Burla 33KV Incomer Metering CT& PT Report

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 4

TEST REPORT OF 33KV INCOMER

FEEDER

AGILE ENGINEERING SERVICE


PROJECT : GANGADHAR MEHER LIFT IRRIGATION PROJECT
CLIENT : WATER RESOURCES DEPARTMENT,ODISHA
CUSTOMER: L&T CONSTRUCTION

1. Equipment Details : 33KV INCOMER FEEDER METERING CT SHEET NO – 1 OF 6


Make: PRAGATI ELECTRICAL Pvt. Ltd.
. Type: Wound Frequency- 50Hz
Ratio: 200-400/1A
ADOPTED RATIO: 400/1 A
A.CLASS :0.2S
BURDEN : 15VA
Year of mfg: 2022
2. Location & Feeder Name: 33 KV INCOMER METERING FEEDER CT.

3. General Inspection : OK

R PH Y PH B PH
SL NO 22/M-113602 22/M-113604 22/M-113603

4. Polarity Test:
(Using Equipment Details)

Make: OSWAL Sl. No. - AY0012

R ph Y ph B ph
CORE-1 Ok Ok Ok
CORE-2 Ok Ok Ok

5. Ratio Test:
(Using Equipment Details)
Make: MASTECH Range: 0-1000A Sl. No.- IN160802966
Make: KYORITSU Range: 3mA-100A Sl. No.- 8300571

APPLIED MEASURED CURRENT (SEC) Mamps


CERCUIT CT RATIO CURRENT(PRIMARY)
REF. IN AMPS R ph Y ph B ph

1S1-1S2 200/1 100AMP 499 mA 499 mA 499 mA

400/1 100AMP 250 Ma 253 mA 250 mA


1S1-1S3 200/1 100AMP 501 mA 500 mA 500 mA

400/1 100AMP 249 mA 249 mA 249 mA

Tested by: M/S POWER TECH Witnessed by- L&T CONSTRUCTION


Witnessed by-WAPCOS
Name : SITARAM PANDA Name: Name:

Designation :T&C ENG. Designation: Designation:


Signature Signature Signature
& Date : & Date : & Date :
TEST REPORT OF 33KV INCOMER
FEEDER

AGILE ENGINEERING SERVICE


PROJECT : GANGADHAR MEHER LIFT IRRIGATION PROJECT
CLIENT : WATER RESOURCES DEPARTMENT,ODISHA
CUSTOMER: L&T CONSTRUCTION

6. CORE RESISTANCE TEST : - ( in Ω)


(Using Equipment Details)

Make: FLUKE Range: 1000V Sl. No.3598/322WS


R ph Y ph B ph
1s1-1s2 1.7 Ω 1.7 Ω 1.8 Ω
1s1-1s3 3.7 Ω 3.7 Ω 3.6 Ω

7. Insulation resistance test : (VALUES IN GΩ)

(Using Equipment Details)

Make: MOTWANE Range: 5KV/1TΩ Sl. No. – A03521G16


BETWEEN VOLTAGE RPH YPH BPH
PRIMARY TO EARTH 5000V 211 GΩ 217 GΩ 224 GΩ
PRIMARY TO CORE-1 5000 V 190 GΩ 336 GΩ 253 GΩ
CORE-1 TO EARTH 500 V >100 GΩ >100 GΩ >100 GΩ
8. Functional Checks :

1 CT Secondary Spare Terminal Should be Short & Earthed Ok


2 CT Secondary All Terminals Tightness Should be Checked Ok
3 Continuity of Primary & Secondary Ok
4 Current measured in relay for all phase as per ratio Ok
5 Current measured in ammeter as per ratio Ok
6 Current measured in energy meter for all phase as per ratio Ok
9. Remarks: CT And CT circuit Found healthy

1. EQUIPMENT DETAILS : 33 KV INCOMER METERING PT


TYPE : OUTDOOR
Tested by: M/S POWER TECH Witnessed by- L&T CONSTRUCTION
Witnessed by-WAPCOS
Name : SITARAM PANDA Name: Name:

Designation :T&C ENG. Designation: Designation:


Signature Signature Signature
& Date : & Date : & Date :
TEST REPORT OF 33KV INCOMER
FEEDER

AGILE ENGINEERING SERVICE


PROJECT : GANGADHAR MEHER LIFT IRRIGATION PROJECT
CLIENT : WATER RESOURCES DEPARTMENT,ODISHA
CUSTOMER: L&T CONSTRUCTION

MAKE : PRAGATI ELECTRICAL PVT. LTD.


SERIAL NO. R PH- 22/M-113591 Y PH- 22/M-113590 B PH- 22/M-113592
RATIO : 33/0.11KV
ACC CLASS : 0.2
BURDEN : 50VA
LOCATION &FEDEER NAME : INCOMER METERING PT
YOM : 2022

3. General Inspection : OK

4. Insulation Resistance Test: (Value in GΩ)


(Using equipment details)
Make: MOTWANE Range: 5KV/1TΩ Sl. No. – A03521G16

BETWEEN VOLTAGE R ph Y ph B ph

PRIMERY TO EARTH 5000 V 257 GΩ 74.1 GΩ 99.7 GΩ


PRIMERY TO CORE1 5000 V 134 GΩ 172 GΩ 99.9 GΩ
CORE1 TO EARTH 500 V 27 GΩ 19.1 GΩ 26.8 GΩ

5. Winding Resistance Test. (Value in Ω)


(Using equipment details)

Make: FLUKE Range: 0-999Ω Sl. No. – 3598/322WS

R ph Y ph B ph
CORE -1 0.3 0.3 0.3

6. Ratio Test: -
(Using equipment details)
MAKE : FLUKE RANGE : 0-1000V SI. 3598/322WS

NAME Applied Voltage at Primary in Measured Voltage at secondary in


OF THE volts volts
CORE RY YB BR Ry yb br
CORE-1 440.1 438.9 442.2 1.4 1.4 1.4

7. Polarity Test:
(Using equipments details)
Tested by: M/S POWER TECH Witnessed by- L&T CONSTRUCTION
Witnessed by-WAPCOS
Name : SITARAM PANDA Name: Name:

Designation :T&C ENG. Designation: Designation:


Signature Signature Signature
& Date : & Date : & Date :
TEST REPORT OF 33KV INCOMER
FEEDER

AGILE ENGINEERING SERVICE


PROJECT : GANGADHAR MEHER LIFT IRRIGATION PROJECT
CLIENT : WATER RESOURCES DEPARTMENT,ODISHA
CUSTOMER: L&T CONSTRUCTION

MAKE – Oswal SL NO- AY0012

CORE
NAME R PHASE Y PHASE B PHASE

OK OK OK
CORE-1
CORE-2 OK OK OK

8. Functional Checks:

1 PT Secondary Spare Terminal is in proper position. OK


2 PT Secondary All Terminals Tightness Checked OK
3 PT Primary and secondary neutral earthling is checked OK
4 PT healthy indication N/A
5 PT in service indication N/A
6 PT in test indication N/A
7 Gas pressure low and lockout indications N/A
8 Voltage measured in voltmeter of all panel as per ratio N/A
9 Voltage measured in relays of all panel as per ratio N/A
10 Voltage measured in energy meters of all panel as per ratio N/A

9. PT AND PT CIRCUIT FOUND HEALTHY

Tested by: M/S POWER TECH Witnessed by- L&T CONSTRUCTION


Witnessed by-WAPCOS
Name : SITARAM PANDA Name: Name:

Designation :T&C ENG. Designation: Designation:


Signature Signature Signature
& Date : & Date : & Date :