, as required
PROJECT
ENGINEER System will allow for interconnection to Saudi Aramco VoIP, PABX, or
DATE
PSTN exchange.
CERTIFIED
The base station will be open, scalable, and modular to accommodate
additional capacity requirements.
DATE
CONSTRUCTION
AGENCY
DATE
OPERATIONS
DATE
WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED All Program
FOR
CONSTRUCTION Q76 T PP-118324 4
0
UNTIL CERTIFIED of
AND DATED. 29
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914/302-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT
ZHK
data.
The works should conform to the requirements of the latest issues and
DESCRIPTION
THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
SAES-P-103 UPS and DC System
SAES-P-104 Wiring Methods and Materials
10-00914/302-0001
JO/EWO NO.
SAES-P-111 Grounding
SAES-T-481 Powered in-plant Communications
SAES-T-492 VHF/UHF Land-Mobile and Fixed Radio
SAES-T-744 Installation of Communication Towers
SAES-T-795 Communications Facility Grounding System
DATE
05/27/10
CERTIFIED
The following documents and drawings are referenced in this FSD and
form part of the specification.
DATE
CONSTRUCTION
AGENCY
Q76-T-PP-118327 Radio Tower Functional Specification
Q76-T-PP-118035 Mobile Radio System Block Diagram
DATE
OPERATIONS
DATE
WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED All Program
FOR
CONSTRUCTION Q76 T PP-118324 5
0
UNTIL CERTIFIED of
AND DATED. 29
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914/302-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT
ZHK
RJV
THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
End users shall have the ability to dial into the Saudi Aramco telephone
system as well as accessing the public telephone network to make phone
10-00914/302-0001
JO/EWO NO.
System shall be compatible and shall interface with the existing Saudi
Aramco TETRA infrastructure per BI-10-00112. It shall follow the standard
practices of similar facilities. The Base Station at Wasit shall be connected
DATE
05/27/10
DRAWN
DATE
2.2.1 Base Station
CHECKED
The base station shall be capable to provide radio users within and around
BY
DATE the project facilities with required access to the TETRA network in Eastern
Province.
DISCIPLINE
ENGINEER Contractor shall provide the Base Station equipment and racks including
DATE Controller, Transceivers, RF Distribution System, and Ethernet LAN Switch
PROJECT
at the Administration Building Main Telecommunications Equipment Room
ENGINEER (MTER). Base Station Controller shall be switch based and IP-capable for
DATE the interface with Ras Tanura SCN and dispatcher consoles.
CERTIFIED
2.2.2 Switching and Control Node (SCN)
DATE
CONSTRUCTION
SCN provides vital network functions including digital switching, resource
AGENCY management, trunking, speech item allocation, signaling services, data
DATE services, statistics, call control functions, and interface to other Base
OPERATIONS
Station SCNs, dispatcher consoles, Network Management System
DATE
WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED All Program
FOR
CONSTRUCTION Q76 T PP-118324 6
0
UNTIL CERTIFIED of
AND DATED. 29
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914/302-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT
ZHK
The Base Station under the Wasit Project shall be interfaced to the TETRA
ENG’G
RJV
The entire fleet shall be divided into different talk-groups. Users assigned a
Issued for Bid
THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
groups at a time. Users will access the system via RF communications
with the Base Station. Indoor users in all PIBs, Substations, and manned
10-00914/302-0001
buildings will have the TETRA coverage via RF signal enhancers installed
JO/EWO NO.
Contractor shall submit the Wasit Talk-group Plan for reservation to BI-10-
00112 to reserve.
DATE
05/27/10
DRAWN
2.2.4 Dispatcher Consoles
DATE
CHECKED
Dispatchers have access to advanced features and functions of the
BY
DATE trunked radio system. Dispatchers can manage fleets and maintain the
system. Operators will be able to assign, change, or delete user or group
aliases over the air.
DISCIPLINE
ENGINEER
DATE Radio System Contractor shall provide and install two switch-based, IP
capable Dispatcher Consoles. One Console shall be installed in the
PROJECT
ENGINEER Central Control Room (CCR). The other Console shall be installed in the
DATE Disaster Control Center (DCC) of the Administration Building.
Communications between the CCR and DCC shall utilize the Outside Plant
CERTIFIED
Fiber Optic, IP-based network between the two facilities.
DATE
CONSTRUCTION
AGENCY
DATE
OPERATIONS
DATE
WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED All Program
FOR
CONSTRUCTION Q76 T PP-118324 7
0
UNTIL CERTIFIED of
AND DATED. 29
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914/302-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT
ZHK
RJV
Operational areas within and around the Wasit Gas Plant and key facilities
shall have radio coverage 95% of the time and 95% of locations. The
minimum received signal level required shall meet Mean Opinion Score
(MOS) of 3.5 as per Perceptual Evaluation of Speech Quality (PESQ)
Issued for Bid
THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
Propagation analysis shall determine the required tower height, transmit
10-00914/302-0001
Radios. Contractor shall use the latest Mentum Planet software for the
propagation analysis. Contractor shall also supply the latest Mentum
Planet software, with a 30m digital terrain resolution (image, vector, clutter
files) for the kingdom wide area, to the Saudi Aramco Engineering
DATE
coverage analysis showed that a 30m tower is required to cover the Wasit
Gas Plant perimeter and surroundings. Contractor shall confirm this
REV
NO.
DRAWN
requirement during the detailed design phase of the project.
DATE
CHECKED
Contractor shall undertake co-channel, adjacent channel interference
BY
analysis. Contractor shall request from BI-10-00112 the coverage analysis
DATE and frequency plan of the Northern Area for the Contractor to consider in
the interference/coverage analysis.
DISCIPLINE
ENGINEER
As an option, Contractor may hire the same radio consultant used by BI-
DATE
10-00112 to conduct the coverage and interference analysis.
PROJECT
ENGINEER
A field analysis shall be conducted to verify the theoretical studies. At
DATE minimum, field analysis shall measure the Received Signal Strength
CERTIFIED
Indications (dBm) and the Voice Quality within the Wasit Gas Plant
Perimeter and the area up to the downstream pipeline to verify the tower
DATE
height requirements prior to system installation.
CONSTRUCTION
AGENCY
DATE
OPERATIONS
DATE
WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED All Program
FOR
CONSTRUCTION Q76 T PP-118324 8
0
UNTIL CERTIFIED of
AND DATED. 29
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914/302-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT
ZHK
Contractor shall perform the required analysis to derive the user profile
such as call types, duration, and call rates to incorporate the effect of
additional users and traffic channels. The following shall be identified:
Issued for Bid
The total traffic load the system can support with the available traffic
channels
THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
The maximum number of users that can be served given the available
10-00914/302-0001
traffic channels.
JO/EWO NO.
05/27/10
System shall operate in the UHF band in the 410-430 MHz range with 25
kHz channel bandwidth subject to local government authority’s final
REV
NO.
approval.
0
DRAWN
DATE
Contractor shall submit the Wasit frequency plan and requirements to BI-
CHECKED
10-00112 based on the Coverage/Interference Analysis.
BY
DATE
3.5 Telephone Interconnects
DISCIPLINE
ENGINEER System shall include optional feature for radio users providing capability of
DATE dialing into the Saudi Aramco Telephone System and PSTN telephone
network to make phone calls. A radio user with the proper authorization
PROJECT
ENGINEER may call a Saudi Aramco Telephone system extension or PSTN number
DATE via the site telephone system by dialing pre-assigned access codes.
Radio users are capable of receiving calls from any Telephone system
CERTIFIED
extension or PSTN telephone. Radio shall be able to display incoming and
DATE out-going phone numbers.
CONSTRUCTION
AGENCY Telephone network interface at Ras Tanura SCN will be provided under
DATE BI-10-00112. Contractor shall determine the number of users with access
OPERATIONS
to the PSTN via the TETRA network and submit a plan.
DATE
WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED All Program
FOR
CONSTRUCTION Q76 T PP-118324 9
0
UNTIL CERTIFIED of
AND DATED. 29
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914/302-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT
ZHK
RJV
Tanura SCN shall be able to perform on the Wasit TETRA network the
following functions:
Define groups and sub groups
Control how the network works
DESCRIPTION
THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
Signaling over the air shall be compliant with ETSI 300392-2. System shall
10-00914/302-0001
The Base Station shall be installed inside the MTER. All equipment will be
housed inside standard 19”/23” rack mountable cabinets. All Base Station
modules shall be equipped with front panel LED displays indicating their
operating status.
DATE
05/27/10
DATE
WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED All Program
FOR
CONSTRUCTION Q76 T PP-118324 10
0
UNTIL CERTIFIED of
AND DATED. 29
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914/302-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT
ZHK
RJV
THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
Receiver Dynamic Sensitivity: -109 dBm (4% BER) or better
10-00914/302-0001
JO/EWO NO.
05/27/10
DRAWN TETRA system at the Wasit Gas Plant. It controls the local radio traffic as
DATE well as all in-bound/outbound communications to other Base Stations.
CHECKED
DATE
Ethernet 10/100 Mbit Interfaces, RJ 45 Connectors
CERTIFIED
Four E1 interfaces 75/120 ohm
DATE Operations and Maintenance interface via RS232 or TCP/IP
CONSTRUCTION Automatic switch over to a redundant Controller at failure
AGENCY
DATE
If during the time of construction, the SCN or the Controller is not yet IP
capable, the Contractor shall provide Ethernet to E1 converters to
OPERATIONS
interconnect the Wasit Gas Plant Base Station and Ras Tanura SCN.
DATE
WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED All Program
FOR
CONSTRUCTION Q76 T PP-118324 11
0
UNTIL CERTIFIED of
AND DATED. 29
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914/302-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT
ZHK
RJV
The antenna system includes, but not limited to, the following components:
Antennas
Issued for Bid
THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
10-00914/302-0001
05/27/10
DRAWN
DATE
Max Power Input: 300 Watts
CHECKED VSWR: Less than 1.5:1 @ 50 ohms
BY
DATE Minimum Stand-Off: ¼ Wavelength
Lightning Protection: Direct ground protection to radio tower
DISCIPLINE
ENGINEER Connector Input: Type N-male connector on antenna
DATE base
PROJECT Polarization: Vertical
ENGINEER
DATE
WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED All Program
FOR
CONSTRUCTION Q76 T PP-118324 12
0
UNTIL CERTIFIED of
AND DATED. 29
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914/302-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT
ZHK
RJV
400MHz
Maximum permissible twist and tilt angle for tower installed antennae will
be ± 0.5°. Ensure antennae mounting brackets comply with these
parameters.
DESCRIPTION
THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
Receiver multi-coupler with pre-selector filter, expandable
Adjacent channel separation: ≤ 180 kHz
10-00914/302-0001
JO/EWO NO.
05/27/10
components:
Indoor antennas, ceiling mounted, as required
REV
NO.
DRAWN
Outdoor antennas mounted on a pole on top of the buildings
DATE
CHECKED
Transmission coaxial cables (Refer to Sec. 3.6.5.1)
BY Signal enhancer
DATE
DATE
WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED All Program
FOR
CONSTRUCTION Q76 T PP-118324 13
0
UNTIL CERTIFIED of
AND DATED. 29
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914/302-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT
ZHK
RJV
Building
# Building #
THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
6 Maintenance Service Building 1 470
7 Maintenance Service Building-2 469
10-00914/302-0001
JO/EWO NO.
05/27/10
DATE
WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED All Program
FOR
CONSTRUCTION Q76 T PP-118324 14
0
UNTIL CERTIFIED of
AND DATED. 29
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914/302-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT
Building
CERT
# Building #
ZHK
ENG’G
THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
technology or equivalent shall be installed: one in the Control Room and
one in the Disaster Control Center. Dedicated dispatch personnel will be
10-00914/302-0001
JO/EWO NO.
05/27/10
Keyboard, Mouse
Table Microphone
REV
NO.
BY External Speaker
DATE
Headset
DISCIPLINE Smart Card Reader Access
ENGINEER
DATE
Ethernet 10/100 Mbit Interface, RJ 45 Connector
CERTIFIED
4 USB 2.0 ports, 9 pin serial, parallel ports
DATE One Gigabyte RAM
CONSTRUCTION 250 Gigabyte Internal Hard Drive, 7200 RPM
AGENCY
DATE
CD-RW/DVD Combo Drive
OPERATIONS
DATE
WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED All Program
FOR
CONSTRUCTION Q76 T PP-118324 15
0
UNTIL CERTIFIED of
AND DATED. 29
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914/302-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT
ZHK
Place and receive individual and group calls in voice and data
communication modes
ENG’G
RJV
Create, modify, and delete radio subscribers and groups; modify their
call rights and attributes
Create and modify network parameters
Display activity log windows (on the monitor) for every call activity.
Display the corresponding talk-group, radio aliases, call type, and time
DESCRIPTION
of day
Setup a minimum of 10 connections involving PSTN users in a non-
Issued for Bid
blocking configuration
Call other Dispatcher Console operators
THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
Access conventional external networks
10-00914/302-0001
Track and identify status of all users whenever they log-onto the
system and display a time-stamp
Contractor shall provide the required Ethernet Switches or equivalent
hardware for Controller to Console fiber optic communications between the
DATE
05/27/10
DRAWN
DATE A digital logging recorder will be provided at Ras Tanura SCN by BI-10-
CHECKED 00112.
BY
DATE
Contractor shall upgrade the logging recorder and provide licenses as
required to accommodate the Wasit Gas Plant traffic requirements.
DISCIPLINE
ENGINEER
DATE
3.10 Radio Specifications
DATE
Conventional Operation
CERTIFIED Repeater Talk Around
DATE Operator Emergency/Alert
CONSTRUCTION
AGENCY
Individual Call
DATE Group Call
OPERATIONS Call to public network and emergency
DATE
WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED All Program
FOR
CONSTRUCTION Q76 T PP-118324 16
0
UNTIL CERTIFIED of
AND DATED. 29
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914/302-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT
ZHK
RJV
The fixed desktop radios shall have the following minimum features:
DESCRIPTION
THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
Channel Bandwidth 25 kHz
Frequency Stability ±0.0002%
10-00914/302-0001
JO/EWO NO.
05/27/10
DRAWN
DATE
Coax Cable, flexible, 12.5 mm (1/2”) low loss foam dielectric (50 ohm),
N-type connectors complete with hanging hardware
CHECKED
DATE
Detachable Microphone with coil cord
CERTIFIED
Tone Coded Squelch (Programmable)
DATE Temperature Range Operation -20°C to +55°C
CONSTRUCTION Storage -30°C to +70°C
AGENCY
DATE
Relative Humidity 10% to 95% at 50°C, non-condensing
OPERATIONS
DATE
WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED All Program
FOR
CONSTRUCTION Q76 T PP-118324 17
0
UNTIL CERTIFIED of
AND DATED. 29
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914/302-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT
ZHK
THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
Channel Spacing 25 kHz
Channel Bandwidth 25 kHz
10-00914/302-0001
JO/EWO NO.
05/27/10
DRAWN
DATE
Receiver Dynamic Sensitivity -103 dBm (4% BER)
CHECKED Radio Mounting Dash or Trunk Mounted
BY
DATE Antenna Vehicle Mounted for optimum radio
signal
DISCIPLINE
ENGINEER
Antenna Gain 5 dBi minimum
DATE Coax Cable, 3 m long flexible, 12.5 mm (1/2”) low loss foam dielectric
PROJECT
(50 ohm), N-type connectors complete with hanging hardware
ENGINEER
Channel Scan Capable
DATE
Alphanumeric Display
CERTIFIED
DATE
DTMF Keypad (back-lit)
CONSTRUCTION
External Speaker 7 Watt
AGENCY
Audio Distortion < 5%
DATE
Detachable Noise Cancelling Microphone with coil cord, push-to-talk
OPERATIONS
button
DATE
WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED All Program
FOR
CONSTRUCTION Q76 T PP-118324 18
0
UNTIL CERTIFIED of
AND DATED. 29
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914/302-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT
ZHK
RJV
the current operating mode and an indication of low battery voltage. All
portable hand-helds are intrinsically safe radios and have heavy-duty
THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
batteries.
10-00914/302-0001
05/27/10
DRAWN
Frequency Stability ±0.0002%
DATE Modulation π/4 DQPSK
CHECKED
Transmit Power Minimum of 0.6 Watt with adaptive
BY
DATE power control of 3 steps of 5dB
Receiver Static Sensitivity -112 dBm (4% BER)
DISCIPLINE
ENGINEER Receiver Dynamic Sensitivity -103 dBm (4% BER)
DATE
Antenna High Gain Helical Type
PROJECT
ENGINEER One Battery Spare per radio
DATE
Battery Capacity ≥ 900mAh with 10/10/80 duty cycle for
CERTIFIED 8 hours of continual use
DATE Single rapid battery charger 110 – 220 VAC, 50-60 Hz with US type
CONSTRUCTION
plugs, 220 VAC European adapters in
AGENCY limited quantities
DATE
Charging time < 2.5 hrs
OPERATIONS
Channel Scan Capable
DATE
WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED All Program
FOR
CONSTRUCTION Q76 T PP-118324 19
0
UNTIL CERTIFIED of
AND DATED. 29
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914/302-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT
Alphanumeric Display
CERT
ZHK
RJV
THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
Storage: -30°C to +70°C
10-00914/302-0001
DRAWN Procedure I
DATE
Compact, rugged, and lightweight
CHECKED
DATE
Radio System is to provide a monitoring feature of all system equipment
PROJECT status.
ENGINEER
DATE
4.0 INSTALLATION
CERTIFIED
DATE
4.1 General
CONSTRUCTION
AGENCY
Contractor shall install all equipment required by this specification to
produce a fully functioning system ready for handover to Saudi Aramco.
DATE
OPERATIONS
DATE
WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED All Program
FOR
CONSTRUCTION Q76 T PP-118324 20
0
UNTIL CERTIFIED of
AND DATED. 29
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914/302-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT
Fully trained personnel who are familiar with the systems, equipment and
installation techniques, shall carry out the installation.
CERT
ZHK
RJV
Modular design
THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
Internal or self-diagnostics for component failures
Maintainable on a unit basis without affecting the ongoing operation of
10-00914/302-0001
JO/EWO NO.
05/27/10
DRAWN
shall be secured with tamper proof fasteners.
DATE
CHECKED
Contractor shall verify the mounting locations with Saudi Aramco prior to
BY
DATE installation. Contractor shall notify Saudi Aramco if a particular location is
not suitable for the application.
DISCIPLINE
ENGINEER Contractor shall label each wire and cable on each end indicating the wire
DATE designation that appears in the System Design Manual and/or wiring and
cabling schedule. The labeling shall be identical in nomenclature and all
PROJECT
ENGINEER labels shall be typed and covered with transparent heat-shrinkable tubing.
DATE
Contractor shall neatly arrange all cable on cable ladder rack, cable tray,
CERTIFIED
or supports and prevent twisting and unnecessary crossover of cables. All
DATE signal cables and wiring shall be secured with lace twine or, in isolated
CONSTRUCTION
cases, tie wraps.
AGENCY
DATE Where necessary, the installation shall include the integration of the
OPERATIONS
equipment being supplied into an existing system.
DATE
WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED All Program
FOR
CONSTRUCTION Q76 T PP-118324 21
0
UNTIL CERTIFIED of
AND DATED. 29
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914/302-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT
ZHK
RJV
Saudi Aramco places a very high onus upon all of its employees and its
contractors and their staff to conduct their business with safety and
DESCRIPTION
Ensure safety rail for climbing and maintenance operations, complete with
Issued for Bid
THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
The equipment supplied shall operate without creating a hazard to the user
directly and/or other third parties.
10-00914/302-0001
JO/EWO NO.
05/27/10
DRAWN
DATE
Contractor shall perform all activities in accordance with Saudi Aramco
safe working procedures.
CHECKED
BY
DATE Contractors shall fully comply with the statutory requirements of the Saudi
Arabian Government Supreme Commission for Industrial Security, Safety
DISCIPLINE
and Security Directives pertaining to communications sites.
ENGINEER
DATE Contractor staff shall obtain clearance to gain entry to all sites and carry
PROJECT
suitable identification at all times.
ENGINEER
DATE
4.3 Material Included
CONSTRUCTION
AGENCY Contractor shall provide all necessary equipment and installation materials
DATE necessary for a fully functioning system. This may include, but is not
OPERATIONS
limited to the following items:
DATE
WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED All Program
FOR
CONSTRUCTION Q76 T PP-118324 22
0
UNTIL CERTIFIED of
AND DATED. 29
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914/302-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT
ZHK
RJV
THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
of the equipment to it, or connection to an existing system
10-00914/302-0001
JO/EWO NO.
05/27/10
DRAWN Verification of cable marking shall be carried out as part of the Mechanical
DATE Completion inspection.
CHECKED
BY
DATE
5.0 INSPECTION AND TESTING
5.1 General
DISCIPLINE
ENGINEER
DATE
Contractor shall develop a system test plan, test schedule, and test
procedures for each of the following test activities.
PROJECT
ENGINEER
Contractor shall be responsible for ensuring conformance to
DATE
specification(s) and standards. Completion of inspections shall not relieve
CERTIFIED Contractor of the ultimate responsibility for equipment conformance.
DATE Inspection and testing requirements shall be in accordance with all
relevant Saudi Aramco inspection requirements and the applicable
CONSTRUCTION
AGENCY specifications, to the relevant sections of this specification and the data
DATE
sheets.
OPERATIONS
DATE
WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED All Program
FOR
CONSTRUCTION Q76 T PP-118324 23
0
UNTIL CERTIFIED of
AND DATED. 29
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914/302-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT
ZHK
RJV
THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
standards herein and specifications
10-00914/302-0001
Test and inspection plans produced by, and as part of, the Quality Plan
JO/EWO NO.
05/27/10
All spare parts shall be subject to the same inspection standards and full
material certification as the main Radio system order.
REV
NO.
DRAWN Contractor shall give a minimum of 30 working days notice prior to carrying
DATE out any tests on the equipment covered by this specification.
CHECKED
OPERATIONS
DATE
WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED All Program
FOR
CONSTRUCTION Q76 T PP-118324 24
0
UNTIL CERTIFIED of
AND DATED. 29
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914/302-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT
Contractor may use their standard format ITP, provided the content
includes (and references) the information and all requirements of the Saudi
CERT
ZHK
RJV
5.3 Commissioning
by Saudi Aramco.
THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
Any piece of equipment, device, or material shall be made available for
inspections or tests, as deemed necessary by Saudi Aramco. Use of the
10-00914/302-0001
05/27/10
DRAWN
DATE
supplied by an approved laboratory or manufacturer.
CHECKED
Contractor shall make available all necessary personnel required to carry
BY
DATE out the commissioning and acceptance testing.
DISCIPLINE
Installation, engineering, software and system personnel shall be available
ENGINEER on-site during any testing carried out under this section. Such personnel
DATE shall be familiar with the installation and function of the Radio TETRA
PROJECT
system, and shall undertake all tests as requested, in order to verify that
ENGINEER the Radio system components individually and as a whole, meet the
DATE specifications.
CERTIFIED
5.4 Factory Acceptance Testing (FAT)
DATE
CONSTRUCTION
Factory Acceptance Testing (FAT) shall demonstrate that the Radio
AGENCY system meets the functional and operational requirements established in
DATE this specification. FAT procedures shall be issued for Saudi Aramco
OPERATIONS
CE&TSD approval four (4) months prior to FAT.
DATE
WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED All Program
FOR
CONSTRUCTION Q76 T PP-118324 25
0
UNTIL CERTIFIED of
AND DATED. 29
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914/302-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT
ZHK
RJV
THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
5.5 Field Testing
10-00914/302-0001
JO/EWO NO.
05/27/10
DRAWN
System and equipment configuration
DATE
CHECKED
Parameters to test (shall conform to applicable ITU-G
BY
recommendations
DATE
Test conditions
DISCIPLINE List of required test equipment and materials
ENGINEER
DATE
Explanation and diagrams of the test set-up
PROJECT
Pass/fail criteria for each test
ENGINEER
Test record forms for each test
DATE
OPERATIONS
DATE
WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED All Program
FOR
CONSTRUCTION Q76 T PP-118324 26
0
UNTIL CERTIFIED of
AND DATED. 29
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914/302-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT
ZHK
RJV
following:
Voice and data communications between all radio devices and the
Wasit Gas Plant Base Station
Issued for Bid
Communications between any radio that falls inside the WASIT Gas
Plant coverage area (determined by the theoretical/field analysis) and
THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
any radio on the Saudi Aramco network including and not limited to the
Berri Gas Plant and Khursaniya Gas Plant
10-00914/302-0001
JO/EWO NO.
Group Calling
Emergency Calling
Conventional Mode Calling
Access to the Saudi Aramco PSTN by any radio user in the coverage
DATE
05/27/10
area
System control, configuration, management, and monitoring by a
REV
NO.
BY
DATE
5.7 Hardware Component Testing
CERTIFIED All COTS software shall be verified in-plant for proper function prior to
DATE shipment.
CONSTRUCTION
AGENCY Contractor shall provide documentation of software verification testing.
DATE
OPERATIONS
DATE
WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED All Program
FOR
CONSTRUCTION Q76 T PP-118324 27
0
UNTIL CERTIFIED of
AND DATED. 29
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914/302-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT
ZHK
conforms to Saudi Aramco standards, and that all required equipment has
RJV
specification requirements.
THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
Once the “Yes” exception list is cleared, the Mechanical Completion
Certificate can be issued and the Commissioning can proceed to the Site
10-00914/302-0001
Acceptance Test.
JO/EWO NO.
The Radio system MCC shall be considered complete only when the SAT
approval has been signed-off by a Saudi Aramco representative.
DATE
DRAWN
DATE
Contractor obligations (Material and Non-material) shall be considered
CHECKED
fulfilled only by means of the Performance Acceptance Test (PAT)
BY
DATE approval, signed-off by Saudi Aramco.
Contractor shall carry out the PAT in the presence of Saudi Aramco
DISCIPLINE
ENGINEER personnel, who will certify the acceptance of the system on a test-by-test
DATE basis.
PROJECT
ENGINEER Contractor shall guarantee performance of the supplied equipment in
DATE accordance with the requirements of the Radio system and Tower FSD. If
the required performance is not achieved, Contractor shall implement all
CERTIFIED
required modifications at his expense.
DATE
DATE As a minimum, the following documents and drawings shall be provided for
OPERATIONS
SLI review:
DATE
WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED All Program
FOR
CONSTRUCTION Q76 T PP-118324 28
0
UNTIL CERTIFIED of
AND DATED. 29
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914/302-0001
OPRNS SAUDI ARABIAN OIL COMPANY
WASIT GAS PROGRAM
PMT
ZHK
RJV
As a minimum, the books shall include the final revision of the above listed
documents.
THIS DRAWING AND THE INFORMATION HEREIN ARE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF THE OWNER
6.1 Drawings
10-00914/302-0001
JO/EWO NO.
DRAWN
RFE drawings shall be provided for each bay. All major components shall
DATE
be shown including module and part numbers.
CHECKED
BY
DATE 6.4 As-Built Drawings
OPERATIONS
DATE
WASIT GAS PROGRAM PLANT NO. INDEX DOCUMENT NO. SHT.NO. REV.NO.
THIS DOCUMENT IS
NOT TO BE USED All Program
FOR
CONSTRUCTION Q76 T PP-118324 29
0
UNTIL CERTIFIED of
AND DATED. 29
Wasit Gas Program SAUDI ARAMCO JO/EWO NO. 10-00914/302-0001