MINUTES OF MEETING HELD BETWEEN M/s APPSIL AND M/S

SPML INFRA LIMITED AT 220/132/33KV RATU SUBSTATION ON


22.10.2020
Sale order no:

Present Members:

APPSIL SPML

Mr. Soumya Swain, 1. Avijit Panja


2. Kameshwar ray
SAS Engineer.

M/s ABB Engineer Arrival date : 12/10/2020

M/s ABB Engineer Departure date : 22/10/2020

1. Status of Breaker, isolator (89A, 89B, 89C and 89D) and


earthswitch(89AE, 89CE1 and 89CE2 ) is checked and verified from
SCADA for all 220KV same has been witness by customer.
2. Remote operation of Breaker, isolator (89A, 89B, 89C and 89D) is
checked and verified from SCADA for all 220KV with interlock as per
the approved scheme. Same has been witness by customer.
3. Status of Breaker, isolator (89A, 89B, and 89D) and earthswitch
(89BE) is checked and verified from SCADA for all132KV. Same has
been witness by customer.
4. Remote operation of Breaker, isolator (89A, 89B, and 89D) is
checked and verified from SCADA for all132KV with interlock as per
the approved scheme. Same has been witness by customer.
5. Status of Breaker, isolator (89A, 89B, and 89D) and earthswitch
(89BE) is checked and verified from SCADA for all 33KV. Same has
been witness by customer.
6. Remote operation of Breaker is checked and verified from SCADA
for all 33 KV with interlock as per the approved scheme. Same has
been witness by customer.
7. Configured SERVER-1 with last final backup. Now it working fine,
same has been witness by customer.
8. New DC supervision relay is installed (S/N-194430152A). Front side
name plate is require.
9. New relay REF-615 (132KV TRF-4 BAY) is install and tested with
function LV REF OPTD. Same has been witness by customer. Details
of relay is mentioned below.

RELAY SERIAL RELAY REAR PORT


  NUMBER IP ADDRESS
1 1VYV91388568. 172.16.6.8

PENDING POINTS.

1. Both Inverter regulator is not working properly and the output voltage
is showing more than rated voltage (263V)
2. Voltmeter in (TBC-BAY) of 33kv side is not working properly.
3. MFM in (113-BAY) of 132kv and (202-BAY) of 220kv light is
contineously glowing.
4. Semapore lamp is indicating half for 89-B in 202-BAY.
5. Test report need to submitted for all line bay and LV-REF of 113-bay.
6. Aux system is not commissioned as still field wiring is not completed.

APPSIL SPML INFRA LIMITED