PROJECT LOCATION Concreting of Road, Barangay Sta. Cruz, Talicud Island to Purok Tisa to Leticia by the Sea Resort to Drilon, Lindgreen and Lanos Beaches, Island Garden City of Samal, Davao del Norte
APPROVED BUDGET COST Php 67,547,473.30
DAYS TO COMPLETE 240 calendar days
TO BE IMPLEMENTED 190 calendar days from the start of the project AS PER CASH FLOW
A.1.2(2) Provision of 4x4 Pick Up Type Service Vehicle for the Engineer on Rental Basis Mo. 3 57,395.44 172,186.32
B.22 Support Equipment (Crane Barge Rental) Mo. 3 471,691.67 1,415,075.00 33,923,115.72
PART E SURFACE COURSES
300(1) Gravel Surface Course Cu.m. 980.00 1,413.54 1,385,269.20 1,095,551.07 282,783.50 6,934.99 1,385,269.56
311(1)a PCC Pavement (Unreinforced), 0.15m. thk. Sq.m. 1,842.80 1,140.43 2,101,584.40 1,561,482.35 415,225.04 124,877.05 2,101,584.44
311(1)c1 PCC Pavement (Unreinforced), 0.23m. thk. Sq.m. 16,223.02 1,691.05 27,433,925.39 20,756,601.88 5,473,980.64 1,203,342.87 27,433,925.39
B.22 Support Equipment (Crane Barge Rental) Mo. 3 471,691.67 1,415,075.00
TO BE IMPLEMENTED 240 calendar days from the start of the project AS PER CASH FLOW
PARTICULAR TOTAL
ACCOMPLISHMENT, IN % 100.00%
CASH FLOW, IN PhP
CUMULATIVE ACCOMPLISHMENT, IN % 100.00%
CUMULATIVE CASH FLOW, IN PhP
Submitted by:
icud Island to Purok Tisa to Leticia by the Sea Resort to Drilon, Lindgreen and
, Davao del Norte
Y FLOW BY QUARTER
240 calendar days
3 months 3 months 2 months
26.20% 50.22% 23.58%
17,695,842.215 33,923,115.716 15,928,515.366
26.20% 76.42% 100.00%
17,695,842.215 51,618,957.932 67,547,473.297