R2000 Operations Manual Design Standards
R2000 Operations Manual Design Standards
R2000 Operations Manual Design Standards
C-1 INTRODUCTION
The Roads 2000 involves the maintenance and spot improvement of classified roads
using local resources where technically and economically feasible. As the majority
of the classified road network is unpaved (about 85%), the focus in terms of
establishing effective maintenance and carrying out spot improvement is on
unpaved roads.
The contents of this manual are partly standards (which as a general rule should be
the target by steady improvement over a period of time) and partly guidelines and
recommendations to be considered. In some instances special conditions may
demand modifications to these recommendations at the discretion of the DRE.
Individual roads for inclusion in the programme will be selected according to pre-
described procedures (prioritisation).
The improvement (partial rehabilitation) of roads will as much as possible follow the
existing vertical and horizontal alignment. Realignment will only be carried out
where there is a very strong technical or safety justification. This is to minimise the
earthworks and land acquisition, and to reduce the overall cost of the improvement
works.
The aim of the Roads 2000 Programme is to bring as much of the road network
under effective maintenance as quickly as possible and at low cost. Because of the
expense and logistics of gravelling, this will normally be restricted to spot
gravelling. Where more extensive regravelling is required due to poor subsoil or
high traffic, separate justification and funding should be sought under the Periodic
Maintenance programme. In many cases gravelling might also not be a durable and
cost effective solution. For such cases alternative surfacing options should be
considered, especially for trouble section, e.g. steep gradients, poor soils, where
the gravel source is far away or the gravel quality is poor, etc.
It will not be possible to bring all roads immediately to an “all weather” standard
with the funds and resources available. However, the pilot projects demonstrated
that it is more important that roads are provided with adequate drainage capable of
collection and discharging surface water rapidly. With limited resources it is more
cost effective to ensure adequate camber to the road and that the drainage system
is functioning by installing/improving culverts where necessary.
May 05 C-1
R2000 Operations Manual DESIGN STANDARDS C
The vertical and horizontal alignment criteria for classified roads are specified in
order to make the roads safe and compatible with the “all weather” requirements.
The roads shall be maintained or steadily improved over time to meet the following
geometric design requirements where possible.
The Road Design Manual does also specify alignment standards for classified D, E
and Rural Access Roads. However, the following alignment standards have been
adjusted through the MRP to comply with labour-based construction and
maintenance methods and are therefore recommended for adoption in the Roads
2000 Programme:
• The desirable minimum gradient is required for adequate drainage and the
absolute maximum gradient will be acceptable over a maximum length of 100m.
Most loaded vehicles would be unable to safely negotiate steeper gradients than
those given above on a gravel surface. If the absolute criteria cannot be
achieved, the Provincial Road Engineer should be consulted with a view to
considering options such as hairpin bends, alternative surfacings, etc, and the
erection of warning signs in advance of the hazard.
• Gradients and crossfall can be checked simply using an Abney level or line-and-
level.
The following Figures show how the horizontal radius of curvature and stopping
sight distance of an existing road alignment can be checked:
May 05 C-2
R2000 Operations Manual DESIGN STANDARDS C
X
Radi
If the centre line of the road is difficult to determine, use the line of the side ditch
as an approximation.
If the desirable standards in Table C.1 cannot be achieved then warning signs
should be erected.
May 05 C-3
R2000 Operations Manual DESIGN STANDARDS C
C-3 CROSS-SECTIONS
A/B/C Main +
6.0m 8.4m 9.6m Standard
Secondary Roads
D/E Minor Roads,
5.4m 7.8m 9.0m Standard
Width Established
RAR Roads, Width
4.5m 6.5m 7.3m Standard
Established
Minor/RAR Roads,
3.5m 5.5m 5.5m* Temporary
Insufficient Width
* No ditch widening, only “V” ditch
Note:
• Paved roads should be maintained to their original constructed cross section.
• Cross-sections for the Main and Secondary Roads (A, B and C classification)
depend on the specific requirements of a particular road, mainly in terms of
traffic capacity.
• Figures C.3 and C.4 set out the standard cross-sections to be maintained for
Minor Roads (D and E classification) and Rural Access Roads. The RAR cross
section is usually adequate for traffic of up to 20 vpd.
• Figure C.5 shows the cross-section to be applied for black cotton soil sections on
Minor Roads, Figure C.6 shows the embankment cross-section and Figure C.7
explains the superelevation.
• The measurements of the side ditches have been chosen to enable a constructed
camber crossfall of 8% to be achieved after compaction / consolidation, whether
there are one or two ditches. On sidelong ground the outer shoulder provides
sufficient material.
• Maintaining a reasonably steep crossfall is important especially if the road in not
gravelled. It is better to keep the crossfall steep to drain the surface and protect
its camber, rather than let vehicles rapidly destroy a flat, poorly drained camber.
May 05 C-4
R2000 Operations Manual DESIGN STANDARDS C
• The choice of cross section should be made at the Annual Work Plan stage. This
choice should be checked on site as works proceed.
• Many of the existing roads do not have an existing standard width over the
entire length of the road. Often the width is changing frequently. For Roads 2000
partial rehabilitation to be cost effective, it is advisable to only make minor
corrections to the existing width in order to avoid excess earth works.
May 05 C-5
R2000 Operations Manual DESIGN STANDARDS C
Figure C.3
May 05 C-6
R2000 Operations Manual DESIGN STANDARDS C
Figure C.4
May 05 C-7
R2000 Operations Manual DESIGN STANDARDS C
Figure C.5
CROSS SECTION;
BLACK COTTON SOIL SECTIONS ON MINOR ROADS
May 05 C-8
R2000 Operations Manual DESIGN STANDARDS C
Figure C.6
CROSS SECTION;
EMBANKMENT ON MINOR ROADS
May 05 C-9
R2000 Operations Manual DESIGN STANDARDS C
Figure C.7
CROSS SECTION;
SUPERELEVATION
May 05 C - 10
R2000 Operations Manual DESIGN STANDARDS C
Figure C.8
JUNCTION LAYOUT
May 05 C - 11
R2000 Operations Manual DESIGN STANDARDS C
May 05 C - 12
R2000 Operations Manual DESIGN STANDARDS C
The quality requirements are described in Road Design Manual and are further
specified in the contract document.
The minimum quality requirements for Gravel Wearing Courses may be defined
as follows (TRL guidelines):
Table C.3; Grading Table C.4; Plasticity
Grading Requirement After
Plasticity Requirement (PI)
Compaction
% by Weight
Sieve (mm) Zone Minimum Maximum
passing
40 100 Wet 5 20
28 95 – 100 Dry 10 30
20 85 – 100 Plasticity Index (PI) =
14 65-100 Liquid Limit (LL) minus Plastic Limit (PL)
10 55 – 100
5 35 – 92 Mechanical Stabilisation
2 23 – 77 If suitable natural gravel is not available, it may be
1 18 – 62 possible to achieve the above requirements by mixing
or mechanical stabilisation of different materials. The
0.425 14 – 50 requirements will apply to mixtures of natural gravel
and sand or up to 30% of stone (crushed or not)
0.075 10 - 40
May 05 C - 13
R2000 Operations Manual DESIGN STANDARDS C
Where reliable testing facilities are available, gravel material should be tested
against the criteria given in the Roads Department, Road Design Manual. However,
in practice it is usually not possible to organise testing of all gravel surfacing
material.
Particular situation may require that more gravel be placed on the road than the
minimum thickness quoted above. The reasons for this include:
• Weak Insitu Soil: Certain soils require a greater thickness of gravel to spread
the traffic load to remain within the bearing capacity of the soil, especially when
moist (e.g. Black Cotton Soil).
• High Traffic: High traffic will cause faster gravel loss.
• Steep Sections: Rate of loss of gravel on section steeper than 8% is
significantly higher than on flatter road sections.
On such problem road sections the recommended thickness of gravel is 20cm
compacted.
May 05 C - 14
R2000 Operations Manual DESIGN STANDARDS C
The Transport Research Laboratories (TRL) estimates the annual gravel loss to be:
TA 2
G = F(4.2 + 0.092TA + 3.5R f + 1.88VC) 2
( TA2 + 50 )
Where TA = total annual traffic in both directions measured in thousands of vehicles
Rf = annual rainfall in metres
VC = average percentage road gradient
F = 1.5 for coral gravels / 1.29 for lateritic gravels / 1.51 for quartzitc gravels / 0.96 for
volcanic gravels / 1.38 for sandstone gravels
Gravel Loss is measured in mm/year
May 05 C - 15
R2000 Operations Manual DESIGN STANDARDS C
For simple and low cost structures also refer to the MRP
Structure Manual and to the TRL Manual ORN 9; Design of
Small Bridges.
May 05 C - 16
R2000 Operations Manual DESIGN STANDARDS C
• Where vehicle access is required to land or properties adjacent to the road, the
ditch should be lined with stone pitching or a small culvert (30/45cm
diameter) should be provided.
• Scour checks are to be provided in side ditches of gradient greater than 4%
according to the following guidelines.
May 05 C - 17