Nodes Activity Time (Weeks)
Nodes Activity Time (Weeks)
Score:
Test I:
1. Given the following data for building to be constructed:
Time
Nodes Activity
(weeks)
1-2 A Demolition and clearing 8
2-3 B Excavation 14
2-5 C Underground installations 6
3-4 D Foundation and column 5
4-5 E Dummy 0
4-6 F Construction of second floor 6
4-7 G Roof framing and roofing 6
5-7 H Ground floor slab 4
5-8 I Mechanical and electrical services 12
6-7 J Construction of exterior walls 12
7-8 K Dummy 0
7-9 L Construction of interior partitions 10
8-9 M Mechanical and electrical fixtures 12
9-10 N paining and finishing 8
Required:
a. Draw the network diagram.
b. Determine the Early Start, Early Finish, Late Start and Late Finish
c. Determine the Total Float and Free Float
d. Find the CPM of the project.
e. What is the duration of the project?
f. Make a data sheet corresponding to this project.
g. If the project starts on May 23, 2011, what is the completion date of the project considering
that the man works 5 days in a week (Mon. to Fri) including holidays?
a. PERT
b. CPM
c. Project
d. Free Float
e. Gantt chart
f. Management
g. Construction
h. Dummy
i. Network
j. Event
4. Enumeration:
a. Differentiate PERT/CPM
b. Three Time Estimate
c. Network Diagram composition
d. Conventional way of making network
5. Project: