Esia Final Km500
Esia Final Km500
Esia Final Km500
APRIL 2020
RSK GENERAL NOTES
Project No.: 182279-17 (05)
Title: Environmental and Social Impact Assessment for first 250 MMscfd for KM500
Gas Treatment Plant - Khor Mor, Kurdistan Region of Iraq
Signature Signature
Date: 01 April 2020 Date: 20 December 2019
Social technical
Project manager Cyndi Teulon reviewer Corinne Kennedy
Signature Signature
Date: 08 April 2020 Date: 01 April 2020
RSK Environment LLC (RSK) has prepared this report for the sole use of the client, showing reasonable skill and care, for the
intended purposes as stated in the agreement under which this work was completed. The report may not be relied upon by
any other party without the express agreement of the client and RSK. No other warranty, expressed or implied, is made as to
the professional advice included in this report.
Where any data supplied by the client or from other sources have been used, it has been assumed that the information is
correct. No responsibility can be accepted by RSK for inaccuracies in the data supplied by any other party. The conclusions
and recommendations in this report are based on the assumption that all relevant information has been supplied by those
bodies from whom it was requested.
No part of this report may be copied or duplicated without the express permission of RSK and the party for whom it was
prepared.
Where field investigations have been carried out, these have been restricted to a level of detail required to achieve the stated
objectives of the work.
This work has been undertaken in accordance with the quality management system of RSK Environment LLC.
Pearl Petroleum
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
CONTENTS
NON-TECHNICAL SUMMARY
1 INTRODUCTION .............................................................................................................................. 1
1.1 Operator's name and contact information ................................................................................ 1
1.2 Key personnel – environmental consultant .............................................................................. 1
2 DESCRIPTION OF THE OPERATIONS AND ACTIVITIES ............................................................ 3
2.1 Background and project purpose ............................................................................................. 3
2.2 KM250A Project schedule ........................................................................................................ 3
2.3 Project location and site description ......................................................................................... 4
2.4 Current activities at the site ...................................................................................................... 6
2.5 Description of KM250A Project ................................................................................................ 8
2.5.1 Introduction ................................................................................................................... 8
2.5.2 Project components ...................................................................................................... 8
2.5.3 Expansion Area ............................................................................................................ 9
2.5.4 Development Area ........................................................................................................ 9
2.5.5 Tie-ins .........................................................................................................................10
2.5.6 Process description ....................................................................................................10
2.5.7 Utilities for the KM250A Project..................................................................................17
2.5.8 Flares ..........................................................................................................................18
2.5.9 Thermal oxidiser .........................................................................................................18
2.5.10 Drainage .....................................................................................................................18
2.5.11 Venting .......................................................................................................................19
2.5.12 Produced water ..........................................................................................................20
2.5.13 Hot oil circulation and heater ......................................................................................20
2.5.14 Power supply ..............................................................................................................20
2.5.15 Safety exclusion/buffer zones ....................................................................................20
2.6 Project activities for all Project phases ...................................................................................21
2.6.1 Construction phase.....................................................................................................21
2.6.2 Pre-commissioning and commissioning .....................................................................28
2.6.3 Operations phase .......................................................................................................29
2.6.4 Decommissioning .......................................................................................................32
2.7 Resource consumption ...........................................................................................................33
2.7.1 Construction phase.....................................................................................................33
2.7.2 Operations phase .......................................................................................................33
2.7.3 Decommissioning phase ............................................................................................34
2.8 Emissions, wastes and other environmental issues ...............................................................34
2.8.1 Air emissions ..............................................................................................................34
2.8.2 Noise ..........................................................................................................................35
2.8.3 Liquids ........................................................................................................................36
2.8.4 Waste .........................................................................................................................37
2.8.5 Visual effects ..............................................................................................................39
2.8.6 Traffic ..........................................................................................................................40
2.8.7 Land use .....................................................................................................................41
2.9 Future development................................................................................................................41
Pearl Petroleum ii
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
2.10 Associated facilities ................................................................................................................41
2.10.1 Site clearance and mobilisation ..................................................................................42
2.10.2 Drilling .........................................................................................................................43
2.10.3 Demobilisation ............................................................................................................46
2.10.4 Emissions, discharges and wastes ............................................................................46
2.10.5 Schedule .....................................................................................................................47
3 BASELINE PROPERTIES OF THE ENVIRONMENT ................................................................... 48
3.1 Methodology ...........................................................................................................................48
3.2 Physical environment .............................................................................................................48
3.2.1 Geography, climate and meteorology ........................................................................48
3.2.2 Geology ......................................................................................................................49
3.2.3 Soil ..............................................................................................................................51
3.2.4 Water resources .........................................................................................................57
3.2.5 Noise ..........................................................................................................................68
3.2.6 Air quality ....................................................................................................................72
3.3 Biological environment ...........................................................................................................80
3.3.1 Area of influence - biodiversity ...................................................................................80
3.3.2 Past field data collection in the Project area ..............................................................82
3.3.3 Current field data collection in the Project area .........................................................82
3.3.4 Critical habitat assessment ........................................................................................86
3.3.5 Biodiversity baseline conditions .................................................................................89
3.4 Social baseline .....................................................................................................................100
3.4.1 Methodology .............................................................................................................100
3.4.2 Political history..........................................................................................................105
3.4.3 Administrative structure and governance .................................................................106
3.4.4 Demographics ..........................................................................................................107
3.4.5 Health .......................................................................................................................112
3.4.6 Education ..................................................................................................................117
3.4.7 Economy and livelihoods ..........................................................................................119
3.4.8 Workers’ rights and working practices......................................................................128
3.4.9 Land ..........................................................................................................................130
3.4.10 Infrastructure and services .......................................................................................139
3.4.11 Community safety, security and welfare...................................................................146
3.4.12 Cultural heritage and archaeology ...........................................................................156
3.5 Ecosystems services ............................................................................................................159
3.5.1 Provisioning services ................................................................................................159
3.5.2 Regulating services ..................................................................................................161
3.5.3 Cultural services .......................................................................................................161
3.5.4 Supporting services ..................................................................................................161
4 STAKEHOLDER ENGAGEMENT ............................................................................................... 162
4.1 Introduction ...........................................................................................................................162
4.2 Objectives of the stakeholder engagement ..........................................................................162
4.3 Stakeholder identification and analysis ................................................................................162
4.3.1 Stakeholder identification .........................................................................................162
4.3.2 Scoping phase ..........................................................................................................163
4.3.3 Disclosure phase ......................................................................................................170
4.4 Stakeholder engagement activities ......................................................................................170
Pearl Petroleum iv
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
6.5.3 Operations phase .....................................................................................................302
6.5.4 Decommissioning phase ..........................................................................................303
6.6 Waste management .............................................................................................................303
6.7 Socio-economic ....................................................................................................................303
6.7.1 Construction phase...................................................................................................304
6.7.2 Pre-commissioning and commissioning phases ......................................................323
6.7.3 Operations phase .....................................................................................................324
6.7.4 Decommissioning phase ..........................................................................................327
6.8 Associated facilities ..............................................................................................................328
7 KEY OPTIONS AND ALTERNATIVES........................................................................................ 331
7.1 Introduction ...........................................................................................................................331
7.2 Technical alternatives considered ........................................................................................331
7.3 ‘Do nothing’ alternative .........................................................................................................332
8 UNCERTAINTIES......................................................................................................................... 339
8.1 Introduction ...........................................................................................................................339
8.1 Key uncertainties ..................................................................................................................340
8.1.1 Lender requirements ................................................................................................340
8.1.2 Stakeholder engagement .........................................................................................340
8.1.3 Baseline socio-economic conditions ........................................................................340
8.1.4 Air quality ..................................................................................................................341
8.1.5 Soil and water resources ..........................................................................................342
8.1.6 Noise ........................................................................................................................343
8.1.7 Biodiversity/ecology ..................................................................................................343
8.1.8 Cultural heritage .......................................................................................................344
8.2 Conclusions ..........................................................................................................................344
9 RELEVANT INTERNATIONAL AND DOMESTIC REGULATIONS ...........................................345
9.1 Introduction ...........................................................................................................................345
9.2 International conventions and agreements ..........................................................................345
9.3 Iraq federal and regional legal system .................................................................................346
9.4 Kurdistan Region of Iraq institutional framework ..................................................................347
9.5 Environmental legislation in Kurdistan .................................................................................347
9.5.1 Environmental protection improvement and environmental impact assessment
requirements .............................................................................................................348
9.5.2 Legal basis for categorisation of projects and environmental conditions .................350
9.5.3 Oil and Gas Law .......................................................................................................353
9.5.4 Petroleum Development Agreement ........................................................................354
9.5.5 Investment law..........................................................................................................354
9.6 Land and property legislation in Iraq and Kurdistan .............................................................354
9.7 Selection of Project Standards .............................................................................................355
9.7.1 Soil quality standards ...............................................................................................356
9.7.2 Water quality standards ............................................................................................356
9.7.3 Noise standards........................................................................................................357
9.7.4 Air quality standards .................................................................................................357
9.8 Requirements for Project financing ......................................................................................358
9.8.1 International Finance Corporation Performance Standards .....................................358
9.8.2 International Finance Corporation Environmental, Health and Safety guidelines ....360
9.8.3 U.S. International Development Finance Corporation..............................................362
Pearl Petroleum v
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
10 ENVIRONMENTAL AND SOCIAL MANAGEMENT ................................................................... 364
10.1 Introduction ...........................................................................................................................364
10.2 Pearl Petroleum HSSE&SP MS ...........................................................................................365
10.2.1 Pearl Petroleum HSSE&SP requirements ...............................................................365
10.2.2 HSSE&SP Policy, Standards and Procedures .........................................................366
10.3 KM250A HSSE&SP MP .......................................................................................................370
10.4 Roles and Responsibilities ...................................................................................................372
10.4.1 Globally at Pearl Petroleum ......................................................................................372
10.4.2 Current Pearl Petroleum HSSE and SP teams ........................................................372
10.4.3 Contractors ...............................................................................................................374
10.5 Communication.....................................................................................................................374
10.5.1 Internal communications ..........................................................................................374
10.5.2 External communications and stakeholder engagement principles .........................375
10.6 Management of Change .......................................................................................................375
11 SAFEGUARDS, MEASURES AND PLANS ................................................................................ 377
11.1 Introduction ...........................................................................................................................377
11.2 General approach .................................................................................................................377
11.3 Construction phase...............................................................................................................378
11.3.1 Social Investment Program ......................................................................................380
11.3.2 Local Community Employment Plan ........................................................................381
11.3.3 Influx Management Strategy ....................................................................................381
11.3.4 Livelihood Restoration Plan ......................................................................................381
11.3.5 Traffic Management Plan .........................................................................................382
11.3.6 Biodiversity Plans .....................................................................................................382
11.4 Monitoring and reporting ......................................................................................................383
11.5 Operations phase .................................................................................................................383
11.6 Decommissioning .................................................................................................................384
12 REFERENCES ............................................................................................................................. 385
TABLES
Table 1-1 Operator’s name and contact information .............................................................................. 1
Table 1-2 Environmental consultant contact details ............................................................................... 2
Table 2-1 Key project activities ............................................................................................................... 4
Pearl Petroleum vi
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Table 2-2 KM250A tie-ins......................................................................................................................10
Table 2-3 Cut and fill earthworks ..........................................................................................................22
Table 2-4 Indicative list of construction phase equipment ....................................................................24
Table 2-5 Estimated quantities of construction phase materials ..........................................................33
Table 2-6 Expected Project water use during operations .....................................................................34
Table 2-7 Waste management at the existing Pearl Petroleum KM facility (CPDG, 2018h) ................38
Table 3-1 AOI - soil ...............................................................................................................................51
Table 3-2 Soil sampling locations .........................................................................................................53
Table 3-3 Laboratory results of the current soil sampling survey in 2019 (mg/kg) ...............................55
Table 3-4 AOI - water resources ...........................................................................................................57
Table 3-5 Status of existing abstraction wells in the Khor Mor area .....................................................59
Table 3-6 Water sampling locations (MapCom, 2018) .........................................................................59
Table 3-7 Summary of spring and groundwater results (MapCom, 2018) ............................................60
Table 3-8 Groundwater sampling locations (RSK, 2019) .....................................................................61
Table 3-9 Field parameter data for water resources (RSK, 2019) ........................................................62
Table 3-10 Field parameter data for water samples (RSK, 2019) ........................................................62
Table 3-11 Groundwater depths ...........................................................................................................63
Table 3-12 Laboratory results of the current water resources sampling survey in 2019 (mg/L or as
stated) ...................................................................................................................................................65
Table 3-13 AOI - noise ..........................................................................................................................68
Table 3-14 Nearest noise sensitive receptors to the facility .................................................................68
Table 3-15 Ambient noise levels (dB (A)) at Khor Mor (MapCom, 2010) .............................................69
Table 3-16 Current noise survey results in 2019 ..................................................................................71
Table 3-17 AOI - air quality ...................................................................................................................72
Table 3-18 Ambient air quality results (MapCom, 2010) ......................................................................75
Table 3-19 Ambient air quality results for VOCs (MapCom, 2010).......................................................75
Table 3-20 Ambient air quality results (ERM, 2015) .............................................................................76
Table 3-21 Ambient air quality results (MapCom, 2018) ......................................................................77
Table 3-22 Current air quality monitoring results in 2019 .....................................................................79
Table 3-23 AOI - biodiversity.................................................................................................................80
Table 3-24 Locations of small mammal traps .......................................................................................85
Table 3-25 Locations of camera traps ..................................................................................................85
Table 3-26 Summary of findings of the CHA ........................................................................................88
Table 3-27 Rare and threatened bat species within ranges that overlap the AOI ................................95
Table 3-28 Mammal species identified during baseline surveys in the study area in 2019 ..................96
Table 3-29 PACs within the AOI .........................................................................................................101
Table 3-30 Data collection activities in the PACs ...............................................................................104
Table 3-31 Population and households (HH) in the PACs..................................................................108
Table 3-32 Leading causes of death in the KRI in 2014 (Moore et al, 2014) .....................................113
Table 3-33 Number of livestock owned amongst households ............................................................124
Table 3-34 Traffic survey locations .....................................................................................................145
Table 3-35 GII values for the KRI, Iraq and other countries in the region ..........................................149
Table 3-36 Key findings and analysis of vulnerable groups ...............................................................152
Table 4-1 Project level of influence and impact on the Project ...........................................................164
Table 5-1 Environmental impact identification matrix .........................................................................186
Table 5-2 Socio-economic impact identification matrix .......................................................................187
Table 5-3 Criteria for determining receptor sensitivity ........................................................................190
Pearl Petroleum ix
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Table 6-12 Summary of construction phase mitigation measures and residual impacts on public health
............................................................................................................................................................317
Table 6-13 Summary of construction phase mitigation measures and residual impacts on
infrastructure and services ..................................................................................................................319
Table 6-14 Summary of construction phase mitigation measures and residual impacts on traffic.....320
Table 6-15 Summary of construction phase mitigation measures and residual impacts on vulnerable
groups .................................................................................................................................................322
Table 6-16 Summary of pre-commissioning and commissioning phase mitigation measures and
residual impacts on infrastructure and services ..................................................................................323
Table 6-17 Summary of operations phase mitigation measures and residual impacts on the regional
economy ..............................................................................................................................................324
Table 6-18 Summary of operations phase mitigation measures and residual impacts on land access
and livelihoods ....................................................................................................................................325
Table 6-19 Summary of operations phase mitigation measures and residual impacts on community
safety and security ..............................................................................................................................326
Table 6-20 Summary of operations phase mitigation measures and residual visual impacts ............327
Table 6-21 Summary of decommissioning phase mitigation measures and residual impacts on
infrastructure and services ..................................................................................................................328
Table 6-22 Mitigation measures for associated facilities (five production wells) ................................329
Table 7-1 Key alternatives considered in the KM250A Project...........................................................333
Table 9-1 International conventions signed/ratified by Iraq ................................................................345
Table 9-2 Acceptable limit of noise for construction activities ............................................................352
Table 9-3 Sound intensity inside the workplace and indoor places ....................................................352
Table 9-4 Overview of IFC PSs ..........................................................................................................358
Table 9-5 Applicable IFC/World Bank EHS guidelines .......................................................................361
Table 10-1 HSSE&SP policy, standards, procedures and supporting tools .......................................367
FIGURES
Figure 2-1 KM location ............................................................................................................................ 4
Figure 2-2 KM area ................................................................................................................................. 5
Figure 2-3 KM site plan ........................................................................................................................... 5
Figure 2-4 Location of existing and proposed future KM production wells and flowlines .......................7
Figure 2-5 KM250A Project gas plant flow diagram .............................................................................12
Figure 2-6 Planned access routes during construction phase of KM250A Project...............................26
Figure 3-1 Soil map of Iraq (Buringh, 1960)..........................................................................................52
Figure 3-2 Soil sampling locations ........................................................................................................56
Figure 3-3 Water resources and sampling locations ............................................................................58
Figure 3-4 Noise monitoring locations (RSK, 2019) .............................................................................70
Figure 3-5 Ambient air quality monitoring locations ..............................................................................74
Figure 3-6 AOA and AOI - biodiversity ..................................................................................................81
Figure 3-7 Biodiversity baseline survey locations .................................................................................83
Figure 3-8 Photograph of Chemchemal KBA and IBA (Nature Iraq, 2017) ..........................................90
Figure 3-9 Habitat map .........................................................................................................................92
Figure 3-10 Steppe grassland habitat ...................................................................................................93
Figure 3-11 Typical cropland habitat with shrubs .................................................................................93
Figure 3-12 Pond and reedbed .............................................................................................................93
Figure 3-13 Khor Mor perimeter fence at coordinate 35.143803°(N), 44.815793° (E) .........................95
Figure 3-14 Khor Mor perimeter fence at coordinate 35.141154°(N), 44.829062° (E) .........................95
Figure 3-15 Photographs from cameral trapping survey ......................................................................97
Pearl Petroleum x
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Figure 3-16 Social baseline primary and secondary spheres of influence .........................................102
Figure 3-17 Age structure in Governorate of Sulaymaniyah and KRI, 2017 (IOM, 2018a) ................108
Figure 3-18 Treatment type sought by households ............................................................................116
Figure 3-19 Students enrolled in public and private schools in the KRI, 2017 – 2018 (KRSO, 2019)118
Figure 3-20 Children attending school within versus outside the AOI ................................................118
Figure 3-21 Distribution of GDP by sector, 2017 (PwC, 2018) ...........................................................120
Figure 3-22 Primary crops grown by households ...............................................................................122
Figure 3-23 Livestock owned by households ......................................................................................123
Figure 3-24 Livestock well in Takhta Mina Saru .................................................................................125
Figure 3-25 Percentage of formally employed household members ..................................................126
Figure 3-26 Unemployment by governorate, 2017 (KRSO, 2019)......................................................127
Figure 3-27 Percentage of unemployed household members ............................................................127
Figure 3-28 Access to arable land amongst households ....................................................................131
Figure 3-29 Number of plots owned or used by households ..............................................................132
Figure 3-30 Profile of flowline land owners and land users ................................................................134
Figure 3-31 Methods of solid waste disposal ......................................................................................141
Figure 3-32 Public electricity supply by governorate, 2018 (IOM, 2018a) ..........................................142
Figure 3-33 Example housing in Khor Mor Gawra ..............................................................................143
Figure 3-34 Age of household structures ............................................................................................144
Figure 3-35 Poverty rates in the KRI, 2018 (KRSO, 2019) .................................................................147
Figure 3-36 Archaeological sites in the general Project area .............................................................158
Figure 3-37 View of the area of Sarcham Tepe (left) and Tape Julaka (right) archaeological sites ..159
Figure 4-1 Stakeholder mapping .........................................................................................................170
Figure 4-2 Locations of community level stakeholder engagement meetings ....................................171
Figure 4-3 Community meeting at Khor Mor Bichuk, 5 October 2019 ................................................174
Figure 4-4 Community meeting at Shekh Hameed, 5 October 2019 ..................................................174
Figure 4-5 Community meeting at Awaye Jalal, 8 October 2019 .......................................................175
Figure 4-6 Women’s focus group discussion at Khor Mor Gawra, 5 October 2019 ...........................175
Figure 4-7 Frequency of issues raised by topic across community meetings ....................................178
Figure 4-8 Frequency of issues raised by social sub-topic across community meetings ...................178
Figure 4-9 Project community Grievance Management Procedure ....................................................180
Figure 5-1 Schematic of the impact assessment process ..................................................................188
Figure 5-2 Buildings assessed in BPIP for downwash effects ............................................................199
Figure 5-3 Model predictions for 1-hour averaging period (Scenario 2) - NO2 ...................................203
Figure 5-4 Model predictions for 24-hour averaging period (Scenario 2) - NO2 .................................203
Figure 5-5 Model predictions for annual averaging period - NO2 .......................................................204
Figure 5-6 Model predictions for 3-hour averaging period (thermal oxidiser) – SO2 ..........................207
Figure 5-7 Model predictions for 1-hour averaging period (thermal oxidiser) – SO2 ..........................208
Figure 5-8 Model predictions for 24-hour averaging period (thermal oxidiser) – SO2 ........................208
Figure 5-9 Model predictions for annual averaging period (thermal oxidiser) – SO2 ..........................209
Figure 5-10 Model predictions for 1-hour averaging period – CO ......................................................211
Figure 5-11 Model predictions for 24-hour averaging period – PM10 ..................................................213
Figure 5-12 Predicted operations phase noise levels under routine conditions (1.5 m above ground
level) ....................................................................................................................................................232
Figure 5-13 Predicted operations phase noise levels under non-routine conditions (1.5 m above
ground level) .......................................................................................................................................233
Figure 9-1 MNR submission and review process ...............................................................................350
Pearl Petroleum xi
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Figure 10-1 KM environmental and social framework ........................................................................365
Figure 10-2 HSSE mangement structure ............................................................................................366
Figure 10-3 Corporate standard elements ..........................................................................................367
Figure 10-4 Structure of Pearl Petroleum SP Standard ......................................................................370
Figure 10-5 Plan-do-act-check methodology ......................................................................................376
Pearl Petroleum xv
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Term Definition
MSW municipal solid waste
MW megawatt
NA not analysed
NAAQS national ambient air quality standards
NACE National Association of Corrosion Engineers
NCD non-communicable diseases
ND not detected
NGL natural gas liquids
NGO non-governmental organisation
NM not measured
NOx nitrogen oxides
NS not specified
NTS Non-technical Summary
NTU Nephelometric turbidity unit
O3 ozone
OHS occupational health and safety
OPF Oil Police Force
PAC Project-affected community
PAH polycyclic aromatic hydrocarbons
PAP Project-affected person
PDA Production Development Agreement
PHC primary health care
PM10 particulate matter (PM10 particles smaller than 10 microns)
PM2.5 particulate matter (PM2.5 particles smaller than 2.5 microns)
PMT Pearl Petroleum management team
ppb parts per billion
ppm parts per million
PS Performance Standard
QRA qualitative risk assessment
RoW right of way
RP Retrenchment Plan
RSK RSK Environment LLC
SDM Sub-District Manager
SIMOPS simultaneous operations
SIP Social Investment Programmes
SLO Social Liaison Officer
Figure 3 KM site
Pearl Petroleum xx
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Local communities
Several communities are located within 10 km of the KM250A Project site (Figure 4), most of which
are relatively small, with less than 100 residents. The average distance of the three nearest
communities - Awaye Jalal, Khor Mor Bichuk and Khor Mor Gawra - from the nearest boundary of
the KM Expansion Area is 2 km.
Land ownership and usage
The KM250A Project will be mostly constructed on land which is already occupied by Pearl
Petroleum. New flowlines will, however, be installed outside the existing site on land currently used
for livestock rearing and crop farming. To allow the flowlines to be laid during construction and to
ensure that the flowlines are not damaged during operations, permissions to acquire or access the
land within the flowline corridors will need to be obtained, and restrictions to land use will be put in
place (e.g. through restricting digging activities or the construction of buildings).
Stakeholder engagement
Stakeholder engagement is an important part of the ESIA process and a national and international
requirement. A Stakeholder Engagement Plan (SEP) was developed for the ESIA process and
engagements were undertaken to:
• inform stakeholders in an accessible and appropriate manner about the KM250A Project
and the ESIA and provide opportunities for them to engage and register grievances
• ensure that stakeholders understand how they might be affected by the KM250A Project
and their potential role in impact identification and management
• obtain the input of stakeholders into KM250A Project impact identification and impact
management
• provide opportunities for stakeholders to express their opinions and concerns about the
KM250A Project and the ESIA and ensure that these opinions and concerns are
considered in the ESIA and any related management decisions.
During the disclosure phase of the ESIA, further engagement will be undertaken to provide
feedback and obtain comments from stakeholders on the impact assessment and associated
management or mitigation measures.
Community stakeholder engagement
Ten community stakeholder engagement meetings, attended by 184 stakeholders, were held in
October 2019. The main issues and concerns raised during these meetings revolved around social
issues (including employment and community development, land use and worker safety), general
environmental impacts, stakeholder engagement and KM250A Project characteristics (for
example, security).
Non-community stakeholder engagement
Pearl Petroleum holds regular meetings with the MNR regarding the KM250A Project and general
matters. Feedback and input are obtained from the MNR, particularly on key issues such as social
impacts, water and waste. The MNR has advised waiting until disclosure before holding further
non-community engagement meetings, at which point a selection of other government ministries
and other non-community stakeholders will be contacted to discuss the Project.
A critical habitat assessment was conducted as part of the ESIA that included consultation
with various experts (Nature Iraq, University of Sulaymaniyah and Polytechnic University of
Sulaymaniyah). Impacts on all of the critical habitat qualifying species were considered to be
insignificant (minor or slight) and no biodiversity offsetting/net gain is required.
While the habitats within the AOI are considered to have low conservation importance, the
habitat may support endangered or critically endangered species. A number of species and
habitats were considered. It was concluded that the habitat of these species and their possible
presence at the Project site are unlikely to be affected by KM250A Project activities.
Biodiversity or ecology-related mitigation measures are expected to include the following, thus
bringing all impact significance during all phases to minor:
Cumulative impacts
Cumulative impacts result from the incremental impact from other existing, planned or reasonably
defined developments. Cumulative impacts for the KM250A Project may occur during further
expansion of the Khor Mor site. Although details regarding the potential configuration (and thus
impacts) of future expansion projects are not currently known, the likely adverse impacts are as
follows:
• increased air emissions
• increased groundwater consumption
• increased local traffic
• increased pressure on Pearl Petroleum Khor Mor waste management facilities
• additional pressure on habitat and biodiversity via installation of additional flowlines.
Positive impacts include the ability to recruit construction workers for future projects as a partial
solution to retrenchment, and increased use of local goods and services (including labour).
Associated facilities
Five production wells will be developed in association with the KM250A Project. A comprehensive
separate ESIA will be developed for these facilities in late 2020. A high-level impact assessment
was developed based on baseline information collected for this (KM250A Project) ESIA, on the
existing ESIA undertaken for wells KM9, KM10 and KM12 by MapCom (2018), and on RSK
experience with onshore oil and gas drilling. High-level mitigation measures (similar to those
described for the KM250A Project) were identified for impacts that may be significant. These
potential impacts and mitigations will be further evaluated as part of the ESIA specific to the five
wells.
Project ESIA for first 250 MMscfd Train for Khor Mor 500 Gas Treatment Plant in the
Title Kurdistan Region of Iraq
Corporate Head of HSSE (Sharjah)
Stuart Harrower E-mail: sharrower@crescent.ae
Tel.: +97165070454
Construction HSE Manager for KM500 (Khor
Mor)
Matthew Brown E-mail: mbrown@crescent.ae
Pearl Tel.: +9647707702964 (Khor Mor 24-hour
Operator’s Petroleum Movcon Command)
name Company Social Performance Field Manager (Khor
Limited Mor)
Steven Bungay E-mail: kmspfieldmgr@crescent.ae
Tel.: +9647707702964 (Khor Mor 24-hour
Movcon Command)
Senior HSSE Manager (Erbil)
Mark Mincheau E-mail: MMinchaeau@crescent.ae
Tel.: +9647712321984
Pearl Petroleum 1
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Box 45103, Abu Dhabi, United Arab Emirates. In 2017, the Iraq Ministry of Health and
Environment accredited RSK as an advisory office for environmental consultancy and
RSK is an approved supplier with the KRG Ministry of Natural Resources (MNR). Contact
details for RSK is presented in Table 1-2.
Pearl Petroleum 2
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
2 DESCRIPTION OF THE OPERATIONS AND
ACTIVITIES
This section presents a description of all aspects of the Project that is the subject of this
environmental and social impact assessment (ESIA).
Pearl Petroleum 3
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Table 2-1 Key project activities
Pearl Petroleum 4
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Figure 2-2 KM area
Pearl Petroleum 5
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
2.4 Current activities at the site
The existing site contains a gas plant and LPG extraction facilities that produce sales
gas, LPG and condensate from the KM reservoir. The facilities occupy approximately
50 ha within an overall fenced area of 600 ha, and consist of:
• two parallel LPG extraction trains (‘Cryo#’) (150 MMscfd sales gas capacity
each)
• early production facility (EPF) (120 MMscfd sales gas capacity)
• condensate stabilisation, storage and export (13,000 barrels per day – bpd -
nominal)
• LPG storage and truck loading (1,020 metric tons per day nominal)
• sales gas compression for LPG recovery trains and export by pipeline
• utilities.
Figure 2-4 shows existing KM production wells and flowlines. The gas plant is fed by gas
from the original production wells (KM3, KM4, KM5, KM6, KM7 and KM8) within or near
the KM site. KM9 has just been brought online. KM10 and KM12 have been drilled and
suspended; there are currently no plans to tie these into the gas plant. KM14 is a potential
appraisal well that has not been drilled yet.
The existing production well flowlines are buried at 1 m depth. The routings have been
extracted from a general site plot plan and will be confirmed via site survey during the
detailed project design phase by the engineering, procurement and construction (EPC)
Contractor. An underground survey has been commissioned by Pearl Petroleum. The
existing flowlines are routed to the north-west corner of the existing Cryo# plant.
As mentioned earlier, the main four areas (as shown in Figure 2-2) within the KM
fenceline are:
• existing EPF and Cryo# Plant
• KM Expansion Area (to the south of the existing EPF/Cryo plant)
• Development Area
• Offsites Area.
Pearl Petroleum 6
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Figure 2-4 Location of existing and proposed future KM production wells and flowlines
Pearl Petroleum 7
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
2.5 Description of KM250A Project
2.5.1 Introduction
Pearl Petroleum intends to conduct a phased development of the existing gas plant with
capacity initially increased by debottlenecking of the EPF, which was completed in Q4
2018. The first phase (KM500 project) is to add a nominal 500 MMscfd of sales gas export
and 26,000 bpd of condensate export with two 250 MMscfd gas trains. These gas trains
will be phased with the first 250 MMscfd train (KM250A) to be completed in 2022. The
proposed KM250A Project (the subject of this ESIA) involves engineering design,
procurement and construction of a gas processing facility capable of producing sales gas,
LPG and condensate within the existing 600 ha site via the first of two gas treatment
trains. Up to five additional flowlines (from up to five new production wells) external to the
site boundary will also be required.
For the first 250 MMscfd gas train, sales gas will be routed through the existing 24’’ sales
gas pipeline to Erbil, Chemchemal, Sulaymaniyah (Bazian) power stations. Liquified
petroleum gas (LPG) will continue to be exported by truck. Condensate will continue to
be transported by truck and/or pipeline to Jambur.
Some of the existing facilities will be used in the KM250A Project, and there will be tie-
ins with the existing facilities. The Project will also include
• new flowlines
• rerouting of the existing condensate export pipeline to Jambur.
Construction is anticipated to start end of Q3 2020 with completion and first production
of gas/liquids by the end of Q1 2022.
Pearl Petroleum 8
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
2.5.3 Expansion Area
The Expansion Area is about 1.5 km by 1.5 km. The main KM250A gas processing facility,
which will be located within the Expansion Area, will comprise
• new production manifold and test manifold
• common new reception facilities (new gas/liquid separator, hydrocarbon
liquid/water separator and test separator)
• one 262.5 MMscfd gas processing train (KM250A) consisting of the following
unit operations:
• de-ethylamine (DEA) unit for gas desulphurisation
• molecular sieve gas dehydration units
• mercury removal unit
• gas dew pointing and LPG recovery unit
• de-ethaniser and debutaniser to refine NGL to raw LPG to supply the local
market
• common condensate stabilisation unit
• common flash gas compression.
In addition to the gas processing plant and the new flowlines (as mentioned above), the
KM Expansion Area will also include the following developments:
• flares
• central control building and laboratory
• utilities and central power generation area
• KM Expansion Area project offices, construction workshops/yards/laydown
areas, designated muster areas and the construction accommodation camp.
The section of the existing condensate export line to Jambur located within the site
perimeter fence will be rerouted as part of the Project.
Pearl Petroleum 9
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
o new truck weighbridges or incoming trucks, two for outgoing trucks
o new truck access roads including new road to the LPG loading facility.
2.5.5 Tie-ins
As mentioned earlier, the Project requires various tie-ins to the existing facilities for the
gas processing operations and transportation of the sales gas, condensate and LPG. The
main tie-ins are shown in Table 2-2.
Condensate tie-ins and facilities will allow
• combined storage of condensate from KM250A and existing operations in the
existing and new condensate storage tanks
• Cryo# and KM250A condensate export to a new condensate truck loading
facility (located in the Development Area)
• KM250A condensate export to the existing Jambur export pipeline (a short
section of this pipeline within the site perimeter will be re-routed to run just north
of the KM Expansion Area footprint)
• tie-ins to storage and export facilities planned in future expansion phases.
Tie-ins will allow the use of Cryo# plant selected utilities and services to support the tie-
ins described above such as firewater, instrument air and fuel gas. Transfer of EPF/Cryo#
plant control from the existing control room to the KM central control building (located in
the KM Expansion Area) will be implemented.
Pearl Petroleum 10
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
all within a few kilometres of the site. New 10” flowlines (that are within the scope of the
current ESIA) will bring additional gas to the site from new production wells.
For the KM expansion a northern and southern flowline/trunk line corridor will be
established. The southern flowline/trunkline corridor runs approximately 20 m inside the
existing site eastern perimeter fence. This will allow installation of a planned security track
and inner fence. The northern flowline/trunk line corridor will be inside the export pipeline
corridor along the eastern perimeter fence.
KRG and Ministry of Natural Resources (MNR) do not require formal restrictions on
access to the flowline corridors/right-of-way (RoW) during flowline construction.
Nonetheless, Pearl Petroleum will take precautions to avoid possible risks associated
with entry of non-Project personnel to the construction; areas by 1) marking the routes;
2) making concerned parties aware of construction activities within the corridors or below-
grade activities (although farming in the area may not be precluded); and 3) conducting
frequent inspections along the corridors conducted by dedicated inspection personnel.
At the inlet to each flowline there will be a removable spool to allow installation of a
temporary pig launcher to facilitate commissioning and periodic inspection of the flowline.
The outlet of the flowline is equipped with a removable spool to allow installation of a
temporary pig receiver to facilitate commissioning and periodic inspection of the flowline.
The inlet gas separator is a two-phase gas liquid separator designed for the full KM500
gas processing capacity; it is designed to operate during initial high pressure (HP)
operations at 76 barg. Liquid holdup in the separator is not expected; any liquids will drain
by gravity to the downstream inlet liquid/liquid separator. The separator separates liquid
from the gas stream before the gas is routed downstream for further processing. The
separator does not have any slug holdup volume.
The liquid/liquid separator is nominally a three-phase separator, although the vapour
space allowed for vapour separation is small, as very little vapour carried over from the
inlet gas separator is expected. Any vapour separated is routed back to the inlet gas
separator via a balance line.
Pearl Petroleum 11
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Figure 2-5 KM250A Project gas plant flow diagram
Pearl Petroleum 12
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
2.5.6.4 Amine unit
The amine unit consists of the amine contactor and an amine regeneration system. The
amine contactor is a trayed column that uses DEA to remove hydrogen sulphide (H2S)
from the process gas so that the gas export specification can be met and to ensure that
downstream equipment does not need to be specified to standards required for H2S-
containing gas streams. The amine contactor has single block valve isolation at its inlet
and outlet such that the entire KM250A gas train would need to be depressurised but
would not need to be fully de-inventoried for maintenance to be affected on the amine
contactor. The contactor has a manual hydrocarbon skim facility to allow any hydrocarbon
build up in the vessel to be removed. Liquids (rich amine stream) in the amine contactor
are routed under level control to amine regeneration (amine flash drum). Fresh lean
(regenerated) amine is fed into the column at the top under flow control.
The amine regeneration system receives H2S-rich amine from the amine contactor. Its
pressure is let down to that of the amine flash drum, which operates at about 5 barg. The
amine flash drum also receives liquids from scrubbers and coalescers downstream of the
amine contactor that may contain amine carried over from the contactor. Rich amine from
the amine flash drum passes through the rich amine filters to remove solids (that can
cause foaming) and receives pre-heating by recovery of heat from the hot lean amine
stream exiting the amine still using the lean/rich amine exchanger.
Warm rich amine enters the amine still (under level control from the amine flash drum).
The amine still treats the rich amine to remove H2S (and co-absorbed carbon dioxide)
with heat provided by the amine reboiler and reflux by the amine reflux condenser air
cooler. The H2S-rich acid gas is routed to the thermal oxidiser (or future sulphur removal
package), joining the offgas stream from the amine flash drum.
From the amine still, hot lean amine is pumped back by amine booster pumps via the
lean/rich amine exchanger to recover heat. The amine cooler is provided to further cool
the amine to the required operating temperature for the amine contactor. The temperature
of the amine leaving the air cooler is controlled such that the exit temperature of the amine
is 5 to 10°C warmer than the process gas stream entering the amine contactor in order
to minimise condensation of hydrocarbons in the amine contactor.
Desulphurised gas leaves the amine contactor and enters the treated gas scrubber which
is designed to catch any amine carried over from the upstream contactor to both minimise
amine loss and protect the downstream dehydration molecular sieve. The treated gas
scrubber is equipped with a water wash system which circulates water to minimise the
amount of amine that is lost to the downstream system. The wash system has a single
pump as the wash system is not critical to operation of the gas train.
A gas analyser which measures the amount of H2S in the gas outlet stream will be
installed downstream of the treated gas scrubber. There is a spill-off valve to flare
downstream of the treated gas scrubber which allows gas to be vented to flare during
start-up such that the desulphurisation system can be brought up to minimum flowrate
operation and the correct H2S specification of the gas reached before gas is routed to the
downstream systems. The treated gas scrubber includes anti-foam chemical injection
points to minimise the risk of amine solution foaming. Make-up water is with weekly batch
injection of deaerated demineralised water.
Pearl Petroleum 13
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
2.5.6.5 Dehydration and mercury removal
Dehydration of the desulphurised gas is achieved using molecular sieve beds. Gas flows
from the amine unit to a dehydration superheater, which adds one or two degrees of
superheat to the gas entering dehydration by heating a side stream off the main gas flow
(to minimise equipment size) thereby avoiding liquids condensing upstream and on
contact with the molecular sieve beds due to cooling or retrograde condensation (which
can cause problems with the beds).
Three molecular sieve beds are to be installed with two beds in dehydration mode via
adsorption, dehydrating the gas whilst the third bed is undergoing a regeneration cycle.
Each molecular sieve bed is equipped with double block and bleed valves on all inlets
and outlets such that a single bed can be taken offline for maintenance without the entire
KM250A gas train being taken out of service (although a 40-50% reduction in throughput
will be required). The molecular sieve system is designed for the raw gas flow through
the plant in addition to the recycled regeneration gas that enters the process upstream of
the molecular sieve beds.
Regeneration gas for the molecular sieve beds is taken from downstream of dehydration.
Gas is compressed to a high enough pressure to flow through the regeneration system
and be recycled back upstream of the inlet of the dehydration inlet coalescer. There are
three modes of operation for the recycle gas:
• Regeneration heating: In heating mode the regeneration gas is heated to about
260°C in the regeneration gas heater with the hot gas being routed through the
molecular sieve bed being regenerated with the flow routing controlled by
automated switching valves.
• Cooling: In cooling mode the regeneration gas is bypassed around the
regeneration gas heater. The gas then enters the hot molecular sieve bed
thereby bringing the molecular sieve bed down to the normal adsorption
temperature.
• Standby: In standby mode regeneration gas is bypassed around the molecular
sieve beds (in between other operating modes or switching the molecular sieve
bed to be regenerated) such that there is no need to stop/start the regeneration
gas compressor and the system runs with a stable operating flow.
After exiting the molecular sieve beds, warm/hot regeneration gas, which is high in water
content, is routed through the regeneration aftercooler. After cooling, the regeneration
gas is routed to the regeneration knockout (KO) drum to separate the liquid water and
gas. Regeneration gas at its water dew point is routed back to the process upstream of
dehydration (or to flare if the regeneration gas compressor is bypassed). Removed water
is routed to the condensate stabiliser feed separator under level control such that any
bulk hydrocarbons are removed prior to the water being routed to the produced water
degasser.
Gas next passes to the mercury removal unit (although mercury has not been present in
current operations, mercury removal has been included for KM250A). Mercury is
removed to avoid:
• damage to the downstream aluminium plate-fin exchanger
• hazards to personnel during maintenance of the downstream cryogenic
process.
Pearl Petroleum 14
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
A mercury guard bed downstream of the molecular sieve beds is used to absorb mercury
from the process gas using a non-regenerable absorbent. The mercury guard bed is
equipped with a single block valve at its inlet and outlet such that the entire KM250A gas
train would need to be depressurised but not fully de-inventoried to affect maintenance
on the unit.
All mercury wastes will be managed in accordance with good international industry
practice (GIIP).
Pearl Petroleum 15
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
provide cooling flow to the column. The remaining portion is taken off as raw LPG product
under pressure control and routed to existing LPG storage.
Pearl Petroleum 17
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
• power generation
• fuel gas
• plant and instrument air
• nitrogen generation
• demineralised water
• firewater system.
Further details on key utilities are provided in the following sections.
2.5.8 Flares
The design includes the following flare systems:
• HP flare system, with two separate headers
• HP flare header (for hot/wet releases)
• low temperature (LT) flare header (for cold/dry releases)
• LP flare system, with a single header
• low-low pressure (LLP) flare system for condensate storage where a very low
backpressure is required.
Each of the flare systems will be provided with its own dedicated KO drum, associated
pumps and flare stack with pilot and ignition systems. Liquids collected in the HP flare
KO drum are pumped to the LP flare KO drum from where combined liquids are pumped
to the condensate stabiliser feed separator for reprocessing. The LP flare KO drum will
also receive liquids for reprocessing from the closed drain drum.
Common HP and LP flare systems shall be provided for KM500 (that is, suitable for both
KM250A and KM250B combined). These shall be provided initially in a temporary
location, close to the KM500 plot space south of the KM250A gas plant site, within the
existing site fenceline, and will be moved at a later stage to a remote flare system area
outside of the southern site fenceline. All flare hydraulics shall be based on the final flare
location and the HP and LP flare headers provided with flanged tie-ins, without valves, to
allow future tie-in of the permanent flare systems. It is intended that the temporary flare
systems initially provided for KM500 will be used for later gas plants (that is, KM1000).
There will be no routine flaring during operations.
2.5.10 Drainage
The drainage system is designed to allow the disposal of liquid inventory and surface
water runoff from the Project site in a safe manner. The Project will have closed and open
drains. Aqueous and hydrocarbon fluids will be segregated in both systems.
Pearl Petroleum 18
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
2.5.10.1 Closed drain
Closed drains will be provided to collect the hydrocarbon residual liquids from process
equipment. The closed drain system will be a hard-piped collection system based on
gravity flow for the collection of drain liquids. The closed drain system will have vent lines
connected to the LP flare system.
No process system will be drained to the closed drain system unless the process system
is fully depressurised. Hydrocarbon liquids collected in the closed drain drum will be
pumped to the condensate separator, which is an automatically initiated operation. An
alternative disposal route to the new condensate storage tank will also be provided for
use during the full plant shutdown. Aqueous fluids collected from the closed drain drum
will be pumped to the produced water treatment facility.
2.5.11 Venting
An air assisted vent will be provided to dispose of gases vented from condensate trucks
during filling operations. Vapours released from the tankers during filling will be diluted
with air using forced draught and the vapours released to atmosphere via a vent
(approximately 1300 tonnes/year). Pearl Petroleum is considering various abatement
measures, including flaring and a vapour recovery unit. These options will be further
investigated during the detailed engineering phase of the Project. A new condensate
export pipeline to Chemchemal will be installed in the near future which would obviate
the need for tanker loading operations at KM.
A cold vent is provided for the rental sales gas compressors. The cold vent will be used
for emergency blowdown of the compressors and for maintenance depressurisation.
Volumes vented are expected to be low and infrequent.
Atmospheric vents will be provided for the release of air and inert gases if required.
Atmospheric vents will be blinded during routine operation to prevent accidental releases.
Pearl Petroleum 19
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
2.5.12 Produced water
Production wells are initially expected to produce very little water (based on experience
of existing wells), such that only condensation water will be produced. Later in field life
produced water is expected to break through into the wells such that the design flow of
water is to be 11,000 bpd. The timing of increased produced water production is difficult
to predict. Consequently, the produced water treatment system is designed such that its
capacity can be easily expanded when required.
Produced water will be sent to the produced water degasser. The KM250A produced
water treatment plant shall initially be designed with a capacity of 2,000 bpd, with the
capability to be expanded up to 11,000 bpd. Produced water shall be treated to a
standard where it can be safely discharged to the environment. Water from the degasser
is routed to a skimming tank via a coalescer to remove any hydrocarbons; water from the
skimming tank is routed to a lined evaporation pond for disposal. Water in the evaporation
pond will contain less than 100 mg/L of condensate (Hatch, 2019c). Gas from the
produced water degasser will be routed to the LP fuel gas system.
Pearl Petroleum 20
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
the distance to the nearest sensitive receptors outside of the site fenceline imply that
safety zones extending outside of the fenceline may not be necessary; this will be further
evaluated by Pearl Petroleum during the detailed design phase (see Section 5.10).
Nonetheless Pearl Petroleum will continue to work with Project-affected communities with
regard to emergency response planning and exercises; the existing Emergency
Response Plan will be extended to incorporate the KM250A Project (see Section 11
Safeguards, Measures and Plans).
Buffer zones could eventually be designated in relation to recognised biodiversity or
critical habitat zones within the KM250A Project biodiversity/ecology area of influence
following further evaluation (see Section 6 Mitigations measures). The engineering,
procurement and construction (EPC) Contractor will establish a temporary exclusion
zone around the flowline construction sites. Once the flowlines are covered and the area
revegetated, the flowline RoWs will be reopened to local stakeholders, although certain
activities within the exclusion zone for the life of the KM250A Project (especially digging
and installation of structures).
Pearl Petroleum 21
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Table 2-3 Cut and fill earthworks
Aggregate required for backfilling will be transported from a quarry by truck. The volume
of aggregate and other materials required will be specified during the EPC phase of the
Project. Further earthworks will be required after early works, with required volumes of
backfilling to be determined during that stage of the Project.
The surface will be sealed concrete paving in equipment areas where hydrocarbon
spillage could occur. Specific activities will include grading and drainage of:
• KM250A Project site
• Development Area.
A road layout will be designed. For road structures, sub-base and base layers shall be
put in place before paving and other areas with no traffic might require paving to favour
surface drainage. Gravel surface will be placed at places where there is no paving or
roads.
The early works contractor will excavate culverts and ditches.
Water will be sprayed to suppress dust while earthworks are undertaken.
The following other activities are due to take place as part of the early construction work:
• demolition or removal of warehouses/equipment laydown area and the drilling
equipment warehouse located in the North Development
• relocation of Cryo# LPG offices and car parking
• cutting of 20” Jambur pipeline and removal of the parts of the pipeline that are
within the Khor Mor site and rerouting
• protection of existing Flowlines and other services within the limits of the
Project.
The elevation of the Project equipment pads will be developed to achieve a cut and fill
balance, so no materials will need to be sourced from outside the site to be used as
general backfill. Granular material will nonetheless be required and will need to be
sourced outside the plant from existing nearby quarries.
Early works will be managed under a specific Project HSE Plan for each scope. Bridging
will be in place between the relevant contractor and Pearl Petroleum. The specific Project
HSE procedures (for example for control of work) have already been established. The e
bridge will determine whether the contractor, an existing Pearl Petroleum operation, or a
Project-specific procedure will apply
Pearl Petroleum 22
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
2.6.1.2 Installation of main equipment
2.6.1.2.2 Flowlines
The flowlines from production wells to the gas plant will have the same stages of
construction. Where a new flowline is to be installed alongside an existing hydrocarbon
pipeline, appropriate separation distances will be observed to prevent accidental damage
to the existing pipeline.
The buried flowline installation stages are as follows:
• RoW preparation, stripping and grading
• pipe stringing
• welding
• excavating the trench
• lowering flowline segments into the trench
• backfilling the trench.
The flowline RoW will be surveyed and marked out. As necessary, stakeholder
engagement will determine whether (and where) the working corridor may disturb
farmland, and where land is sufficiently fertile to warrant clearing of vegetation, stripping
of topsoil and stockpiling vegetation and topsoil for re-use during reinstatement work. The
flowline contractor will grade the RoW to create a suitable work surface for construction
vehicles and erect temporary security barriers around the section of the RoW where work
is in progress.
Flat-bed trailers will transport the pipe sections to the laydown areas where they will be
stockpiled. When the RoW has been marked out, trucks will set down sections of pipe
along the route, laying the ends on sandbags or pipe holders to protect the pipeline
coating. A mechanical excavator will dig a trench of suitable width and depth for the
diameter of the pipeline in question along the marked pipeline route.
Soil from excavating the trench will be placed into heaps running beside the trench. The
trench will be deep enough to allow the pipeline to be buried with 1.2 m of fill over the top
of the pipe. If the trench bottom has abrasive soils that could damage the pipeline’s
polyethylene coating, clean sand from local commercial sources will used as padding to
line the bottom of the trench and give the pipeline a smooth bed to lie on.
The pipeline contractor will line up the pipeline sections, fixing the ends with clamps, and
weld the sections together to form a continuous pipeline. Once the welds have been
inspected radiographically or by ultrasound and the welds approved, polyethylene shrink
wrap coatings will be applied to protect the field joints. Side-boom tractors will lift the
pipeline and lower it into the trench. When it has been installed in a section of trench, the
Pearl Petroleum 23
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
pipeline coating, field joints, fittings, and bends will be inspected and repaired as
necessary, before backfilling.
Mechanical excavators will use rock-free sand to backfill around the pipe and to cover
the pipe to a depth of 30 cm from the surface. The contractor will then backfill the rest of
the trench using native material excavated during trenching. The backfilled earth will be
compacted using a roller or hydraulic tamper.
Pearl Petroleum 24
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
The majority of construction workers will reside at the site. The construction camp will be
self-contained and include contractor accommodation, catering/welfare facilities,
workshops, warehouses and equipment/piping/materials laydown areas, as well as
security, office buildings, accommodation units, catering and laundry services, mosque,
medical clinic and recreational facilities. Camp utilities typically include diesel power
generators, diesel fuel storage, potable water storage, sewage and wastewater
treatment, irrigation water storage and treated wastewater evaporation pond (lined). Car
parking areas for cars and buses stop will facilitate worker transportation.
An area in the south of the KM Expansion Area has been selected for the KM250A Project
construction camp.
Pearl Petroleum 25
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Figure 2-6 Planned access routes during construction phase of KM250A Project
Pearl Petroleum 26
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
2.6.1.7 Site security
The KRG Ministry of Interior provides and manages an Oil Police Force (OPF) of 125
persons to protect and secure the immediate local area of the KM oil and gas production
fields and gas processing facility. This service includes permanent road checkpoints on
roads outside of the KM processing facility fenceline as well as protection of the 11 km
processing facility perimeter. Pearl is invoiced by MNR for services provided by the OPF
at an agreed rate that applies to all oil and gas operators in the KRI.
A further 52 Peshmerga personnel are deployed by the KRG for area security; additional
forces are provided by the Counter Terrorist Unit based within the KM area as required.
The Asaish (local police force) also support protection of the site.
Security within the KM site is the responsibility of a private security company that was
contracted by Pearl Petroleum for two years via an open tender process that conformed
to MNR procurement guidelines. This group provides mobile armed escort services, static
guarding services, explosive detection and canine search teams. The contract is re-
tendered bi-annually to ensure that the services provided are in line with the latest KRG
security threat matrix and the current security situation at the KM site. Pearl Petroleum
policy and standard procedures are integral to this contract.
The MNR have a full-time representative at the site; this person participates at many of
the regular business meetings held at the site, and has the right to participate at all
meetings. Pearl Petroleum actively engages and consults with the MNR representative
on all matters. Pearl Petroleum’s regional General Manager, based in Erbil, has weekly
meetings scheduled with the senior MNR representative to address all aspects of the
business. Topic-specific engagement occurs on a frequent basis.
The current permanent asset protection/security presence on-site will be maintained
throughout the construction phase of the Project. Access to the site will be via the South
and East VCP where vehicles will be security screened. Within the site, a new asset
protection control building will be constructed to provide overall services, and as access
to the process plant. This system will be in place for all Project phases (that is,
construction, pre-commissioning/commissioning, operations and decommissioning) and
is therefore not covered in those sections.
Pearl Petroleum supports voluntary principles regarding security and human rights in the
extractive sector, concerning risk assessment, relations with public security, and relations
with private security: 1: Key features of these principles, which are in place at the existing
KM site, are as follows:
• The ability to accurately assess risks present in the operating environment is
critical to the security of personnel, local communities and assets, the success
of Pearl Petroleum's short and long- term operations; and to the promotion and
protection of human rights. Civil society, home and host government
representatives, and other sources are consulted to identify risks presented by
the potential for violence. Pearl Petroleum will examine any patterns of violence
in areas of their operations. Available human rights records of public security
forces, paramilitaries, local and national law enforcement, as well as the
reputation of private security, are considered. Identification of and
1 Adapted by Pearl Petroleum based on Khor Mor LPG Recovery Plant CPDG Corporate Security Policy
(document KM-P-SEC-001 Rev. 4).
Pearl Petroleum 27
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
understanding the root causes and nature of local conflicts, as well as the level
of adherence to human rights and international humanitarian law standards by
key factors is instructive for the development of strategies for managing
relations between Pearl Petroleum, local communities, Pearl Petroleum
employees and their unions, and host governments.
• Pearl Petroleum recognises that Iraqi and Kurdish regional governments have
the primary role of maintaining law and order, security and respect for human
rights. Pearl Petroleum have an interest in ensuring that actions taken by those
governments, particularly the actions of public security providers, are
consistent with the protection and promotion of human rights. Pearl Petroleum
consults regularly with host governments and local communities about the
impact of their security arrangements on those communities and
communicates their policies regarding ethical conduct and human rights to
public security providers.
• Pearl Petroleum records and reports any credible allegations of human rights
abuses by public security in their areas of operation to appropriate host
government authorities. Where appropriate, investigations are undertaken and
actions are taken, as required, to prevent any recurrence.
• Private security entities employed by Pearl Petroleum must observe Pearl
Petroleum policies regarding ethical conduct and human rights; the law and
professional standards of the country in which they operate; emerging best
practices developed by industry, civil society, and governments; and
observance of international humanitarian law. Private security must maintain
high levels of technical and professional proficiency, particularly with regard to
the local use of force and firearms. Private security must exercise restraint and
caution in a manner consistent with applicable international guidelines
regarding the local use of force, including the United Nations Principles on the
Use of Force and Firearms by Law Enforcement Officials and the United
Nations Code of Conduct for Law Enforcement Officials, as well as with
emerging best practices developed by Pearl Petroleum, civil society, and
governments.
No formal memorandum of understanding is in place concerning provision of the above
services; however, Pearl Petroleum has outlined its expectations regarding the voluntary
principles and use of force with the MNR and OPF representatives, who have verbally
confirmed that the principles have been established for government forces. Pearl
Petroleum maintains regular and frequent contact with public security forces, ranging
from field level contacts (between Pearl Petroleum’s Asset Protection Manager and local
security forces) to senior level contacts (between Pearl Petroleum’s senior leadership
and KRG/MNR/Ministry of Interior representatives).
Pearl Petroleum 29
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Pearl Petroleum will operate plant lighting at night for safety. The plant is designed not to
require flaring during routine operations, but flare systems will be available for use when
required and flare pilots will remain lit at all times.
During operations there will be significant logistics activity. Supplies of, proprietary oil for
the hot oil system, amine, and water treatment chemicals will be procured and delivered
to the Project site by road.
Pearl Petroleum 30
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
if routing to the HP flare header would be more costly (e.g. if a separate HP
sub header would need to the area for that source). Otherwise it can be routed
to the HP flare header.
• Any relief source that has appreciative amounts of water must be routed to the
HP flare header.
• LP vent sources are routed to the LP flare header.
• Vents/blowdown of temporary sales gas/booster compression is routed to a
local cold vent.
• Vent gas from the new condensate storage tank is routed to a dedicated LLP
flare.
2.6.3.3 Maintenance
Pearl Petroleum has a permanent maintenance team with its own maintenance storage
and warehouse which will be based at the KM site. The maintenance team performs
routine maintenance of rotating equipment and pumps, such as topping up lube oils and
fitting replacement parts. Firefighting systems will be function tested regularly.
Planned major maintenance will be conducted in accordance with the plant maintenance
strategy and plan, based on criticality analysis, reliability and availability requirements.
This will allow for the internal inspection of vessels and contactor beds, and the
replacement of spent catalysts and mol sieve. It will also allow safety critical equipment
to be tested.
Pearl Petroleum staff will drive the pipeline routes on a regular basis to inspect the
pipelines for problems that may lead to damage and to look for any sign of leaks. Planned
maintenance of the pipelines will include running pigs for condition monitoring and
corrosion management.
2.6.3.4.1 Accommodation
Operations staff will be based in the site accommodation block and have a rotational
cycle with equal time off. Therefore, two postholders (‘back-to-back’) will occupy each
position. Production staff will provide 24-hour cover working 12-hour shifts. Maintenance
staff will work day shifts but will provide night and emergency cover.
2.6.3.4.2 Recruitment
Local labour will be employed by Pearl Petroleum at the KM site to the maximum extent
possible, with due consideration to the technical job description and availability of local
workers who meet the requirements laid out therein. The workforce will travel to the
KM250A Project site from the local area or stay at the construction accommodation camp.
2.6.3.4.3 Training
Pearl Petroleum provides in-house training for all positions related to the existing (LPG
plant) site. This will be extended to the KM250A Project. Induction training for new
Pearl Petroleum 31
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
employees is offered in security and health, safety and environment (HSE). Regular
training will be provided to workers according to their respective positions, include
• emergency response
• workplace safety (e.g. working in confined spaces and at height)
• first aid
• personal protective equipment (PPE).
Third party training is also offered.
2.6.4 Decommissioning
The plant will be decommissioned once Pearl Petroleum determines that its effective life
has been achieved. Specification of decommissioning activities will be developed closer
to the decommissioning date. Decommissioning activities will be executed in a manner
consistent with the Decommissioning Plan which will be agreed with the MNR prior to
commencing decommissioning activities. For safety of personnel and the environment,
decommissioning activities will be implemented after operations have been ceased and
equipment properly deactivated.
Pearl Petroleum is likely to return the site to its pre-development condition following
decommissioning, although the decision regarding the state of the site to be achieved
following closure will be based in part on further assessment by Pearl Petroleum and
consultation with responsible authorities and other stakeholders, which will take place
closer to the expected date of plant closure. Typically, decommissioning a facility involves
the following stages:
• depressurise plant
• remove all hydrocarbons to render the plant inert
• remove all chemicals and certify that the whole plant is hydrocarbon and
hazardous chemical-free
• disconnect and dismantle the equipment, and remove modules and scrap from
the site for refurbishment or recycling
• demolish structures and paving and remove the materials from site as inert
waste
• level the site and undertake soil and groundwater survey to determine whether
any remediation is needed.
• spread stored topsoil for site rehabilitation.
Typically, decommissioning pipelines by cleaning and abandonment in-situ involves little
environmental disturbance. If the flowlines are removed, decommissioning would involve
the following stages:
• flush and inert the pipelines using water and pig trains, then empty them
• excavate the pipeline trenches
Pearl Petroleum 32
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
• cut the pipeline into sections, lift them from the trench and remove as scrap for
recycling
• backfill the trench and restore the RoW to its original profile, spreading topsoil
and replanting where appropriate.
A Decommissioning Plan for the KM site and wells will be developed. The detailed
programme for decommissioning will be determined and agreed with the KRG authorities
prior to shut down. Decommissioning and dismantling will be performed by specialist
contractors supported by a core team of project operations and maintenance personnel
and will need to follow the waste hierarchy to minimise waste.
Pearl Petroleum 33
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Table 2-6 Expected Project water use during operations
2 Construction traffic will comprise haulage/construction vehicles and vehicles used for workers’ trips to and from
the site.
Pearl Petroleum 34
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
• movement of vehicles over surfaces where muddy materials have been
transferred offsite (for example, on to public roads).
2.8.2 Noise
Pearl Petroleum 35
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
• graders, concrete mixer trucks and dump trucks that typically generate 75-80
dB LAeq at 10 m
• large power generators that typically generate 80-85 dB LAeq at 10 m.
Installation and erection of process modules will involve the use of cranes and welding
set generators that typically generate less than 75dB LAeq at 10 m.
Pipeline construction will involve the use of:
• excavators, side booms and welding sets that typically generate less than 75
dB LAeq at 10 m
• dump trucks that typically generate 75-80 dB LAeq at 10 m
• a rock breaker that typically generate 80-85 dB LAeq at 10 m.
All these noise sources will be mobile within the limits of the Project site and the flowline
RoWs. Furthermore, delivery of process modules by road will involve the use of haulage
trucks that typically generate less than 75 dB LAeq at 10 m.
2.8.3 Liquids
Pearl Petroleum 36
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
• Waste lubricating and hydraulic oils generated during construction or by
maintenance will be contained in a slop tank and sent to an authorised waste
oil recycling facility offsite.
2.8.4 Waste
There are landfill sites in the KRI approved by the KRG that receive unsorted non-
hazardous municipal waste (food waste, plastic, cans, bottles, aluminium, scrap metal).
Current practice in Iraq is to send these types of waste to landfill sites until recycling
options become available.
The destination of various waste streams generated at the existing Pearl Petroleum
facility is presented in Table 2-7 and will be adapted for all phases of the Project. A facility
for managing hazardous wastes to international standards does not currently exist in
Kurdistan. Waste oil is considered a hazardous waste. Current practice at the Pearl
Petroleum site relies on a third-party contractor to transport used oils to Asia Oil and
Dubai Oil facilities at Diyala for reprocessing. Other hazardous wastes (for example
batteries and waste liquids) are stored in a temporary waste storage facility at the site.
Batteries are removed from the site by a third-party contractor for processing and reuse.
Pearl Petroleum 37
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Table 2-7 Waste management at the existing Pearl Petroleum KM facility (CPDG,
2018h)
Waste
management Description of waste Destination
description
Food, cardboards, used water
Collected by approved third-party waste
Existing landfill bottles, foam products (plates,
contractor for offsite management
cups)
Collected by approved third-party waste
Barrels and scrap metals
contractor for offsite management
Collected by approved third-party waste
Used lube oil
contractor for offsite management
Collected by approved third-party waste
Batteries
contractor for offsite management
Recycled and Collected by approved third-party waste
Electric waste
reused contractor for offsite management
Collected by approved third-party waste
Tyres
contractor for offsite management
Electronic office equipment
Donated to Chemchemal schools
(printers etc)
Reuse for animal shelters and landscaping
Wood
(tree support)
Collected by approved third-party waste
Used filters
Incineration contractor
Medical wastes Sardam Hospital
Evaporation Produced water Produced water evaporation pond (lined)
Treatment Sewage On-site STP
Pearl Petroleum 38
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
2.8.4.2 Pre-commissioning and commissioning phases
Wastes generating during pre-commissioning are expected to be similar to those
generated during construction, but much lower in quantity. Commissioning phase wastes
will be similar to those generated during the operations phase of the Project, but in lower
volume as the pre-commissioning has a much shorter duration than the operations
phase.
Pearl Petroleum 39
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
expected to be small, therefore the flame would not be expected to be visible at nearby
villages.
During emergency (unplanned) situations, flare flames will be visible when lit; the visible
impact will be particularly noticeable at night. The height of high-level flares during
shutdowns of the gas treatment trains will determine the distance from which they are
visible. When process gases are flared, the flame of an 50 m high flare would, typically,
be visible at 30 km from the site under clear atmospheric conditions.
The various Project fractionation towers (including the de-propaniser and de-ethaniser
may be visible during the day at surrounding villages, and at night because they will
feature lighting for worker safety.
2.8.6 Traffic
Pearl Petroleum 40
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
2.8.7 Land use
Pearl Petroleum 41
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
in association with the KM250A Project, at the preliminary locations specified in Figure
2-4. The five new production wells will be subject to an additional detailed Environmental
and Social Impact Assessment (ESIA). Potential impacts and associated mitigation
measures to reduce potential impacts associated with the production wells are presented
in Section 5.11 and 6.8, respectively.
The well locations have been selected based on a review of satellite imagery,
geomorphological mapping and the results of seismic studies that indicated the potential
for hydrocarbon reserves. Development of these wells will be sequential.
The technical description of development of each of the wells will be similar, and will be
in line with the following general steps:
• site clearance and construction and/or upgrading of well pads and access
roads
• mobilisation (drilling rigs and auxiliary equipment and facilities)
• drilling operations
• demobilisation (removal of all other equipment and restoration of the
surrounding site to its original condition).
Pearl Petroleum 42
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
aboveground diesel storage tanks, compressors, drilling mud product processing area, a
flare pit, and a guard shack.
Power required for the camps and well site will be sourced from primary and backup
diesel generator (DG) sets, including stacks for exhaust emissions. These generators will
likely have ratings of 400 to 600 kVA each. The DG units will run 24 hours per day.
At each well site, fuel will be stored in two storage tanks within dedicated areas equipped
with spill containment measures to contain any unplanned discharges (spills and leaks).
The fuel dispensing area will be constructed with impervious flooring and/or drip collection
trays will be provided adjacent to the vehicle fuel storage area. Diesel tanks will have
secondary containment with a berm perimeter and a 2 mm high density polyethylene
(HDPE) liner able to contain 110% of the largest tank volume. Oil spill clean-up kits will
be placed at strategic locations.
A maintenance workshop will also be installed. Materials and spare parts will be stored
in containers.
2.10.2 Drilling
Drilling of each well will require approximately 75 days to complete, if conducted 24 hours
per day. A detailed drilling program has not yet been developed. The drill rig consists of
typical mobile land-based drilling units. The rig will be equipped with standard operational
and critical safety devices that meet industry best practices and company requirements.
Drilling typically proceeds by applying the weight of a drilling assembly and rotating the
drill string to turn a drill bit at its lower end. The drill string is typically made up of 9 m
sections of hollow drill pipe, and a bottom hole assembly including drill collars and down-
hole measuring equipment. The drill bit has a larger diameter, so that an annular space
is formed around the drill pipe as drilling progresses. The drill string is rotated by the rig’s
rotary table or by using a down-hole motor driven by the drilling mud (see below)
circulation. The drill bit cuts into the rock formation and detaches cuttings. Water-based
drilling mud is pumped into the drill pipe and through nozzles in the drill bit. The drilling
mud flushes the cuttings up through the annular space between the drill string and the
borehole wall and carries them to the surface.
At the surface, mud carrying cuttings from the borehole flows down an inclined mud return
line and is distributed to a rank of shale shakers. The shale shakers have vibrating
screens that separate rock cuttings from the drilling mud. The mud passes through
apertures in the shale shaker screens, and through a sequence of tanks (including a sand
trap) where equipment (mud cleaner and centrifuge) and settling removes small particles
of rock from the circulating mud. The mud is then recycled through the well.
The separated drill cuttings and solids are discharged initially into an excavated, lined
waste pit on-site. The well will be vertical. Once a section has been drilled to its target
depth using a drill bit of a given diameter, a tubular steel casing is run into the hole and
cemented in place. Subsequent sections are drilled with smaller diameter drill bits.
Reserve pits are being considered for collection of drill cuttings and drilling fluid from the
operating rig. The proposed pits will be open-top and lined with impermeable geo-
membrane liner. The volume of cuttings pits at each well site will be approximately
5,200 m3. The pits will be used for disposal, dumping, or storage of fluids, wastes, or
other debris and fluids used or recovered while drilling and completing the wells. The pits
Pearl Petroleum 43
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
will not be located within or near any water bodies or groundwater recharge or pumping
zones. They will be located such that they do not block natural drainage patterns. Fluids
from these pits will evaporate into the atmosphere during drilling and testing operations.
The pits will be of sufficient size to contain all the cuttings and fluids expected from the
drilling operations. In the case of stimulation/completion activities, the pits will be tested
to ensure the absence of any contaminants. Once this is confirmed, HDPE liners will be
placed over the top of the pits to enclose them. The pits will then be backfilled and
compacted using previously stockpiled surface soil and topsoil. The reclaimed pits will be
surface sloped, as practicable, to promote surface drainage away from the reclaimed pit
area.
Flare pits will be constructed and available as needed. The pits will be concrete-lined and
waterproof, and of sufficient capacity to collect any produced water or condensate
collected from the bulk gas stream upstream of the flare. Once the flare pits are no longer
required, they will be backfilled and compacted using previously stockpiled soil. Pitless
drilling is also being considered.
A water supply pit of approximately 5,000 m3 capacity will be installed at each well site
adjacent to the well pad, but outside of the berm for the well pad. Water will be supplied
from existing or drilled water wells in the vicinity of the respective well sites. Upon
completion, the lining of the water pits will be removed and stored for future use. These
pits will be subsequently backfilled and compacted using stockpiled soil.
There will be an OPF camp constructed off the well pad along the access road to the well
site at each of the five production well sites. Each OPF camp will accommodate about 45
people. Power for the OPF camp will be supplied using a diesel-powered generator.
Blowout preventer systems will be installed at the wellheads to prevent fluids from
unintentionally escaping from the boreholes. American Petroleum Institute rated rams
and annular preventers and drilling spools equipped with outlets for the choke and kill
lines will also be used. In addition, blowout preventer stacks and diverter elements will
be used for drilling of the surface hole sections. The well test package shall be equipped
with an integrated emergency shutdown (ESD) system, capable of securing the well in
an emergency. A testing programme (approximately two weeks) shall be conducted rig-
less.
Rig components include the mast, the draw work, a rotator table, a top drive, mud pump,
engines, and supporting generators. The rigs will have the following support equipment
in addition to the diesel engines: pickup trucks, a crane, a forklift, a cherry picker, an
ambulance, a passenger bus, a water truck, light plant generators, and a welding
machine. Welding machines will also be in use at the well sites and will run on diesel.
Some light vehicles may run on gasoline.
Drilling mud, which is required for lubrication of the drill bit and for removing cuttings from
the drilling face, will be water-based. Drilling mud will contain the following main
components: brine (base fluid), soda ash (for calcium removal), sodium chloride, caustic
(for pH control), xanthan gum (for viscosity control), and an H2S scavenger. The specific
drilling mud formulations for the lower portion of the hole will be adapted during drilling
operations depending on the type of material encountered during the drilling operation.
The drilling mud typically contains 80% water and the drill cuttings contain about 20%
water.
Pearl Petroleum 44
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Two drilling mud tanks, to be hydrotested before the operation to ensure integrity, will be
installed. Mud tanks will have secondary containment with a berm perimeter and a liner
of HDPE (2 mm thickness) able to contain 110% of the largest tank volume.
All produced water will go to the wastewater pit, as described above.
In total, approximately 20 to 50 m3/hour of industrial quality water will be required for
drilling. Potable water will be sourced from existing drilled wells or new wells to be drilled
with the water pumped to end users by pipeline. Daily peak potable water consumption
will be approximately 480 L per person, or approximately 150 m3 per day total. Additional
water for drilling fluid will be used. A series of water storage pits located on and off the
well pad will hold a combined total of 5,000 m3. Water storage capacity will be provided
by tanks installed at the base camp. There will be three water tanks, each with 40 m3
capacity.
The drilling program will require a work force of employees for manning the drilling rigs,
base camp operations (maintenance, kitchen, and housekeeping), and OPF operations.
To the extent possible, local people from within and around the project area will be
selected based on their skill sets and experience. Drill crews will be trained on HSE
topics, including necessary environmental requirements and the need to respect the
rights and interests of land owners and land users prior to the start of the drilling
operations. There will be approximately 100 people at the well site during the day; this
includes technical personnel, office workers, site logistics personnel, and security
personnel.
A drill rig camp will be established at the well site at the same location as the base camp
to support the drilling operations. The drill rig camp will be located at the actual well site
and will be sized to minimise environmental impacts. The drill rig camp will be powered
by generators and house approximately ten people. Other site workers will be transported
to and from the well site daily from the main KM gas plant site or surrounding
communities.
Traffic volume during drilling operations will be light, consisting of transport vehicles for
workers and supervisory staff taking approximately 10 to 20 journeys each day. Traffic
will increase during short periods of mobilisation and demobilisation (of people and
equipment) as well as during certain drilling activities, including, but not limited to, casing
installation and cementing and well stimulation. These higher volume traffic periods will
involve the mobilisation and demobilisation of the drill rig and support equipment as well
as the delivery of supplies needed for drilling.
The movement of equipment and vehicles associated with drilling operations will adhere
to all local traffic ordinances and laws. About 30 cars or light vehicles (mostly light
pickups) and 15 heavy vehicles could be expected to be deployed for the proposed
drilling operations at the well site.
Once hydrocarbons are reached, well completion will be implemented. This usually
involves installing production tubing to isolate production from the well annulus. Following
well completion, the wells will be capped. Flowline connections will eventually be
installed. Extended well tests will not be required. Short-term testing of discrete sub-
surface zones will require approximately 15 to 30 days. Stimulation of the well with an
acid treatment may be used to improve performance.
Pearl Petroleum 45
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
2.10.3 Demobilisation
Once drilling has been completed, the well site will be returned, to the extent possible, to
its original state and allow original uses to take place (including possible herding and
habitat for fauna). A small concrete pad to which access will be restricted will be left in
place directly surrounding the wellhead. All pipelines connecting the wellhead to the
nearest flowline will be underground. All residual water and oil in the pits (should the pit
option be selected) will be removed before the well sites are restored to their original
state. Once dehydrated, inert fly-ash, lime, or bio-remedial media will be mixed in with
the cuttings and other wastes to serve as a bulking agent.
Pearl Petroleum 46
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
2.10.5 Schedule
The required ESIA for the five wells will be completed during Q2 to Q3 2020. Drilling of
the first well is expected to take place in Q4 2020. The wells will be capped when drilling
has been completed and will come online at the expected KM250A gas plant start-up in
Q1 2022.
Pearl Petroleum 47
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
3 BASELINE PROPERTIES OF THE
ENVIRONMENT
3.1 Methodology
The baseline studies were conducted using a combination of secondary data (desk-
studies and data collected by others) and primary data (field surveys conducted by RSK).
The desk-based portion of the baseline study was undertaken through a review of various
documents and data sources that are referenced in the text. These included the following
ESIA and baseline studies, and various sources of information listed in the references
(Section 12):
• Environmental Social Impact Assessment Report (KM-9, KM-10 and KM-12)
Khor Mor Block, (MapCom, 2018)
• Khor Mor Gas Plant: Environmental Impact Assessment, (ERM, 2015)
• Environmental Baseline Survey, (MapCom, 2010)
• Kurdistan Gas Project Environmental Impact Assessment Volume i: Gas
Pipeline from Khor Mor to Erbil, (WorleyParsons, 2007).
Field surveys were undertaken in cases where existing data and information were
deemed insufficient, for noise, air quality, water quality, soil quality, and biodiversity, in
order to supplement desktop data and information (including information from previous
studies) and ensure that local data and information is up to date. Field survey
methodology is described in the sections below.
The area of influence (AOI) was defined for various topic areas based upon the definitions
given in the International Finance Corporation (IFC) Performance Standard (PS) 1 and
represent the geographical area expected to be affected by:
• impacts (direct and indirect) arising from Project activities and facilities (this
includes the Project site, flowlines, well pads, and road transport network used
for the transportation of personal and materials)
• impacts from unplanned, non-routine events
• indirect impacts on biodiversity or on ecosystem services that are linked to the
livelihoods of affected communities
• associated facilities consisting of five new production wells
• cumulative impacts.
The AOIs were used to guide baseline development and provide focus for environmental
and social impact assessment (ESIA) baseline activities. The specific AOI is presented
under each specific topic.
3.2.1.1 Geography
The Khor Mor site is located within the Garmiyan Administration of Sulaymaniyah
Governorate in the Kurdistan Region of Iraq (KRI). The Sulaymaniyah Governorate is
Pearl Petroleum 48
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
one of four governorates in the KRI. The study area is situated within Qadir Karam sub-
district, Chemchemal district.
The Khor Mor existing facility is located at an approximate elevation of 450 m above sea
level. The general area is characterised by very rugged topography with anticlinal
mountains. In the Khor Mor area, the landscape is primarily rocky and barren with narrow
valleys, ridges, hills, slopes and plains. Surface water bodies are relatively rare and
generally seasonal.
3.2.2 Geology
3.2.2.2 Stratigraphy
The surface geology in the block comprises primarily Tertiary and Quaternary age units.
Further details are provided below.
Pearl Petroleum 49
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
alternation of hard and soft rocks. This formation constitutes much of the surface outcrop
in the Khor Mor concession (Pearl Petroleum, 2018).
3.2.2.3 Seismicity
Tectonically, the KRI Iraq is located in an active seismic zone, thus it experiences an
appreciable level of earthquake activity. Th KRI is directly influenced by the seismicity of
the Alpine-Himalayan orogenic system (Zagros-Tauros range). This system, identified
with high mountain ranges and shallow, somewhat diffuse seismicity constitutes one of
the most seismically active continental regions of the world with a long and well-
Pearl Petroleum 50
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
documented history of earthquakes. The KRI is rated ‘very high’ for seismic hazards by
the World Health Organisation (WHO, 2010). Oil Serv (2018) conducted a seismic
investigation at the KM250A Project site and reported that the site is located in a Zone III
seismic zone.
3.2.3 Soil
3A soil that mixes itself: its surface layers shrink and swell, forming deep cracks into which soil falls.
4This term is used to describe a subsoil with a field texture of 35% or more clay that experiences significant
shrinking and swelling, resulting from drying and wetting.
Pearl Petroleum 51
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
of the soil are not sufficiently developed for a true vertisol. This is likely due to the high
CaCO3 content, which tends to suppress the swelling behaviour of the clay.
Upland/hilly soils in the Block consist of deep, brown soils and deeply eroded brown soils.
These brown soils yield important dry farming lands upon which wheat is grown or which
are used for grazing. The thickness of the soils varies with relief, whereby the deepest
soils exist on level plains and the shallower soils exist on the upper slopes and summits
of hills. Leaching and accumulation of lime and swelling and shrinking of clays in the
upland areas are generally more pronounced than in the plains and valleys. The lime
accumulation horizon tends to start slightly deeper in the upland areas than in the plains
and valleys due to higher rainfall in the upland areas.
In the valleys and river embankments, the soil is mainly alluvium consisting of gravel and
sand. The fluvisols present in the block have visible stratification and irregular amounts
of organic material.
All photographs of sampling locations are included in Appendix 2 (Table A2.1) along with
laboratory certificates. The sampling indicated that the soil is grey and brown silty and
sandy clay with root fragments. No evidence of visual or olfactory contamination was
observed at any of the locations.
Pearl Petroleum 53
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Sample storage was undertaken in accordance with the RSK quality management
system procedure and all samples were shipped to the Al Futtaim Element Materials
Technology Dubai laboratory for analysis.
The reported concentrations of all parameters were either below the laboratory detection
limit or below the Project Standard, with the exception of nickel concentrations as shown
in Table 3-3. Nickel concentrations exceeded the Project Standard at all locations and
may represent background soil conditions and composition. The KM250A Project will not
exacerbate nickel concentrations in soil. The soil sampling locations are presented as
Figure 3-2.
Pearl Petroleum 54
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Table 3-3 Laboratory results of the current soil sampling survey in 2019 (mg/kg)
Project
Parameter SS1 SS2 SS3 SS4 SS5 SS6 SS7 SS8 SS9 SS10 SS11 SS12 SS13 Standard
(mg/kg)
Arsenic 4.1 3.6 2 2.7 3.4 4.9 3.9 3.7 4.1 2.8 3.4 4.3 3.4 20
Barium 101 123 137 112 270 134 182 99.5 95.4 91 98.6 93.8 117 -
Cadmium <0.5 0.6 0.7 <0.5 <0.5 <0.5 <0.5 0.7 0.6 <0.5 <0.5 0.6 <0.5 3
Copper 19 21.1 20 17.9 21.7 20.5 19.4 17.6 17.1 16.8 22.1 19.7 19.7 100
Lead 8.1 9.4 7 6.7 7.1 6.9 6.2 6.2 6.5 6.4 7.6 7.9 6.9 300
Nickel 75.6 79.7 80.1 67.8 81.6 80.7 76 72.4 69.9 67.9 84.7 74.8 76.1 60
Selenium <3.0 <3.0 <3.0 <3.0 <3.0 <3.0 <3.0 <3.0 <3.0 <3.0 <3.0 <3.0 <3.0 -
Zinc 47.6 53.3 51.5 47.5 56.8 52.3 55.6 48.3 46.9 46.9 57.4 53.8 51.6 200
EPH C10-
53 <50 89 <50 72 <50 65 <50 <50 <50 <50 <50 <50 90
C40
VPH C5-
<0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 -
C10
Pearl Petroleum 55
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Figure 3-2 Soil sampling locations
Pearl Petroleum 56
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
3.2.4 Water resources
Pearl Petroleum 57
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Figure 3-3 Water resources and sampling locations
Pearl Petroleum 58
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Table 3-5 Status of existing abstraction wells in the Khor Mor area
Abstracted
SWL
Well Easting Northing Status Lithology/formation name volume
(m)
(L/week)
Temporarily Upper Bakhtiari
WW1 482105 3885755 11 No data
abandoned (claystone/siltstone/sandstone)
Upper Bakhtiari
WW2 481888 3885416 36 Operating 22,082,000
(claystone/siltstone/sandstone)
Upper Bakhtiari
WW3 482156 3884612 32 Operating 1,635,000
(claystone/siltstone/sandstone)
WW4 482664 3884538 NM Abandoned no data No data
WW5 481461 3884598 NM Abandoned no data No data
Pearl Petroleum 59
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Table 3-7 Summary of spring and groundwater results (MapCom, 2018)
Regular testing of samples of groundwater from WW1, WW2 and WW3 is undertaken by
Pearl Petroleum. The samples are tested for lead, copper, iron, nitrate, nitrite, pH,
chlorine, hardness, alkalinity, bacteria and pesticides. Data for the period of September
2018 to February 2019 were provided by Pearl Petroleum. With the exception of one
sample, none of the results exceed the Project Standard; on 30/2/18, at WW1, copper
concentrations (1.4 mg/L) exceeded the Project Standard of 0.01 mg/L and bacteria
tested ‘positive’.
Pearl Petroleum 60
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
completed at the EnviroLab laboratory in Basra (due to the fact that the samples required
testing within 24 hours). All samples were analysed in the laboratory for:
• turbidity
• selected inorganic parameters and dissolved heavy metals
• selected cations and anions
• hydrocarbons and polycyclic aromatic hydrocarbons (PAHs)
• pesticides
• bacteriological parameters (total coliforms and Escherichia coli).
The following quality control measures were implemented to ensure that accurate and
reliable data are collected:
• single use bailer sampling in wells/boreholes to prevent cross-contamination of
samples
• duplicate sample was taken to check reproducibility
• use of nitrile gloves to prevent contamination of samples.
• calibration of the multi-parameter probe prior to the survey
• daily calibration checks.
Table 3-9 and Table 3-10 present the field parameter readings for groundwater and
spring samples. The values are all typical of groundwater and springs. There are no
Project Standards for these parameters except for pH and DO. The pH is within the
Project Standard. The DO at some locations is < 5mg/L which does not meet the Project
Standard (> 5 mg/L).
Pearl Petroleum 61
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Table 3-9 Field parameter data for water resources (RSK, 2019)
Electrical
Temperature
Sample ID conductivity pH DO (mg/L) DO (%)
(°C)
(µs/cm)
20.1 793 8.33 0.98 10.9
Paryawla
20.1 792 8.34 0.85 9.4
well
20.0 792 8.34 0.83 9.1
25.2 319.3 7.56 2.54 30.9
WW2 25.2 317.8 7.59 2.73 33.2
25.2 317.6 7.59 2.68 32.6
24.6 290.5 7.57 6.43 77.4
WW3 24.5 314.8 7.64 5.68 69.4
24.5 317.3 7.74 5.45 65.5
Project
- - 6.5 to 8.5 >5 -
Standard
Red – does not meet Project Standard
Table 3-10 Field parameter data for water samples (RSK, 2019)
Electrical
Temperature
Sample ID conductivity pH DO (mg/L) DO (%)
(°C)
(µs/cm)
21.7 283.7 7.35 6.07 69.0
Khor Mor
Gawra 21.7 279.5 7.36 5.91 67.8
Spring
21.7 274.6 7.41 5.82 66.1
24.7 446.5 7.39 5.32 64.0
Taza Shar
24.6 424.5 7.21 4.64 55.8
Spring
24.6 407.3 7.14 4.61 55.4
21.2 363.6 7.05 3.68 41.5
Shekh
Hameed 21.1 360.8 7.04 3.49 39.3
Spring
21.1 355.7 7.06 3.29 37.1
23.4 353.4 7.33 3.31 38.9
SP2 23.4 353.2 7.32 3.31 38.9
23.4 351.9 7.31 3.33 39.2
23.9 264.4 7.38 4.68 55.5
SP4 23.9 263.8 7.36 4.56 54.1
23.9 263.6 7.35 4.58 54.3
21. 417.6 7.43 5.67 63.6
GW5 21 419.7 7.44 4.90 55.0
21 420.4 7.44 4.82 54.1
Pearl Petroleum 62
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Electrical
Temperature
Sample ID conductivity pH DO (mg/L) DO (%)
(°C)
(µs/cm)
19.6 1273 7.62 5.36 58.7
Zhazh Spring 19.6 1289 7.61 5.33 58.4
19.6 1302 7.61 5.30 58
25.7 403 7.26 2.67 32.4
Takhta Mina
25.7 402 7.27 2.56 31.4
Spring
25.7 400 7.27 2.46 30.1
24 612 7.63 4.99 59.4
Ibrahim
Ghulam 24 604 7.62 4.55 54.4
Spring
24 605 7.63 4.62 54.9
Project
- - 6.5 to 8.5 >5 -
Standard
Red – does not meet Project Standard
Groundwater depth levels were measured where possible and the results are presented
in Table 3-11. Photographs of all sampling locations are presented in Appendix 2 (Table
A2.2) along with laboratory certificates.
Note: mbtoc: metres below top of casing of well. No topographical data are available, so the levels
were not measured in relation to a local datum.
Laboratory results for the samples are shown in Table 3-12. All samples were compared
to the Project Standards (Appendix 3, Table A3.2 and A3.3). The results of the duplicate
sample that was tested (WW6 and SP3) indicated that the results are reproducible.
The results indicate the presence of total coliforms at all locations which exceeds the
Project Standard (1.1 colony forming units per litre) and water at these locations is not
considered potable without appropriate treatment. Concentrations of chloride, sulphate,
total dissolved solids, magnesium and calcium at Zhazh Spring exceeded the Project
Standards. Calcium concentrations exceeded the Project Standard at several locations.
No further exceedances were detected. All other parameters, including Escherichia coli,
hydrocarbons and PAHs were not detected. The coliform levels are due to improper
wastewater discharge in surrounding villages. The KM250A Project would not exacerbate
this problem. Similarly, regarding the high levels of TDS, chlorides, sulphate, magnesium
and calcium, raw groundwater is treated prior to human consumption, so there should be
Pearl Petroleum 63
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
no threat to local drinking water supply. The KM250A Project will not exacerbate the low
quality of raw groundwater.
In some cases, the laboratory limit of detection exceeded (mercury, cadmium and
phenols) or was equivalent (chromium, selenium, arsenic and lead) to the Project
Standard.
Pearl Petroleum 64
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Table 3-12 Laboratory results of the current water resources sampling survey in 2019 (mg/L or as stated)
Bacteriological
Escherichia coli No Growth No Growth No Growth No Growth No Growth No Growth No Growth No Growth No Growth No Growth No Growth No Growth No Growth No Growth <1.1*
Total coliforms
1000 100000 100 100 100 100000 1000 10000 100000 10000 10 10 10 100 <1.1
(cfu/L)
Anions
Chloride 7 9.5 11 10 8.5 24.5 9.5 334 10.5 20.5 50 7.5 7 8 200
Fluoride 0.5 0.4 0.3 0.3 0.3 0.6 0.2 0.7 0.4 0.9 1 0.5 0.4 0.6 -
Nitrate 0.66 0.49 1.02 0.58 1.24 1.86 0.66 0.89 1.99 0.66 2.17 0.4 0.71 0.18 15
Nitrite 0.016 0.02 0.026 0.02 <0.016 0.259 0.016 0.168 0.016 0.016 0.023 0.02 <0.016 0.02 3.0
Inorganic
Total hardness 191 370 370 185 178 218 262 677 210 147 60 140 134 141 500
Total dissolved solids 239 328 375 341 228 444 337 1450 306 398 600 215 203 215 1000
Surfactants anionic 0.015 0.018 0.017 0.017 0.018 0.017 0.016 0.017 0.015 0.017 0.016 0.015 0.016 0.017 0.3
Turbidity (NTU) 0.1 1.8 2.8 0.7 0.3 4.3 0.7 4.7 0.9 0.4 <0.1 <0.1 <0.1 0.7 5
pH (units) 8.2 7.8 7.7 7.9 7.9 7.9 8 7.9 7.7 8.2 8.3 8.1 8.1 7.9 6.5-8.5
Metals
Chromium <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 0.05
Mercury <0.030 <0.030 <0.030 <0.030 <0.030 <0.030 <0.030 <0.030 <0.030 <0.030 <0.030 <0.030 <0.030 <0.030 0.001
Aluminium <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 0.1
Arsenic <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 0.01
Barium 0.14 0.23 0.28 0.13 0.04 0.09 0.13 0.05 0.27 0.05 0.02 0.16 0.21 0.14 0.7
Cadmium <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 0.003
Calcium 66 135 136 62.6 62.9 51.2 93.4 180 64.4 29.1 14 43 42 43 50
Copper <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 0.05
Iron <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 0.3
Lead <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 0.01
Magnesium 6.4 7.9 7.2 7 5.1 22 7.1 55.1 11.9 18.5 6.5 7.8 7.1 8.3 50
Manganese <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 0.1
Nickel <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 0.02
Selenium <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 0.01
Sodium 11.6 12.2 8 6.6 7 60.9 6.6 186 16.2 76.7 165 13.2 12.2 14.4 200
Zinc <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 0.5
Phenols
Total phenols <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 <0.05 0.002
Pearl Petroleum 65
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Parameter Khor Mor Shekh SP3 Ibrahim WW6
Taza Shaher- SP2 SP4 GW5 Zhazh- Takhta Mina- Paryawla Well WW2 WW3 Project
Gawra Hameed- (duplicate of Ghulam- (duplicate of
(mg/L) Spring (spring) (spring0 (spring) Spring Spring (groundwater) (groundwater) (groundwater) Standard
Spring Spring SP2) Spring WW3)
Hydrocarbons (µg/l)
EPH C10-C40 <50 129 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 -
VPH C5-C10 <7 <7 <7 <7 <7 <7 <7 <7 <7 <7 <7 <7 <7 <7 -
PAHs (µg/l)
Acenaphthene <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 -
Acenapthylene <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 -
Anthracene <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 -
Benzo (a) anthracene <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 -
Benzo (a) pyrene <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 -
Benzo (b) fluoranthene <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 -
Benzo (g, h) perylene <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 -
Benzo (k) fluoranthene <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 -
Chrysene <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 -
Dibenzo (a,h)
<0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 -
anthracene
Fluoranthene <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 -
Fluorene <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 -
Indenol (1,2,3- c,d)
<0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 -
pyrene
Napthalene <0.02 <0.02 <0.02 <0.02 0.04 <0.02 <0.02 <0.02 <0.02 <0.02 <0.02 <0.02 <0.02 <0.02 -
Phenanthrene <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 -
Pyrene <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 <0.01 -
Pesticides – organochlorine (µg/l)
BHC alpha <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 -
BHC beta <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 -
BHC delta <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 -
BHC gamma (Lindane) <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 -
Chlordane <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 -
DDD-p, p’ <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 -
DDE-p, p’ <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 -
DDT-p,p <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 -
Endosulfan alpha <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 -
Endosulfan beta <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 -
Endosulfan sulphate <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 -
Endrin <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 -
Endrin aldehyde <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 -
Methoxychor <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 -
Heptachlor <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 -
Aldrin <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 -
Dieldrin <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 -
Pearl Petroleum 66
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Parameter Khor Mor Shekh SP3 Ibrahim WW6
Taza Shaher- SP2 SP4 GW5 Zhazh- Takhta Mina- Paryawla Well WW2 WW3 Project
Gawra Hameed- (duplicate of Ghulam- (duplicate of
(mg/L) Spring (spring) (spring0 (spring) Spring Spring (groundwater) (groundwater) (groundwater) Standard
Spring Spring SP2) Spring WW3)
Heptachlor epoxide <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 <0.03 -
Chlorpyrifos <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 -
Dichlorvos <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 -
Dimethoate <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 -
Disulfoton <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 -
Fenchlorphos <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 -
Methyl parathion <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 -
Parathion <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 -
Phorate <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 -
Famphur <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 -
Guthion <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 -
o, o, o-
<50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 -
triethylphosphorothionate
Sulfotep <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 -
Thionazin <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 -
Tokuthion <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 -
Ethoprophos <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 <50 -
Pearl Petroleum 67
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
3.2.5 Noise
Within the AOI the nearest noise sensitive receptors in the vicinity of the proposed
development are summarised in Table 3-14 below. Further details are provided in the
following sections.
Direction relative
ID Receptor to Khor Mor
existing facility
R1 Khor Mor Gawra West
R2 Mamisik East
R3 Khor Mor Bichuk North-west
R4 Awaye Jalal South
Permanent
R5 South-west
camp
Pearl Petroleum 68
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Table 3-15 Ambient noise levels (dB (A)) at Khor Mor (MapCom, 2010)
Location
Leq L5 L10 L50 L90 Project Standard*
(see note)
AQ1 35.5 30.5 30.0 30.0 30.0
AQ2 40.5 40.0 35.5 35.0 30.0
AQ3 45.0 40.5 40.0 35.5 30.0
50-60
AQ4 35.0 30.0 30.0 30.0 30.0
AQ5 45.5 45.0 40.5 40.0 35.0
AQ6 40.5 40.0 35.5 35.0 30.0
Pearl Petroleum 69
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Figure 3-4 Noise monitoring locations (RSK, 2019)
Pearl Petroleum 70
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Table 3-16 Current noise survey results in 2019
Pearl Petroleum 71
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Measurement data (dB) Project
Ref. Survey location Period
LAeq LAFmax LA90 LA10 Standard
Pearl Petroleum 72
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
3.2.6.2 Description of Project area air quality
Air quality degradation has been observed in various regions in Iraq, including Kurdistan.
primarily due to industrial and petroleum operations.
Degradation of ambient air quality specific to Kurdistan stems mainly from increasing
vehicle numbers in the region generally, as well as increasing cement production and
increases of oil refining capacity (Hamid et al, 2013).
Further sources of air pollution in Kurdistan include the following:
• emissions from industrial facilities including power plants, petroleum refineries,
chemical production, brick kilns, and lead and aluminium smelters
• open burning of waste resulting from a lack of waste management facilities
• increase in illegal logging for fuel use.
Increasing frequency and severity of dust and sandstorms resulting from soil
disintegration and erosion, deterioration of vegetation, desertification, and deterioration
of green spaces has led to increased particulate emissions to the atmosphere (World
Bank, 2017).
Air quality in the Khor Mor area and the region could likely be affected by emissions from
industries, traffic and power generation in the area. Previous studies conducted in the
Project area indicate ambient concentrations of sulphur oxides (SOX) and particulate
matter (PM10 particles smaller than 10 microns) to be above Project Standards.
Pearl Petroleum 73
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Figure 3-5 Ambient air quality monitoring locations
Pearl Petroleum 74
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Table 3-18 Ambient air quality results (MapCom, 2010)
Concentration (μg/m3)
Location Location
SO2 NO2 O3
Qarah Chewar AQ1 45.63 45.63 85.97
Zhazh AQ2 59.51 59.51 112.05
Khor Mor AQ3 61.18 61.18 119.53
Mamisik AQ4 138.32 98.32 95.05
Shekh Jalal AQ5 93.76 83.76 76.14
Taza Shar AQ6 95.19 75.19 64.87
KM250A Project Standard (unless otherwise stated) 20* 40 100 (8 hour)**
MapCom (2010) also included measurement of dust levels at the above locations using
a direct reading particulate matter (PM) monitor. Measured dust concentrations were
found to vary from 61 μg/m3 near the settlements, to 127 μg/m3 at location AQ3 (Khor
Mor), adjacent to asphalt roads. These exceeded the Project annual standard for PM10
of 20 μg/m3.
Ground level O3 exceeded the Project Standard in Zhazh and Khor Mor village. Ozone is
formed in the atmosphere by photochemical reactions in the presence of sunlight and
precursor pollutants, such as NOx and volatile organic compounds (VOCs). Ozone
precursors can come from car exhaust.
VOC monitoring at residential areas was undertaken using solid adsorption/solvent
extraction and gas chromatograph/mass spectrometer. The results of the VOC
monitoring are summarized in Table 3-19. Benzene concentrations in ambient air were
reported to be above the Project annual standard of 0.003 milligrams per cubic metre
(mg/m3, 0.94 part per billion, ppb).
Table 3-19 Ambient air quality results for VOCs (MapCom, 2010)
Pearl Petroleum 75
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Concentration KM250A Project
Sl No Pollutant
(ppb) Standard (ppb)
6 P-dichlorobenzene 8.19 None
7 Ethyl benzene 0.80 None
8 Styrene 1.47 None
9 Bromobenzene 4.65 None
10 1,3,5-trimethylbenzene 2.27 None
11 1,2,4-triethylbenzene 2.16 None
12 N-butyl benzene 5.0 None
13 Naphthalene 4.57 None
14 p-Isopropyletoluene 5.18 None
15 1,2,4 trichlorobenzene 5.4 None
Red – exceeds Project Standard
Ambient air quality data for Khor Mor was collected by ERM (2015) as part of an EIA
study for the Khor Mor Gas Project. The survey included ambient air quality data
collection from within the Project study area as well as three other locations for a 24-hour
period. The results are presented in Table 3-20 and show that ambient concentrations of
SOx and PM10 exceeded Project Standards. Dust levels were found to approach the first
target level indicating the ambient dust levels are elevated but may be expected on a
windy day at the end of a dry summer.
Project Standard
Pollutant Results (μg/m3) 24-hour
(μg/m3)
SOX 25 20
NO2 21 94
Carbon monoxide (CO) 155 11456*
PM10 95 50
VOCs 0.30 765**
Red – exceeds Project Standard
* As there is no 24-hour standard prescribed for CO, the results have been compared to the 8-hour
averaging period limit.
** As there is no 24-hour standard prescribed for VOC, the results have been compared to the 3-
hour standard. For conversion average molecular weight has been assumed to be 78 g/mol
In 2018, MapCom conducted an air quality survey for SO2, NO2, VOC, CO, O3, PM10 and
PM2.5 (particles smaller than 2.5 microns) at 11 locations (Table 3-21). The results have
been compared to the annual average limits in the Project Standards. Concentrations of
SO2, CO and O3 were not detected or did not exceed the Project Standard at any location.
For NO2 concentrations, a minor exceedance is reported at location 10. VOC
concentrations exceeded the Project Standard at location 2 and 5 and exceedances were
reported at all locations for PM10 and PM2.5.
Pearl Petroleum 76
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Table 3-21 Ambient air quality results (MapCom, 2018)
Pearl Petroleum 77
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
3.2.6.4 Current field data collection in the Project area
A baseline air quality monitoring survey for the KM250A Project was undertaken in August
2019 at eight sampling locations (Figure 3-5) within the Project AOI (Table 3-17) by RSK.
The survey was undertaken at the following locations:
• Khor Mor Gawra village (MP1)
• Awaye Jalal village (MP2)
• Taza Shah village (MP3)
• Shekh Hameed village (MP4)
• Khor Mor Bichuk village (MP5)
• Mamisik village (MP6)
• Qadir Karim village (MP7)
• Key location outside of villages (MP8).
Baseline air quality conditions at each of the eight sites was characterised in order to
effectively assess the potential impacts of the proposed development. Diffusion tubes
were deployed to measure concentrations of NO2, SO2, hydrogen sulphide (H2S), PM10,
CO, O3 and VOCs including benzene. The diffusion tubes were analysed after exposure
(approximately 30 days) by Gradko International, based in the UK. A field blank was also
analysed.
A comparison of the air quality monitoring results with the Project Standards indicate the
measured pollutants are largely within the limits (Table 3-22).
The Project Standard for SO2 concentrations (20 μg/m3) was exceeded at:
• Jalal village (MP2) (23.54 μg/m3)
• Taza Shah village (MP3) (21.87 μg/m3)
• Khor Mor Bichuk village (MP5) (25.25 μg/m3).
The Project Standard for O3 concentrations (100 μg/m3) was exceeded at:
• Jalal village (MP2) (106.61 μg/m3)
• Taza Shah village (MP3) (118.27 μg/m3)
• Mamisik village (MP6) (125.42 μg/m3)
• Key location outside of villages (MP8) (119.23 μg/m3).
Pearl Petroleum 78
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Table 3-22 Current air quality monitoring results in 2019
Pearl Petroleum 79
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
3.3 Biological environment
Pearl Petroleum 80
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Figure 3-6 AOA and AOI - biodiversity
Pearl Petroleum 81
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
3.3.2 Past field data collection in the Project area
Secondary data were used to characterise the biodiversity of the Project area, provide
context to the information returned from the biodiversity field surveys and to identify
potential critical habitat qualifying features. Secondary data sources in the Project area
included:
• previous surveys undertaken by others:
o Nature Iraq (2008 and 2017) Key Biodiversity Surveys of Kurdistan,
Northern Iraq
o Ararat (2009) Key Biodiversity Areas: Rapid Assessment of Birds in
Kurdistan, Northern Iraq
• Integrated Biodiversity Tool for Business
• Protected Planet
• World Wildlife Fund Global Ecoregions
• Nature Conservancy Ecoregional Assessments
• Critical Ecosystem Partnership Fund Biodiversity Hotspots
• Wetlands International’s Critical Site Network Tool
• International Union for the Conservation of Nature (IUCN) Red List of
Threatened Species
• freely available satellite imagery and land cover classification
• previous environmental impact studies:
o Worley Parsons (2007) Kurdistan Gas Project Environmental Impact
Assessment Volume i: Gas Pipeline from Khormor to Erbil. Crescent
Petroleum Dana Gas (CPDG)
o ERM (2015) Khor Mor Gas Plant: Environmental Impact Assessment,
CreDan
o MapCom (2010) Environmental Baseline Study, Environmental Social
Impact Assessment Report Khor Mor Block.
Pearl Petroleum 82
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Figure 3-7 Biodiversity baseline survey locations
Pearl Petroleum 83
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
3.3.3.1 Habitats and flora
A rapid walkover habitat and botany survey was undertaken between 28 September and
2 October 2019 by Nature Iraq. The dominant habitat types located within the study area
were identified and their floristic composition was characterised by a botanical specialist.
The survey confirmed the presence/likely absence of any rare or threatened habitats of
conservation importance within the study area.
The survey also confirmed the presence/likely absence of any vascular plant species of
conservation importance. In the context of this baseline assessment, vascular plants of
conservation importance are defined as nationally and/or globally rare or threatened
species, and endemic and/or restricted range species. Focus was given to species that
may trigger critical habitat in accordance with PS6 (IFC, 2012).
Habitat mapping was undertaken using visual interpretation of satellite imagery,
supplemented by existing baseline data and ground-truthing conducted during the
surveys. Satellite imagery used for habitat mapping was based on Vivid Digital Globe
aerial imagery (2015). The mapping was further validated and refined based on the
findings of the field surveys to include any priority habitats that were not previously
identified.
Habitats were further categorised into modified and natural habitats in accordance with
IFC PS6 criteria (IFC, 2012) which defines these as follows:
• Natural habitats are areas composed of viable assemblages of plant and or
animal species of largely native origin, and or where human activity has not
essentially modified an area’s primary ecological functions and species
composition.
• Modified habitats are areas of land that support a large proportion of flora and
or fauna species that are non-native in origin, and or where human activity has
substantially modified an area’s primary ecological functions and species
composition.
Areas composed of shrubland habitat were considered to be transitional habitat 5. These
areas are included as modified habitats.
5Transitional habitats are habitats in the process of becoming modified but that have the potential for restoration,
and which may support important ecosystem functions and connectivity.
Pearl Petroleum 84
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
If evidence of a priority fauna or flora species was observed, the following parameters
were recorded:
• species
• location
• type of observation: direct evidence (i.e. sighting, call) and indirect evidence
(e.g. faeces, prints, feeding remains, nests, burrows etc.)
• number of observations
• surrounding habitat type
• photographs taken where possible.
Pearl Petroleum 85
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
3.3.3.5 Birds
A bird survey was undertaken between 28 September and 2 October 2019 by an
ornithologist. The survey began between one or two hours after sunrise to coincide with
peak bird activity. All bird species that were sighted or heard vocalising were recorded on
field maps along with notes of behavior. Binoculars and a scope were used to increase
the surveyor’s field of vision. Focus was given to priority bird species of conservation
importance namely: nationally and/or globally rare or threatened species, endemic and/or
restricted range species, and congregatory and migratory bird species present in
significant numbers.
3.3.3.6 Bats
A Song Meter 4 (SM4) detector was placed close to aquatic habitat considered suitable
for foraging bats (Latitude N 35.138005° Longitude E 44.811548°) and set to record for
a period of two nights. The detector commenced recording 15 minutes before sunset and
ceased recording 15 minutes after sunrise. The bat calls obtained from the static bat
detector surveys were analysed using appropriate sound analysis software.
The data was analysed to:
• characterise the habitat usage of the study area by priority bats species (i.e.
nationally and/or globally rare or threatened species, endemic/restricted range
species and congregatory species)
• assess species composition in the study area
• gauge the presence of a significant number of roosting bats.
3.3.4.1 Methodology
The determination of critical habitat is initially undertaken in isolation of any proposed
project activities. The following steps were followed in assessing candidate species
against Criteria 1 to 3:
1. define the overall ecologically appropriate area of analysis (AOA)
2. prepare a list of candidate species to include in the assessment
3. obtain or calculate the global extent of occurrence6 (EOO), area of occupancy 7
(AOO), population size and/or number of known sites for candidate species
4. obtain or calculate:
a. the EOO, AOO, population size and/or number of known sites of each
candidate species within the area of analysis
b. for CR, EN and vulnerable (VU) species that are wide-ranging and/or
whose population distribution is not well understood, an assessment of
the importance of the broader landscape was made based on literature
review and professional judgement
5. calculate the proportion of the global or national EOO, AOO and/or population
represented by these results
6. screen outputs against significance thresholds.
The AOA was determined using interpretation of aerial imagery to select an appropriate
area of homogenous habitat type and supporting similar species, as shown in Figure 3-6.
The KM250A Project is located in moist steppe habitat in undulating terrain. This habitat
type extends out to the mountain range to the east and a similar ridge to the west. The
northern extent of the AOA includes a network of roads and settlements that are likely to
form a barrier to movement to most species. The southern boundary is represented by
the Awa Spi river running west to east which appears to delineate a flatter habitat area
comprising lower lying wetland type habitats and small river valleys which is likely to
support a different range of species than the KM250A Project AOA. The AOA is
approximately 4,785 km2 in area. The AOA is used as the basis for a landscape-based
approach to assess potential biodiversity risks so encompasses a much larger area than
the AOI for the KM250A Project construction phase, also shown in Figure 3-6.
For the Criterion 4 method, the IUCN is developing a Red List of Ecosystems (IUCN-
CEM, 2016; IFC, 2019), following a similar approach to the IUCN Red List of Threatened
Species (2019). Where formal IUCN assessments of ecosystems have been undertaken,
these should be used to assess habitats for Criterion 4. Where no formal IUCN
assessments have been undertaken, habitats may trigger Criterion 4 if they are
determined to be of high priority for conservation by regional or national systematic
conservation planning.
6 EOO is defined as the area contained within the shortest continuous imaginary boundary which can be drawn to
encompass all the known, inferred or projected sites of present occurrence of a species, excluding cases of
vagrancy This measure may exclude discontinuities or disjunctions within the overall distributions of taxa e.g.
large areas of obviously unsuitable habitat (IUCN, 2001).
7 AOO is defined as the area within a species extent of occurrence which is occupied by that species, excluding
cases of vagrancy. This measure reflects the fact that a species will not usually occur throughout the full area of
its EOO, which may contain unsuitable or unoccupied habitats (IUCN, 2001).
Pearl Petroleum 87
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
For the Criterion 5 method, the structural attributes of a region, such as its topography,
geology, soil, temperature and vegetation, and combinations of these variables, can
influence the evolutionary processes that give rise to regional configurations of species
and ecological properties (IFC, 2019). This criterion will typically be triggered in areas
that have been previously investigated and that are already known or suspected to be
associated with unique evolutionary processes. It is further noted that while systematic
methods to measure and prioritise evolutionary processes in a landscape do exist, they
are typically beyond a reasonable expectation of studies conducted by the private sector.
Pearl Petroleum 88
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
IFC PS6 criteria IFC PS6 Critical habitat-qualifying features
criterion
threshold
numbers
3.3.5.1 Eco-regions
The Project is located in an area known as the Zagros Mountain Forest Steppe eco-
region. Zagros Mountain Forest Steppe is one of the most divergent eco-regions for plant
habitat as it is part of the Taurus-Zagros Mountain range, which has a unique
geographical formation that occupies 7 % of the entire KRI (Ahmad et al., 2018).
The Zagros Mountain Forest Steppe eco-region is mainly populated by oak-dominant
deciduous forests and pistachio-almond forest with a diverse population of steppe flora.
The key known fauna of this eco-region includes brown bear (Ursus arctos), Asiatic black
bear (Ursus thibetanus), eagles (Aquila sp), wild goats (Capra aegragus), sheep (Ovis
orientalis), wolves (Canis lupus), leopards (Panthera pardus) and other wild cats (Felis
sp). It should be noted that these species have not been recorded in the study area
according to available information. Anthropogenic activities within the study area (i.e.
cultivation and overgrazing) has resulted in extensive natural habitat loss in the region.
Pearl Petroleum 89
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
3.3.5.2 Designated or protected areas
The Project area is not located within any nationally or internationally designated
protected areas for biodiversity. The closest designated area for biodiversity to the Project
area is the Chemchemal Key Biodiversity Area (KBA) and Important Bird Area (IBA)
which are located approximately 12 km south-west of the Project area (Figure 3-8; site
#IQ035, Sulaimani-35.421389°N 44.618333°E). KBAs are sites that contribute
significantly to the global persistence of biodiversity, in terrestrial, freshwater and marine
ecosystems and IBAs are places of international significance for the conservation of birds
and other biodiversity (Birdlife International, 2019a).
Chemchemal KBA and IBA is located in the Moist Steppe Zone. The site is known to
support the Eastern imperial eagle (Aquila heliacal) during the winter months which is
categorised as Vulnerable by the IUCN Red List of Threatened Species (2019). The
KBA/IBA also supports breeding populations of two Mediterranean, three Irano-Turanian
and three Sahara-Sindian Desert biome-restricted bird species (Birdlife International,
2019b). Other fauna species of conservation importance that have been recorded in the
KBA/IBA include the goitered gazelle (Gazella subgutturosa) which is categorised by
IUCN (2019) as VU at the global scale and CR in the Mediterranean. This KBA/IBA has
been adversely impacted by habitat loss and degradation arising from urban
development, grazing and poor urban waste management.
Figure 3-8 Photograph of Chemchemal KBA and IBA (Nature Iraq, 2017)
3.3.5.3 Habitats
Nature Iraq (2019) has identified the following zones of plant communities in Kurdistan:
• dry steppe zones (recorded in Kalar and Fishkhaboor-Syrian Border)
• moist steppe zone (recorded in Dukan, Atrush Sangaw)
• forest zones - primarily Quercus sp forests however, pine forest is restricted to
the Amadiya district of Dohuk in Zawita.
A habitat map providing an overview of the habitats within the AOI and surrounding area
is presented as Figure 3-9 and photographs are shown in Figure 3-10 to Figure 3-12. The
area is located within the moist steppe zone in Kurdistan (Guest, 1966). The majority of
the habitats located within the survey area are categorised as modified habitats. These
modified habitats include agro-pastoral land (predominantly cropland), unsurfaced roads,
Pearl Petroleum 90
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
cleared ground and urban settlements. Natural habitats comprised steppe grassland, an
ephemeral stream and a small pond with small stands of reedbeds located within the
riparian zone. The Project area is dominated by grazed steppe grassland that had been
modified by cutting in recent years. Small areas of scattered scrubs were present within
these modified habitats. Habitats of conservational importance at the Project level are
the steppe grassland, the pond and ephemeral waterbodies.
Pearl Petroleum 91
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Figure 3-9 Habitat map
Pearl Petroleum 92
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Figure 3-10 Steppe grassland habitat
3.3.5.4 Flora
The botanical survey confirmed the presence of twenty vascular plant species within the
study area (Appendix 4, Table A4.1). Of these, the status of only seven species have
been assessed by the IUCN Red List of Threatened Species (2019). These assessed
species are common and widespread in nature and as such are categorised as least
concern (LC).
Most unassessed species are native to multiple countries and therefore not classed as
endemics. However, the Catalogue of Life: 2019 Annual Checklist (Roskov et al., 2019)
indicates that Lomelosia leucactis (synonym Scabiosa leucactis) may have a range that
is restricted to north-west Iraq. Further analysis and consultation with biodiversity experts
have confirmed that these species are not of conservation importance for the KM250A
Project.
The literature review identified that a total of 56 species of flora were observed by
MapCom (2018) as part of surveys undertaken for the development of the Khor Mor LPG
facility, none of which are considered threatened (IUCN, 2019 and Nature Iraq, 2017).
Ecology surveys undertaken in the Chemchemal KBA and IBA by Nature Iraq in 2008
Pearl Petroleum 93
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
(Nature Iraq, 2017) confirmed the presence of 57 species of vascular plants. At the time
of this survey, the ecological condition of the KBA/IBA was identified as being 75%
disturbed. The dominant recorded plants were the trees Salix aegyptiaca (not assessed
by IUCN (2019)) and white poplar (Populus alba; LC); the shrub Rubus sanctus (not
assessed by IUCN (2019)), the thistle (silybum marianum; LC) and common reed
(Phragmites australis; LC).
Two plant species were recorded for the first time in Kurdistan, namely: Brassica
tournefortii (LC) and Euphorbia boissieriana (not assessed by IUCN (2019)). Key flora
species found within the Chemchemal KBA and IBA with potential to occur in the Project
area are Carlina kurdica, Pisum sativum and Paronychia kurdica; three species endemic
to all four parts of Kurdistan (Iraq, Iran, Syria, and Turkey) and two species which are
locally endemic (Kurdistan Iraq); Dianthus basianicus and Ornithogalum iraqense are
both CR according to the IUCN Red List. In addition, Xi Zang Xiao Mai (Triticum aestivum;
IUCN 2019 listed data deficient) and Triticum durum (not assessed by IUCN 2019) were
found in the Chemchemal area. These species are cultivars specific to the region and
therefore of significance as genetic resources.
A complete list of threatened, rare and/or endemic plants is not yet available for Iraq,
however Nature Iraq (2017) have proposed that five vascular plant species, presented in
Appendix 4 (Table A4.1) recorded in the northern region of Iraq in 2008 should be
considered. Habitats located within the study area have the potential to support these
species. The conservation status of these species has been categorised by IUCN (2019)
as LC, with the exception of Quercus macranthera and Linum velutinum, which have not
been assessed. The Catalogue of Life: 2019 Annual Checklist (Roskov et al., 2019)
indicates that Quercus macranthera ranges across Iran, Lebanon-Syria, North Caucasus,
Transcaucasus and Turkey, whilst Linum velutinum may have a range that is restricted
to north-west Iraq. Further analysis and consultation with biodiversity experts have
confirmed that these species are not of conservation importance for the KM250A Project.
3.3.5.5 Bats
The bat survey confirmed the presence of Kuhl's pipistrelle (Pipistrellus kuhlii) within the
study area. This species is common and widespread in nature and as such is categorised
as LC by the IUCN Red List of Threatened Species (2019). This species is congregatory
in nature with summer colonies typically numbering 30-100 individuals (IUCN, 2019).
There are twenty species of bat present in Iraq included on the IUCN Rd List of
Threatened Species (2019). Of these, 17 are classified as LC, one is categorised as NT
(the Mediterranean horseshoe bat (Rhinolophus euryale)) and two species are
categorised as VU (the long-fingered bat (Myotis capaccinii) and Mehely’s horseshoe bat
(Rhinolophus mehelyi)) (Table 3-27).
The long-fingered bat is sparsely populated throughout its range and is in a state of
decline throughout its range. There are isolated populations from Iberia, through the
northern Mediterranean, Anatolia into Iran, Iraq and Northern Africa. The species is
dependent on aquatic habitats (including artificial waterbodies) for foraging and has a
roosting preference for caves. Although present in Iraq, the species range does not
directly overlap the Project AOI and this species presence cannot be discounted within
the wider study area.
Pearl Petroleum 94
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Mehely’s horseshoe bat forages in Mediterranean scrubland and woodland, in dry
steppes with particular links to water bodies (Salsamendi et al., 2012). This species
almost exclusively roosts in caves or abandoned mines and doesn’t use artificial habitats.
The species is largely restricted to the Mediterranean, but it does have a fragmented
distribution from north Africa and southern Europe, through Anatolia to Transcaucasia,
Iran and Afghanistan. The species is present in Iraq, but only in one isolated area north
of Erbil (north of the Project AOI). The Project AOI lies between this population and the
known range in Iran so whilst it is unlikely that the Mehely’s horseshoe bat is present in
the AOI, it cannot be discounted altogether.
Table 3-27 Rare and threatened bat species within ranges that overlap the AOI
Figure 3-13 Khor Mor perimeter fence at coordinate 35.143803°(N), 44.815793° (E)
Figure 3-14 Khor Mor perimeter fence at coordinate 35.141154°(N), 44.829062° (E)
Pearl Petroleum 95
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
The fauna baseline survey confirmed the presence of six mammal species (Table 3-28).
These species are common and widespread in nature and as such are categorised by
IUCN (2019) as LC. The presence of Indian grey mongoose, wild cat, red fox and short-
tailed bandicoot rat in the survey area was confirmed during the camera trapping survey
(Figure 3-15).
There was some uncertainty regarding the speciation of the short-tailed bandicoot rat
(Nesokia indica) based on the camera trapping data. Further examination of captured
animal would be required to exclude the possible presence of the Bunni's short-tailed
bandicoot rat (Nesokia bunni) as this species shares similar morphological characteristics
to the short-tailed bandicoot rat. Bunni's short-tailed bandicoot rat is IUCN listed EN at
the global scale and endemic to Iraq (IUCN, 2019) and as such would be of high
conservation importance for the Project. However, the likelihood of the occurrence of
Bunni's short-tailed bandicoot rat within the survey area is low as this species is
reportedly endemic to the marshlands of south-eastern Iraq in the Tigris and Euphrates
Valleys (IUCN, 2019).
Table 3-28 Mammal species identified during baseline surveys in the study area in
2019
IUCN
Common Scientific
(2019) Habitat of occurrence (IUCN, 2019)
name name
status
Indian grey Grassland, shrubland, urban areas,
Herpestes
mongoose LC dry secondary forests and thorn
edwardsii
(Figure 3-15) forests.
Inhabit a wide variety of habitats
wild cat including deserts, scrub grassland,
Felis silvestris LC
(Figure 3-15) forests, marsh boundaries and along
sea coasts and scrub desert.
Desert, forests, urban areas, mixed
landscapes with abundant "edge" of
red fox
Vulpes vulpes LC scrub and woodland, moorlands,
(Figure 3-15)
mountains, sand dunes and
agricultural areas.
Tropical and sub-tropical dry
deciduous forests, scrublands,
grasslands, arable land, pastures,
short-tailed plantations, natural grasslands,
bandicoot rat Nesokia indica LC cultivated fields & orchards.
(Figure 3-15) The species typically lives in moist
soils near permanent water sources in
areas of dense vegetation including
agricultural areas.
Inhabits a wide variety of habitats
golden jackal Canis aureus LC including forests, grassland,
shrubland and savanna
Very wide range of man-made
habitats, arable land, pastures,
house mouse Mus musculus LC coastal sand dunes, salt marshes,
and scrubby road verges. Tend not to
be found in forests and deserts.
Pearl Petroleum 96
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Indian grey mongooses (17/10/2019) Wild cat (09/10/2019)
The Chemchemal KBA and IBA has been recorded as supporting the goitered gazelle
(IUCN listed VU at the global scale and CR in the Mediterranean) (BirdLife International,
2019b; IUCN, 2019). The goitered gazelle inhabits a wide range of semi-desert and
desert habitats and has a range that extends from Mongolia and north-west China
through Central Asia (Kazakhstan, Turkmenistan, Uzbekistan, and a small portion of
Kyrgyzstan and Tajikistan) through Iran, Afghanistan and Pakistan. The global population
is in a state of decline due to illegal hunting for subsistence and trophy hunting, and
habitat loss due to economic development and agro-pastoral development. This species
habitat usage is reportedly restricted to protected areas in Iran (IUCN, 2019) and as such
is unlikely to inhabit the study area.
Based on secondary data, rapid screening was undertaken to determine the likely
occurrence of other fauna species of conservation importance for the Project within the
study area. The results are presented in Appendix 1 (Table A1.5 to A1.8). Surveys
undertaken by MapCom in 2008 identified a total 12 mammals and several
Pearl Petroleum 97
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
domesticated/livestock mammals (MapCom, 2010) but none are considered threatened
(by IUCN, 2019 and Nature Iraq, 2017). In addition, the globally vulnerable goitered
gazelle Gazella subgutturosa was reported by locals during other surveys by Nature Iraq
in the region.
The literature review identified nine fauna species with IUCN ranges that overlap with the
study area (IUCN, 2019). Of these, only one species has potential to occur in the Project
footprint, marbled polecat (Vormela peregusna; global VU; Europe VU; Mediterranean
VU), assuming polecats are able to climb the perimeter fence. Other species of
conservation importance with potential to use habitats in the wider study area are Arabian
sand gazelle (Gazella maric; IUCN listed VU) and striped hyaena (Hyaena hyaena; IUCN
listed NT on the global scale and VU in the Mediterranean).
3.3.5.7 Avifauna
The ornithology survey confirmed the presence of 29 species of bird within the survey
area (Appendix 4, Table A4.2). These species are common and widespread in nature
and as such are categorised as LC by the IUCN Red List of Threatened Species (2019).
Of these, 16 species are migratory and five species are congregatory (and dispersive) in
nature. The literature review identified 12 species of rare and threatened birds with IUCN
ranges that overlap with the study area and 59 species known to be present in the area
from previous surveys by Nature Iraq in 2009 and 2013 as shown in Appendix 1, Table
A1.7). There is potential for these species to use habitats in the study area. The Project
footprint and wider study area are not considered to provide suitable habitat to support
globally significant numbers of migratory and/or congregatory bird species.
Pearl Petroleum 98
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
The Euphrates softshell turtle is almost exclusively riverine, preferring permanent and
temporary tributaries and oxbow lakes, as well as slow-flowing sections of main river
channels. The species has undergone a severe population decline over the last 15 years,
and with Iraq encompassing the majority of its range, the species has been classed as
EN. The major threat to the species has been the anthropogenic alteration and
destruction of suitable habitat. Within Iraq, several marshlands were drained in the years
post the Gulf war which significantly impacted the Iraqi population of the species. Oil
development is also seen as a major threat to the species within Iraq (Taskavak et al.
2016).
The common tortoise’s natural habitat includes semi-arid scrub and Mediterranean forest
to the verges of semi-desert, where it can be found inhabiting outcrops of Euphorbia. If
found in the southern parts of the species range, individuals are active during the warm
winter periods and then estivate during the hotter summer. In northern ranges, this cycle
is reversed (IUCN, 2019).
The Armenian viper is present in Turkey, Armenia, Nakhichevan (Azerbaijan) and Iraq,
with fragmented populations also in the mountains of north-western Iran and is restricted
in range to these areas. Little is known about its range in Iraq. This species is generally
found in rocky montane areas with sparse scrubby vegetation at elevations above 1,000m
above sea level. Animals may occasionally be found at rocky sites within woodlands
(IUCN 2019).
The siirt lizard occurs in north-eastern Syria, south-eastern Turkey, south-western Iran
(the central Zagros Mountains), and possibly northern Iraq (IUCN 2019)
The black headed snake ranges discontinuously from eastern Turkey, southwards to
western Syria, Lebanon, Israel and western and central Jordan, possibly extreme north
Saudi Arabia and eastwards to Armenia, Azerbaijan, northern Iraq and western Iran
(Central Province and Khuzistan Province). It also occurs as an isolated population at
Santa Katarina on the Sinai Peninsula (Egypt) (IUCN 2019).
Four subspecies of the Caspian turtle are recognized: the eastern Caspian turtle,
Siebenrock's Caspian turtle, the spotted-bellied Caspian turtle, and the western Caspian
turtle. Siebenrock's Caspian turtle (M. c. siebenrocki) occurs in Iran and Iraq, with relict
populations in Saudi Arabia and on the island of Bahrain; it intergrades with M. c. caspica
in Mesopotamia (Fritz et al 1997).
3.3.5.9 Invertebrates
No specific invertebrate surveys were undertaken as part of the baseline surveys, as
such, no invertebrates were identified. In Iraq, there are 61 species of insect that have
been assessed on the IUCN Global Red list of threatened species. Of these, the majority
(41) are of the family Odonata – or dragonflies. Two dragonfly species, waved pincertail
(Onychogomphus flexuosus) and dark-winged groundling (Bracyhthemis fuscopalliata)
are classified as VU. The Apollo butterfly (Parnassius apollo) is also listed as VU. Four
species of insect are classified as near threatened whilst the remaining 54 are either LC
or data deficient.
Pearl Petroleum 99
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
3.3.5.10 Fish
According to IUCN (2019), there are five species of fish of conservation importance that
are found in Iraq which are listed as follows:
• Mesopotamian bream - LC
• yellowfin barbel (Luciobarbus xanthopterus) - VU
• pike barbel (Luciobarbus esocinus) - VU
• binni (Mesopotamichthys sharpeyi) - VU
• leopard barbel (Luciobarbus subquincunciatus) - CR.
No riverine habitats were surveyed as part of the baseline survey.
3.4.1 Methodology
8 Aside from Takeya Jabari, there are no communities within 5 km of the AOI that have similarly large population
sizes and available social infrastructure and services. The closest community to the AOI, which possesses such
features, is Chemchemal, located approximately 65 km away.
Pearl Petroleum 100
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Table 3-29 PACs within the AOI
9 The field team consisted of six local social consultants, one local environmental consultant and an archaeologist
from the University of Sulaymaniyah.
Pearl Petroleum 103
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Table 3-30 Data collection activities in the PACs
KII with village leader KII and KII and Observations of road
Household FGD with
Activities (Anjuman) or Sub- observations observations conditions and traffic
interviews women
District Manager (SDM) (schools) (health facilities) volumes
Primary sphere of influence
Zhazh
Khor Mor Gawra
Khor Mor Bichuk
Awaye Jalal
Taza Shar
Shekh Hameed
Kani Qadir Qala
Mamisik
Secondary sphere of influence
Chala Dwana
Ali Mustafa
Takhta Mina Saru
Ibrahim Ghulam
Qadir Karim
Cham Surkhaw
Aliawa
Qarah Chewar
Paryawla
Takeya Jabari
3.4.4 Demographics
The KRI population is 6,033,814 with annual growth at 2.3% (KRSO, 2019). The
population of the Governorate of Sulaymaniyah was 2,021,175 in 2017, representing
approximately 34% of all persons in the region that year. In 2019, population density in
the KRI was 129 persons per km2. In this respect, Sulaymaniyah is the least densely
populated of Kurdistan’s four governorates, with 110 persons per km2 (KRSO, 2019).
Approximately 98% of the population of Kurdistan were born in Iraq and 99% are Iraqi
citizens; a small minority (2%) were born in neighbouring countries such as Syria, Turkey
and Iran (KRSO, 2019). Consistent with data at the regional level, the vast majority
(98.9%) of Sulaymaniyah’s population were born in Iraq and the majority (99.2%)
maintain Iraqi citizenship.
The gender distribution at regional level is balanced, with males and females representing
3,029,889 (50.2%) and 3,003,925 (49.8%) of the population respectively. Consistent with
the regional level, primary data in AOI showed that, of 145 households interviewed
(representing 866 household members across eight PACs), 50.5% were men and 49.5%
were women.
The average household size at regional level in KRI is 5.1 members, which is higher than
in Sulaymaniyah Governorate, where average household size is 4.6 members. In the
PACs, the average household size varied from seven in Khor Mor Bichuk to one in
Mamisik.
As shown in Figure 3-17, the population of the KRI and the Governorate of Sulaymaniyah
is predominantly young, with 0-24-year olds representing more than half (54.3%) of the
total population at regional level and just over a half (50.8%) of the population at
governorate level.
KRI Sulaymaniyah
Figure 3-17 Age structure in Governorate of Sulaymaniyah and KRI, 2017 (IOM, 2018a)
There is a wide variation in population size at local level across the PACs, ranging from
over 1,500 persons in Takeya Jabari to fewer than five persons in Mamisik. The majority
of the communities (72%) are relatively small with less than 100 residents in total.
Table 3-31 presents a population breakdown population for the PACs in the AOI.
Total population
Total
Full time Part Largest Smallest
PAC number
Males Females HH 10 time HH HH HH
of HH
(%) (%)
95
Ali Mustafa 19 19 - 10 3
50 50
77
Awaye Jalal 27 27 0 15 2
60 40
30
Chala Dwana 4 4 - 7 3
70 30
75
Cham Surkhaw 12 12 - 10 5
50 50
18
Ibrahim
11 11 - 9 3
Ghulam
35 65
70 19 15 4 15 1
10 Full time households are households which live in the PACs on a permanent basis throughout the year. Part
time households are households which, for various reasons, are absent from the PACs at certain times in the
year and therefore do not live there permanently.
Pearl Petroleum 108
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Total population
Total
Full time Part Largest Smallest
PAC number
Males Females HH 10 time HH HH HH
of HH
(%) (%)
Kani Qadir
60 40
Qala
Khor Mor 45
25 6 19 16 5
Bichuk
40 60
Takhta Mina 20
9 9 - 10 2
Saru 50 50
13
Zhazh 15 2 13 9 2
39 61
11 According to IFC PS7, the defining characteristics of IPs are: self-identification (as members of a distinct
indigenous cultural group and recognition of this identity by others), collective attachment (as persons who
identify as a group or community linked to geographically distinct habitats or ancestral territories and to the
natural resources in these habitats and territories), customary cultural, economic, social or political institutions
(separate from those of the dominant society or culture) and an indigenous language (often different from the
official language of the country or region in which they reside). Whilst not stated by IFC PS7, marginalisation and
discrimination are additional characteristics of IPs identified by other international organisations (e.g. the UN).
Pearl Petroleum 110
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
under the leadership of village Anjuman and do not have separate
leaders.
o Whilst Arab persons are a minority in the AOI, there is no evidence
indicating that they are experiencing marginalisation and discrimination.
On the contrary, data confirming benevolence towards Arab households
was collected during the social baseline surveys.
o As with Kurdish households, Arab households do not tend to rely on local
habitats or territories to obtain natural resources, typically purchasing
food and other items from towns and cities.
o Arab people speak Arabic. Although spoken less extensively in the AOI
than Kurdish, Arabic is one of the KRI’s two official languages and is not
considered to be distinctive in the broader regional context.
In terms of religion, all households in the PACs are Sunni Muslims.
As indicated above, the official languages of the KRI are Kurdish and Arabic. Kurdish is
the most widely spoken language of the two. The most commonly spoken dialects of
Kurdish are Sorani and Kurmanji; the KRG’s policy is to promote the teaching and use of
both dialects in the education system and the media (KRG, 2019b). The dialect of Kurdish
predominantly spoken in Sulaymaniyah is Sorani.
Of the 145 households interviewed, the vast majority of households (89%) primarily speak
Kurdish whilst a minority of households (11%) primarily speak Arabic. This correlates with
the ethnicity of the households interviewed (89% Kurdish and 11% Arab).
The Kurdistan Region is also home to a number of tribal groups, which are based on
family then clan affiliations. Tribal groups mentioned during household interviews
included the Zangana, the Gill, the Shekhanyi, the Jabari, the Dalo, the Lak and the
Talabany groups. The majority of households are affiliated with the Zangana (32%), Gill
(21%) and Talabany (14%).
3.4.4.2 Migration
Conflict in the region and other parts of the country (both recently and historically) has
produced a highly mobile population and has played an important role in shaping
Kurdistan’s contemporary demographic profile.
Since 2014, Kurdistan has hosted many internally displaced persons (IDPs) fleeing
armed conflict between government forces and ISIS. The Syrian War, which began in
2011, also led to the arrival of significant numbers of refugees who regard the KRI as a
place of relative safety (World Bank, 2015).
As of 2019, the KRI hosts 226,000 Syrian refugees and approximately 1.5 million IDPs
(EASO, 2019; KRG, 2019c); only 32,000 IDPs have returned to their homes or migrated
abroad since arriving in the KRI. The Governorate of Sulaymaniyah currently hosts
approximately 150,000 persons displaced by the recent conflict involving ISIS (UNOCHA,
2019). Over 90% of these persons live outside of traditional IDP camp settings and do
not receive the same level of humanitarian support as those residing in camps, instead
relying largely on the generosity of host communities (UNOCHA, 2019).
Internal displacement is not a new phenomenon in Kurdistan. During the 1970s and
1980s, under Saddam Hussein’s Baathist regime, the destruction of Kurdish towns and
Pearl Petroleum 111
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
villages displaced thousands of Kurdish people living close to the borders with Iran and
Turkey. In 2003, there were approximately 800,000 Kurdish IDPs present in the
Governorates of Dohuk, Erbil and Sulaymaniyah, the majority of whom had been
displaced by the Baathist regime (Lischer, 2008).
The regional context is reflected in the AOI. Whilst no refugees were identified during
primary baseline data collection, a total of 16 internally displaced families (all Sunni
Arabs) were identified across five PACs. These families reportedly come from the
Governorate of Diyala (including Kifri District), the Governorate of Kirkuk (including the
city of Kirkuk) and the Governorate of Saladin (including the cities of Tuz Khurmatu and
Tikrit). They arrived in the PACs as a result of the ISIS conflict and represent a population
of 104 IDPs, 48% of whom are male and 52% female.
Consistent with data at the regional level, internal displacement is not a new phenomenon
in the PACs. Several households fled from the local area during the 1970s and 1980s to
escape detainment and persecution by the Baathist government. This movement
intensified during the years of the Anfal campaign (KII with village Anjuman). Whilst a
number of households have since returned to the PACs, the impacts of the Baathist
regime and Anfal campaign can be observed in the presence of widows and other family
members who lost husbands and relatives during this period.
Similar to other parts of Iraq, the KRI has undergone urbanisation, with people seeking
economic opportunities not available in rural areas (Al Jarah et al., 2019). As many as
81.4% (4,911,795) of the region’s population now live in urban areas (KRSO, 2019).
The rural-urban transition has been particularly intense in the Governorates of Erbil and
Sulaymaniyah (IOM, 2018b). Data collected during the baseline surveys in the PACs
supports this trend with the rural-urban migration of households witnessed in Mamisik,
Kani Qadir Qala, Qarah Chewar and Takhta Mina Saru (KII with village Anjuman).
While many households live in the PACs full time, the AOI is characterised by a mobile
population. Many families own properties in cities such as Kirkuk and Tuz Khurmatu
where they live for several months of the year whilst their children attend school, returning
to the PACs only during the holidays. A number of households left PACs such as Khor
Mor Bichuk and Shekh Hameed several years ago in search of job opportunities and
better services in urban areas; these households have retained their properties in the
PACs, returning to them throughout the year for leisure and recreational or maintenance
purposes, or to undertake seasonal livelihood activities such as crop farming and
livestock rearing. Economic migrants from cities such as Mosul, Tikrit and Tuz Khurmatu
have migrated to some of the PACs in search of work as shepherds (KII with village
Anjuman in Ali Mustafa, Chala Dwana, Cham Surkhaw, Kani Qadir Qala and Ibrahim
Ghulam).
3.4.5 Health
Life expectancy in the KRI is 75.3 years; this rate is slightly higher among women (76.7
years) compared to men (73.9 years) (KRSO, 2019).
The key regional health indicators show the following:
• total fertility rate of three children per woman, representing a decline from 3.3
children per woman in 2011 (IOM, 2018a)
Table 3-32 Leading causes of death in the KRI in 2014 (Moore et al, 2014)
Condition
Rank
Deaths in children <5 years Deaths in persons >5 years
1 Prematurity Injury (all types)
2 Septicaemia Cancer (multiples types)
3 Birth asphyxia Stroke
4 Dyspnoea Heart disease
5 Injury (all types) Heart attack
6 Congenital malformation Encephalitis
7 Pneumonia Kidney failure
8 Neonatal heart failure Diabetes
9 Gastroenteritis Respiratory failure
10 Peritonitis Hypertension
As shown in Table 3-32, non-communicable diseases (NCDs) such as heart disease and
cancer are amongst the leading causes of death in persons over five in Kurdistan. The
rise of NCDs in Kurdistan is consistent with national trends and can be attributed to
factors such as economic growth and lifestyle choices (Cetorelli et al., 2017). Prematurity,
septicaemia and birth asphyxia are the leading causes of mortality amongst children
under five.
Consistent with data at the regional level, NCDs such as diabetes and high blood
pressure are amongst the main health problems in the PACs. KII with medical staff in
Qadir Karim and Takeya Jabari identified NCDs as being more common amongst elderly
persons (i.e. those over the age of 65). Women are particularly affected by migraines and
back pain; the latter was attributed to women’s role in carrying water between tanks and
homesteads as identified during a women’s focus group in Shekh Hameed.
Injuries rank highly as a leading cause of death amongst both categories. The majority of
injuries result from road traffic accidents; according to the Ministry of Health, vehicle
collisions lead to approximately 850 deaths and 10,000 injuries annually (Rudaw, 2017b).
In contrary with regional statistics, injuries resulting from road traffic accidents at local
level in PACs were not identified as an issue; this may reflect the low traffic volumes in
90% 80%
Percentage of Households
80%
70%
60%
50%
40%
30%
16%
20%
10% 2% 2%
0%
Medical Health Traditional Healer Self Medicated Mixture
Facility
Treatment Type
There are two PHC centres within the AOI, namely Qadir Karim Medical Centre and
Takeya Jabari Health Care Centre. These centres are located approximately nine km and
fifteen km from the existing facility respectively.
Of the 145 households interviewed, 28% seek medical treatment from Qadir Karim
Medical Centre. None of the households reported visiting Takeya Jabari Health Care
Centre for treatment; this may be attributed to the fact that Qadir Karim Medical Centre
is the nearest facility to the PACs and the types of services offered are very similar.
Despite this, the quality of services and care available at Qadir Karim Medical Centre was
consistently described as poor (FGD with women), motivating PAC members to seek
medical treatment from facilities outside the AOI. Whilst the costs associated with using
these facilities are unknown, PAC members indicated that they are generally accessible.
There are no hospitals in the AOI. The nearest hospital is located approximately 140 km
from the PACs in the city of Chemchemal. Ambulance transportation from the PHC
centres in Qadir Karim and Takeya Jabari to the hospital in Chemchemal is available to
patients free of charge. Nevertheless, the most commonly cited medical facility after
Qadir Karim’s was Kirkuk Hospital, accounting for 21% of households interviewed. PAC
members also use hospitals in the city of Sulaymaniyah.
A small proportion of households interviewed (20%) chose alternative treatment options.
This was mainly attributed to a combination of two factors: distance and/or cost, which
indicates that health care access remains an issue for some members of the PACs.
3.4.6 Education
1,600,000 1,581,202
1,400,000
Number of Students
1,200,000
1,000,000
800,000
600,000 519,340 473,492
400,000 263,237
200,000 25,133
0
KRI Erbil Sulaymaniyah Dohuk Halabja
Figure 3-19 Students enrolled in public and private schools in the KRI, 2017 – 2018
(KRSO, 2019)
FGD with women in PACs indicated that children’s education is considered to be highly
important. Consistent with this belief, primary school attendance rates in the PACs are
high. In Shekh Hameed, Khor Mor Gawra, Qadir Karim and Takeya Jabari, between 95%
and 100% of children are attending primary school on a regular basis (KII with
schoolteachers). School attendance rates decline at the secondary level with rates of
60%, 40% and 30% reported in Khor Mor Bichuk, Khor Mor Gawra and Taza Shar
respectively (FGD with women). Consistent with data at the regional level, secondary
school attendance rates are lower amongst girls from the PACs. Fears around the mixing
of boys and girls and the potential for relationships to start at an early age (i.e. before
marriage) were cited during KII with teachers and FGD with women.
According to interviews with women in PACs, while some children attend schools in the
AOI, the majority of households send their children to schools outside the AOI (see Figure
3-20).
80%
68%
Percentage of Households
70%
60%
50%
40% 32%
30%
20%
10%
0%
School Within AOI School Outside of AOI
Location of School
Figure 3-20 Children attending school within versus outside the AOI
3% 6%
27%
19% Agriculture
Manufacturing
Construction
Services
Public administration
45%
3.4.7.2 Tourism
With its relative political stability and security, abundance of natural attractions and
approximately 3,500 historical and religious landmarks, there is potential for tourism in
Kurdistan (Altaee et al. 2017). As of 2017, the region received approximately 2.25 million
(predominantly domestic) tourists, representing an increase from 1.8 million in 2016
(Foreign Policy, 2019). Cities such as Sulaymaniyah and Erbil have been promoted
based on their offering of first-class hotels, cultural features (e.g. museums, a citadel)
and leisure activities (e.g. shopping malls and theatres) (General Board of Tourism of
Kurdistan, 2015b).
Tourism is not a major income source in the PACs. Nevertheless, interviews with village
Anjuman and SDMs revealed that tourists visit the following PACs during Spring (March,
April and May): Awaye Jalal, Cham Surkhaw, Kani Qadir Qala, Ibrahim Ghulam, Qarah
Chewar, Qadir Karim, Takeya Jabari and Zhazh. Interviewees stated that tourists are
attracted by the natural landscapes and scenery of the local area. Tourists typically visit
Pearl Petroleum 121
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
the PACs on day trips, though some stay for two or three days. The majority of tourists
stay with relatives and thus it is not common to rent accommodation; some tourists camp
in tents along the edges of streams and near seasonal springs.
6%
Wheat
43% Barley
Other
1%
12 A donum, also known as dunam or dunum, was the Ottoman unit of land area equivalent to the English acre. It
remains in widespread use in the KRI today. One donum is equivalent to approximately 0.25 acres or 0.1
hectares.
Pearl Petroleum 122
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
The average size of agricultural land holdings in the AOI is 80 donums (or 8 hectares).
The amount of wheat and barley produced by households in a given year varies
depending upon the fertility of the land and levels of rainfall (KII with land owner, Khor
Mor Bichuk). Data gathered during household interviews indicates that, on average, nine
tons of wheat and 21.1 tons of barley are produced annually per household. Annual levels
of barley production ranged from one to 35 tons amongst households interviewed. Annual
levels of wheat production ranged from 0.5 to 60 tons except for one household, which
reported produces 300 tons of wheat per year.
The main challenges associated with crop farming reported during baseline data
collection included damage caused by pests, insects and occasionally livestock; a
shortage of water for irrigation, the risk of crops catching fire during hot weather and in
the dry season; and a decline in government support for farmers.
25% Chickens
14%
Sheep
Goats
Ducks
Donkeys
32%
37% Other
The average number of livestock owned by the households interviewed varies according
to livestock type (see Table 3-33).
Livestock types and numbers vary widely between households and across the PACs.
Chickens, sheep and goats were identified during household interviews in all the selected
PACs; no cattle were identified during household interviews in Awaye Jalal, Kani Qadir
Qala, Khor Mor Gawra, Mamisik and Zhazh. The number of sheep ranged from two to 10
amongst households interviewed in Khor Mor Bichuk, compared to between 70 to 550
amongst households interviewed in Kani Qadir Qala. The number of chickens ranged
from seven to 230 in Awaye Jalal, compared to a range of six to 50 in Shekh Hameed.
Livestock rearing is a year-round activity and the income is mainly derived from sale at
livestock markets in cities such as Chemchemal. During Eid Qurban, PACs may sacrifice
meat for poorer members of the community.
Access to grazing land is a vital provisioning ecosystem service for livestock rearers.
During focus groups with land users in Taza Shar, Qarah Chewar and Khor Mor Gawra,
it was reported that while grazing predominantly takes place on village land adjacent to
the PACs, some use pastures located between 2 to 5 km from the PACs. Individuals
travel to these pastures with a few other household members or in small groups with
other households.
Groundwater is a key provisioning ecosystem service providing water for livestock;
seasonal springs and ponds are relied upon to a lesser extent (household interviews,
FGD with land users). An example of a groundwater well used to water livestock in Takhta
Mina Saru is presented in Figure 3-24. A generator is used to pump water to a storage
area on the surface where it is consumed by livestock.
During primary baseline data collection, water scarcity and poor water quality were
commonly cited issues in the context of livestock rearing. According to focus group
participants in Taza Shar, groundwater well water levels are decreasing, corroborating
trends at the regional level with regards to the declining availability of groundwater across
the KRI.
3.4.7.7 Employment
Precise data on employment by sector were unavailable at the time of writing. Accounting
for more than 50% of employment (26% in non-military employment), the KRG is the
main employer in the region (World Bank, 2016a). This is one of the highest public sector
employment rates in the world.
26% 24%
24% 22%
Percentage of Household
21%
22% 19%
20%
18% 15%
16% 13%
14%
12%
10%
Members
8% 7%
6%
4%
2% 0%
0%
Awaye Kani Khor Mor Khor Mor Mamisik Shekh Taza Zhazh
Jalal Qadir Gawra Bichuk Hameed Shar
Qala
PAC
Recruitment at the existing facility follows an established process whereby the SDM of
Qadir Karim is engaged by and agrees with Pearl Petroleum the distribution of
employment opportunities across the local communities; contractors and sub-contractors
are required to honour this agreement when hiring personnel. Support is provided to
persons who experience difficulties with reading and writing when applying for
employment at the existing facility.
As of 2018, the KRI had an overall unemployment rate of 9%, declining from 13% in 2015
(PwC, 2018). Unemployment is higher amongst females (20.1%) compared to males
(8.1%) and particularly affects young people. Many unemployed youths are university
graduates, owing to the fact that the KRI’s education sector has developed at a rate faster
than the labour market can absorb (World Bank, 2015).
Pearl Petroleum 126
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Unemployment also varies geographically, with higher rates reported in Dohuk compared
to Erbil and Sulaymaniyah (see Figure 3-26) (KRSO, 2019).
Unemployment rates in the PACs are extremely high relative to the region. Approximately
80% of household members were unemployed at the time of the household survey, of
whom 69% were actively seeking work and 31% were not. These figures exclude those
unable to work because of age, educational commitments, retirement or disability.
Figure 3-27 shows unemployment as a percentage of household members interviewed
across the PACs. Over 60% of household members interviewed in Kani Qadir Qala, Khor
Mor Bichuk and Mamisik were unemployed and seeking work at the time of the household
survey. Except for Khor Mor Gawra, 20% or more household members in the PACs were
unemployed and not seeking work.
100%
100%
Percentage of Household
90%
80%
70% 60% 63% 60% 63%
60% 54%
Members
50% 43%
35% 38%
40% 30% 31%
30% 20% 19% 21% 21%
20%
10%
0%
Awaye Kani Qadir Khor Mor Khor Mor Mamisik Shekh Taza Shar Zhazh
Jalal Qala Gawra Bichuk Hameed
PAC
Unemployed and Seeking Work Unemployed and Not Seeking Work
Consistent with data at the regional level, unemployment is an issue which particularly
affects female PAC members. No women are employed in Awaye Jalal, Kani Qadir Qala,
Taza Shar, Shekh Hameed and Zhazh (FGD with women). A very small number of
3.4.9 Land
Land use and ownership in the KRI is regulated by a number of laws and legislative acts
supported by ongoing land reform and cadastral improvements. The combination of
100% 100%
Percentage of Households
40% 33%
20%
0%
0%
Awaye Kani Khor Mor Khor Mor Mamisik Shekh Taza Shar Zhazh
Jalal Qadir Gawra Bichuk Hameed
Qala
PAC
50% 48%
Percentage of Households
40%
30%
20% 14%
10% 12% 10%
10% 6%
1%
0%
1 2 3 4 5 6 7
Number of Plots
14This includes inherited land, which has been passed from generation to generation but frequently results in an
unmanageable number of owners (USAID, 2019a).
Pearl Petroleum 132
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Current data on the distribution of land according to land tenure category is scarce
(USAID, 2019a). All land is generally categorised as either urban or rural.
A series of KII and FGD with flowline land owners and land users were conducted in October 2019. These activities
sought to collect data on:
A mixture of land ownership and usage arrangements were described during KII and FGD. The land associated
with the flowline land owners is privately owned and was acquired by these individuals through inheritance. This
land has typically been owned for over 100 years by the same family, having been passed down through
generations. Contrary to trends observed during household interviews, the flowline land owners reportedly possess
formal documentation proving their ownership of the land.
Alternatively, the land associated with the flowline land users is eased to these individuals by friends or family or the
Ministry of Agriculture. The rental of land from friends or family is highly informal and often based on verbal
agreements whereas land which is rented by the Ministry of Agriculture is based on a formal process. Some of the
flowline land users reportedly possess formal documentation (e.g. letters from the Ministry of Agriculture) proving
their right to use the land whereas others do not.
Land is primarily used for crop farming, with some livestock rearing taking place (mainly sheep, goats and
occasionally cows). Natural resources, including wild plants (gundelia and mushroom, grass and berries) are also
collected and consumed, or sold for cash income. Land boundaries are typically clearly demarcated by the use of
stones or strips of non-cultivated land.
Key challenges for land owners and land users include drought, insufficient water supply and inadequate water
quality, attacks on livestock (from wild animals, such as wolves), lack of veterinary services, wildfires and lack of
support from government and organisations (e.g. lack of agricultural inputs). Conflicts over land are rare; the few
disputes that do occur are mostly related to land demarcations or trespassing by livestock. Conflicts are typically
resolved by elders and relatives within a matter of days.
3.4.9.6 Procedure for access to land for oil and gas activities
In the oil and gas sector, access to land located in rural areas can be obtained with the
permission of the KRG Ministry of Natural Resources (MNR), and only for agreed
durations (MNR, 2013b). In May 2013, the MNR issued a decree stipulating that
companies undertaking exploration and production activities must pay annual rents to
owners and/or users on whose land oil well drilling blocks are located. Landowners and/or
users and local communities can apply for land-related compensation by completing
standard application forms available from the Ministry. An initial committee is established
by the District Manager during the pre-acquisition phase, composed of representatives
from the district authorities and the Ministry (Directorate) of Agriculture. This committee
processes the written request from the company to access land and identifies the land
area, coordinates and land owners by undertaking a site visit.
During the actual land acquisition phase, another committee is established by the MNR
composed of representatives of the MNR, the Ministry (Directorate) of Agriculture, the
Directorate of Real Estate Registration, a land surveyor, local authorities from the district
and a company representative. The committee determines the level of crop and land
compensation to be paid based on several criteria, including the land area, the type of
land, how the land is used, whether it is cultivated, and the previous year’s type of crop
as assessed through a survey and land boundary records from the Ministry of Agriculture.
The local land office also plays an important role in identifying and certifying the category
of the land.
A Higher Committee, formed at the level of the Governorate during the compensation
phase, consists of members from the Council of Ministers, the MNR, the Governorate,
the Ministry (Directorate) of Agriculture and the Directorate of Real Estate Registration.
This committee evaluates the compensation request forms from the affected people and
the proposed rates and directs a disbursement request to the MNR. The MNR prepares
the agreement to be signed with the land owners and/or users.
Companies are also required to pay annual rents to community members who lose
access to the use of public pastures on which drilling blocks are located (MNR, 2013b).
Roads used by companies are to be returned to the original users after 50 years.
15 These activities were undertaken prior to the publication of more recent ministerial instructions requiring the
establishment of three separate committees to handle land-related issues for oil and gas operations in the KRG
(see Section 3.4.9.6).
Pearl Petroleum 136
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
• their understanding and acceptance that:
o as a result of compensation, they no longer had rights to use the land
o their compensation was a one-off payment and no additional
compensation would be paid
o the land was now allocated to the MNR for petroleum purposes according
to regional law and regulations.
The contents of the agreement were explained orally to land users to confirm their
understanding and acceptance of the agreement. Records of each agreement were
retained by the MNR and Pearl Petroleum. In line with regional regulatory requirements,
a completion audit was undertaken by joint committees, comprising representatives from
regional and local government and Pearl Petroleum, to confirm that the affected land
users had been compensated in line with the terms of their agreement. Following the
completion audit, Pearl Petroleum has remained in contact with the MNR to discuss any
related complaints or comments received.
During stakeholder engagement for the ESIA, some of these land users expressed
dissatisfaction with the compensation process that was followed, the amount of
compensation that they received and the frequency of their compensation payment (one-
off rather than yearly). They were advised to report their grievances to Pearl Petroleum’s
SPD by RSK (through its local in-country partner), using the Community Grievance
Management Procedure (see Section 4.6). At the time of writing, however, Pearl
Petroleum has not received any related grievances.
In relation to the above concerns, Pearl Petroleum note that the compensation process
was:
• implemented in accordance with the regulations of the KRG
• transparent and understandable to all affected persons, with the conditions of
compensation payments being clearly stated in supporting documentation (e.g.
the compensation agreements between the affected land users and the MNR)
• accepted by the affected land users, who agreed to a one-off compensation
payment and understood that no additional compensation would be paid.
Pearl Petroleum further note that the amounts of compensation paid was higher than the
amounts that land users typically receive in similar situations across Kurdistan.
Outside the boundary of the existing facility, but within the boundaries of the Khor Mor
concession area, there are three well pads (KM3, KM6 and KM9) which are used by Pearl
Petroleum but are located on land that has been the property of the government since
the 1970s, when it was acquired by the government for oil and gas exploration purposes.
According to anecdotal evidence, there is dissatisfaction amongst the former land
users/land owners and their descendants, who allege that compensation issues were not
properly resolved at the time of acquisition. In addition, there are cases whereby sections
of pipeline, connected to the existing facility but located outside the Khor Mor concession
area, have allegedly been constructed on land prior to the compensation process (led by
the MNR and MoAWR) being finalised.
Such issues are in the process of being addressed by the MNR with a Land Acquisition
and Compensation Committee having been established in mid-2019 (with participation
from other governmental agencies) to expedite the process.
Percentage of Households
80% 66.5% 71%
62%
55%
60% 45%
33.5% 38%
40% 29%
15%
20%
0%
Awaye Kani Khor Mor Khor Mor Mamisik Shekh Taza Zhazh
Jalal Qadir Gawra Bichuk Hameed Shar
Qala
PAC
Burned in Private Waste Pit Disposed of at Waste Collection Point
Almost all food waste is fed to livestock; some households in Awaye Jalal, Khor Mor
Bichuk, Taza Shar and Zhazh burn food waste in private waste pits.
Except for in Mamisik (which consists of only one household), interviewed households
mainly dispose of solid waste at waste collection points in the PACs. A private company
– Shkar – is contracted by the local government to collect waste from these points weekly;
the waste is subsequently burned or deposited in landfills (KII with SDMs). Alternatively,
over a quarter of households interviewed in Khor Mor Bichuk, Shekh Hameed, Taza Shar
and Zhazh burn solid waste in private waste pits.
Despite a growing interest in recycling at the regional and governorate level, reports of
recycling in the PACs were extremely uncommon. During the household interviews, one
of the internally displaced families reported that they recycle aluminium. This, however,
is to generate income rather than manage waste.
3.4.10.3 Energy
Until 2007, the KRI suffered an acute electricity crisis and an absence of locally generated
power; many businesses and residents typically had access to electricity for only two
hours a day (PwC, 2018). By 2017, gas supplies accounted for approximately 80% of the
energy used for electricity generation in the KRI (PwC, 2018). Though a significant
proportion of the electricity generated in Kurdistan is consumed domestically, the region
has the greatest electricity access in Iraq, enabling it to supply power to other parts of the
country (MNR, 2013a).
The average public electricity supply is limited to 17 hours per day. The number of hours
of electricity across the governorates is presented in Figure 3-32.
Percentage of Households
70% 74%
80%
60%
54%
60% 49%
40% 30% 33% 31%
49%
16% 15% 18%
20% 7% 10%
2%
0%
Awaye Kani Qadir Khor Mor Khor Mor Mamisik Shekh Taza Shar Zhazh
Jalal Qala Gawra Bichuk Hameed
PAC
3.4.10.5 Transport
3.4.10.5.1 Roads
The KRI has a road network of 23,400 km (World Bank, 2015). This network includes
primary roads (linking governorate centres with one another and border crossings),
secondary roads (linking areas within districts and sub-districts) and tertiary roads (linking
communities in rural areas with one other and with arterial roadways) (Invest in Group,
2013c). The primary and secondary road network is mostly paved, with 52 km being
identified as earth, gravel or tracks. Tertiary roads are mostly unpaved and are in poor or
very poor condition.
The existing road network in the Project area is the principal means of transporting
personnel and equipment to the Project site. There are no buses or public transportation
networks available. Generally, most people reported using private cars to go to school,
medical centres, shopping and work and 65% of the households interviewed own cars.
The road conditions vary significantly from good asphalt paved roads, to high-grade and
low-grade gravel roads, down to dirt roads in very poor condition. The main road between
Qadir Karam and Khor Mor is considered to be in especially poor condition. Bridge
crossings do not identify the load capacity and could represent a safety hazard or heavy
loads.
The northern portion of the existing facility is easily accessed by a paved Qadir Karam –
Khor Mor - Nojol Road, crossing the Rokhana River through a bridge in Qadir Karam.
The southern portion also has easy access by a paved road which runs from Kirkuk along
3.4.10.5.2 Traffic
A road traffic and pedestrian count survey was undertaken by RSK in September 2019
in order to understand the existing traffic demand for both light vehicles, heavy vehicles
and pedestrians. The surveys were undertaken in the AOI where Project-related traffic
during the construction phase is expected to represent a significant increase of traffic on
the local public road network. These include main road transportation routes north-east
of the site, near the villages of Cham Surkhaw and Qadir Karim, and south-west of the
site, near the villages of Khor Mor Gawra and Khor Mor Bichuk. The survey locations are
presented in Table 3-34 and illustrated in Figure 2-6 (Section 2.6.1.6).
The traffic count survey (15-minute periods) consisted of:
• manual counting at six strategic locations, north and south directions for each
location
• two survey periods:
• morning survey between the hours of 0700 and 1000
• afternoon survey between the hours of 1300 and 1600
• classification of vehicles as motorcycle, car, van, medium goods vehicle (MGV)
or heavy goods vehicle (HGV).
Survey results are illustrated in Appendix 2 (Figure A2.1 to A2.6). The busiest periods on
the local road network are between the hours of 0800 and 1000, 1400 and 1600.
Location Description
Near the village of Zardah, the first entry point into the AOI along
Traffic count location 1
the main road transportation route.
After the junction near the village of Cham Surkhaw; this route will
Traffic count location 2
then continue towards the site.
Traffic count location 3 Near the junction towards the village of Mamisik.
Traffic count location 4 Near the junction towards the Project site.
Traffic count location 5 Near the junction towards Khor Mor Gawra.
Near the junction towards the villages of Khor Mor Bichuk, Awaye
Traffic count location 6
Jalal and Taza Shar.
3.4.10.5.4 Airports
The KRI is serviced by two international airports, one located in Erbil and one located in
Sulaymaniyah. The number of passengers, airport movements and cargo handled by the
region’s largest airport – Erbil International Airport (EIA) – has shown an overall increase
between 2008 and 2018. The construction of a third international airport, located in
Dohuk, began in 2012 and, when complete, will handle 328,000 passengers, 8,700 tons
of cargo and 3,450 aircraft movements per year (Airport Technology, 2019).
There are no airports in the AOI. The closest airport to the PACs is Sulaymaniyah
International Airport (approximately 140 km away).
16 For all Project phases: 150 m either side of road transport routes where the project’s contribution to road
transport is expected to be significant.
17 The HDI is a composite measure of human development which takes into account life expectancy at birth,
education and per capita income. The HDI was developed by the United Nations and classifies countries into four
tiers of human development: very high, high, medium and low.
Pearl Petroleum 146
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
9.00% 8.60%
8.00%
6.70%
7.00%
Poverty Rate (%) 5.46%
6.00%
5.00% 4.46%
4.00%
3.00%
2.00%
1.00%
0.00%
KRI Erbil Sulaymaniyah Dohuk
Living standards are generally lower in rural parts of Kurdistan, owing to numerous factors
such as lower levels of literacy and educational attainment and scarcer opportunities for
employment (Harun et al., 2015). With an HDI value of 0.764 and poverty rate of 4.46%,
the Governorate of Sulaymaniyah has a higher level of human development and lower
level of poverty than other parts of the KRI.
Village Anjuman and SDMs reported a mixture of socio-economic classes within their
communities. 50% of population in approximately two thirds of the PACs considered
themselves as middle class, having more than one source of income, owning assets
(such as land, a car and/or farming equipment) and having ability to hire agricultural
labour if needed.
PAC members identified to be lower class was based on their reliance only on one source
of income, lack of land and/or other assets and employment as agricultural laborers
themselves. The proportion of lower-class PAC members ranges from less than 10% of
the population in Ali Mustafa, Awaye Jalal, Chala Dwana and Taza Shar to 80% and
above in Khor Mor Gawra and Qadir Karim.
Approximately one third of residents living in Ibrahim Ghulam, Khor Mor Bichuk, Qarah
Chewar, Shekh Hameed and Takeya Jabari were identified as belonging to the upper
class due to having more than one income source, having their own business or large
amount of land and assets to cultivate that land, as well as having ability to hire people
to do farming and livestock rearing.
Household interview data indicates that the ownership of consumer goods by PAC
members is high, with up to 80% of the households in PACs such as Khor Mor Bichuk
and Zhazh owning a car. All interviewed households except for the one household in
Mamisik reported to have mobile phones, and every household in Kani Qadir Qala, Khor
Mor Gawra, Khor Mor Bichuk, Taza Shar and Zhazh reported to own a television. Up to
75% of households interviewed owned a fridge, increasing to 86%, 88% and 93% in
Zhazh, Khor Mor Gawra and Kani Qadir Qala respectively. The ability to afford such items
indicates that households enjoy a certain level of disposable income.
Nevertheless, it is important to acknowledge that PACs comprise a mixture of socio-
economic classes with a number of poorer households identified by village Anjuman and
SDMs, particularly in Cham Surkhaw, Khor Mor Gawra and Qadir Karim. Moreover,
demands for improvements in health care, schools, water supply and electricity were
3.4.11.3 Gender
The United Nation’s (UN) Gender Inequality Index (GII) 18 indicates that women in the KRI
experience greater equality than women in the remainder of Iraq and other countries in
the Middle East (see Table 3-35).
18 The GII is a composite measure reflecting inequality in achievement between men and women in three
dimensions: reproductive health, empowerment and participation in the labour market (UNDP, 2017a). It ranges
from zero to one, where the lower the score the more equality there is between men and women (Open
Democracy, 2016).
Pearl Petroleum 148
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Table 3-35 GII values for the KRI, Iraq and other countries in the region
Women in the KRI have more legal rights than women in other parts of the country (Kaya,
2017). The KRG has introduced new legislation and amended existing laws to advance
the status of women in society. The Government has also ratified the principles of the
Convention on the Elimination of Discrimination against Women (CEDAW) and launched
a National Strategy to Confront Violence against Women in 2012.
Notwithstanding these improvements, Kurdish society remains patriarchal and male-
dominated (Samad, 2018). As stated in Section 3.4.6, literacy levels and school
attendance rates are lower amongst females compared to males (IOM, 2018a).
Unemployment rates are 12% higher for women than men, and female labour market
participation rates are 50% lower (KRSO, 2019). Household level data is consistent with
these findings.
Forced marriage was reported during FGD with women. Participants of focus groups in
Khor Mor Bichuk, Khor Mor Gawra and Taza Shar stated that local girls, sometimes as
young as 13, are coerced into marrying partners without their agreement.
Vulnerability is defined as a set of specific characteristics that might influence the
likelihood of a household of experiencing hardships and result in increased poverty (IOM,
2018b).
3.4.11.3.6 Children
Whilst the lives of children in the KRI have improved (UNICEF, 2018b), some children
remain vulnerable. Access to education and educational attainment is lower amongst
children from poorer backgrounds (UNICEF, 2018b), whose families may be unable to
afford school-related costs (e.g. transportation, uniforms) or may require them to
undertake household tasks (e.g. agricultural and domestic work).
The loss of hundreds of Kurdish Peshmergas during the war against ISIS has also
produced a large number of widows and orphaned children, many of whom struggle to
access food, water, shelter, health care and education (KSCF, 2014). Some orphans
have turned towards child labour to provide for themselves and remaining family
members (KSCF, 2014).
19 Only one internally displaced household reported that they had a member who was living with a disability.
Pearl Petroleum 153
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Group Key findings Analysis of vulnerability
3.4.12.2 Archaeology
An archaeology survey was conducted in November 2019 by an archaeologist from the
Directorate of Antiquities of the Garmiyan Region. There are various identified
archaeological sites surrounding the main Project site (see Figure 3-36 and Appendix 2).
Only one, Sarcham Tepe (see Figure 3-37), is located near a KM25A Project construction
site, concerning the proposed flowlines. The site is a hill with rectangle shape with
Pearl Petroleum 156
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
approximate dimensions of 20 m by 30 m. Sarcham Tepe is thought to date from the
Sassanid period (226-637 AD). The site is approximately 5 m higher than the surrounding
flat area. The proposed flowline is not expected to disturb the site, although possible
movement of flowline locations following additional surveys could bring flowline
construction activities closer to the site. According to the Directorate of Antiquities, the
Sarcham Tepe grave site is not threatened.
The Tapa Julaka grave site (Ottoman 1500 to 1918 AD) is located adjacent to the berm
to the west of the KM site. The rectangular site is approximately 150 m by 100 m and
approximately 1 m higher than the surrounding flat area. There are no on-going activities
associated with KM250A Project or the existing gas plant in the vicinity of the Tape Julaka
grave site. According to the Directorate of Antiquities, the Tapa Julaka grave site is not
threatened.
Label for
Stakeholder name and category Level of influence Level of impact stakeholder
mapping
Regional government
High- Administers all operations regarding the
petroleum industry in the Kurdistan Region of Iraq
Ministry of Natural Resources (MNR) (KRI) Low- Potential contribution of the
(including the MNR Representative for Project to the long-term development 1
the Governorate of Sulaymaniyah) Actively involved in the review and approval of ESIA goals of the MNR
studies for the petroleum industry – ability to
facilitate or block Project
Medium- Can provide information (e.g. regarding Low- Potential disturbances to
Ministry of Agriculture and Water local land owners) agricultural land and water by the 2
Resources
Can damage/boost reputation Project
Medium- Can provide information (e.g. on history of Low- Potential for the Project to have
Anfal in Khor Mor area, people affected by Anfal) disproportionate impacts on people
Minister of Martyrs and Anfal Affairs 5
affected by Anfal (a potentially
Can damage/boost reputation vulnerable group)
Medium- Can provide information (e.g. regarding
unexploded ordinance that may be disturbed by the Low- Potential for the Project to disturb
Mine Action Agency Project) unexploded ordinance in Khor Mor 6
block
Can damage/boost reputation
Zhazh, Khor Mor Gawra, Khor Mor High- Potential Project-related benefits
Bichuk, Awaye Jalal, Taza Shar, Medium- Support for or resistance to the Project Potential impact of Project upon
10
Shekh Hameed, Kani Qadir Qala and Can provide information (e.g. for ESIA studies) community members
Mamisik Close proximity to Project
Chala Dwana, Aziz Bag, Takhta Mina Medium- Potential Project-related
Saru, Ibrahim Ghulam, Cham Medium- Support for or resistance to the Project benefits
Surkhaw, Aliawa, Qarah Chewar, Ali 11
Mustafa, Paryawla, Qadir Karim and Can provide information (e.g. for ESIA studies) Potential impact of Project upon
Takeya Jabari community members
Civil society
Low- Support for or resistance to the Project Low- Potential for the Project to
University of Sulaymaniyah generate employment and training 23
Can provide information (e.g. for ESIA studies) opportunities for graduates
Low- Potential for the Project to
Low- Support for or resistance to the Project generate employment and training
Charmo University opportunities for graduates 24
Can provide information (e.g. for ESIA studies)
As noted in Section 4.4.1.3, women’s focus groups were undertaken to provide further
opportunities to learn and ask questions about the Project and the ESIA. An example of
a women’s focus group is shown in Figure 4-6.
Figure 4-6 Women’s focus group discussion at Khor Mor Gawra, 5 October 2019
Ecological and
Groundwater
Noise quality
environment
Soil quality
I
Air quality
biological
quality
Construction phase
Early works (civil work, site preparation, earth works for foundation and internal roadways) X X X X
Installation of main equipment X X X X
Use of construction equipment X X X X
Site gravelling and levelling X X X X
Self-contained construction camps including accommodation; catering/welfare facilities; workshops, warehouses and storage yards X X X
Shutting-down and de-pressurizing gas plant and eventual decommissioning of a gas processing facility located within the existing site boundary,
including:
- remove all hydrocarbons to render the plant inert
- remove all chemicals and certify that the whole plant is hydrocarbon and hazardous chemical-free
X X X X X
- disconnect and dismantle the equipment, and remove modules and scrap from the site for refurbishment or recycling
- demolish structures and paving and remove the materials from site as inert waste
- level the site and undertake soil and groundwater survey to determine whether any remediation is needed.
- spread stored topsoil for site rehabilitation
Local economy
and livelihoods
Infrastructure
Public health
development
and services
Land access
Employment
Community
Labour and
Vulnerable
conditions
safety and
and skills
economy
I
Regional
heritage
security
working
Cultural
groups
Construction phase
Early works (civil work, site preparation, earth works for foundation and internal roadways) X X X X X X
Installation of main equipment X X X X X X
Use of construction equipment X X X X X
Site gravelling and levelling X X X X X
Self-contained construction camps including accommodation; catering/welfare facilities; workshops, warehouses and
X X X X X X X
storage yards
Gas plant construction X X X X X X X
Flowlines construction including: RoW preparation, stripping and grading; Pipe stringing; Welding; Excavating trenches;
X X X X X X X X X
Lowering; Backfilling (reinstating)
Requirements for chemicals and other raw materials X X X
Transportation of process equipment, pipe racks, piping and other materials by roads X X X X
Construction workforce commuting to/from site X X X X X
Site security X X X X X X
Pre-commissioning and commissioning phase
KM250A Testing Gas plant units X X X X
Project Flowline hydrotesting and commissioning (water intake, discharge and safety issues) X X X X X X
activities Requirements for chemicals and other raw materials
(aspects) Operations phase
Requirements for chemicals and other raw materials X
Export of gas, LPG and condensate via pipelines or bulk transport X X X X X
Emergency response and relief, flare and blowdown systems
Maintenance activities X X X X
Permanent operations workforce and accommodation (80-100 ppl/rotational) X X X X X X
Decommissioning
Shutting-down and de-pressurizing gas plant and eventual decommissioning of a gas processing facility located within
the existing site boundary, including:
- remove all hydrocarbons to render the plant inert
- remove all chemicals and certify that the whole plant is hydrocarbon and hazardous chemical-free
- disconnect and dismantle the equipment, and remove modules and scrap from the site for refurbishment or X X X X X X
recycling
- demolish structures and paving and remove the materials from site as inert waste
- level the site and undertake soil and groundwater survey to determine whether any remediation is needed.
- spread stored topsoil for site rehabilitation
Intensity Description
The receiving environment or receptors where disturbance due to the
Low Project impacts is minimal or tolerant to changes from the Project. (e.g.
desert, industrial areas)
The receiving environment or receptors are moderately sensitive or
Medium
reasonably tolerant of changes, where it may cause some disturbance
The receiving environment or receptors where people or habitats are
High particularly susceptible to changes from the Project (e.g. residential areas,
schools, ecological sensitive areas)
Sensitivity of receptor
Magnitude
of impact
High Medium Low
Positive impacts, particularly within the socio-economic sphere (for example increase in
local employment due to the Project), can result from Project activities. In this
circumstance, such impacts have not been ranked but were assigned a ‘positive impact’
for simplicity (see Table 5-4) and discussed as appropriate, based on the assumption
that any measures that would optimise benefits will be effectively implemented.
20 See ‘Technical Guidelines on Environmental Impact Assessments for Petroleum Operations in the Kurdistan
21‘Trackout’ is solid material from a site that adheres or agglomerates on the exterior of a motor
vehicle (including tires), then subsequently falls onto a paved public roadway.
Pearl Petroleum 195
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
5.7.1.1.4 Summary
Impact significance for the construction phase is summarised in Table 5-5.
Unmitigated Mitigation
Impact Magnitude Sensitivity impact required
significance (Y/N)
Site clearance, preparation, excavation
and grading leading to potential increase Medium Low Minor N
in air emissions (exhaust)
Site clearance, preparation, excavation
and grading leading to a potential periodic
Medium Low Minor N
increase in fugitive dust levels due to
vehicle movements
Number of
Sl No. Source Fuel Rating (MW)
units
1 Booster compressor Gas 3 19.5
2 Sales gas compressor Gas 4 28.1
3 Power generation turbine Gas 5 20.25
4 Hot oil heater Gas 1 67.73
5 Thermal oxidiser Sour Gas 1 4.35
Mass flared in
Flare stack Gas
unplanned Flare stack
Sl NO Flare diameter velocity
condition height
(inches) (m/s)
(kg/hour)
HP flare (with LT
1 521095 30 50 330
flare)
2 LP flare 14416 8 20 171.50
3 LLP flare 485 18 25 8.65
The impact on ambient air quality from the KM250A Project has been assessed through
an atmospheric air dispersion modeling study (ADMS) of emissions from the point
sources and flaring operations. Two scenarios were modeled in the ADMS, namely:
Source characterisation
At this stage of the Project design, there is limited information available concerning the
emission sources. The point sources modeled in the ADMS was characterised using data
provided by the client, engineering assumptions and United States Environmental
Protection Association (EPA) air pollutant (AP) emission factors. Table 5-8 below
provides stack parameters for the point sources modeled in the ADMS.
Flares in AERMOD are modeled as point sources, as a specific flare option is not
available in AERMOD. While EPA Screen provides for a flare option, this model is
suitable only for screening purposes and not for refined modeling. EPA Screen has built-
in algorithms to account for buoyancy from the calculated heat release
Building downwash
Building downwash refers to the effect that wind flowing around and over buildings can
have on plume from stacks. EPA’s Building Profile Input Programme (BPIP) is an
algorithm used to determine downwash effects for single and multi-tiered buildings and
structures. The following buildings have been assessed using BPIP (Figure 5-2):
1. Accommodation camp
2. Training center
3. Warehouse
4. LPG office
5. Laydown yard and warehouse
6. Drilling warehouse
7. Medical center.
Receptors
Sensitive receptors (see Table 5-9) used for this analysis are the same points at which
baseline diffusion tube data was collected for various pollutants relevant to the KM250A
Project (see Figure 3-5). Seven of these locations are villages within the KM250A Project
air quality AOI. The eighth receptor is a key strategic location to the north of the site.
Table 5-10 Model predictions for the 1-hour averaging period – NO2
Table 5-11 Model predictions for the 24-hour averaging period – NO2
Table 5-12 Model predictions for the annual averaging period – NO2
Model
predicted
concentration Baseline Cumulative Project
Sl.No Receptor ID Location (µg/m3) concentration impact Standard
Routine (µg/m3) (µg/m3) (µg/m3)
operations
(Scenario 1)
Khor Mor
1 MP1 1.37 2.5 3.86596
Gawra
Awaye
2 MP2 0.24 2.2 2.44269
Jalal
Taza
3 MP3 0.20 1.4 1.6037
Shaher
Sheikh
4 MP4 0.12 2.4 2.5189
Hameed
Khor Mor
5 MP5 0.97 2.7 3.66703 40
Bichuk
6 MP6 Mamisik 1.63 2.5 4.12611
Qadir
7 MP7 0.14 2.5 2.64379
Karam
Key
8 MP8 1.09 4.6 5.68966
location
Maximum
9 offsite - 4.35 - 4.34667
concentration
Red – exceeds Project Standard
Figure 5-4 Model predictions for 24-hour averaging period (Scenario 2) - NO2
7 MP7 Qadir
166.31 166.27 164.96
Karam
8 MP8 Key
350.25 350.25 348.88
location
9 Maximum -
offsite 2563.12 2563.12 2563.12
concentration
10 95th percentile -
offsite 638.20 638.20 638.20
concentration
Red – exceeds Project Standard
Table 5-14 Model predictions for the 3-hour averaging period – SO2
Table 5-15 Model predictions for the 24-hour averaging period – SO2
Model predicted
concentrations (µg/m3) Project
l.No Receptor ID Location Routine Thermal Standard
operations oxidiser (µg/m3)
(Scenario 1) alone
1 MP1 Khor Mor Gawra 4.04 3.89
2 MP2 Awaye Jalal 4.68 4.64
3 MP3 Taza Shaher 1.85 1.83
4 MP4 Sheikh Hameed 2.49 2.48
5 MP5 Khor Mor Bichuk 8.68 8.52 20 (interim
limit 125)
6 MP6 Mamisik 2.01 1.86
7 MP7 Qadir Karam 0.37 0.36
8 MP8 Key location 1.34 1.24
Maximum offsite -
9 47.0 46.94
concentration
Red – exceeds interim limit
Figure 5-6 Model predictions for 3-hour averaging period (thermal oxidiser) – SO2
Figure 5-8 Model predictions for 24-hour averaging period (thermal oxidiser) – SO2
Model predicted
concentrations (µg/m3) Project
Sl.No Receptor ID Location Routine Non-routine Standard
operations operations (µg/m3)
(Scenario 1) (Scenario 2)
1 MP1 Khor Mor 39.15 39.15
Gawra
2 MP2 Awaye Jalal 30.67 30.67
34.368
3 MP3 Taza Shaher 20.25 20.34
4 MP4 Sheikh 13.81 13.81
Hameed
Model predicted
concentrations (µg/m3) Project
Sl.No Receptor ID Location Routine Non-routine Standard
operations operations (µg/m3)
(Scenario 1) (Scenario 2)
1 MP1 Khor Mor
Gawra 11.17 11.17
2 MP2 Awaye Jalal 4.63 4.77
3 MP3 Taza Shaher 4.12 4.49
4 MP4 Sheikh
Hameed 2.69 4.14
5 MP5 Khor Mor 10,310
Bichuk 13.67 13.67
6 MP6 Mamisik 9.89 9.90
7 MP7 Qadir Karam 3.01 3.50
8 MP8 Key location 7.00 7.00
9 Maximum offsite - 30.92 30.95
concentration
Red – exceeds Project Standard
10,310 µg/m3 = 9 ppm
Table 5-19 Model predictions for the 24-hour averaging period – PM10
Model predicted
concentrations (µg/m3) Project
Sl.No Receptor ID Location Routine Non-routine Standard
operations operations (µg/m3)
(Scenario 1) (Scenario 2)
1 MP1 Khor Mor 0.33 0.33
Gawra
Table 5-20 Model predictions for the annual averaging period – PM10
Model predicted
concentrations (µg/m3)
Project Standard
Sl.No Receptor ID Location
(µg/m3)
Routine operations
(Scenario 1)
Khor Mor
1 MP1 0.04
Gawra
2 MP2 Awaye Jalal
0.02
4 MP4 Sheikh
0.02
Hameed
5 MP5 Khor Mor
0.05
Bichuk
20
6 MP6 Mamisik
0.06
Qadir Karam
7 MP7 0.02
Maximum -
9 offsite 0.11
concentration
Red – exceeds Project Standard
Table 5-21 Summary of unmitigated potential impacts on air quality during operation
Unmitigated Mitigation
Impact Magnitude Sensitivity impact required
significance (Y/N)
Emissions from routine or non-routine
operations of the gas plant leading to
High Medium High Y
increase in NO2 ambient ground level
concentrations
Emissions from routine or non-routine
operations of the gas plant leading to High Medium High Y
Increase in SO2 levels in ambient air
Emissions from routine or non-routine
operations of the gas plant leading to Slight Medium Slight N
increase in CO levels in ambient air
Emissions from routine or non-routine
operations of the gas plant leading to Slight Medium Slight N
increase in PM10 levels in ambient air
23 Scope 1 concerns direct GHG emissions from site sources that are controlled by Pearl Petroleum. Scope 2
concerns indirect GHG emissions that are emitted in the generation of electricity.
Pearl Petroleum 214
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
The contribution of VOCs has been excluded.
The estimated GHG emissions for the KM250A Project are presented in Table 5-22.
methane 1,060 30 0 0
NO2 0 79 0 0
KM250A Project operations phase gas plant GHG emissions are likely to be largely
neutralised by the reduction of high-carbon diesel for relatively low-carbon gas at
Kurdistan power plants as a result of the Project. The net impact of the Project with
respect to GHG emissions is therefore positive. More precision will be obtained during
the construction phase of the Project once equipment is specified.
Unmitigated Mitigation
Impact Magnitude Sensitivity impact required
significance (Y/N)
Operation of gas train leading to potential
decrease in GHG emissions from regional power Positive Medium Positive N
plants due to substitution of KM250A sales gas for
current diesel fuel at those installations
5.7.2 Soil
5.7.2.1.4 Summary
The impact significance is presented in Table 5-24 below.
Unmitigated Mitigation
Impact Magnitude Sensitivity impact required
significance (Y/N)
Ground excavation for flowlines leading
Low Medium Minor N
to loss of land/soils
Storage and handling of fuels, chemicals
and waste leading to reduction in soil Low Low Slight N
quality
5.7.2.2.4 Summary
A summary of unmitigated potential KM250A Project pre-commissioning and
commissioning impacts on soil is presented in Table 5-25.
Unmitigated Mitigation
Impact Magnitude Sensitivity impact required
significance (Y/N)
Leaks and discharge of hydrotesting
water to ground leading to soil Low Medium Minor N
contamination
5.7.2.3.4 Summary
A summary of unmitigated potential KM250A Projects operations phase impacts on soil
is presented in Table 5-26.
Unmitigated Mitigation
Impact Magnitude Sensitivity impact required
significance (Y/N)
Storage and handling of fuels, chemicals
Slight Low Slight N
and waste leading to soil contamination
5.7.2.4.4 Summary
A summary of unmitigated potential KM250A Project decommissioning phase impacts on
soil is presented in Table 5-27.
Unmitigated Mitigation
Impact Magnitude Sensitivity impact required
significance (Y/N)
Storage and handling of fuels, chemicals
Slight Low Slight N
and waste leading to soil contamination
5.7.3.1.4 Summary
A summary of unmitigated potential KM250A Project construction phase impacts on
water resources is presented in Table 5-28.
Unmitigated Mitigation
Aspect Magnitude Sensitivity impact required
significance (Y/N)
Groundwater abstraction leading to aquifer
Medium High High Y
drawdown
Storage and handling of fuels and
chemicals leading to leaks/spills and Low High Moderate Y
reduced groundwater quality
Table 5-29 Summary of unmitigated potential impacts on water resources during pre-
commissioning and commissioning
Unmitigated Mitigation
Impact Magnitude Sensitivity impact required
significance (Y/N)
Groundwater abstraction leading to aquifer
Low High Moderate Y
drawdown
Generation of wastewater from hydrostatic
testing of piping leading to possible Slight High Minor N
contamination of soil and groundwater
5.7.3.3.4 Summary
A summary of unmitigated potential KM250A Project operations phase impacts on
groundwater is presented in Table 5-30.
Unmitigated Mitigation
Aspect Magnitude Sensitivity impact required
significance (Y/N)
Groundwater abstraction leading to aquifer
Medium High High Y
drawdown
Storage and handling of fuels and
chemicals leading to leaks/spills and Slight High Minor N
reduced groundwater quality
Storage of hazardous solid and liquid
waste leading to reduced groundwater Slight High Minor N
quality
5.7.4 Noise
Traffic Movements
A quantitative assessment has been undertaken to determine the potential noise impacts
associated with vehicle movements associated with the construction phase of the Project.
It is anticipated that there will be heavy goods vehicles (HGVs) movement, including up
to twenty two-way wagon movements during the day and twenty crew bus movements to
transport local workers (about 300 in number) to and from the site.
The specific routes and frequency of HGVs has not been defined at this stage. For the
purposes of this assessment a realistic worst case in which all vehicles will take the same
currently low-density traffic route to and from the site has been assumed. The wagons
used to transport the materials to/from the site are likely to be spaced throughout the day,
rather than occurring within a concentrated period. An hourly flow of twenty HGVs has
been assumed.
Noise from HGV movements have been calculated using the haul road calculation
formula contained within Section F.2.5 of BS 5228-1:2009+A1:2014. The assessment
has been undertaken on the basis of:
• maximum pass-by data for HGV based on a sound power level of 104 dB(A)
• peak hourly one-way flow comprising of twenty HGVs
• mean speed of 48 km/hour (30 miles per hour) when HGVs are travelling near
to or through residential areas.
The resulting noise levels have been calculated at a range of typical setback distances
as noted in Table 5-31. This enables the influence of HGV movements to be considered
against the defined acoustic criteria.
Table 5-31 Noise from construction phase HGV movements on highway network
20 57 53 50 48 47 44 42
Noise Total
No. of
BS5228 at % on noise at
Activity Plant items in
Ref. 10m, Time 10 m,
use
dB(A) dB(A)
KM250A Project
Tracked excavator C.2.3 78 80 3
Roller (rolling fill) C.2.37 79 50 2
Excavator mounted
C.9.13 95 30 1
Site rock breaker
preparation,
Grader C.6.31 86 50 2 93
drainage &
earthworks Dozer C.2.12 81 80 3
Articulated dump
C.4.1 81 80 3
truck
Lorry C.2.34 80 30 1
Tracked excavator C.5.35 74 80 2
Dozer C.5.13 82 80 2
Articulated dump
Internal road C.5.17 81 80 2
truck 88
construction
Vibratory roller C.5.20 75 50 2
Asphalt paver +
C.5.31 77 80 2
tipper lorry
07:00 to 18:00
18:00 to 22:00
22:00 to 07:00
Khor Mor Gawra
Residential
Residential
Residential
Construction activity
Construction
Mamisik (R2)
Camp (R5)
(R1)
Site preparation 46 44 49 52 64 58
Internal road construction 41 38 44 47 58 52
Foundations for
38 36 41 44 56 50 45-55 40-50
plant/equipment
50-60 See See
Installation of plant &
41 39 44 47 59 53 note note
prefab structures
Flowlines
Site clearance 38 44 38 39 44 44
Trenching, pipe installation
42 49 42 44 49 48
and backfill
Red - exceeds Project Standard for day time (07:00 to 18:00)
Note - in exceptional cases, construction activities will occur in the evening (18:00 to 22:00) or night-time
(22:00 to 07:00)
Based on the predicted noise levels presented above, it is evident that the construction
phase noise levels will be highest at the accommodation camps (R5 and R6), with noise
levels ranging by activity, from 44 to 64 dB LAeq; the elevated noise levels are a function
of the proximity to the boundary of the KM250A Project site. When considering the offsite
villages (R1-R4), the highest noise levels are predicted to occur at Awaye Jalal (R4) to
the south of the KM250A Project site with noise levels ranging by activity from 44 to 52 dB
LAeq
In the absence of appropriate mitigation measures, the construction phase noise levels
have the potential to give rise to medium-term, minor adverse impacts when works are
undertaken during daytime hours. If the works extend into the night-time period (giving a
night-time limit in residential areas of 40 to 50 dB), the unmitigated noise levels have the
potential to give rise to medium-term, major adverse impacts.
Table 5-34 presents a summary of the potential construction phase noise impacts.
Unmitigated Mitigation
Impact Magnitude Sensitivity impact required
significance (Y/N)
Construction activities - daytime
leading to potential increases in Slight High Minor N
ambient noise
Construction activities - night-time
leading to potential increases in High High Major Y
ambient noise
Construction traffic leading to potential
Slight High Minor N
increase in ambient noise
Project Traffic
A quantitative assessment has been undertaken to determine the potential noise impacts
associated with tanker movements associated with the operations phase of the Project.
It is anticipated that the development will generate up to 50 two-way tanker movements.
The assessment has considered a daytime hourly flow of ten tankers, which assumes
that the tanker movements will typically be spaced throughout the day, rather than
occurring within a concentrated period.
Table 5-35 Noise from operations phase HGV movements on highway network
10 54 50 47 45 44 42 41
On the basis of the predicted levels, the noise from operations phase tanker movements
have the potential to give rise to short-term, minor adverse impacts during daytime hours
at receptors situated close to the main road. The noise assessment should be updated
to reflect the Traffic Management Plan once specific transport routes and vehicles
numbers are confirmed.
Site operations
The noise levels generated by the operation of the KM250A Project have been calculated
using the computational noise modelling software SoundPlan (v8.1). The software
calculates industrial noise from mobile and static sources in accordance with International
Standard ISO 9613-2:1996 'Acoustics, attenuation of sound during propagation outdoors.
General method of calculation'.
The ISO 9613-2 method predicts noise levels under meteorological conditions favourable
to noise propagation from the sound source to the receiver, such as downwind
propagation. The modelling parameters are presented in Table 5-36 and are considered
to provide realistic worst-case predictions. The methodology takes account of the
following physical effects:
• geometrical divergence
• atmospheric absorption
• ground effect
At this stage in the assessment, vendor datasheets are not available for the proposed
plant installations. In the absence of vendor/measurement data, the noise emissions from
the proposed plant items will generally not exceed a level of 85 dB(A) at 1 m as defined
in the KM250A Project ‘Basis of Design, rev B’ (Hatch 2019c). The main exceptions are
the temporary generators which has been modelled as 97 dB(A) at 1 m and the
maintenance flaring which has been modelled with an assumed sound power level of
115 dB(A).
Peak noise associated with non-routine flaring events are assumed to result in a sound
power level of 126 dB(A) at each of the two flares. The predicted noise levels during non-
routine flaring events are only expected to occur for a 15-minute duration, no more than
twice a year.
Parameter Setting
Receptor Height A receptor height of 1.5 m above ground level has been assumed
No allowance has been made for directivity of the plant noise emissions
i.e. model assumes omni-directional propagation.
With the exception of the flares, all plant items have been modelled
with a source height of 2 m above local ground level. The LP and HP
flares have been modelled with a source height of 20 m and 50 m
above local ground level respectively (assumed to flare concurrently).
Assessment 1-hour assessment period for both daytime and night-time assessment
Period periods
The noise prediction model has incorporated 10 m elevational contours
Terrain
beyond the KM250A Project site.
The model does not incorporate features on site which may provide
partial screening (e.g. columns, pipe racks, structural steelwork, and
small equipment). Consequently, the contribution of certain sources,
particularly those located well within the facility, may be overestimated.
Barriers/structures
No allowance has been made for barriers or large obstructions,
therefore the results represent robust predictions. Note: a substantial
structure (building) or barrier can provide a sound reduction of 5-15
dB(A) if it obscures the source from view at the receiver position.
The KM250A Project plot plan has been taken from Hatch drawing ref.
Site Layout
‘H358098-00000-250-290-0002 Rev. 1’
The predicted KM250A Project operations phase noise levels at the surrounding sensitive
receptor areas are presented in Figure 5-12, Figure 5-13 and Table 5-37; for context, the
existing baseline noise environment has also been presented. The predicted values do
not include existing noise sources associated with the wider facility on the basis that these
form part of the current noise environment captured during the baseline survey.
Residential Project
Khor Mor Bichuk
Standard
Khor Mor Gawra
accommodation
camp (KM250)
Condition
Construction
Awaye Jalal
Permanent
Mamisik
camp
Baseline – Daytime ambient, LAeq,15hr 41 36 43 47 52 - 50-60
Under routine operating conditions, it is evident that the operations phase noise levels
will be highest at the adjacent Project camp locations with predicted noise levels up to 50
dB LAeq,1hr. When considering the offsite villages, the highest noise levels under routine
operating conditions are predicted to occur at Awaye Jalal to the south of the site with
predicted noise levels of 39 dB LAeq,1hr.
For the Project camp areas, the absolute noise levels during routine operating conditions
should not adversely affect the functionality of the camp areas during daytime or night-
time periods, particularly when considering the noise attenuation provided by boundary
treatments e.g. walls, the external envelope of the accommodation blocks and the
screening provided by the buildings themselves.
During non-routine flaring, a substantial increase in noise, most notably at the Project
accommodation camp locations and Awaye Jalal, has been predicted. As noted above,
the non-routine flaring events are only expected to occur for a 15-minute duration, no
more than twice a year. On this basis, the elevated noise resulting from these infrequent
and short duration non-routine events are not considered to give rise to significant
adverse noise impacts.
On the basis of routine operating conditions, the predicted noise levels have the potential
to give rise to long-term, minor adverse impacts during both daytime and night-time
periods at the surrounding villages. During non-routine operating conditions, the
Pearl Petroleum 234
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
predicted noise levels have the potential to give rise to long-term, minor adverse impacts
at the surrounding villages. The impact significance for the non-routine operating
condition reflects the limited timescales over which flaring will occur throughout the year.
5.7.4.3.4 Summary
Table 5-38 presents a summary of potential impacts on noise during the operations phase
of the KM250A Project.
Unmitigated Mitigation
Impact Magnitude Sensitivity impact required
significance (Y/N)
Potential noise impacts due to routine
KM250A Project operating conditions - Slight High Minor N
daytime
Potential noise impacts due to routine
KM250A Project operating conditions – Slight High Minor N
night-time
Potential noise impacts due to non-
routine KM250A Project operating Slight High Minor N
conditions
The noise associated with the decommissioning process will be limited in duration and
extent, with predicted noise levels that are similar to those identified during the
construction phase. At this stage, it is assumed that the decommissioning works will be
undertaken during daytime hours only. On this basis, there is potential for the
decommissioning activities to give rise to noise impacts of minor significance (see Table
5-39).
Table 5-39 presents a summary of the potential decommissioning phase noise impacts.
Unmitigated Mitigation
Aspect Magnitude Sensitivity impact required
significance (Y/N)
Potential increases in ambient noise
due to daytime decommissioning Slight High Minor N
activities
The increased movement of people into a region can have detrimental effects on natural
habitat as workers and families increase their utilisation of natural resources for example
wood for fuel, collection of medicinal plants, hunting of wild animals and fishing. The
extent of in-migration due to the Project is expected to be small as the workforce are
likely to be local and therefore impacts are considered to be of a low magnitude. The
workforce will be housed in a construction camp within the existing fenceline or will be
employed from the local area, and so are unlikely to have detrimental effects on natural
habitat outside of construction works. Local workers living at their homes will be bused
offsite to their respective villages at the end of every working day. Workers based at
construction camps within the fenceline will not be allowed to go beyond the fenceline,
and will be instructed regarding risks to sensitive habitat or species.
There is also risk of habitat loss and degradation through accidental spills or seepages
of hazardous substances (i.e. diesel fuel, oil, concrete etc) and grey-water or septic
systems. This impact would most likely occur within the construction site fenceline and
near the construction camp where sewage will be generated.
Project-related movement of people and vehicles arising from construction activities
increases the risk of the introduction and transfer of invasive alien species of vascular
plants into the Project area. Alien invasive species are often aggressive competitors,
rapidly outcompeting existing plant species thus degrading the floristic diversity of
habitats and dominating areas. The use of herbicides, burning, mowing and clearing
generally favours disturbance-tolerant invasive plants which can rapidly colonise human-
disturbed areas. Likely colonisation sites will be on the edges of new and old access
routes and tracks and cleared areas (ISSG, 2018). Whilst the presence of alien invasive
vascular plants within the AOI is currently unknown, seeds or rhizomes of invasive
species (e.g. Water Hyacinth (Eichhornia Spp.) which is problematic in the region
(Ministry of Environment, 2010)) could potentially be transferred from affected areas into
the Project area by vectors e.g. workers and Project vehicles. No invasive alien species
were observed during the field surveys.
Fugitive dust emissions measured as particulate matter of varying particle size (e.g. PM10
and PM2.5) will be generated by land clearance and earthwork activities (see also Section
5.7.1.1). Construction of the plant, pipeline and access routes will expose the area to
wind erosion, resulting in dust generation. Dust emissions generated by the habitat
clearance and landscaping are likely to be wider-reaching depending on weather
conditions.
An accumulation of dust on leaves can block stomata and thereby impact on normal
photosynthetic, transpiration and cellular respiration rates (Sharifi et al., 1997) and finer
dust can be directly taken into the stomatal openings (Farmer, 1993) impairing the
biological fitness of plants. Prolonged smothering can result in the mortality of the plants.
Habitats and flora located near the dust emission sources are expected to experience
Pearl Petroleum 238
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
the greatest impacts during construction. Assessment of impacts from dust and gaseous
emissions were identified as of minor significance and hence impacts on flora are also
considered minor.
Vehicles and plant machinery that use diesel fuel will generate combustion emissions
such as CO, SO2, NOx, particulate matter (PM10 and PM2.5) and VOCs. Respiration of
nitrogen and sulphur oxides can potentially have a significant impact on the biological
fitness of vascular plants (Emberson et al., 2001). However, the magnitude of air quality
impacts from the combustion of diesel fuel during construction is expected to be relatively
low. Consequently, impacts on flora is also expected to be low.
The Project will mainly result in the loss of areas of previously cultivated land and modified
habitats within the KM site fenceline with some small patches of natural habitat affected,
leading to an impacts severity of moderate. The un-mitigated significance is rated as
moderate.
As the flowlines will be buried and the land restored, flowline impact will be moderate.
Restoration of habitat (particularly over the buried flowlines) can be negatively affected
by soil erosion and/or compacted soils if not managed adequately during the construction
phase. This impact has been given a significance rating of moderate.
The gas plant footprint is not considered to be an important habitat for vulnerable species.
Significance of this impact has been rated as moderate.
5.7.5.1.4 Summary
Construction phase Project impacts are summarised in Table 5-41.
Unmitigated Mitigation
Impact Magnitude Sensitivity impact required
significance (Y/N)
Development of Project footprint leading to
potential direct permanent loss of
Medium Medium Moderate Y
ecologically significant habitat and
vegetation
Development of Project footprint (for areas
to be restored after construction such as
storage areas, construction camp,
flowlines) leading to potential direct
Low High Moderate Y
temporary loss of ecologically significant
terrestrial habitat and vegetation within
flowline RoW and other temporary
facilities.
Various construction activities leading to
permanent loss and fragmentation of Low High Moderate Y
breeding and foraging habitat (fauna)
Site preparation leading to soil erosion or
compaction resulting in poor re- Medium Medium Moderate Y
establishment of vegetation
Transport of materials to the site leading to
introduction of alien invasive species out- Slight Medium Slight N
competing native species
Various construction activities leading to
Medium Medium Moderate Y
noise and disturbance to fauna
Various construction activities leading to
disturbance, loss of prey availability and
Medium Medium Moderate Y
potential accidental mortality to foraging
and nesting birds
Illegal hunting and collection of natural
resources by Project workers leading to Slight High Minor N
injury/mortality of fauna and flora
Site clearance works leading to direct
mortality of species from collisions with Low High Moderate Y
equipment and vehicles
Inadvertent chemical spills leading to
habitat loss and injury/mortality of flora and
Medium Medium Moderate Y
fauna from food and surface water
contamination
Barriers and fences around the operational site have the potential to cause restriction of
movement of fauna and fragmentation of habitats. Many species in the area are wide
ranging and highly mobile (e.g. wild cat) and can easily navigate around barriers without
major disruption. However, small species including small mammals and reptiles may be
affected by long-term range restrictions. As the existing facility is already fenced, habitat
fragmentation from additional fencing is not considered to be a significant impact.
The operation of the plant will produce noise and visual disturbance from movement of
people and vehicles and maintenance activities. These activities can result in stress,
reduced biological fitness and decreased breeding success in mammals and birds
(Francis and Barber, 2013). Sudden noise can cause a flight response especially to
infrequent noises. It is anticipated that noise and vibration emissions arising from
operational activities will result in the displacement of fauna from habitats within the
Project footprint and surrounding environs.
Light spill is known to cause disturbance to crepuscular (fauna that are active primarily
during dawn and dusk) and nocturnal species (i.e. bats) and can cause a range of
behavioural changes such as altered feeding and roosting patterns. Light spill from the
operational facility is likely to cause displacement of fauna from habitats within the Project
footprint and surrounding habitats.
The fenceline will keep fauna away from the Project’s operating facilities, thus limiting
exposure to site activities. Significance is therefore rated as slight. Similarly, noise and
vibrations are likely to have minor impacts on mammals and birds (existing activities
within the fenceline are likely to cause birds to avoid the site). Hunting is likely to be
minimal for the same reasons cited in the construction phase impact section (see Section
5.7.5.1), and so is rated at minor significance.
5.7.5.3.4 Summary
Table 5-42 presents a summary of unmitigated potential Project impacts on ecology and
biology during the operations phase.
Unmitigated Mitigation
Aspect Magnitude Sensitivity impact required
significance (Y/N)
Barriers and fencelines restricting
Slight Low Slight N
movement of fauna
Air quality issues resulting in a potential
increase of air emissions affecting flora Low Medium Minor N
communities
Noise and visual disturbance affecting
Low Medium Minor N
birds and mammals
Contamination of fauna food and water
Low Medium Minor N
supply from human waste
Lighting from the operation affecting
Low Medium Minor N
nocturnal species
Illegal human activities such as hunting
Slight High Minor N
and collecting natural resources
Disturbance from noise and vibration from
Medium Medium Moderate Y
people using the office area
Injury/mortality of flora and fauna from
food and surface water contamination from Medium Medium Moderate Y
chemical spills and sedimentation
5.7.6.1.4 Summary
A summary of unmitigated potential impacts of Project construction activities on regional
waste management is provided in Table 5-43.
Unmitigated Mitigation
Impact Magnitude Sensitivity impact required
significance (Y/N)
Improperly stored waste leading to
potential increase in vermin around waste
storage areas and the consequent Low Medium Minor N
increase in availability of prey for
carnivorous birds and mammals
Transport of hazardous wastes offsite
leading to contamination of agricultural Low Medium Minor N
land and/or groundwater aquifers.
5.7.6.3.4 Summary
A summary of unmitigated potential impacts of waste management during the Project
operations phase is presented in Table 5-44.
Unmitigated Mitigation
Impact Magnitude Sensitivity impact required
significance (Y/N)
Strain on existing landfills due to the
Low Low Slight N
generated non-hazardous solid wastes
Improperly stored waste leading to
potential increase in vermin around waste
storage areas and the consequent Low Medium Minor N
increase in availability of prey for
carnivorous birds and mammals
Transport of hazardous wastes offsite
leading to contamination of agricultural Low Medium Minor N
land and/or groundwater aquifers.
5.7.6.4.4 Summary
A summary of unmitigated potential impacts of waste management during the
decommissioning phase is presented in Table 5-45.
Unmitigated Mitigation
Impact Magnitude Sensitivity impact required
significance (Y/N)
Generation and accumulation of solid
wastes (i.e. materials and equipment) Medium Medium Moderate Y
during decommissioning.
5.7.7 Socio-economic
Project aspects
It is estimated that between 500 and 1,000 workers may be required during the
construction phase, with the possibility of more workers during the peak construction
period.
There will be opportunities for local companies to win contracts to supply goods and
services to the Project.
Summary
The significance of potential impacts prior to mitigation are summarised in Table 5-46.
Unmitigated Mitigation
Impact Magnitude Sensitivity impact required
significance (Y/N)
Opportunities for local and
regional businesses to supply
goods and services to the
Project, generating multiplier Positive High Positive N
effects across the local
economy.
Local price inflation indirectly
arising from economic
opportunities generated by the Low High Moderate Y
Project, leading to increased
living costs for PAC members.
Project-induced in-migration,
leading to increased competition
Medium High High Y
for land, housing and basic
services.
Summary
The significance of potential impacts prior to mitigation are summarised in Table 5-47.
Unmitigated Mitigation
Impact Magnitude Sensitivity impact required
significance (Y/N)
Project-related employment opportunities,
leading to an improvement in household Positive High Positive N
living standards and well-being.
Project-related training opportunities,
leading to improved OHS awareness and
the enhancement of future employment Positive High Positive N
prospects.
Project-related employment opportunities,
leading to skills shortages in other sectors. Medium High High Y
Unmet expectations, leading to
dissatisfaction and loss of support for the High High Major Y
Project amongst PACs.
Tensions between those who benefit
economically from the Project and those High High Major Y
who do not leading to conflict.
Retrenchment of workers, leading to
economic shock and reduced living High High Major Y
standards at the household level.
24It is possible that future facility expansion will reduce the scale of retrenchment, but no details are currently
available. Therefore, this cannot be considered in the assessment of impact significance.
Pearl Petroleum 254
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
Work at the existing facility, in fields such as construction and transportation, is typically
outsourced to contractors and sub-contractors. Pearl Petroleum has established systems
in place in order to manage the potential risk of labour rights violations occurring amongst
existing contactors.
The sensitivity of this receptor is considered to be high.
Project aspects
It is estimated that between 500 and 1,000 workers will be required during the
construction phase, with the possibility of more workers during the peak construction
period. The vast majority of employment will be conducted through contractors and sub-
contractors; working hours will be flexible and will vary according to season/local weather
conditions.
Non-local workers (from other parts of Kurdistan or further afield) will be housed in a
construction camp located within the boundary of the existing facility; the construction
camp will be designed, built and operated in align with IFC/EBRD requirements
(considering issues such as a safe and healthy location, the application of appropriate
construction standards, the provision of adequate and sanitary living conditions and the
provision of appropriate leisure and health facilities).
Construction works will be located both within and outside of the boundary of the existing
facility, including along up to five additional flowlines that are to be installed.
Unmitigated Mitigation
Impact Magnitude Sensitivity impact required
significance (Y/N)
Labour rights violations in the Project
supply chain, leading to negative
impacts on workers’ health and well- High High Major Y
being.
Failure to meet international OHS
standards by contractors and sub-
contractors, leading to increased risk of High High Major Y
workplace accidents.
Tensions within and/or between
different groups of workers resulting
High High Major Y
from disparities in wages and working
conditions, leading to conflict.
Summary
The significance of potential impacts prior to mitigation are summarised in Table 5-49.
Unmitigated Mitigation
Impact Magnitude Sensitivity impact Required
significance (Y/N)
Temporary loss of access to land used for
crop farming, livestock rearing and natural
High High Major Y
resource harvesting, leading to decreased
income, food security and living standards.
Exacerbation of existing conflicts and/or
generation of new conflicts during the
Project land acquisition and compensation Medium High High Y
process, leading to loss of support for the
Project.
Temporary reduction in access to watering
wells and pastureland for livestock, leading
to loss of livelihood and increased Medium High High Y
pressure on alternative pasture land and
watering wells.
Accidents involving livestock, leading to
Medium High High Y
injury and potential mortality.
25For example, according to the access route land use survey conducted within the framework of this ESIA, Khor
Mor Gawra is situated approximately 170 m away from the main transportation road, west of the Project site. The
PAC is surrounded by agricultural and grazing lands with barns, on both sides of the route. There is also a
graveyard and Khor Mor Gawra Primary School along the main road. At Shekh Hameed, there is a school and
mosque near the roadside.
Pearl Petroleum 259
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
in the number of roadblocks and other forms of protest across the AOI. Baseline data
indicates that such events have been staged by members of the PACs in relation to
activities at the existing facility in the past. An increase in roadblocks and other forms of
protest may contribute to an increased security presence in the AOI and a reduction in
the overall sense of peace and stability in the PACs. The magnitude of this impact is
medium.
The flaring of gas during non-routine events may lead to anxiety, irritation and a reduction
in the overall well-being of PAC members associated with perceived impacts to their
health. Individuals living with underlying mental health conditions will be particularly
sensitive to this impact. The magnitude of this impact is medium.
Summary
The significance of potential impacts prior to mitigation are summarised in Table 5-50.
Unmitigated Mitigation
Impact Magnitude Sensitivity impact Required
significance (Y/N)
Increased risk of accidents involving
community members at work sites, leading High High Major Y
to injury and potential mortality.
Increased volume of traffic, leading to an
increased risk of road traffic accidents High High Major Y
involving community members.
Tensions between non-local workers and
members of the PACs, leading to conflict. Medium High High Y
Negative interactions between community
members and Project security personnel,
leading to conflict and potentially the Medium High High Y
inappropriate use of force.
Dissatisfaction with the handling of social
issues by the Project amongst PAC
members, leading to an increase in the Medium High High Y
number of road blocks and other forms of
protest.
Anxiety, irritation and a reduction in overall
well-being amongst the PACs resulting Medium High High Y
from gas flaring during non-routine events.
Project aspects
It is estimated that between 500 and 1,000 workers may be required during the
construction phase, with the possibility of more workers during the peak construction
period.
Non-local workers (from other parts of Kurdistan or further afield) will be housed in a
construction camp located within the boundary of the existing facility; local workers will
be recruited from the PACs and will commute to the site using local roads on a daily
basis.
All construction activities involving the emission of noise, pollution, dust and waste by the
Project could potentially impact baseline health conditions in the AOI.
Summary
The significance of potential impacts prior to mitigation are summarised in Table 5-51.
Unmitigated Mitigation
Impact Magnitude Sensitivity impact Required
significance (Y/N)
Transmission of new communicable
diseases between the non-local and
local Project workforce, leading to a
reduction in health and well-being at Medium Medium Moderate Y
the community level and increased
pressure on local health care
facilities.
Anxiety, irritation and reduced well-
being amongst PACs resulting from Medium Medium Moderate Y
an increase in ambient noise levels.
Increase in respiratory conditions or
exacerbation of existing respiratory
Medium Medium Moderate Y
conditions resulting from a decline in
local air quality.
Project aspects
The construction of the Project will rely on the use of the local road network to transport
goods, materials and personnel to and from work sites.
Waste generated by construction activities will be managed by the Project and will not
rely on local waste management infrastructure
Requirements for water will be managed by the Project and will not rely on water sources
in the PACs.
The medical needs of contractor and sub-contractor employees will be met by the Project
and will not require assistance from local health facilities.
Bridges may need to be upgraded and electricity pylons may need to be moved to allow
access for Project vehicles.
Summary
The significance of potential impacts prior to mitigation are summarised in Table 5-52.
Unmitigated Mitigation
Impact Magnitude Sensitivity impact Required
significance (Y/N)
Deterioration in existing road conditions,
leading to vehicle damage, longer journey
Medium High High Y
times and increased risk of accidents for
local people.
Improper handling and disposal of Project
waste, leading to a deterioration in
Medium High High Y
environmental conditions and potential
outbreak of diseases.
Use of local health services by contractor
and sub-contractor employees, leading to
Medium High High Y
negative outcomes for health care
provision for the PACs.
Blame directed towards the Project by
PAC members over perceived reduction
Medium High High Y
in access to water, leading to loss of
support for the Project.
Upgrading, movement or damage to
community infrastructure, leading to loss
Medium High High Y
of access and/or power for households
and public services.
Project aspects
Project activities related to installation of the new flowlines could have an impact on one
of the identified archaeological sites, although very little is known about that site.
All Project activities implemented during the construction phase could potentially affect
the existing baseline conditions of cultural events (especially in March or April).
Summary
The significance of potential impacts prior to mitigation are summarised in Table 5-53.
Unmitigated Mitigation
Impact Magnitude Sensitivity impact Required
significance (Y/N)
Risk for cultural heritage
artefacts or other evidence Slight Medium Slight N
during earthworks/excavation
Risk for festivals, weddings and
Low Medium Minor N
other intangible cultural heritage
Project aspects
Vehicle movements during construction have the potential to impact traffic on access
roads.
Summary
The significance of potential impacts prior to mitigation are summarised in Table 5-54.
Unmitigated Mitigation
Impact Magnitude Sensitivity impact Required
significance (Y/N)
Increased community safety See Section 5.7.7.1.5
risks from the frequent passage
of tanker trucks leading to a
higher number of injuries and
fatalities.
Interference with users of the
public road network arising from
High Medium High Y
temporary road closures and
deviations.
Deterioration of the physical
condition of the public road
network leading to vehicle
High Medium High Y
damage, longer journey times
and increased risk of accidents
for local people.
Project aspects
Changes to landscape and visual impacts will occur during construction due to the
physical presence of construction machinery, the workforce and perimeter fencelines.
The existing Khor Mor operating facility has lighting at night for reasons of safety; this will
be the case for the KM250A Project as well.
Light will be generated at night during construction by artificial lighting along perimeter
fences and in working areas. A downlighting strategy will be used during construction and
operations that will minimise the generation of light outside the perimeter area, so that
harsh lights are not directed to people moving outside the Project boundaries.
Summary
The significance of potential visual impacts prior to mitigation are summarised in Table
5-55.
Unmitigated Mitigation
Impact Magnitude Sensitivity impact Required
significance (Y/N)
Placement of construction
equipment (including cranes)
leading to disturbance of visual Low Low Slight N
perspective by local
stakeholders
Night lighting leading to
disturbance of sleep and other
Low Medium Minor N
night-time activities at local
residences
Project aspects
All Project activities implemented during the construction phase (as listed in Table 5-2)
could potentially affect the existing baseline conditions of vulnerable groups and women.
Summary
The significance of potential impacts prior to mitigation are summarised in Table 5-56.
Unmitigated Mitigation
Impact Magnitude Sensitivity impact Required
significance (Y/N)
Reduced ability of vulnerable
groups to access Project-related
economic benefits, leading to Medium High High Y
increased levels of vulnerability
and inequality.
Reduced ability of women to
access Project-related economic
Medium High High Y
benefits, leading to increased
levels of gender inequality.
Challenges to power structures
and social dynamics as a result
of women’s employment by the
High High Major Y
Project, leading to an increase
in conflict and GBV amongst
households.
Reduced ability of vulnerable
groups to effectively engage and
participate in the Project land
acquisition and compensation Medium High High Y
process, leading to
discrimination and increased
inequality.
Reduced ability of vulnerable
groups to access Project-related
information, leading to lower
Medium High High Y
levels of awareness about the
Project and the potential
associated benefits.
Reduced ability of women to
access Project-related
information, leading to lower
Medium High High Y
levels of awareness about the
Project and the potential
associated benefits.
Unmitigated Mitigation
Impact Magnitude Sensitivity impact required
significance (Y/N)
Association of hydrotesting with
problems surrounding local
water quality and quantity,
Medium High High Y
leading to a loss of support for
the Project amongst PAC
members.
Regional economy
• The operation of the Project will contribute to the development of the KRI’s oil
and gas sector and regional economic growth by increasing the production and
sale of gas, LPG and condensate. It is anticipated that the export of products,
procurement of goods and services and employment will contribute to regional
energy supply and gross domestic product (GDP) during this period. This
impact is positive.
Public health
• Transmission of new communicable diseases between the non-local and local
Project workforce, leading to a reduction in health and well-being at the
community level and increased pressure on local health care facilities.
• Increase in respiratory conditions or exacerbation of existing respiratory
conditions resulting from a decline in local air quality.
Visual impacts
The magnitude of tall structures installed at the site adding to disturbance of well-being
of residents of local communities is low.
The magnitude ranking of the impacts of operations phase lighting (whether at night or
during the day), in terms of quality of life for local communities, taking into account
downward facing lighting and other standard lighting approaches for reduction of impacts,
is low.
The generation of light from flaring will be most noticeable during night-time periods. The
quantity of gas flared, and the frequency of flaring incidents, will be minimised by Pearl
Petroleum as flaring natural gas represents a loss of revenue and waste of the resource
that Pearl Petroleum is involved in gathering and processing. The magnitude ranking for
daytime flaring under non-routine events is low
The height of high-level flares during non-routine events (for example, shutdowns of one
or both trains) will determine the distance from which they are visible. The flares will only
be used for process upsets and emergencies. Under clear air conditions, a 50 m high
flare would, theoretically, be visible up to 30 km from the site.
The magnitude ranking for daytime flaring under non-routine events is low. The
magnitude ranking for night-time non-routine flaring is medium.
5.7.7.3.4 Summary
The significance of potential impacts related to the regional economy; land access and
livelihoods; community safety and security; traffic on access roads near the Project site
and visual impacts, prior to mitigation are summarised in Table 5-58, Table 5-59, Table
5-60, Table 5-61 and Table 5-62 respectively.
Unmitigated Mitigation
Impact Magnitude Sensitivity impact required
significance (Y/N)
Contribution of the Project to the
development of Kurdistan’s oil
and gas sector and regional Positive Medium Positive N
economic growth
Table 5-59 Summary of unmitigated potential impacts on land access and livelihoods
during operations
Unmitigated Mitigation
Impact Magnitude Sensitivity impact required
significance (Y/N)
Restriction on the rights of crop
farmers to use and to develop
land during the operation of the
Project, leading to limitations on Medium High High Y
the types of crops grown and
used to generate income
Unmitigated Mitigation
Impact Magnitude Sensitivity impact required
significance (Y/N)
Health and safety risks for local
communities, the local
environment and the Project
workforce due to interference or
tampering with Project High High Major Y
infrastructure by community
members, leading to
environmental damages, injury
and potential mortality
Unmitigated Mitigation
Impact Magnitude Sensitivity impact Required
significance (Y/N)
Interference with users of the
public road network arising from
High Medium High Y
temporary road closures and
deviations.
Deterioration of the physical
condition of the public road
network leading to vehicle
High Medium High Y
damage, longer journey times
and increased risk of accidents
for local people.
Unmitigated Mitigation
Impact Magnitude Sensitivity impact Required
significance (Y/N)
Tall structures installed at the
site adding to disturbance of
Low Low Slight N
well-being of residents of local
communities
Daytime non-routine flaring
leading to disturbance of well-
Low Medium Minor N
being of residents of local
communities
Night time non-routine flaring
leading to disturbance of well-
Medium High High Y
being of residents of local
communities
Night lighting leading to
disturbance of well-being of Low Medium Minor Y
residents of local communities
Unmitigated Mitigation
Impact Magnitude Sensitivity impact required
significance (Y/N)
Deterioration in PAC living standards and
well-being if the PACs become dependent on
Pearl Petroleum and related economic High High Major Y
opportunities, support and services are
withdrawn.
5.10.2.1 Methodology
A meeting of a group of experts was convened for implementation of the HAZID. The
purpose of the workshop was to identify hazards. Solutions were proposed in terms of
actions; actions were evaluated during action close-out.
The following steps were adopted for the HAZID:
• Distinct areas of activity with the potential to give rise to hazardous conditions
within the defined KM500 scope were identified.
• Guidewords were used as prompts to identify hazards.
• The potential safety consequences of each hazard were recorded on
worksheets along with existing or planned safeguards that eliminate, prevent,
detect, control or mitigate the hazard. During the meeting worksheets were
projected onto a screen so all attendees could see and review entries as they
were made.
• The identified hazards were ranked according to risk, taking into account the
identified safeguards.
• Actions were raised if additional measures were required to adequately
mitigate a hazard.
5.10.3.1 Methodology
The following approach was adopted for the FDHA:
• failure case identification and definition
• consequence modelling to determine hazard over a range of hazard
consequences
• risk assessment, including identification of the generic hazard, determination
of causes, specific assessment of the consequences for each scenario (hole
size for each failure case), and prevention and mitigation controls for each
failure case
5.10.4.1 Methodology
The HAZOP technique is a means of systematically reviewing a process, as designed, to
identify potential hazardous events and operability problems. The HAZOP was conducted
using engineering line diagrams and was at a coarse level only, with a more detailed
HAZOP to be completed at later stages of the design.
The study was carried out by a multi-disciplinary team of individuals led by an
independent chair using a set of guidewords to ensure thoroughness and a structured
approach to the study. Guidewords were combined with process parameters to develop
deviations from the designed operating conditions. Where safety or operability issues
were identified, actions were raised to ensure the issue was addressed.
The HAZOP considered deviations from routine operating modes of the process plant,
including start-up, operation, and shutdown, in order to identify hazards and safeguards
that must be put in place.
26Equipment and piping are designed for H2S (sour) service. NACE material requirements for H2S service ensure
resistance to sulphide stress cracking for petroleum production, drilling, gathering / flowline equipment and
processing facilities to be used in H2S-bearing hydrocarbon service.
Pearl Petroleum 286
Environmental and Social Impact Assessment for first 250 MMscfd for KM500 Gas Treatment Plant
182279-17 (05)
5.10.4.2 Summary of results
The key HAZOP findings related to the following process control issues:
• response time of high high-pressure trip on inlet gas separator and test
separator
• overpressure of inlet gas separator and test separator on common mode failure
of choke valve pressure control
• loss of amine leading to stress corrosion cracking
• low temperature embrittlement of high pressure (HP) and low pressure (LP)
cold separator piping to de-ethaniser column
• design criteria for condensate stabiliser
• HP/LP flare interface upstream of the sales gas compressor inlet scrubber
• local collection of liquids at the sales gas booster compressor package
• overfill of condensate storage tanks
• overpressure of new condensate tanker loading.
Air Quality Site preparation and levelling (mobilisation) Dust (particulate matter) can arise at the site and on unpaved roads. In this arid
and return of site to its original conditions region groundwork during construction and the movement of heavy vehicles on
following well completion (demobilisation) gravel roads or unpaved can raise dust. Exposure to increased levels of dust can
and vehicle traffic on unpaved roads. affect the health of local people and exacerbate respiratory illnesses. Generally,
dust particles settle on the ground within approximately 100 m, so outside of
villages dust is not likely to be a significant impact. Dust raised within villages by
passing traffic to be controlled by measures like those adopted within this ESIA.
Operation of construction equipment Emissions from diesel generators, vehicles and other equipment, including CO,
(including generators and vehicles and CO2, NOx, SO2, H2S, VOCs and particulate matter. Emissions are not likely to
other moving equipment have an impact on PACs.
Flaring during drilling Possibly high ground level concentrations of NOx and SO2 at PACs.
Noise Operation of construction equipment The production wells will be in remote locations, such that human receptors are
(including generators, vehicles and other unlikely to be present, unless individuals (including herders) pass through the site.
moving or stationary equipment
Noise and vibration may cause temporary displacement of species from breeding
and foraging habitat. This will be of relatively short duration.
Operation of drilling equipment (including
drilling machinery and compressors)
Water Resources Accidental releases from fuel storage tanks Fuel storage tanks at the well sites will include spill containment measures, thus
and Soil limiting possible leaks or spills to soil and subsequent leaching to groundwater.
Accidental releases of drilling and related This could result in contamination of soil and groundwater. However, the use of
fluids water-based muds significantly reducing the possibility of harmful effects.
Drilling the production wells could provide Deep groundwater flows are most likely protected by overlying, less permeable
a conduit for water from saline aquifers to strata.
mix with the fresh groundwater.
While the well is being drilled it will be filled with drilling mud that has a density
sufficient to balance the groundwater pressure. The purpose of this is to prevent
groundwater from entering the well, where it could affect the ability of the drilling
mud to remove cuttings from the well. The upper sections of the well will be drilled
in a few days, and then a casing will be installed. Once the casing has been
cemented (during completion) the well will be isolated from groundwater flows, and
the aquifers will be isolated from each other.
Leaching from reserve pits Reserve pits will be lined, thus reducing the possibility of harmful effects.
Loss of vegetative cover This could result in erosion and changes in natural drainage patterns.
Worker sanitary facilities Sanitary wastes will be collected and managed offsite.
Transport of diesel fuel by tanker truck The capacity of a road tanker (c. 30-40 m3) defines an upper limit for a diesel
release away from the site. However, away from the rig site, there will not be
secondary containment of the spill.
Biodiversity Removal of vegetation within Project Breeding and foraging habitat loss and/or fragmentation for small mammals and
footprint (including the access road) avifauna.
Waste pits Discharge and storage of drilling waste in water pits has the potential to affect birds
and animals that are attracted to the water and either drown (because they cannot
climb up the sides of the pit) or become contaminated with oil. Migrant birds may
be particularly at risk along with predatory birds, of which there are some
threatened species in the Project area.
Accidental releases of fuel or drilling Potential contamination of food and water sources used by fauna
related fluids
Flaring Noise and light disturbance causing temporary displacement of fauna from
breeding and forage habitat
Socio-economic – Procurement of goods and services Opportunities for local and regional businesses to supply goods and services,
local economy generating multiplier effects across the local economy.
Socio-economic – Recruitment of workforce In-migration, leading to increased competition for land, housing and basic services.
employment and
Employment opportunities, leading to an improvement in household living standards
skills development
and well-being.
Unmet expectations, leading to dissatisfaction and loss of support for the production
wells amongst PACs. Tensions between those who benefit economically and those
who do not, leading to conflict.
Socio-economic – Use of contractors and sub-contractors Labour rights violations in the supply chain, leading to negative impacts on workers’
labour and working health and well-being. Failure to meet international OHS standards by contractors
conditions and sub-contractors, leading to increased risk of workplace accidents.
Socio-economic – Acquisition of land for well sites Loss of access to land used for crop farming, livestock rearing and natural resource
land access and harvesting, leading to decreased income, food security and living standards.
livelihoods
Exacerbation of existing conflicts and/or new generation of new conflicts during the
land acquisition and compensation process, leading to loss of support by PACs.
Socio-economic – Transportation of process equipment, drill Increased volume of traffic, leading to increased noise and an increased risk of road
community safety pipe and other materials by road traffic accidents involving community members and livestock.
and security
Workforce commuting to/from site during
all phases (mobilisation, drilling and
demobilisation)
Site security Negative interactions between community members and security personnel, leading
to conflict and potentially the inappropriate use of force.
Flaring Anxiety, irritation and a reduction in overall well-being amongst the PACs resulting
from the noise and light generated by gas flaring.
Socio-economic – Transportation of process equipment, drill Deterioration in existing road conditions, leading to vehicle damage, longer journey
infrastructure and pipe and other materials by road times and increased risk of accidents for local people.
services
Workforce commuting to/from site during
all phases (mobilisation, drilling and
demobilisation)
Mobilisation and drilling activities Blame directed towards the production wells by PAC members over perceived
reduction in access to water, leading to loss of support amongst PACs.
Socio-economic – Mobilisation and drilling activities Risk for cultural heritage artefacts or other evidence.
cultural heritage
Socio-economic – Recruitment of workforce Reduced ability of vulnerable groups and women to access economic benefits,
vulnerable groups leading to increased levels of vulnerability and inequality.
Acquisition of land for well sites Reduced ability of vulnerable groups to effectively engage and participate in the land
acquisition and compensation process, leading to discrimination and increased
inequality.
Mobilisation and drilling activities Reduced ability of vulnerable groups and women to access information, leading to
lower levels of awareness about the production wells and the potential associated
benefits.
Table 6-1 Summary of operations phase mitigation measures and residual impacts -
air quality
Unmitigated Residual
Mitigation
Potential impact impact impact
measures
significance significance
Emissions from routine or non-routine operations of the
gas plant leading to increase in NO2 ambient ground High ENV01 Minor
level concentrations
Emissions from routine or non-routine operations of the ENV01
gas plant leading to Increase in SO2 levels in ambient High Minor
air ENV02
6.2 Soil
Impacts on soil during the construction phase of the Project were all rated insignificant
(minor or below) so no mitigation measures are required.
Unmitigated Residual
Mitigation
Potential impact impact impact
measures
significance significance
ENV03
Groundwater abstraction leading to aquifer
High ENV04 Minor
drawdown
ENV06
Storage and handling of fuels and chemicals leading ENV06
to leaks/spills and reduced groundwater quality Moderate Minor
ENV07
6.3.4 Decommissioning
To avoid leaks and spills leading to reduced groundwater quality, Pearl Petroleum will
apply the same measures developed for the construction phase (see Table 6-2).
6.4 Noise
During the construction phase of the KM250A Project there is potential for significant
adverse impacts if construction works are undertaken (exceptionally) during the night. At
this stage, the detailed methodology for the construction works has not been defined and
consequently specific mitigation measures cannot be given.
Standard best practice control measures shall be adopted on-site to ensure that noise
management forms an integral part of the contractors’ scope of works.
The following mitigation measures are proposed to limit the potential for noise impacts at
surrounding receptors in the event that night-time working is deemed necessary:
• Adopt quiet working methods, where reasonably practicable, using plant with
lower noise and vibration emissions (ENV08).
• Avoid or limit noisy construction activities during the night-time period (ENV09)
• Use acoustic screens and/or enclosures for static items of plant which generate
noise levels that have the potential to cause disturbance (ENV010).
• Carry out regular inspections of noise mitigation measures to ensure integrity
is maintained at all times (ENV011).
• Provide briefings for all site-based personnel so that noise issues are
understood, and mitigation measures are adhered to (ENV012).
A summary of the construction phase mitigation measures and residual impacts for noise
is presented in Table 6-3. The mitigation measures allow full compliance with lender
requirements (including but not limited to the IFC PS and EHS guidelines) and
other Project Standards, and reduce residual impacts ratings below significant.
Table 6-3 Summary of construction phase mitigation measures and residual impacts -
noise
Unmitigated Residual
Mitigation
Potential impact impact impact
measures
significance significance
ENV08
ENV09
Construction activities – night-time leading to potential
Major ENV10 Minor
increases in ambient noise
ENV11
ENV12
6.5.1.1 Habitats
This document will set out ways in which potential impacts on sensitive habitats will be
reduced and will include the following:
• Limit vegetation removal to the extent required for construction activities,
including storage and laydown areas, and safety requirements.
• Limit driving to designated routes on existing roads, where possible.
• Areas identified as potential natural habitat in the impact assessment sections
will be avoided, where possible.
• Restore natural habitats on pipeline route and storage areas after construction
activities are complete including returning the segregated topsoil to the site and
reseeding or replanting areas with native species. To be developed through
the production of a Bio-restoration Plan which will form part of the construction
phase contractor HSSE&SP MP.
• Develop a Biodiversity Management Plan (to include bio-security and bio-
restoration) (ENV13) which will form part of the construction phase contractor
HSSE&SP MP and will incorporate the following considerations:
o any ecology restoration will utilise native plant species
6.5.1.2 Flora
Mitigation is required to retain the population of important plant species if present within
natural habitats. To mitigate the potential impacts of development, the following
measures will be implemented:
• Undertake a preconstruction survey for important plant species in areas
identified as potential habitat in particular along flowlines where routes are
likely to be re-surveyed (ENV14).
• Evaluate practical alternatives to avoid or reduce impacts to the important plant
species if these species are identified within areas subject to land disturbing
activities (ENV15).
• Prohibit the collection of natural resources, such as plant materials for
firewood, food or medicine (ENV16).
• Use appropriate technique (seed harvesting/cutting/translocation) to move
individual plants from the construction footprint if the individual cannot be
avoided during land disturbing activities (ENV17).
6.5.1.3 Fauna
The following measures will be used to reduce impacts on fauna during the construction
phase:
• Undertake site clearance with due consideration to main breeding season
(ENV18).
• Conduct preconstruction surveys to identify any active burrows or nests of
sensitive species (see above).
• Establish a 10 m buffer zone, if possible and practical, around the burrow or
nest where no construction may occur until monitoring indicates that the
species has left the nest/burrow. if sensitive species active nests or burrows
are found within areas subject to land disturbance (ENV19).
• Evaluate alternatives to relocate the species, if sensitive species active nest or
burrow cannot be avoided; and seek approval from regulator (ENV20).
• Prohibit deliberate disturbance or killing of fauna by site workers - any
unintentional killing or injury of species to be reported and tracked internally. If
required adaptive management may be used to reduce unanticipated impact
on animals (ENV21).
• Limit vegetation removal to the extent possible (ENV22).
• Consider animal bypass around flowline construction zones, as deemed
necessary (ENV23).
• Restore habitats in temporary workspaces after construction activities are
complete including returning the segregated topsoil to the site and restore
ecology with native species (ENV24).
• Reduce the time between construction and reinstatement for works undertaken
in sensitive habitats to the extent possible (ENV25).
6.5.1.4 Summary
A summary of construction phase mitigation measures and residual impacts is presented
in Table 6-4. The mitigation measures allow full compliance with lender
requirements (including but not limited to the IFC PS and EHS guidelines) and
other Project Standards, and reduce residual impacts ratings below significant.
Table 6-4 Summary of construction phase mitigation measures and residual impacts
– ecology and biodiversity
Unmitigated Residual
Mitigation
Poential impact impact impact
measures
significance significance
Development of Project footprint leading to potential ENV13
direct permanent loss of ecologically significant habitat Moderate Minor
and vegetation ENV14
ENV15
Development of Project footprint (for areas to be
restored after construction such as storage areas, ENV16
construction camp, flowlines) leading to potential direct ENV17
Moderate Minor
temporary loss of ecologically significant terrestrial ENV18
habitat and vegetation within flowline RoW and other ENV19
temporary facilities.
ENV20
Various construction activities leading to permanent ENV21
loss and fragmentation of breeding and foraging Moderate Minor
habitat (fauna) ENV22
Unmitigated Residual
Mitigation
Potential impact impact impact
measures
significance significance
Unmitigated Residual
Mitigation
Potential impact impact impact
measures
significance significance
6.7 Socio-economic
The following section outlines the mitigation and monitoring measures that will avoid,
reduce or remediate the potential negative socio-economic impacts of the Project
alongside measures that will enhance the potential positive socio-economic impacts.
6.7.1.1.3 Summary
The significance of potential impacts following mitigation during construction are
summarised in Table 6-7. The mitigation measures allow full compliance with lender
requirements (including but not limited to the IFC PS and EHS guidelines) and
other Project Standards, and reduce residual impacts ratings below significant.
Table 6-7 Summary of construction phase mitigation measures and residual impacts
on the local economy
Unmitigated Residual
Mitigation
Potential impact impact impact
measures
significance significance
Opportunities for local and regional
SOC01
businesses to supply goods and services to
Positive SOC02 Positive
the Project, generating multiplier effects
SOC03
across the local economy.
6.7.1.2.3 Summary
The significance of potential impacts following mitigation are summarised in Table 6-8.
The mitigation measures allow full compliance with lender requirements (including
but not limited to the IFC PS and EHS guidelines) and other Project Standards, and
reduce residual impacts ratings for Project related employment opportunities to
below significant. For the residual significant impacts for unmet expectations,
tensions and retrenchment of workers, application of the mitigation measures and
accepted international practices (GIIP) result in manageable risks vis-à-vis
sensitive receptors in relation to lender requirements (including but not limited to
the IFC PS and EHS guidelines) and other Project Standards.
27 it is possible that future facility expansion will reduce the scale of retrenchment, but no details are currently
Unmitigated Residual
Mitigation
Potential impact impact impact
measures
significance significance
Project-related employment
SOC13
opportunities, leading to an
Positive SOC14 Positive
improvement in household living
SOC15
standards and well-being.
Project-related training opportunities, SOC16
leading to improved OHS awareness SOC17
Positive Positive
and the enhancement of future SOC18
employment prospects. SOC19
Project-related employment SOC20
opportunities, leading to skills High SOC21 Minor
shortages in other sectors. SOC22
SOC23
Unmet expectations, leading to
SOC15
dissatisfaction and loss of support for Major Moderate
SOC07
the Project amongst PACs.
SOC24
SOC24
Tensions between those who benefit SOC25
economically from the Project and Major SOC15 Moderate
those who do not, leading to conflict. SOC07
SOC26
Retrenchment of workers, leading to
SOC27
economic shock and reduced living Major Moderate
SOC28
standards at the household level.
6.7.1.3.2 Summary
The significance of potential impacts following mitigation are summarised in Table 6-9.
Application of the mitigation measures and accepted international practices (GIIP)
result in manageable risks vis-à-vis sensitive receptors in relation to lender
requirements (including but not limited to the IFC PS and EHS guidelines) and
other Project Standards.
Unmitigated Residual
Mitigation
Potential impact impact impact
measures
significance significance
SOC29
Labour rights violations in the Project SOC30
supply chain, leading to negative impacts Major SOC31 Moderate
on workers’ health and well-being. SOC32
SOC33
Failure to meet international OHS
standards by contractors and sub- SOC34
contractors, leading to increased risk of Major Moderate
SOC35
workplace accidents.
Tensions within and/or between different
groups of workers resulting from disparities
Major SOC36 Moderate
in wages and working conditions, leading to
conflict.
6.7.1.4.2 Summary
The significance of potential impacts following mitigation are summarised in Table 6-10.
The mitigation measures allow full compliance with lender requirements (including
but not limited to the IFC PS and EHS guidelines) and other Project Standards, and
reduce residual impacts ratings below significant.
Table 6-10 Summary of construction phase mitigation measures and residual impacts
on land access and livelihoods
Unmitigated Residual
Mitigation
Potential impact impact impact
measures
significance significance
SOC37
SOC38
Temporary loss of access to land used for SOC39
crop farming, livestock rearing and natural
Major SOC40 Minor
resource harvesting, leading to decreased
income, food security and living standards. SOC41
SOC42
SOC07
Exacerbation of existing conflicts and/or
generation of new conflicts during the SOC43
Project land acquisition and compensation High SOC07 Minor
process, leading to loss of support for the SOC44
Project.
Temporary reduction in access to watering
wells and pasture land for livestock, leading SOC45
to a loss of livelihood and increased High SOC46 Minor
pressure on alternative pasture land and SOC47
watering wells.
SOC48
Accidents involving livestock, leading to
High SOC49 Minor
injury and potential mortality.
SOC07
6.7.1.5.2 Summary
The significance of potential impacts following mitigation are summarised in Table 6-11.
The mitigation measures allow full compliance with lender requirements (including
but not limited to the IFC PS and EHS guidelines) and other Project Standards, and
reduce residual impacts ratings below significant.
Unmitigated Residual
Mitigation
Potential impact impact impact
measures
significance significance
Increased risk of accidents involving SOC48
community members at work sites, leading Major SOC49 Minor
to injury and potential mortality. SOC50
Increased volume of traffic, leading to an
SOC51
increased risk of road traffic accidents Major Minor
SOC50
involving community members.
Tensions between non-local workers and SOC52
High Minor
members of the PACs, leading to conflict. SOC53
Negative interactions between community
members and Project security personnel, SOC54
High Minor
leading to conflict and potentially the SOC55
inappropriate use of force.
Dissatisfaction with the handling of social SOC24
issues by the Project amongst PAC SOC07
members, leading to an increase in the High SOC56 Minor
number of road blocks and other forms of SOC57
protest.
SOC58
Anxiety, irritation and a reduction in overall
SOC59
well-being amongst the PACs resulting High Minor
SOC07
from gas flaring during non-routine events.
6.7.1.6.2 Summary
The significance of potential impacts following mitigation are summarised in Table 6-12.
The mitigation measures allow full compliance with lender requirements (including
but not limited to the IFC PS and EHS guidelines) and other Project Standards, and
reduce residual impacts ratings below significant.
Table 6-12 Summary of construction phase mitigation measures and residual impacts
on public health
Unmitigated Residual
Mitigation
Potential impact impact impact
measures
significance significance
Transmission of new communicable
diseases between the non-local and local
Project workforce, leading to a reduction in SOC60
Moderate Minor
health and well-being at the community SOC61
level and increased pressure on local
health care facilities.
See Noise
Anxiety, irritation and reduced well-being Section
amongst PACs resulting from an increase Moderate 6.4 Minor
in ambient noise levels. SOC62
SOC07
See Air
Increase in respiratory conditions or Quality
exacerbation of existing respiratory Section
Moderate 6.1.1 Minor
conditions resulting from a decline in local
air quality. SOC62
SOC07
6.7.1.7.2 Summary
The significance of potential impacts following mitigation are presented in Table 6-13.
The mitigation measures allow full compliance with lender requirements (including
but not limited to the IFC PS and EHS guidelines) and other Project Standards, and
reduce residual impacts ratings below significant.
Table 6-13 Summary of construction phase mitigation measures and residual impacts
on infrastructure and services
Unmitigated Residual
Mitigation
Potential impact impact impact
measures
significance significance
Deterioration in existing road SOC63
conditions, leading to vehicle damage, SOC64
High Minor
longer journey times and increased risk SOC65
of accidents for local people.
SOC07
Improper handling and disposal of SOC62
Project waste, leading to a deterioration
High Minor
in environmental conditions and
potential outbreak of diseases. SOC07
Use of local health services by
contractor and sub-contractor
employees, leading to negative High SOC66 Minor
outcomes for health care provision for
the PACs.
SOC56
Blame directed towards the Project by SOC57
PAC members over perceived
High SOC67 Minor
reduction in access to water, leading to
loss of support for the Project. SOC68
SOC58
SOC69
Upgrading, movement or damage to SOC70
community infrastructure, leading to
High SOC71 Minor
loss of access and/or power for
households and public services. SOC07
SOC58
6.7.1.8.2 Summary
The significance of potential impacts following mitigation are summarised in Table 6-14.
The mitigation measures allow full compliance with lender requirements (including
but not limited to the IFC PS and EHS guidelines) and other Project Standards, and
reduce residual impacts ratings below significant.
Table 6-14 Summary of construction phase mitigation measures and residual impacts
on traffic
Unmitigated Residual
Mitigation
Potential impact impact impact
measures
significance significance
Interference with users of the public High SOC72 Minor
road network arising from temporary
SOC73
road closures and deviations.
Deterioration of the physical condition High SOC74 Minor
of the public road network.
6.7.1.9.2 Summary
The significance of potential impacts following mitigation are summarised in Table 6-15.
The mitigation measures allow full compliance with lender requirements (including
but not limited to the IFC PS and EHS guidelines) and other Project Standards, and
reduce residual impacts ratings to below significant for
Table 6-15 Summary of construction phase mitigation measures and residual impacts
on vulnerable groups
Unmitigated Residual
Mitigation
Potential impact impact impact
measures
significance significance
Reduced ability of vulnerable groups SOC75
to access Project-related economic Minor
High SOC76
benefits, leading to increased levels of
vulnerability and inequality. SOC77
Reduced ability of women to access
Project-related economic benefits, SOC78 Moderate
High
leading to increased levels of gender SOC76
inequality.
Challenges to power structures and
social dynamics as a result of
women’s employment by the Project, Major SOC79 Moderate
leading to an increase in conflict and
GBV amongst households.
Reduced ability of vulnerable groups
to effectively engage and participate in
SOC80
the Project land acquisition and Minor
High
compensation process, leading to
discrimination and increased SOC81
inequality.
Reduced ability of vulnerable groups
to access Project-related information,
leading to lower levels of awareness High SOC75 Minor
about the Project and the potential
associated benefits.
Reduced ability of women to access
Project-related information, leading to
lower levels of awareness about the High SOC82 Moderate
Project and the potential associated
benefits.
6.7.2.1.2 Summary
The significance of potential impacts following mitigation are summarised in Table 6-16.
The mitigation measures allow full compliance with lender requirements (including
but not limited to the IFC PS and EHS guidelines) and other Project Standards, and
reduce residual impacts ratings below significant.
Unmitigated Residual
Mitigation
Potential impact impact impact
measures
significance significance
Association of hydrotesting with
problems surrounding local water
quality and quantity, leading to a loss of High SOC83 Minor
support for the Project amongst PAC
members.
6.7.3.1.2 Summary
The significance of potential impacts following mitigation are summarised in Table 6-17.
Table 6-17 Summary of operations phase mitigation measures and residual impacts
on the regional economy
Unmitigated Residual
Mitigation
Potential impact impact impact
measures
significance significance
Contribution of the Project to the
development of Kurdistan’s oil SOC84
Positive Positive
and gas sector and regional SOC85
economic growth.
6.7.3.2.2 Summary
The significance of potential impacts following mitigation are summarised in Table 6-18.
The mitigation measures allow full compliance with lender requirements (including
but not limited to the IFC PS and EHS guidelines) and other Project Standards, and
reduce residual impacts ratings below significant.
Table 6-18 Summary of operations phase mitigation measures and residual impacts
on land access and livelihoods
Unmitigated Residual
Mitigation
Potential impact impact impact
measures
significance significance
Restriction on the rights of crop
farmers to use and to develop
land during the operation of the SOC86
High Minor
Project, leading to limitations on SOC07
the types of crops grown and
used to generate income.
6.7.3.3.2 Summary
The significance of potential impacts following mitigation are summarised in Table 6-19.
The mitigation measures allow full compliance with lender requirements (including
but not limited to the IFC PS and EHS guidelines) and other Project Standards, and
reduce residual impacts ratings below significant.
Table 6-19 Summary of operations phase mitigation measures and residual impacts
on community safety and security
Unmitigated Residual
Mitigation
Potential impact impact impact
measures
significance significance
Health and safety risks for local
communities, the local
SOC87
environment and the Project
SOC88
workforce due to interference or
Emergency
tampering with Project Major Minor
response
infrastructure by community
planning (see
members, leading to
Section 11)
environmental damages, injury
and potential mortality.
6.7.3.5.2 Summary
The significance of potential impacts following mitigation are summarised in Table 6-20.
Application of the mitigation measures and accepted international practices (GIIP)
result in manageable risks vis-à-vis sensitive receptors in relation to lender
requirements (including but not limited to the IFC PS and EHS guidelines) and
other Project Standards.
Unmitigated Residual
Mitigation
Potential impact impact impact
measures
significance significance
Night time non-routine flaring leading to
disturbance of well-being of residents of local High SOC89 Medium
communities
6.7.4.1.2 Summary
The significance of potential impacts following mitigation are summarised in Table 6-21.
Application of the mitigation measures and accepted international practices (GIIP)
result in manageable risks vis-à-vis sensitive receptors in relation to lender
requirements (including but not limited to the IFC PS and EHS guidelines) and
other Project Standards.
Unmitigated Residual
Mitigation
Potential impact impact impact
measures
significance significance
SOC24
SOC90
Deterioration in PAC living
standards and well-being if the SOC91
PACs become dependent on Pearl SOC92
Major High
Petroleum and related economic SOC93
opportunities, support and services SOC94
are withdrawn.
SOC95
SOC96
Socio- Loss of access to land used for crop farming, livestock rearing SOC07 and
economic – and natural resource harvesting, leading to decreased income, SOC37 to
land access food security and living standards. SOC42
and Exacerbation of existing conflicts and/or new generation of new SOC07, SOC43
livelihoods conflicts during the land acquisition and compensation process, and SOC44
leading to loss of support by PACs.
Socio- Increased volume of traffic, leading to increased noise levels and SOC50 and
economic – an increased risk of road traffic accidents involving community SOC51
community members and livestock.
safety and
Negative interactions between community members and security SOC54 and
security
personnel, leading to conflict and potentially the inappropriate use SOC55
of force.
Anxiety, irritation and a reduction in overall well-being amongst SOC07 and
the PACs resulting from the noise and light generated by gas SOC59
flaring.
Socio- Deterioration in existing road conditions, leading to vehicle SOC07 and
economic – damage, longer journey times and increased risk of accidents for SOC63 to
infrastructure local people. SOC65
and services Blame directed towards the production wells by PAC members SOC56 to
over perceived reduction in access to water, leading to loss of SOC58, SOC67
support amongst PACs. and SOC68
Socio- Reduced ability of vulnerable groups and women to access SOC75 to
economic – economic benefits, leading to increased levels of vulnerability and SOC78
vulnerable inequality.
groups Reduced ability of vulnerable groups to effectively engage and SOC80 and
participate in the land acquisition and compensation process, SOC81
leading to discrimination and increased inequality.
Reduced ability of vulnerable groups and women to access SOC75 and
information, leading to lower levels of awareness about the SOC82
production wells and the potential associated benefits.
The principles and techniques applied during the Project life cycle will be tailored to the
hazards and risks associated with the Project and consistent with good international
industry practice (GIIP), as reflected in various internationally recognised sources,
including the IFC Performance Standards on Environmental and Social Sustainability
(IFC PS) (2012) and the accompanying IFC Environmental, Health and Safety (EHS)
Guidelines (see Section 9.8.1 and 9.8.2).
Alternative methods
Requirement Key Issues Selected Option
Design Technology options
KM250A gas processing
There are no key constriants in
facility will receive the raw
using either of the options, however
gas from the production wells
using molecular sieve can reduce
and further processing of the
the air emissions, as there are no
inlet raw gas will be
hydrocarbon and aromatic
conducted at the KM250A
emissions expected and there will
premises and the final
be no chemical spillage. Glycol
Gas dehydration products including sales gas, Molecular sieve vs. glycol Molecular sieve
needs to transported to the site in
LPG and condensate will be
regular quantities, added at the
exported to the end-users via
wellhead and then ultimately
pipeline or trucks. Sales gas
removed from the raw gas stream
must meet specifications for
(to the extent possible). This is an
moisture content. Raw gas
expensive option and I suspect this
must therefore be dehydrated
is an advantage over the sieve.
to meet these specifications.
Reciprocating compressors
(rental) will be used for the
KM250A Project.
There are no key constraints in
Reciprocating compressors
using either of the options, however
Compression of gas will be are used for the flash gas
Centrifugal vs. reciprocating centrifugal compressors generate
Compression required at various parts of compressor and for the de-
compressors less noise and increase availability
the gas treatment process. ethaniser overhead
by reducting maintenance
compessor. Centrifugal
requirements
compressors will only be
installed post KM1000
Expansion.
8.1.7 Biodiversity/ecology
Previous ESIAs and baseline studies associated with this site were consulted to
determine whether additional field survey was necessary (see Section 0), and if so, the
necessary scope of those surveys. Previous studies were found not to be representative
of the KM250A Project biodiversity and ecology AOI.
The ecological field survey conducted in October 2019 within the Khor Mor fenceline, just
outside of the Khor Mor site fenceline, and along the RoWs for the new flowlines. Given
the limited time period of the survey, it may not have provided a detailed record of the
species present throughout the year, as some species of flora may not be flowering,
making identification more difficult, and some fauna species may be absent from the site
during the survey period. Nonetheless, this survey provided an overview of species
presence and an understanding of the habitats within the Project area rather than a
detailed ecological baseline. However, the use of already existing biodiversity information
at Khor Mor, online resources, grey literature and an understanding of the habitats on-
site that complemented the field survey meant that assumptions could be drawn
8.2 Conclusions
The impact assessment presented in this report was based on assumptions that were
conservative but in keeping with both good international industry practice and Ministry of
Natural Resources guidelines. Where necessary, field surveys were undertaken to
ensure that available data reflected an accurate view of existing baseline conditions. As
the period of field surveys was limited to the period August through November 2019,
supplemental data was used to ensure reasonably sound knowledge of baseline
information throughout the year. Conservative assumptions were made regarding Project
design data and information to account for any future changes as the design process
evolves. Taken together, the above measures ensure that uncertainties associated with
the conclusions of this ESIA (largely the environmental and social risks estimated via
qualitative or quantitative impact assessment, and the mitigation measures proposed for
reducing the significance of significant impacts) are considered sound and reliable as a
basis for decisions related to the Project.
Environment
1971 Acceded,
Ramsar Convention
2007
1985 Acceded,
Vienna Convention for the Protection of the Ozone Layer
2008
1987 Acceded,
Montreal Protocol
2008
1992 Acceded,
Rio de Janeiro Convention on Biological Diversity
2009
1994 Acceded,
Bonn Convention on Combating Desertification
2010
28 Following the First Gulf War Iraqi forces finally left Kurdistan in October 1991, leaving the region with de facto
autonomy. Hence, Kurdish laws as such were created and enforced past that date, and are recognised in
Kurdistan as the only applicable laws.
Pearl Petroleum 347
Environmental and Social Impact Assessment for first 250MMSCFD for KM500 Gas Treatment Plant
182279-17 (05)
The applicable legislation consists of either laws (local and federal) or instructions. A law
is a binding legislative act and it must be applied in its entirety across the KRI. The details
for implementing the laws are usually explained by instructions. The instructions clarify
or amend existing legislative provisions included in the laws and the guidelines, and
contain additional guidance and information.
9.5.2.1 Siting
The Iraqi Law regulating mineral investment Number (91) of 1988 provides that the
following areas cannot be allocated as land for mineral investment:
9.5.2.2 Noise
Article 27/2 of Kurdish Law number (8) of 2008 concerns the permissible levels for noise.
Instruction number (1) of 2011 for noise reduction in the KRI contains the following
provisions:
• Article 1:
o 4 - Noise is defined as sounds annoying human and animals when heard,
due to the high and variable frequency, and it consists of three types:
external noise, internal noise and back noise.
o 6 - Unacceptable noise is defined as the undesirable sound which
disturbs mind and mood or raises nerves and exceeds 85 dB on daytime
and 70 dB night-time.
o 9 - The standard for the level of noise at the workplace is the constant
(continuous) noise allowed at the working site is 85 dB.
o 10 - The change rate is defined as the level of noise that exceeds the
standard level that will require a decrease in worker exposure.
Table 9-3 Sound intensity inside the workplace and indoor places
Maximum
acceptable noise
Determination the type of place and activity
intensity
equivalent dB
1. Workplaces with night shift until 8 hours 85
2. Workplaces that require hearing of acoustic signs and good
80
speech hearing
3. Workrooms to follow up, measure and set up operation 65
4. Workrooms of computer units or typing machines or similar to that 70
5. Workrooms of activities that require routine mental focus 60
9.5.2.3 Air
Based on the provisions of Article (10), Law number (3) of 2010 and provisions of the
both Articles 26 and 27/1 of Law number (8) of 2008, Instruction number (2) of 2011 was
issued.
• Article 3: The sources of common air pollutants including those concerning oil
storage are to be identified and concerned parties shall provide the
Environmental Protection and Improvement Board in the KRI with
concentrations of each pollutant with annual emissions.
• Article 4: The national standard for each level of the common pollutants is
issued by the Environmental Protection and Improvement Board in the KRI.
29 The Iraqi constitution attempts to strike a balance between needs of the individual and those of the state and
protects tasarruf rights holders (who comprise approximately 70% of all land in Iraq) from expropriation without
compensation (World Bank, 2016b).
30 The Civil Code stipulates how property rights such as tasarruf are regulated, and a couple of important aspects
of tasarruf are worth noting. A person in possession of miri land is entitled to tasarruf rights, which can be used
as security for a loan. However, if a tasarruf holder leaves land unused for three years without cause, rights to the
land are forfeited. With the death of a tasarruf holder, the rights are passed to the deceased’s heirs. If the heirs
do not accept the tasarruf, it is then auctioned off (World Bank, 2016b).
31 The law is focused on the reorganisation of land ownership for lands subject to agricultural projects. It also
provides remedies for compensation to land owners for expropriation (USAID, 2019a).
32 The resolution establishes the ‘Body of Administration and Investment of Awaqf Properties’ that is legally,
financially and administratively independent, but connected with the Ministry of Awaqf and Religious Affairs. The
body administers and develops land and property received as an endowment and acts as a council for all issues
in terms of the administration and investment in Awaqf (also known as waqf) properties. The body is managed by
a council comprising the Minister, several experts, three lawyers and officials from government (USAID, 2019a).
33 The law establishes the Iraqi ‘Company for Contracts of Land Reclamation’ under the Council of Ministers. The
Company implements reclamation projects and acts as a contractor for reclamation projects. The Company is
charged with carrying out its duties both inside and outside Iraq. The Company can sell and lease reclaimed
lands and the properties of the company are considered ‘state domains’ (USAID, 2019a).
34 This law covers a variety of agricultural land ownership issues, including the maximum size limit of lands that
can be owned privately without authorisation. The Agrarian Reform Authority can requisition lands above the
stated limit and stipulate the forms of compensation that the owner of the requisitioned excess land is due. The
Authority takes over the responsibilities of the survey committees regarding lands not yet surveyed, and those
lands against which survey decisions are still pending. The Authority will distribute agrarian reform lands to
peasants both individually and collectively (USAID, 2019a).
35 This law intends to manage pasture lands by planning grazing according to scientific approaches, and
engaging in the protection of natural vegetation and water resources and the organisation of their use. The Law
covers state-owned lands allocated for pasture. The Law states that the Ministry of Agriculture and Agrarian
Reform is to regulate and organise livestock movements according to seasons and regions. The law prohibits the
drilling of artesian wells and cutting plants in pasture lands (USAID, 2019a).
36 The Resolution stipulates that state-owned land not burdened by ‘disposal rights’ shall be sold to farmers, and
pre-existing agricultural contracts are revoked and pre- existing rights extinguished. The Resolution provides
limits of the allocation to farmers — not more than 1,000 m2 with no house and 2,000 m2 for a plot with a house
(USAID, 2019a).
37 This law provides for compensation for the alienation of agricultural land, with alternative land as a first priority
and cash compensation as a secondary priority. The law also prohibits compensation in-kind or cash for certain
types of land (USAID, 2019a).
38 The resolution stipulates that the transfer of real estate owned by Iraqi citizens who left the country is to be
themselves or through others, shall be considered as property of the state with no compensation due, and shall
be registered in the name of the Ministry of Finance as ‘pure’ property. The Ministry of Agriculture shall dispose of
such lands in accordance with laws and regulations in force (USAID, 2019a).
Pearl Petroleum 355
Environmental and Social Impact Assessment for first 250MMSCFD for KM500 Gas Treatment Plant
182279-17 (05)
the Kurdistan legislation, the equivalent standards set up in Iraqi federal laws are
applicable in Kurdistan (for example for water quality).
The KM250A Project Standards were selected from KRI, Government of Iraq (GoI) and
relevant international standards including the World Bank Group/International Finance
Corporation (IFC) standards and World Health Organisation (WHO) standards. The most
stringent applicable standards were selected as the Project Standard. A summary of the
applicable standards and the selected Project Standard is provided in Appendix 3.
The Project has committed to abiding by PS1, including full consultation with local
communities and setting up mechanisms for working with Affected Communities.
The requirements set out in this PS have been in part guided by a number of
international conventions negotiated through the International Labour Organization
(ILO) and the United Nations (UN). Specific objectives of PS2 are:
The Project will need to ensure that it upholds labour rights and provide safe
working conditions during both construction and operation .
PS3 outlines a project approach to pollution prevention and abatement in line with
international available technologies and practices. It promotes the private sector’s
ability to integrate such technologies and practices as far as their use is technically
and financially feasible and cost-effective in the context of a project that relies on
commercially available skills and resources. Specific objectives of PS3 are:
PS3: Resource
Efficiency and • to avoid or minimise adverse impacts on human health and the
Pollution Prevention environment by avoiding or minimising pollution from project activities
• to promote the reduction of emissions that contribute to climate change.
Consideration of resource efficiency and pollution prevention have been made
during project planning. The findings of the ESIA will further advise the design
of the Project.
This PS recognises that project activities, equipment, and infrastructure often bring
benefits to communities including employment, services, and opportunities for
economic development. However, projects can also increase risks arising from
accidents, releases of hazardous materials, exposure to diseases, and the use of
PS4: Community security personnel. While acknowledging the public authorities’ role in promoting the
Health, Safety and health, safety and security of the public, this PS addresses the project sponsor’s
Security responsibility in respect of community health, safety and security.
The ESIA process will include the production of Environmental and Social
Management Plans which will feed into the construction and operational
Management Systems. These plans and procedures to include community health,
safety and security plans.
A critical habitat screening assessment and field surveys have been conducted.
Consistent with the Convention Concerning the Protection of the World Cultural and
Natural Heritage, this Performance Standard aims to protect irreplaceable cultural
heritage and to guide project sponsors on protecting cultural heritage in the course
PS8: Cultural of their business operations.
Heritage
The ESIA baseline surveys included walkover surveys and discussions during
stakeholder consultation. Should any sites of cultural heritage be identified, PS8 will
be followed.
EHS Guidelines for Technical reference document that addresses onshore oil
Onshore Oil and Gas and gas exploration and production operations.
Development (April 2007)
General EHS Guideline Provides information about common techniques for energy
conservation.
1.2 Energy Conservation
(April 2007)
General EHS Guideline Addresses impacts of noise beyond the site boundary
including prevention and control, noise level guidelines for
1.7 Noise (April 2007)
different receptors; and monitoring.
General EHS Guideline These address project activities taking place outside of the
traditional project boundaries, but nonetheless related to
3.0 Community Health and
the project operations, including: Water Quality and
Safety (April 2007)
Availability, Traffic Safety, 3.5 Transport of Hazardous
Materials, 3.6 Disease Prevention, 3.7 Emergency
Preparedness and Response
40 OPIC defines Category A projects as those ’Business activities with potential significant adverse
environmental or social risks and/or impacts that are diverse, irreversible, or unprecedented.’
Pearl Petroleum 363
Environmental and Social Impact Assessment for first 250MMSCFD for KM500 Gas Treatment Plant
182279-17 (05)
10 ENVIRONMENTAL AND SOCIAL
MANAGEMENT
10.1 Introduction
This section details the framework for the management of health, safety, security,
environmental (HSSE) and social performance (SP) issues associated with the KM250A
Project and describes the key elements that form the health, safety, security,
environmental and social management framework that will apply to the KM250A Project,
including:
• Pearl Petroleum HSSE and SP policy and management system (MS)
framework
• Pearl Petroleum HSSE&SP standards
• Pearl Petroleum KM250A Project HSSE&SP Management Plan (MP)
The latter complies with Kurdistan Region of Iraq (KRI) Ministry of Natural Resources
(MNR) and International Finance Corporation (IFC) Performance Standard 1
requirements for the environmental and social management plan. Details concerning the
safeguards, measures and plans that constitute the Pearl Petroleum KM250A Project
HSSE&SP MP (‘KM250A HSSE&SP MP’) are provided in Section 11.
Details are provided regarding the following essential mechanisms embedded in the
KM250A HSSE&SP MP for implementing the same:
• roles and responsibilities
• communications
• management of change.
The Pearl Petroleum KM250A HSSE&SP MP will extend through all phases of the
KM250A Project and is intended to inform Pearl Petroleum and contractor personnel
(including the construction phase engineering, procurement and construction, EPC,
Contractor) of their roles and responsibilities in delivering the Project in compliance with
Pearl Petroleum HSSE&SP standards. As per the Field Development Plan (FDP) (Pearl
Petroleum 2018), the development of specific HSSE&SP requirements will occur in a
phased manner consistent with the requirements for the respective phases.
Figure 10-1 below illustrates the application of the Pearl Petroleum HSSE&SP MS,
spanning the transition from the current system used in the existing operation, through to
the Pearl Petroleum HSSE&SP MS, which will be the basis for the KM250A HSSE&SP
MP for the KM250A Project and future expansion projects.
1 HSSE&SP Policy Details the HSSE&SP principles and Current operations are
expectations for doing business in an conducted under the Crescent
environmentally and socially responsible QHSE Policy. A revised
manner integrated HSSE&SP Policy has
been established for the
KM250A Project and future
operations
HSSE&SP The 16 Standard Elements (Figure 10-3) Developed and in process of
Management System set out the management measures implementation.
Framework and required to reduce the potential health,
Standard Elements safety security, environmental and
social impacts, and to enhance the
benefits of the proposed Project
activities
HSSE&SP Standards
2 HSSE Leadership HSSE&SP Standards to support the HSSE&SP Standards are the
HSSE&SP Policy and Management major part of the HSSE&SP MS
OHS Management
System Framework. development and enhancement
programme and will be applied to
Plant Integrity These standards apply to all Pearl the KM250A Project.
Petroleum assets and locations and may
be supplemented by local Level 3 HSSE&SP standards ensure
instructions or guidance consistency of performance
Security Management across the organisation and
standardise requirements.
Environmental
Management
Social Performance
Hazard Identification,
Risk, Assessment
and Control
Management of
Change
Personnel Training
and Competence
Communication and
Promotion
Documentation and
Information
Management
Contractor
Management and
Purchasing
Emergency
Preparedness and
Response
Incident Management
Performance
Monitoring and
Performance
Periodic Review and
Improvement
Asset/Location/Project-Specific HSSE&SP Procedures*
Pearl Petroleum seeks to develop strong, mutually beneficial relationships with the
communities and other stakeholders wherever it operates, contributing to economic and
social development. Essential to this is understanding and minimising any adverse social
and human rights impacts which may result from its activities. The SP Standard sets out
the basic framework for implementing Pearl Petroleum’s HSSE&SP Policy. The SP
Standard is supported by a set of related Operating Procedures and Guidelines designed
to assist with implementation.
Specifically, Pearl Petroleum will:
• Comply with applicable environmental and social laws, regulations and
obligations and, where these do not exist adopt and apply standards that are
in alignment with the intent of its Policy and international good practice.
• Allocate resources commensurate to social risks, potential impacts and socio-
economic opportunities to ensure appropriate implementation of social
performance management plans throughout the project lifecycle.
• Ensure appropriate governance and management systems are in place to
identify, measure, manage, monitor and oversee its social performance.
• Embed social performance across the organisation through a culture of shared
responsibility and accountability which integrates social performance
considerations into business decision making.
• Include appropriate social performance requirements in contractual
agreements when significant potential adverse social impacts and/or
opportunities to deliver socio-economic development exist.
10.4.3 Contractors
Contractors’ roles and responsibilities for compliance with environmental and social
requirements are reflected in relevant contractor performance guidelines and HSSE&SP
exhibits to their contracts. The contractors shall ensure as minimum the following:
• strict adherence to relevant laws, regulation and guidelines
• providing all workers with written contracts describing their rights under
national labour law
• providing appropriate on-the-job training to enable local employees to improve
their skills whilst working on the Project
• planning of each task to include documented safety, environmental and social
risk identification and assessment
• applying appropriate control measures to reduce safety risks, environmental
impacts and social disturbance
• monitoring parameters agreed with Pearl Petroleum and providing all
monitoring results
• communicating HSSE&SP incidents to Pearl Petroleum and rectifying
immediately
• attending meetings and workshops as directed.
During operations, the Operations Manager is responsible for ensuring conformity with
HSSE&SP requirements as detailed in the HSSE&SP MS and the Project HSSE&SP MP.
The on-site supervisors and personnel will monitor key environmental and social
performance indicators to ensure targets are met. They will monitor effectiveness of the
mitigation measures and report the performance to the senior management and to the
government agencies, as required.
The operations phase contractors will also be required to demonstrate how they will
comply with all relevant legislation and industry good practice, and how they will
implement the proposed mitigation measures. The contractors will monitor environmental
and social performance to evaluate actual performance against its objectives.
10.5 Communication
The construction phase contractor(s) will also be expected to develop the following:
• Gender Inclusion Strategy, which will provide for assessment of the potential
risks that may be associated with women’s participation in the KM250A Project
will be assessed
• Community Health, Safety and Security Plan
• Local Goods and Services Plan (including Local Community Employment
Plans and Retrenchment Plans), to ensure maximum use of local goods and
services (including labour)
• Dust Management Plan, allowing for dust suppression by spraying water onto
dirt tracks and flowline RoWs
• Lighting Plan, that will include minimisation to the extent possible of impacts
on nearby sensitive receptors (villages and habitats)
• Retrenchment Plan with the aim of ensuring social cohesion and reducing the
impacts of the termination of employment contracts. The overall approach will
be aligned with IFC guidelines on retrenchment.
• Health and Safety Plan(s) and Work Management Procedure(s); these will be
approved by Pearl Petroleum and will be aligned with Pearl Petroleum’s
overarching health and safety systems and international standards. Auditing
will be undertaken by Pearl Petroleum to ensure contractor compliance with
health and safety plans and work management procedures.
• Where appropriate, each construction contractor will develop a work-specific
Traffic Management Plan (TMP) which identifies sensitive social receptors
along transportation routes and outline mitigation measures (e.g. speed limit
restrictions, vehicle maintenance activities, awareness campaigns, recruitment
of traffic wardens) to reduce the risk of road traffic accidents occurring.
11.6 Decommissioning
The detailed programme for decommissioning will be determined and agreed with the
MNR authorities prior to shut down. Decommissioning and dismantling are expected to
be performed by specialist contractors supported by a core team of Project operations
and maintenance personnel and will feature:
• use of heavy machinery and plant for demolition
• management of waste streams generated during decommissioning
(equipment, piping and leftover chemicals)
• transport of demolition wastes to an approved landfill
• dismantling equipment to manageable sections
• removal of building structures and paved surfaces
• drainage of oil-based liquids and lubricants from equipment, including vessels
and piping
• waste management in accordance with the Pearl Petroleum Waste
Management Procedure and waste hierarchy principals.
Post-closure monitoring will be carried out before transferring the land to the next land
owner.
Project
Parameter S1 S2 S3 S4 S5
standard
Mercury BCL BCL BCL BCL BCL 1
Arsenic 4.65 5.98 4.12 7.42 5.32 20
Zinc 24.2 26.1 23.8 20.7 23.9 200
Cyanide BCL BCL BCL BCL BCL 10
Cadmium 1.1 4.1 1.1 2.6 37 3
Chromium* 46 35 23 25 54 1vi/400III
Manganese 423 433 354 222 362 500
Magnesium 58.6 65.5 40.4 31.8 72.8 -
Copper 31.8 38.8 42.0 32.1 39.7 100
Lead 4.1 3.8 8.5 9.4 8.3 300
Nickel 43 27 34 32 75 60
Iron 32.4 32.1 29.3 42.6 34.2 -
TPH 3.2 5.2 5.2 6.3 10.2 -
Source: MapCom (2010)
Notes: Red = exceeds Project standard, TPH = total petroleum hydrocarbons (unspecified fraction), BDL = below detection limit
(detection limit not reported), * = valency unspecified, III = Chromium III, VI = Chromium VI.
Table A1.2 Chemical properties of soil sampling sites in the study area of Khor Mor block
Canadian guideline
Canadian
Extractable metals/ Unit of for KM- KM- KM- KM- KM- KM- KM- KM- KM- KM- KM- KM-
guideline for
sampling sites measurement residential/industrial SS1 SS2 SS3 SS4 SS5 SS6 SS7 SS8 SS9 SS10 SS11 SS12
agricultural
commercial
Major cations
Aluminum mg/kg DW 22500 19500 16200 20600 22000 27500 19600 16200 15200 17800 14700 22700
Antimony mg/kg DW 7.5 40 <0.50 <0.50 <0.50 <0.50 <0.50 <0.50 <0.50 <0.50 <0.50 <0.50 <0.50 <0.50
Arsenic mg/kg DW 11 18 6.05 2.95 1.56 4.72 5.09 4.29 4.88 3.57 3.83 4.83 3.40 6.75
Barium mg/kg DW 390 670 62.3 81.6 31 99.5 106 77.8 97.8 89.9 96.2 103 139 57.4
Beryllium mg/kg DW 4 8 0.745 0.602 0.544 0.717 0.793 0.832 0.748 0.500 0.465 0.535 0.490 0.755
Bismuth mg/kg DW <1.0 <1.0 <1.0 <1.0 <1.0 <1.0 <1.0 <1.0 <1.0 <1.0 <1.0 <1.0
Boron mg/kg DW 120 120 5.6 4.4 3 6.1 8.4 11.1 6.4 9.4 8.7 10.4 9.3 6.1
Cadmium mg/kg DW 1.2 1.9 <0.40 <0.40 <0.40 <0.40 <0.40 <0.40 <0.40 <0.40 <0.40 <0.40 <0.40 <0.40
Calcium mg/kg DW 98800 62200 88700 100000 92300 88700 93500 166000 168000 149000 140000 103000
Chromium mg/kg DW 160 160 53.0 44.2 36.1 38.4 43.3 60.0 37.8 56.8 55.6 63.0 53.7 49.6
Cobalt mg/kg DW 22 80 12.7 10.8 9.04 11.1 12 15.2 11.3 11.2 10.3 11.6 10.6 12.4
Copper mg/kg DW 140 230 28.3 17.7 14.7 22.0 22.4 30.6 21.1 20.7 19.1 21.6 22.2 28.4
Iron mg/kg DW 31700 28500 25200 29700 31400 36500 29400 23300 21600 24300 22200 31300
Lead mg/kg DW 45 (120) 120 9.4 7.2 6.2 9.5 9.7 10.4 10.1 6.3 5.5 6.0 8.3 9.5
Lithium mg/kg DW 49.6 33.8 29.7 46.3 50.3 56.5 43.5 28.0 27.2 30.2 27.5 49.3
Magnesium mg/kg DW 18100 12500 10200 13100 14200 18100 11400 16300 15700 19200 12100 17400
Manganese mg/kg DW 638 788 682 639 628 638 618 506 455 466 514 531
Mercury mg/kg DW 0.25 (0.27) 3.9 <0.20 <0.20 <0.20 <0.20 <0.20 <0.20 <0.20 <0.20 <0.20 <0.20 <0.20 <0.20
Molybdenum mg/kg DW 6.9 40 <0.40 <0.40 <0.40 <0.40 <0.40 <0.40 <0.40 0.64 0.57 0.53 0.49 <0.40
Nickel mg/kg DW 100 270 70.4 50.6 39.1 48.3 53.8 80.0 48.6 80.6 75.6 86.9 74.8 66.4
Phosphorus mg/kg DW 474 450 410 446 492 491 510 550 415 490 791 462
Potassium mg/kg DW 2710 1810 1330 2200 2620 3360 2220 3250 2430 3110 3440 2680
Selenium mg/kg DW 2.4 5.5 <2.0 <2.0 <2.0 <2.0 <2.0 <2.0 <2.0 <2.0 <2.0 <2.0 <2.0 <2.0
Silicon mg/kg DW 196 240 232 228 230 226 217 201 192 200 235 207
Silver mg/kg DW 20 40 <0.50 <0.50 <0.50 <0.50 <0.50 <0.50 <0.50 <0.50 <0.50 <0.50 <0.50 <0.50
Sodium mg/kg DW 134 71 44 116 123 162 106 177 176 199 117 111
Strontium mg/kg DW 800 110 123 212 420 234 206 353 426 320 183 829
Sulphur mg/kg DW 112 88 83 97 121 110 126 402 333 369 323 121
Tellurium mg/kg DW <1.0 <1.0 <1.0 <1.0 <1.0 <1.0 <1.0 <1.0 <1.0 <1.0 <1.0 <1.0
Thallium mg/kg DW 1 3.3 <0.50 <0.50 <0.50 <0.50 <0.50 <0.50 <0.50 <0.50 <0.50 <0.50 <0.50 <0.50
Tin mg/kg DW <1.0 <1.0 <1.0 <1.0 <1.0 <1.0 <1.0 <1.0 <1.0 <1.0 <1.0 <1.0
Titanium mg/kg DW 166 476 444 244 343 362 310 406 410 426 303 166
Vanadium mg/kg DW 86 86 45.1 43 42.9 38.6 40.2 48.0 37.9 44.8 43.2 47.2 39.8 45.0
Zinc mg/kg DW 340 340 57.4 49.3 41.7 56.3 59.8 68.4 57.0 40.0 34.5 40.0 42.5 56.8
Zirconium mg/kg DW <5.0 <5.0 <5.0 <5.0 <5.0 <5.0 <5.0 <5.0 <5.0 <5.0 <5.0 <5.0
Petroleum hydrocarbons
C10 - C12 fraction mg/kg DW <2.0 <2.0 <2.0 <2.0 <2.0 <2.0 <2.0 <2.0 <2.0 <2.0 <2.0 <2.0
C10 - C40 fraction mg/kg DW <20 <20 <20 <20 <20 <20 <20 <20 <20 <20 <20 <20
C12 - C16 fraction mg/kg DW <3.0 <3.0 <3.0 <3.0 <3.0 <3.0 <3.0 <3.0 <3.0 <3.0 <3.0 <3.0
C16 - C35 fraction mg/kg DW <10 <10 <10 <10 <10 <10 <10 <10 <10 <10 <10 <10
C35 - C40 fraction mg/kg DW <5.0 <5.0 <5.0 <5.0 <5.0 <5.0 <5.0 <5.0 <5.0 <5.0 <5.0 <5.0
Physical parameters
Dry matter @ 105°C % 90.2 89 86.9 90.2 90.2 89.9 89.6 84.7 86.3 85.7 83.8 91.1
pH (H2O) 8.5 8.4 8.2 8.2 8.3 8.3 8.2 8.3 8.2 8.2 8.2 8.1
BTEX
Benzene mg/kg DW <0.010 <0.010 <0.010 <0.010 <0.010 <0.010 <0.010 <0.010 <0.010 <0.010 <0.010 <0.010
Toluene mg/kg DW <0.030 <0.030 <0.030 <0.030 <0.030 <0.030 <0.030 <0.030 <0.030 <0.030 <0.030 <0.030
Ethylbenzene mg/kg DW <0.020 <0.020 <0.020 <0.020 <0.020 <0.020 <0.020 <0.020 <0.020 <0.020 <0.020 <0.020
meta- & para-Xylene mg/kg DW <0.020 <0.020 <0.020 <0.020 <0.020 <0.020 <0.020 <0.020 <0.020 <0.020 <0.020 <0.020
ortho-Xylene mg/kg DW <0.010 <0.010 <0.010 <0.010 <0.010 <0.010 <0.010 <0.010 <0.010 <0.010 <0.010 <0.010
Sum of BTEX mg/kg DW <0.090 <0.090 <0.090 <0.090 <0.090 <0.090 <0.090 <0.090 <0.090 <0.090 <0.090 <0.090
Sum of xylenes mg/kg DW <0.030 <0.030 <0.030 <0.030 <0.030 <0.030 <0.030 <0.030 <0.030 <0.030 <0.030 <0.030
Note: WB = World Bank, Temp. = Temperature, ºC = degrees Celsius, pH – potential of hydronium, EC = Electrical
Conductivity, µs.cm-1 = micro siemens per centimetre, mg.I-1 = milligram per liter, TSS = Total Suspende Solids, D.O. =
Dissolved oxygen, B.O.D5 = Biological Oxygen Demand of five day incubation time, C.O.D = Chemical Oxygen Demand, SO 4=
= Sulfate, NO3 = Nitrate, MPN = Most Probable Number of Fecal coliform bacteria.
Table A1.4 Physical, chemical and biological properties of groundwater and surface water system in the study area (MapCom, 2018)
Sampling sites GW1 GW2 GW3 GW4 GW5 GW6 GW7 GW8 WHO Norms
Parameters Unit
Aggregate parameters
Calcium Hardness mmol/L 2.9 2.7 4.82 1.42 1.93 2.41 1.14 2.43
Hardness mmol/L 3.4 2.56 6.91 1.63 3.22 2.79 1.47 2.81
mg
Hardness as CaCO3 324 256 691 163 322 279 147 281 500
CaCO3/L
mg
Magnesium Hardness 33.8 28.9 210 21.7 129 38.6 33.2 38.2
CaCO3/L
Dissolved metals/major cations
Aluminium mg/L 0.016 0.014 0.020 0.011 0.013 0.015 0.010 0.015
Antimony mg/L <0.010 <0.010 <0.010 <0.0 10 <0.0 10 <0.0 10 <0.010 <0.010
Arsenic mg/L <0.0050 <0.0050 <0.0050 <0.0 050 <0.0 050 <0.0 050 <0.0050 <0.0050 0.001
Barium mg/L 0.220 0.106 0.0684 0.0287 0.108 0.196 0.171 0.200
Beryllium mg/L <0.00020 <0.00020 <0.00020 <0.00020 <0.00020 <0.00020 <0.00020 <0.00020
Boron mg/L 0.025 0.017 0.255 0.019 0.093 0.034 0.034 0.034
Cadmium mg/L <0.00040 <0.00040 <0.00040 <0.00040 <0.00040 <0.00040 <0.00040 <0.00040 0.003
Calcium mg/L 101 81.2 166 50.1 69.6 87.2 40.5 89.0 150
Chromium mg/L <0.0010 <0.0010 0.0011 <0.0010 <0.0010 <0.0010 <0.0010 0.0011 0.05
Cobalt mg/L <0.002 0 <0.0020 <0.0020 <0.0020 <0.0020 <0.0020 <0.0020 <0.0020
Copper mg/L <0.0010 <0.0010 <0.0010 <0.0010 0.0044 <0.0010 <0.0010 <0.0010 2
Iron mg/L <0.0020 <0.0020 0.0050 <0.0020 0.0996 <0.0020 <0.00050 <0.0020 0.3
Lead mg/L <0.0050 <0.0050 <0.0050 <0.0050 <0.0050 <0.0050 <0.0050 <0.0050 0.01
Lithium mg/L 0.0069 0.0069 0.0297 0.0037 0.0306 0.0059 0.0054 0.0072
Magnesium mg/L 7.11 6.39 44.5 4.64 28 8.40 7.30 8.34 100
Manganese mg/L <0.00050 <0.00050 <0.00050 <0.00050 <0.00050 <0.00050 <0.00050 <0.00050 0.4
Molybdenum mg/L <0.002 <0.002 <0.002 <0.0 <0.0 <0.0 <0.00 <0.00
Nickel mg/L <0.0020 <0.0020 <0.0020 <0.0020 <0.0020 <0.0020 <0.0020 <0.0020 0.07
Phosphorus mg/L <0.050 <0.050 <0.050 <0.050 <0.050 <0.050 <0.050 <0.050
Potassium mg/L 1.76 0.132 15.9 0.104 1.91 0.525 0.338 0.465 250
Selenium mg/L <0.010 <0.010 <0.000 <0.010 <0.010 <0.010 <0.010 <0.010 0.01
Silver mg/L <0.0010 <0.0010 <0.0010 <0.010 <0.010 <0.010 <0.0010 <0.0010
Sodium mg/L 8.28 7.59 64.4 6.74 90.1 12.3 12.3 12.2 200
Thallium mg/L <0.010 <0.010 <0.010 <0.010 <0.010 <0.010 <0.010 <0.010
Vanadium mg/L 0.0015 <0.0010 <0.0010 <0.0010 0.0071 0.0021 0.0035 0.0019
Zinc mg/L <0.0020 <0.0020 <0.0020 <0.010 0.0384 0.0218 0.0042 0.0231 3
Petroleum hydrocarbons
C10 - C12 Fraction µg/L <5.0 <5.0 <5.0 <5.0 <5.0 <5.0 <5.0 <5.0
C10 - C40 Fraction µg/L <50.0 <50.0 <50.0 <50.0 <50.0 <50.0 <50.0 <50.0
C12 - C16 Fraction µg/L <5.0 <5.0 <5.0 <5.0 <5.0 <5.0 <5.0 <5.0
C16 - C35 Fraction µg/L <30.0 <30.0 <30.0 <30.0 <30.0 <30.0 <30.0 <30.0
C35 - C40 Fraction µg/L <10.0 <10.0 <10.0 <10.0 <10.0 <10.0 <10.0 <10.0
Physical parameters
Turbidity NTU <1.0 <1.0 <1.0 <1.0 <1.0 <1.0 <1.0 <1.0
Total metals/major cations
Magnesium mg/L 8.21 7.04 51 5.28 31.4 9.39 8.06 9.28
Mercury µg/L 0.047 <10.0 0.046 <10.0 <10.0 <10.0 <10.0 <10.0
Potassium mg/L 2.10 0.146 18.2 0.126 2.21 0.608 0.424 0.587
Sodium mg/L 9.63 8.49 75.2 7.66 100 13.6 13.7 13.6
Other parameters
pH - 7.42 7.62 7.88 7.72 7.48 7.93 7.58 7.93 6.5-8.5
EC µS.cm-1 520 761 923 290 631 772 547 772 1000
Salinity ppt 0.26 0.23 0.45 0.14 0.32 0.37 0.24 0.37
TDS ppt 338 494.6 599.9 188 410 501 355 501 500
Storage
Well Depth m Spring Spring 55 - 2.5 6 6
Tank
Storage
Water Table Depth m Spring Spring 6 - 20cm 2.5 2.5
Tank
Temperature Co 19.4 19.7 21.11 21.7 19.9 20.3 19.8 20.3
DO ppm 2.99 2.84 2.69 7.99 4.23 3.45 2.87 3.45
BOD5 ppm <1.0 <1.0 <1.0 <1.0 <1.0 <1.0 <1.0 <1.0
COD ppm <5.0 <5.0 <5.0 <5.0 <5.0 <5.0 <5.0 <5.0
Bacteriological analysis
MPN MPN/ml 160 5 28 14 1 240 1 92 <5
T.P.C - 103 103 103 103 103 103 103 103 100
Non-metallic inorganic parameters
Base neutralizing (Acidity) capacity pH 8.3 mmol/L 0.417 0.235 0.203 <0.150 <0.150 1.61 <0.150 <0.150 3
Base neutralizing (Acidity) capacity pH 4.5 mmol/L <0.150 <0.150 <0.150 <0.150 <0.150 <0.150 <0.150 <0.150
Acid neutralizing capacity (alkalinity) pH 4.5 mmol/L 5.17 3.66 5.67 3.11 1.06 4.27 2.48 4.21 3.00
Acid neutralizing capacity (alkalinity) pH 8.3 mmol/L <0.150 <0.150 <0.150 <0.150 <0.150 <0.150 <0.150 <0.150
Biochemical Oxygen Demand (BOD 5) mg/L <1.0 <1.0 <1.0 <1.0 1.6 <1.0 <1.0 <1.0 5
Chemical Oxygen Demand (COD-Cr) mg/L <5.0 <5.0 <5.0 <5.0 13 <5.0 <5.0 <5.0
Sulphate as SO4 2- mg/L 10.5 10.3 130 6.34 117 11.3 6.64 11.8 250
Nitrate mg/L 17.8 19.7 98.7 29.9 282 20.6 19.6 20.8 50
Nitrates as N mg/L 4.02 4.46 22.3 6.76 63.8 4.66 4.43 4.70
Sulphate as SO4 2- mg/L 46.9 70.8 388 17.5 242 73.9 34.0 77.2 250
Biodiversity
Table A1.5 Rare plant species identified by Nature Iraq (2017)
Likelihood
Likelihood of
of species
IUCN species occurring
Scientific to use
Common name (2019) Species range Habitat type in project footprint
name habitats in
status – assuming the
the study
site is fenced
area
It is poorly known, but it appears to be a Unlikely due to
terrestrial species which prefer moist Unlikely restricted range
Bunni's Short- EN
Nesokia habitats, such as marshes and swamps. due to however further
tailed Bandicoot Iraq, presence in Iran is uncertain
bunni Endemic to the marshlands of south- restricted analysis is required
Rat
eastern Iraq in the Tigris and Euphrates range to validate this
Valleys. assumption.
Unlikely,
Afghanistan, Azerbaijan, Bahrain, China,
Global thought to
Iran, Iraq, Jordan, Kazakhstan,
VU; be
Gazella Kyrgyzstan, Mongolia; Oman, Pakistan, Inhabits a wide range of semi-desert and
Goitered gazelle Medite restricted to Unlikely
subgutturosa Saudi Arabia, Syrian Arab Republic, desert habitats
rranea Chamcham
Tajikistan, Turkey, Turkmenistan, United
n CR al KBA &
Arab Emirates, Uzbekistan & Yemen
IBA but
Iraq, Jordan, Kuwait; Oman, Qatar, Deserts, including sand dunes and areas
Arabian Sand Gazella
VU Saudi Arabia, Syrian Arab Republic, of sand and gravel as well as coastal flats; Possible Unlikely
Gazelle marica
United Arab Emirates & Yemen it avoids steep and rocky areas.
VU;
wide range of habitats including desert and
Panthera Medite
leopard >30 counties including Iraq semi-desert, mountainous habitats & Unlikely Unlikely
pardus rranea
rainforests.
n CR
wild boar Sus scrofa LC >30 counties including Iraq Wide variety of temperate and tropical Possible Unlikely
habitats including semi-desert to tropical
Likelihood
Likelihood of
of species
IUCN species occurring
Scientific to use
Common name (2019) Species range Habitat type in project footprint
name habitats in
status – assuming the
the study
site is fenced
area
rain forests, temperate woodlands,
grasslands, shrubland, often raiding
agricultural land for food.
Note: LC = IUCN listed Least Concern; NT = Near Threatened; VU = Vulnerable; EN = Endangered; CR = Critically Endangered
Table A1.7 Rare and threatened bird species with ranges that overlap the study area
IUCN
Common Scientific Habitat of occurrence Migratory Congregatory
(2019)
name name (IUCN, 2019) status status
status
Desert, wetlands (inland), Congregatory
sociable Vanellus Full
CR grassland, (and
lapwing gregarius migrant
artificial/terrestrial dispersive)
Marine intertidal, wetlands
Congregatory
(inland), grassland, Full
saker falcon Falco cherrug EN (and
shrubland, migrant
dispersive)
artificial/terrestrial
Marine coastal/supratidal,
caves and subterranean
habitats (non-aquatic),
rocky areas (eg. inland
Congregatory
Northern bald Geronticus cliffs, mountain peaks), Full
EN (and
ibis eremita wetlands (inland), Migrant
dispersive)
grassland, shrubland,
artificial/terrestrial –
possibly extinct in Iraq
(IUCN, 2019)
Rocky areas (e.g. inland
cliffs, mountain peaks), Congregatory
Egyptian Neophron Full
EN wetlands (inland), (and
vulture percnopterus migrant
grassland, shrubland, dispersive)
savanna, artificial/terrestrial
Wetlands (inland), Congregatory
white-headed Oxyura Full
EN artificial/aquatic & marine, (and
duck leucocephala migrant
marine coastal/supratidal dispersive)
Rocky areas (e.g. inland Congregatory
Aquila Full
steppe eagle EN cliffs, mountain peaks), (and
nipalensis migrant
grassland, savanna dispersive)
Grassland, Full Not
great bustard Otis tarda VU
artificial/terrestrial migrant congregatory
Wetlands (inland), marine Congregatory
Marmaronetta Full
Marbled Teal VU coastal/supratidal, (and
angustirostris migrant
artificial/aquatic & marine dispersive)
Artificial/terrestrial,
Lesser grassland, rocky areas (eg. Congregatory
Anser Full
White-fronted VU inland cliffs, mountain (and
erythropus migrant
Goose peaks), shrubland, dispersive)
wetlands (inland)
Forest, wetlands (inland), Congregatory
greater Clanga Full
VU shrubland, artificial/aquatic (and
spotted eagle clanga migrant
& marine, grassland dispersive)
Asian Chlamydotis Desert, grassland, Full Not
VU
houbara macqueenii artificial/terrestrial migrant congregatory
European Streptopelia Forest, artificial/terrestrial, Full Not
VU
turtle-dove turtur shrubland migrant congregatory
Table A1.8 Avifauna species identified from previous surveys (Nature Iraq)
SS01
SS02
SS03
SS04
SS05
SS06
SS07
SS08
SS09
SS10
SS11
SS12
SS13
Metals
Page 1 of 6
Al Futtaim Element Materials Technology Dubai L.L.C P: +971 (0)4 8851001
Plot 598-221, Dubai Investments Park, F: +971 (0)4 8854004
P.O. Box 34924 me.dxbnorlims@element.com
Dubai, United Arab Emirates element.com
Metals
Page 2 of 6
Al Futtaim Element Materials Technology Dubai L.L.C P: +971 (0)4 8851001
Plot 598-221, Dubai Investments Park, F: +971 (0)4 8854004
P.O. Box 34924 me.dxbnorlims@element.com
Dubai, United Arab Emirates element.com
Metals
Page 3 of 6
Al Futtaim Element Materials Technology Dubai L.L.C P: +971 (0)4 8851001
Plot 598-221, Dubai Investments Park, F: +971 (0)4 8854004
P.O. Box 34924 me.dxbnorlims@element.com
Dubai, United Arab Emirates element.com
Metals
Page 4 of 6
Al Futtaim Element Materials Technology Dubai L.L.C P: +971 (0)4 8851001
Plot 598-221, Dubai Investments Park, F: +971 (0)4 8854004
P.O. Box 34924 me.dxbnorlims@element.com
Dubai, United Arab Emirates element.com
Sample ID 79963-13
Date Received 16/12/2019
Sampled By Karrar Kamal
Sampling Date 14/11/2019
Sampling Time Not Given
Sample Sub Matrix Soil
Sampling Location Not Given
Client Sample ID SS13 / X-484346 -
Y-3887945 / 0.1-
0.4m
Analyte Units Results Results Results Method Limit
of Detection
Metals
Method of Analysis
Method Name Reference
Chromium (Hexavalent) [HACH 8023] Solids-DXB HACH [8023]
EPH C10-C40 by GC-FID [EPA 8015B] SSS-DXB$ EPA [8015B]
Mercury by PSA [EPA 245.7] SSS-DXB$ EPA [245.7]
Metals ICP OES [APHA 3120 B] SSS-DXB$ APHA [3120 B]
VPH C5-C10 by GC-FID [EPA 8015B]-SSS-DXB$ EPA [8015B]
* Reference Method Modified
Page 5 of 6
Al Futtaim Element Materials Technology Dubai L.L.C P: +971 (0)4 8851001
Plot 598-221, Dubai Investments Park, F: +971 (0)4 8854004
P.O. Box 34924 me.dxbnorlims@element.com
Dubai, United Arab Emirates element.com
Comments:
. Tested By : AAP, JCH, SKR
. Date Tested: 23/12/2019 to 24/12/2019
. Please note that if the sample has to be diluted due to the matrix, the reported Limit of Detection (LOD) value will increase from the method LOD.
. Any APHA methods stated herein are documented in-house procedures, referenced to 23rd edition.
. Test methods marked with $ are EIAC (formerly DAC) accredited.
Page 6 of 6
WATER
Table A2.2 Water sampling location photographs
Paryawla – well
WW-2
WW-3
SP-2
SP-4
GW-5
Zhazh – spring
Inorganic Parameters
Page 1 of 22
Al Futtaim Element Materials Technology Dubai L.L.C P: +971 (0)4 8851001
Plot 598-221, Dubai Investments Park, F: +971 (0)4 8854004
P.O. Box 34924 me.dxbnorlims@element.com
Dubai, United Arab Emirates element.com
Metals - Continued
Page 2 of 22
Al Futtaim Element Materials Technology Dubai L.L.C P: +971 (0)4 8851001
Plot 598-221, Dubai Investments Park, F: +971 (0)4 8854004
P.O. Box 34924 me.dxbnorlims@element.com
Dubai, United Arab Emirates element.com
PAH's - Continued
Page 3 of 22
Al Futtaim Element Materials Technology Dubai L.L.C P: +971 (0)4 8851001
Plot 598-221, Dubai Investments Park, F: +971 (0)4 8854004
P.O. Box 34924 me.dxbnorlims@element.com
Dubai, United Arab Emirates element.com
Page 4 of 22
Al Futtaim Element Materials Technology Dubai L.L.C P: +971 (0)4 8851001
Plot 598-221, Dubai Investments Park, F: +971 (0)4 8854004
P.O. Box 34924 me.dxbnorlims@element.com
Dubai, United Arab Emirates element.com
Inorganic Parameters
Page 5 of 22
Al Futtaim Element Materials Technology Dubai L.L.C P: +971 (0)4 8851001
Plot 598-221, Dubai Investments Park, F: +971 (0)4 8854004
P.O. Box 34924 me.dxbnorlims@element.com
Dubai, United Arab Emirates element.com
Metals - Continued
Page 6 of 22
Al Futtaim Element Materials Technology Dubai L.L.C P: +971 (0)4 8851001
Plot 598-221, Dubai Investments Park, F: +971 (0)4 8854004
P.O. Box 34924 me.dxbnorlims@element.com
Dubai, United Arab Emirates element.com
PAH's - Continued
Page 7 of 22
Al Futtaim Element Materials Technology Dubai L.L.C P: +971 (0)4 8851001
Plot 598-221, Dubai Investments Park, F: +971 (0)4 8854004
P.O. Box 34924 me.dxbnorlims@element.com
Dubai, United Arab Emirates element.com
Page 8 of 22
Al Futtaim Element Materials Technology Dubai L.L.C P: +971 (0)4 8851001
Plot 598-221, Dubai Investments Park, F: +971 (0)4 8854004
P.O. Box 34924 me.dxbnorlims@element.com
Dubai, United Arab Emirates element.com
Inorganic Parameters
Page 9 of 22
Al Futtaim Element Materials Technology Dubai L.L.C P: +971 (0)4 8851001
Plot 598-221, Dubai Investments Park, F: +971 (0)4 8854004
P.O. Box 34924 me.dxbnorlims@element.com
Dubai, United Arab Emirates element.com
Metals - Continued
Page 10 of 22
Al Futtaim Element Materials Technology Dubai L.L.C P: +971 (0)4 8851001
Plot 598-221, Dubai Investments Park, F: +971 (0)4 8854004
P.O. Box 34924 me.dxbnorlims@element.com
Dubai, United Arab Emirates element.com
PAH's - Continued
Page 11 of 22
Al Futtaim Element Materials Technology Dubai L.L.C P: +971 (0)4 8851001
Plot 598-221, Dubai Investments Park, F: +971 (0)4 8854004
P.O. Box 34924 me.dxbnorlims@element.com
Dubai, United Arab Emirates element.com
Page 12 of 22
Al Futtaim Element Materials Technology Dubai L.L.C P: +971 (0)4 8851001
Plot 598-221, Dubai Investments Park, F: +971 (0)4 8854004
P.O. Box 34924 me.dxbnorlims@element.com
Dubai, United Arab Emirates element.com
Inorganic Parameters
Page 13 of 22
Al Futtaim Element Materials Technology Dubai L.L.C P: +971 (0)4 8851001
Plot 598-221, Dubai Investments Park, F: +971 (0)4 8854004
P.O. Box 34924 me.dxbnorlims@element.com
Dubai, United Arab Emirates element.com
Metals - Continued
Page 14 of 22
Al Futtaim Element Materials Technology Dubai L.L.C P: +971 (0)4 8851001
Plot 598-221, Dubai Investments Park, F: +971 (0)4 8854004
P.O. Box 34924 me.dxbnorlims@element.com
Dubai, United Arab Emirates element.com
PAH's - Continued
Page 15 of 22
Al Futtaim Element Materials Technology Dubai L.L.C P: +971 (0)4 8851001
Plot 598-221, Dubai Investments Park, F: +971 (0)4 8854004
P.O. Box 34924 me.dxbnorlims@element.com
Dubai, United Arab Emirates element.com
Page 16 of 22
Al Futtaim Element Materials Technology Dubai L.L.C P: +971 (0)4 8851001
Plot 598-221, Dubai Investments Park, F: +971 (0)4 8854004
P.O. Box 34924 me.dxbnorlims@element.com
Dubai, United Arab Emirates element.com
Inorganic Parameters
Page 17 of 22
Al Futtaim Element Materials Technology Dubai L.L.C P: +971 (0)4 8851001
Plot 598-221, Dubai Investments Park, F: +971 (0)4 8854004
P.O. Box 34924 me.dxbnorlims@element.com
Dubai, United Arab Emirates element.com
Metals - Continued
Page 18 of 22
Al Futtaim Element Materials Technology Dubai L.L.C P: +971 (0)4 8851001
Plot 598-221, Dubai Investments Park, F: +971 (0)4 8854004
P.O. Box 34924 me.dxbnorlims@element.com
Dubai, United Arab Emirates element.com
PAH's - Continued
Page 19 of 22
Al Futtaim Element Materials Technology Dubai L.L.C P: +971 (0)4 8851001
Plot 598-221, Dubai Investments Park, F: +971 (0)4 8854004
P.O. Box 34924 me.dxbnorlims@element.com
Dubai, United Arab Emirates element.com
Method of Analysis
Method Name Reference
Chloride [APHA 4500 Cl- B]-DXB APHA [4500 Cl- B]
Page 20 of 22
Al Futtaim Element Materials Technology Dubai L.L.C P: +971 (0)4 8851001
Plot 598-221, Dubai Investments Park, F: +971 (0)4 8854004
P.O. Box 34924 me.dxbnorlims@element.com
Dubai, United Arab Emirates element.com
Comments:
. Tested By : AAP, JCH, SKR, SMO
. Date Tested: 19/12/2019 to 24/12/2019
. Please note that if the sample has to be diluted due to the matrix, the reported Limit of Detection (LOD) value will increase from the method LOD.
. Any APHA methods stated herein are documented in-house procedures, referenced to 23rd edition.
. Test methods marked with $ are EIAC (formerly DAC) accredited.
.
Please note that the metals results reported above are dissolved metals.
. Please see the table below detailing the surrogate recovery of Naphthalene-D8* for the samples shown. The normal acceptable recovery range is 70-
130%, however, the values shown are slightly below this for some of the samples due to the sample matrix effect. The recovery of the counterpart
analytes may therefore also be slightly reduced. All other surrogate compounds had acceptable recovery.
. Sample ID
Surrogate Compounds 79957/1 79957/2 79957/4 79957/5 79957/6 79957/7 79957/8 79957/9 79957/10 79957/12
79957/13 79957/14
Naphthalene-D8* 72 75 65 74 72 70 70 71 73 75 66
66 70 74
Page 21 of 22
Al Futtaim Element Materials Technology Dubai L.L.C P: +971 (0)4 8851001
Plot 598-221, Dubai Investments Park, F: +971 (0)4 8854004
P.O. Box 34924 me.dxbnorlims@element.com
Dubai, United Arab Emirates element.com
Page 22 of 22
Water sampling bacterial laboratory results:
Al Majal Business Park
Berjessah, Az Zubayr, Basra
Page 1 of 3
Laboratory Job Number: 19/10710 Client Project Name: Crescent
Limit of Detection
Depth to Top
Depth To Bottom
Method ref
Date Sampled 11-Nov-19 11-Nov-19 11-Nov-19 11-Nov-19 11-Nov-19 11-Nov-19 11-Nov-19
Units
Sample Type Water - W Water - W Water - W Water - W Water - W Water - W Water - W
EcoliA No Growth No Growth No Growth No Growth No Growth No Growth No Growth Test kit
Coliforms (total)A 1000 100000 100 100 100 100000 1000 cfu/ml Test kit
Page 2 of 3
REPORT NOTES
Notes - General
Subscript "A" indicates analysis performed on the sample as received. "D" indicates analysis performed on the dried sample, crushed to
pass a 2mm sieve, unless asbestos is found to be present in which case all analysis is performed on the sample as received.
For samples that are oil all analysis is performed on the as received sample and this supercedes any “D” subscript.
For samples that are aggregate, stones, concrete or any similar matrices all analysis is performed on the dried and crushed sample.
Uncertainty has been calculated for all procedures and summary data is available upon request.
All calibrations performed by the laboratory are traceable to NIST standards.
Page 3 of 3
Al Majal Business Park
Berjessah, Az Zubayr, Basra
Page 1 of 3
Laboratory Job Number: 19/10723 Client Project Name: Crescent
Limit of Detection
Depth to Top
Depth To Bottom
Method ref
Date Sampled 12-Nov-19 12-Nov-19 12-Nov-19
Units
Sample Type Water - W Water - W Water - W
Page 2 of 3
REPORT NOTES
Notes - General
Subscript "A" indicates analysis performed on the sample as received. "D" indicates analysis performed on the dried sample, crushed to
pass a 2mm sieve, unless asbestos is found to be present in which case all analysis is performed on the sample as received.
For samples that are oil all analysis is performed on the as received sample and this supercedes any “D” subscript.
For samples that are aggregate, stones, concrete or any similar matrices all analysis is performed on the dried and crushed sample.
Uncertainty has been calculated for all procedures and summary data is available upon request.
All calibrations performed by the laboratory are traceable to NIST standards.
Page 3 of 3
Al Majal Business Park
Berjessah, Az Zubayr, Basra
Page 1 of 3
Laboratory Job Number: 19/10883 Client Project Name: Crescent
Limit of Detection
Depth to Top 5.26
Depth To Bottom
Method ref
Date Sampled 13-Nov-19 13-Nov-19 13-Nov-19 13-Nov-19
Units
Sample Type Water - W Water - W Water - W Water - W
Page 2 of 3
REPORT NOTES
Notes - General
Subscript "A" indicates analysis performed on the sample as received. "D" indicates analysis performed on the dried sample, crushed to
pass a 2mm sieve, unless asbestos is found to be present in which case all analysis is performed on the sample as received.
For samples that are oil all analysis is performed on the as received sample and this supercedes any “D” subscript.
For samples that are aggregate, stones, concrete or any similar matrices all analysis is performed on the dried and crushed sample.
Uncertainty has been calculated for all procedures and summary data is available upon request.
All calibrations performed by the laboratory are traceable to NIST standards.
Page 3 of 3
AIR
Air quality laboratory results:
(A division of Gradko International Ltd.) 2187
St. Martins House, 77 Wales Street Winchester, Hampshire SO23 0RH
tel.: 01962 860331 fax: 01962 841339 e-mail:diffusion@gradko.co.uk
Analysed on CARY 60
Analyst Name Sam Minns Report Checked By Andrew Poole
Analysis carried out in accordance with documented in-house Laboratory Method GLM5
Samples have been tested within the scope of Gradko International Ltd. Laboratory Quality Procedures. Results within this report relate only to
samples as received. Data provided by the client and any subsequent calculations shall be indicated by an asterisk (*), these calculations and results
are not within the scope of our UKAS accreditation. Any queries concerning data in this report should be directed to the Laboratory Manager
Gradko International Ltd. This report is not to be reproduced, except in full, without the written permission of Gradko International Ltd.
Form LQF32b Issue 9 – August 2019 Report Number N07476R Page 1 of 1
(A division of Gradko International Ltd.) 2187
St. Martins House, 77 Wales Street Winchester, Hampshire SO23 0RH
tel.: 01962 860331 fax: 01962 841339 e-mail:diffusion@gradko.co.uk
Estimated
Top 5 VOC ng on tube ppb in air* µgm-3*
Benzoic acid 617 6.7 33
2,6-Diphenyl-p-benzoquinone 338 3.7 38
Acetophenone** 79 0.9 4.1
Phenylmaleic anhydride 67 0.7 5.1
Benzaldehyde** 61 0.7 2.8
Estimated
ng on tube ppb in air* µgm-3*
Total VOC (C6 to C16) 1097 12.0 74.4
Samples have been tested within the scope of Gradko International Ltd. Laboratory Quality Procedures. Results within this report relate only to
samples as received. Data provided by the client and any subsequent calculations shall be indicated by an asterisk (*), these calculations and results
are not within the scope of our UKAS accreditation. Any queries concerning data in this report should be directed to the Laboratory Manager
Gradko International Ltd. This report is not to be reproduced, except in full, without the written permission of Gradko International Ltd.
Form LQF32b Issue 9 – August 2019 Report Number N07442R Page 1 of 7
(A division of Gradko International Ltd.) 2187
St. Martins House, 77 Wales Street Winchester, Hampshire SO23 0RH
tel.: 01962 860331 fax: 01962 841339 e-mail:diffusion@gradko.co.uk
Estimated
Top 5 VOC ng on tube ppb in air* µgm-3*
Benzoic acid 924 9.4 46
2,6-Diphenyl-p-benzoquinone 339 3.5 36
Acetophenone** 112 1.1 5.5
Phenylmaleic anhydride 98 1.0 7.0
Benzaldehyde** 79 0.8 3.4
Estimated
ng on tube ppb in air* µgm-3*
Total VOC (C6 to C16) 1804 18.4 117
Estimated
Top 5 VOC ng on tube ppb in air* µgm-3*
Benzoic acid 1204 12 60
2,6-Diphenyl-p-benzoquinone 296 3.0 31
2-Phenacyl-quinoxaline 193 2.0 20
Acetophenone** 139 1.4 6.8
Phenylmaleic anhydride 134 1.4 9.5
Samples have been tested within the scope of Gradko International Ltd. Laboratory Quality Procedures. Results within this report relate only to
samples as received. Data provided by the client and any subsequent calculations shall be indicated by an asterisk (*), these calculations and results
are not within the scope of our UKAS accreditation. Any queries concerning data in this report should be directed to the Laboratory Manager
Gradko International Ltd. This report is not to be reproduced, except in full, without the written permission of Gradko International Ltd.
Form LQF32b Issue 9 – August 2019 Report Number N07442R Page 2 of 7
(A division of Gradko International Ltd.) 2187
St. Martins House, 77 Wales Street Winchester, Hampshire SO23 0RH
tel.: 01962 860331 fax: 01962 841339 e-mail:diffusion@gradko.co.uk
Estimated
Top 5 VOC ng on tube ppb in air* µgm-3*
Benzoic acid 963 10.2 49.6
2,6-Diphenyl-p-benzoquinone 281 3.0 31
2-Phenacyl-quinoxaline 158 1.7 17
Acetophenone** 118 1.2 6.0
Phenylmaleic anhydride 102 1.1 7.5
Estimated
ng on tube ppb in air* µgm-3*
Total VOC (C6 to C16) 1706 18.0 114
Samples have been tested within the scope of Gradko International Ltd. Laboratory Quality Procedures. Results within this report relate only to
samples as received. Data provided by the client and any subsequent calculations shall be indicated by an asterisk (*), these calculations and results
are not within the scope of our UKAS accreditation. Any queries concerning data in this report should be directed to the Laboratory Manager
Gradko International Ltd. This report is not to be reproduced, except in full, without the written permission of Gradko International Ltd.
Form LQF32b Issue 9 – August 2019 Report Number N07442R Page 3 of 7
(A division of Gradko International Ltd.) 2187
St. Martins House, 77 Wales Street Winchester, Hampshire SO23 0RH
tel.: 01962 860331 fax: 01962 841339 e-mail:diffusion@gradko.co.uk
Estimated
ng on tube ppb in air* µgm-3*
Total VOC (C6 to C16) 1801 18.9 120
Estimated
Top 5 VOC ng on tube ppb in air* µgm-3*
Benzoic acid 678 7.8 38
2,6-Diphenyl-p-benzoquinone 212 2.4 25
Nonanal** 128 1.5 8.3
Acetophenone** 89 1.0 4.9
Phenylmaleic anhydride 70 0.8 5.6
Estimated
ng on tube ppb in air* µgm-3*
Total VOC (C6 to C16) 1579 18.1 113
Samples have been tested within the scope of Gradko International Ltd. Laboratory Quality Procedures. Results within this report relate only to
samples as received. Data provided by the client and any subsequent calculations shall be indicated by an asterisk (*), these calculations and results
are not within the scope of our UKAS accreditation. Any queries concerning data in this report should be directed to the Laboratory Manager
Gradko International Ltd. This report is not to be reproduced, except in full, without the written permission of Gradko International Ltd.
Form LQF32b Issue 9 – August 2019 Report Number N07442R Page 4 of 7
(A division of Gradko International Ltd.) 2187
St. Martins House, 77 Wales Street Winchester, Hampshire SO23 0RH
tel.: 01962 860331 fax: 01962 841339 e-mail:diffusion@gradko.co.uk
Estimated
Top 5 VOC ng on tube ppb in air* µgm-3*
Benzoic acid 614 6.6 32
2,6-Diphenyl-p-benzoquinone 222 2.4 25
Acetophenone** 92 1.0 4.7
Benzaldehyde** 56 0.6 2.5
Phenylmaleic anhydride 53 0.6 4.0
Estimated
ng on tube ppb in air* µgm-3*
Total VOC (C6 to C16) 1094 11.8 73.6
Estimated
Top 5 VOC ng on tube ppb in air* µgm-3*
Benzoic acid 458 5.1 25
2,6-Diphenyl-p-benzoquinone 422 4.7 49
Acetophenone** 80 0.9 4.3
Benzaldehyde** 63 0.7 3.0
Phenylmaleic anhydride 57 0.6 4.4
Samples have been tested within the scope of Gradko International Ltd. Laboratory Quality Procedures. Results within this report relate only to
samples as received. Data provided by the client and any subsequent calculations shall be indicated by an asterisk (*), these calculations and results
are not within the scope of our UKAS accreditation. Any queries concerning data in this report should be directed to the Laboratory Manager
Gradko International Ltd. This report is not to be reproduced, except in full, without the written permission of Gradko International Ltd.
Form LQF32b Issue 9 – August 2019 Report Number N07442R Page 5 of 7
(A division of Gradko International Ltd.) 2187
St. Martins House, 77 Wales Street Winchester, Hampshire SO23 0RH
tel.: 01962 860331 fax: 01962 841339 e-mail:diffusion@gradko.co.uk
Estimated
Top 5 VOC ng on tube ppb in air* µgm-3*
Phthalic acid, isoporpyl propyl ester 6 0.1 0.6
1 Compound detected
Estimated
ng on tube
Total VOC (C6 to C16) <5
Results greater than 1000ng (excluding Total VOC results) are outside of our UKAS accredited calibration range.
2,6-Diphenyl-p-benzoquinone is not present in mass spectrum libraries. It has been tentatively identified by
comparison of the mass spectrum and retention times of the standard 2,5-Diphenyl-p-benzoquinone.
2,6-Diphenyl-p-benzoquinone may be an artifact due to degradation of Tenax by nitrogen dioxide.
Samples have been tested within the scope of Gradko International Ltd. Laboratory Quality Procedures. Results within this report relate only to
samples as received. Data provided by the client and any subsequent calculations shall be indicated by an asterisk (*), these calculations and results
are not within the scope of our UKAS accreditation. Any queries concerning data in this report should be directed to the Laboratory Manager
Gradko International Ltd. This report is not to be reproduced, except in full, without the written permission of Gradko International Ltd.
Form LQF32b Issue 9 – August 2019 Report Number N07442R Page 6 of 7
(A division of Gradko International Ltd.) 2187
St. Martins House, 77 Wales Street Winchester, Hampshire SO23 0RH
tel.: 01962 860331 fax: 01962 841339 e-mail:diffusion@gradko.co.uk
**Compounds may be an artifact due to reaction of ozone with the Tenax sorbent.
Uptake Rates:
Benzene 0.70 ng.ppm-1.min-1.
Toluene 1.03 ng.ppm-1.min-1.
Ethylbenzene 1.46 ng.ppm-1.min-1.
m/p Xylene 1.46 ng.ppm-1.min-1.
o-Xylene 1.46 ng.ppm-1.min-1.
All other compounds: 2.00 ng.ppm-1.min-1.
Analysis has been carried out in accordance with in-house method GLM 13
Samples have been tested within the scope of Gradko International Ltd. Laboratory Quality Procedures. Results within this report relate only to
samples as received. Data provided by the client and any subsequent calculations shall be indicated by an asterisk (*), these calculations and results
are not within the scope of our UKAS accreditation. Any queries concerning data in this report should be directed to the Laboratory Manager
Gradko International Ltd. This report is not to be reproduced, except in full, without the written permission of Gradko International Ltd.
Form LQF32b Issue 9 – August 2019 Report Number N07442R Page 7 of 7
(A division of Gradko International Ltd.) 2187
St. Martins House, 77 Wales Street Winchester, Hampshire SO23 0RH
tel.: 01962 860331 fax: 01962 841339 e-mail:diffusion@gradko.co.uk
Kormar Gamara Village 1431383 22/08/2019 23/09/2019 764.67 0.82 0.73 11.66 4.37
Kormar Bichuck Village 1431374 20/08/2019 23/09/2019 815.50 1.77 1.69 25.25 9.47
Taza Shaher Village 1431375 20/08/2019 23/09/2019 814.83 1.55 1.46 21.87 8.20
Aweya Jalal Village 1431377 21/08/2019 23/09/2019 790.33 1.61 1.53 23.54 8.83
Shikh Hameed Village 1431376 21/08/2019 23/09/2019 792.75 1.30 1.21 18.64 6.99
Mamsik Village 1431381 24/08/2019 23/09/2019 726.33 0.85 0.77 12.92 4.84
Qadev Karam Village 1431378 22/08/2019 23/09/2019 774.58 1.08 1.00 15.69 5.88
MP8 1431380 23/08/2019 23/09/2019 746.00 1.02 0.94 15.37 5.76
2-
Overall M.U. ±9.6% Reporting Limit 0.09µg SO4
Analysed on Dionex ICS1100 ICU11
Analyst Name Sam Minns Report Checked By Andrew Poole
Analysis has been carried out in accordance with in-house method GLM1
Samples have been tested within the scope of Gradko International Ltd. Laboratory Quality Procedures. Results within this report relate only to
samples as received. Data provided by the client and any subsequent calculations shall be indicated by an asterisk (*), these calculations and results
are not within the scope of our UKAS accreditation. Any queries concerning data in this report should be directed to the Laboratory Manager
Gradko International Ltd. This report is not to be reproduced, except in full, without the written permission of Gradko International Ltd.
Form LQF32b Issue 9 – August 2019 Report Number N07593R Page 1 of 1
(A division of Gradko International Ltd.) 2187
St. Martins House, 77 Wales Street Winchester, Hampshire SO23 0RH
tel.: 01962 860331 fax: 01962 841339 e-mail:diffusion@gradko.co.uk
-
Overall M.U. ±10.2% Reporting Limit 0.049µg/ml NO3
Analysed on Dionex ICS1100 ICU10
Analysis has been carried out in accordance with in-house method GLM 2
Samples have been tested within the scope of Gradko International Ltd. Laboratory Quality Procedures. Results within this report relate only to
samples as received. Data provided by the client and any subsequent calculations shall be indicated by an asterisk (*), these calculations and results
are not within the scope of our UKAS accreditation. Any queries concerning data in this report should be directed to the Laboratory Manager
Gradko International Ltd. This report is not to be reproduced, except in full, without the written permission of Gradko International Ltd.
Form LQF32b Issue 9 – August 2019 Report Number N07595R Page 1 of 1
LAND USE
During the land use survey, the following features were identified:
One location identified along route (see Dust, noise, vibration from passing vehicles,
Commercial buildings
coordinates in subsequent table) maintaining full access, community road safety.
Public buildings - schools Khor Mor Gawra, Shekh Hameed Proximity to road side, community road safety.
Places of worship Awaye Jalal, Shekh Hameed Timing of religious celebrations and ceremonies.
Four locations identified along the route (see Maintaining full access, awareness of funeral
Graveyards
coordinates in subsequent table) processions.
Security features Junction of Qadir Karim and Kirkuk roads Security terms and conditions.
Awaye Jalal
35.108735 Place of worship -
44.820016 mosque Considerations: Place of local significance
and worship. Schedule of local religious
activities to manage traffic and access.
Shekh Hameed
35.07888 Place of worship -
44.854116 mosque Considerations: Place of local significance
and worship. Schedule of local religious
activities to manage traffic and access.
Ali Mustafa
Residential buildings,
35.199504 agricultural buildings - Considerations: Maintaining full access,
44.793867 cluster of houses and dust, noise, vibration from passing vehicles,
animal shelter community and road safety, animal welfare.
35.131106 Residential buildings – Abandoned properties on either side of the
44.861126 abandoned houses road on route to Mamisik
Shekh Hameed
Aliawa
Taza Shar
On route to Mamisik
35.13687 Water source,
infrastructure – dry Considerations: seasonal water use by
44.861373 water path and bridge livestock rearers, protection of local
infrastructure.
On route to Taza Shar
35.092737 Water source – dry
44.841349 water path Considerations: seasonal water use by
livestock rearers.
Considerations: seasonal water use by
35.087597 Water point, land use –
livestock rearers, presence of grazing
dry water path, grazing
44.724987 animals. occasional road crossings by
land
animals.
On route to Mamisik
35.155575 Water point – dry water
44.833112 path Considerations: seasonal water use by
livestock rearers.
On route to Mamisik
35.150811
Infrastructure - bridge
44.836649 Considerations: protection of local
infrastructure
On route to Mamisik
35.150045 Infrastructure, land use
44.838452 - bridge, grazing land Considerations: protection of local
infrastructure, presence of grazing animals,
occasional road crossings by animals.
On route to Shekh Hameed
On route to Mamisik
35.12338 Security feature -
44.861878 military camp Considerations: security terms and
conditions.
35.09226 Security feature - Considerations: security terms and
44.766788 military base conditions.
3. Governorate: Sulaymaniyah
6. Location Description:
Sarcham Tepe is located near the archaeology investigation site of the flowline (i.e. FL-Arch.7). The
site’s area is a hill with rectangle shape, its dimensions are 20x30 metres. The height to the site is
approximately five metres higher than the surrounding flat area. The nearest PAC is Khor Mor Gawra,
which is located to the north-west of this site. There is an unpaved road connecting to the site. There
are wheat and barley farms nearby. There are signs of grazing in the area around the site. The site
(the hill) is not protected by fence or security guards.
☐ Sumerian (Early Dynastic), Akkadian and New Sumerian periods (3rd Dynastic of Ur) 3000-2000 BC
☐ New Babylonian Period (including Land sea Dynastic, Chaldean Dynastic) 1124-539 BC
Note: Due to the COVID-19 situation at the time of report preparation, the archaeological record was
taken from a screen shot and the archaeologist could not access the original file
APPENDIX 3
PROJECT STANDARDS
Soil standards
Table A3.1: Summary of soil quality standards (mg/kg)
NOTE: IFC guideline values are for noise levels measured out of doors. Daytime and night time periods are defined as 07:00-
22:00 and 22:00-07:00 respectively in the IFC guideline. The stricter time period comes from KRG legislation and shall therefore
be adopted by the Project.
Selected Project
Parameter Averaging Period Unit KRG GoI WHO/IFC
Standard
Sulphur dioxide (SO2) 1 year µg/m³ 20 - 60 47
(0.018 ppm) 20 - 47
24 hours µg/m³ 125 -150 105 20 (interim 2,4
(0.04 ppm) limit 125) 20
3 hours µg/m³ 350 262
3
matter (PM10)
24 hours µg/m³ 150 150 50 50
2
Selected Project
Parameter Averaging Period Unit KRG GoI WHO/IFC
Standard
Particulate 1 year µg/m³ 15 15 10 10
2
matter (PM2.5)
24 hours µg/m³ 35 35 25 25
2
2 Legislated standard is significantly less stringent than IFC. As outlined in the IFC’s Performance Standard 3 (Resources Efficiency and Pollution Prevention), the EPC Contractor will
need to evaluate whether the legislated standards are appropriate in view of specific project circumstances and provide justification for any proposed derogations through the Project’s
environmental and social risks and impacts identification and assessment process.
3 The GoI ambient air quality standard for SO2 at an averaging period of 1 hour is stricter than the KRG’s standard at an averaging period of 3 hours. It is standard
practice for ambient air quality standards to be less strict at shorter averaging periods. Therefore, the GoI/ standard for SO2 at an averaging period of 1 hour is set
as the Project Standard for both 1 hour and 3 hours.
4 Air quality guideline value, as per IFC General Environmental Health and Safety Standards (2007) referencing WHO Ambient Air Quality Guidelines (125 µg/m3 is the
interim limit).
Table A3.7 Maximum Allowable Emissions Limits of Air Pollutants Emitted from Stationary
Sources
Parameter Sources2 Maximum Allowable Emissions Limits
(mg/Nm3)1
KRG GoI IFC Selected
Project
Standard
Combustion
Visible emissions
3
sources 250 250
Opacity All sources 20% 20%
Carbon
monoxide (CO) All sources 500 100 1004
Nitrogen oxide All sources Varies depending on 150 150
(NOx) Combustion Source
Sulphur dioxide (SO2)
All sources 500 75 754
Total suspended particles Combustion
(TSP) sources 250 250
Benzene
All sources 5 5
Mercury and its compound
(Hg) All sources 0.5 0.5
Hydrogen sulphide
(H2S) All sources 5 5
Total volatile organic compounds
(VOC) All sources 20 100 20
Particulate matter (PM10) All sources 10 10
1 All units are in milligram per normal cubic meters (mg/Nm3) where normal cubic meters are
IUCN (2019)
Scientific name Habitat of occurrence Countries of occurrence according to IUCN (2019)
status
Native to It is native to Armenia, Azerbaijan, Georgia, Iran, Iraq,
Lebanon, Syria, Tajikistan, Turkey, Turkmenistan, Ukraine,
Grasslands, disturbed areas (i.e.
Algeria, Tunisia, Albania, Bulgaria, France, Greece, Italy, Spain
Centaurea solstitialis Not assessed roadsides, abandoned fields &
and former Yugoslavia. This species is classed as an exotic /
waste land) and cropland.
invasive species in several counties including but not limited to
Australia, Argentina, Chile & USA (CAB International, 2019).
Zoegea leptaurea Not assessed Saudi Arabia, Syria, Lebanon & Turkey
Anchusa italica Not assessed >39 countries including Iraq (NE-Iraq, NW-Iraq & SE-Iraq)
Turkey, Iran, Iraq (NE-Iraq, NW-Iraq), Lebanon, Syria Armenia &
Onosma sericeum Not assessed
Georgia
Capsella bursa-
Least Concern Artificial / terrestrial, grassland > 39 countries
pastoris
Marine intertidal, artificial/terrestrial,
wetlands (inland), rocky areas (e.g. Bulgaria, Croatia, France, Greece, Italy, Malta, Moldova,
Eruca vesicaria Least Concern
inland cliffs, mountain peaks) & Portugal, Romania, Spain, Turkey & Ukraine
grassland
Lomelosia leucactis
(synonym Scabiosa Not assessed Iraq (NW-Iraq)
leucactis)
Lomelosia
calocephala
Not assessed Turkey, Iran (N-Iran), Iraq (NW-Iraq), Lebanon & Syria
(synonym Scabiosa
calocephala)
Ankyropetalum
gypsophiloides Turkey, Iran (S-Iran, W-Iran), Iraq (NE-Iraq, NW-Iraq), Israel,
Not assessed
(synonym Gypsophila Kuwait, Lebanon, Sinai peninsula & Syria
gypsophiloides)
Dianthus crinitus Not assessed Turkey, Aegean Islands, N.W. Africa, Caucasia, Turkestan, Iran
IUCN (2019)
Scientific name Habitat of occurrence Countries of occurrence according to IUCN (2019)
status
Pakistan (eFlora.org, Date unknown).
Afghanistan, Albania, Algeria, Bulgaria; Cyprus, Egypt; France,
Greece, Iran, Italy, Kazakhstan, Lebanon, Libya, Morocco,
Wetlands (inland), artificial/aquatic
Chrozophora tinctoria Least Concern Pakistan, Palestine, Portugal, Qatar, Romania; Saudi Arabia;
& marine
Slovenia, Spain, Tunisia, Turkey, Turkmenistan, Ukraine &
Yemen
Hypericum
Not assessed Turkey, Iran & Iraq (NE-Iraq)
lysimachioides
Phlomis bruguieri Not assessed Iran, Iraq, Lebanon-Syria & Turkey
Afghanistan, Algeria, Bulgaria, Egypt; Greece, Iran, Iraq,
Gagea reticulata Kazakhstan, Kriti, Kuwait, Lebanon-Syria, Libya, North
(synonym Gagea Not assessed Caucasus, Pakistan, Palestine, Romania, Saudi Arabia, Sinai,
tenuifolia) South European Russi & Tadzhikistan Transcaucasus; Turkey;
Turkmenistan; Ukraine; Uzbekistan; West Himalaya
Artificial / terrestrial, grassland,
Armenia, Azerbaijan, Cyprus, Greece, Iran, Iraq, Lebanon,
Aegilops umbellulata Least Concern marine coastal/supratidal, other &
Serbia, Syrian Arab Republic, Turkey & Turkmenistan
forest
Artificial / terrestrial, forest & Bulgaria, Greece, Iran, Iraq, Israel, Jordan; Lebanon, Palestine,
Aegilops speltoides Least Concern
grassland Syrian & Turkey
Artificial / terrestrial, rocky areas
Avena sterilis subsp.
Least Concern (e.g. inland cliffs, mountain peaks) >30 countries including Iraq
ludoviciana
& grassland
Grassland, shrubland, artificial /
Hordeum bulbosum Least Concern 28 countries including Iraq
terrestrial
Hordeum murinum
Not assessed >30 countries including Iraq
subsp. glaucum
Forest, wetlands (inland), artificial /
Phragmites australis Not assessed >70 countries including Iraq
aquatic & marine
Table A4.2 Species of avifauna recorded within the baseline survey area (2019)
IUCN
Common Habitat of occurrence Migratory Congregatory
Scientific name (2019)
name (IUCN, 2019) Status Status
status
masked Forest, shrubland, Full Not
Lanius nubicus LC
shrike savanna migrant congregatory
Marine Intertidal,
Grassland, Shrubland,
Full Not
crested lark Galerida cristata LC Artificial/Terrestrial,
migrant congregatory
Artificial/Aquatic &
Marine, Savanna
Forest, Rocky areas (eg.
inland cliffs, mountain
peaks), Wetlands
house Passer Not a Not
LC (inland), Grassland,
sparrow domesticus migrant congregatory
Artificial/Terrestrial,
Artificial/Aquatic &
Marine, Shrubland
common Shrubland,
Columba Full Not
wood- LC Artificial/Terrestrial,
palumbus migrant congregatory
pigeon Forest
Marine Intertidal, Desert,
Artificial/Terrestrial,
Isabelline Oenanthe Full Not
LC Shrubland, Grassland,
wheatear isabellina migrant congregatory
Rocky areas (eg. inland
cliffs, mountain peaks)
Artificial/Terrestrial,
Full Not
whinchat Saxicola rubetra LC Shrubland, Grassland,
migrant congregatory
Forest
Grassland,
laughing Streptopelia Full Not
LC Artificial/Terrestrial,
dove senegalensis migrant congregatory
Savanna
Shrubland, Rocky areas
Hume's Oenanthe Not a Not
LC (eg. inland cliffs,
Wheatear albonigra migrant congregatory
mountain peaks).
Forest, Rocky areas (eg.
inland cliffs, mountain
common Not a Not
Corvus corax LC peaks), Grassland,
raven migrant congregatory
Shrubland,
Artificial/Terrestrial
Forest, Rocky areas (eg.
inland cliffs, mountain
Eurasian Not a Not
Pica pica LC peaks), Grassland,
magpie migrant congregatory
Shrubland,
Artificial/Terrestrial
Rocky areas (e.g. inland
Eastern
cliffs, mountain peaks), Altitudinal Not
rock Sitta tephronota LC
Wetlands (inland), migrant congregatory
nuthatch
Shrubland
Artificial/Terrestrial, Congregatory
Eurasian Falco Full
LC Shrubland, Forest, (and
kestrel tinnunculus migrant
Grassland dispersive)
Grassland,
black Francolinus Not a Not
LC Artificial/Terrestrial,
francolin francolinus migrant congregatory
Shrubland
Globally
Forest, Wetlands Congregatory
red-wattled LC; VU Not a
Vanellus indicus (inland), Grassland, (and
lapwing in migrant
Artificial/Terrestrial dispersive)
Europe
Wetlands (inland),
LC; NT
Iraq Turdoides Artificial/Terrestrial, Not a Not
in
babbler altirostris Artificial/Aquatic & migrant congregatory
Europe
Marine
Marine Intertidal, Forest,
white- LC; VU Artificial/Terrestrial,
Halcyon Not a Not
throated in Artificial/Aquatic &
smyrnensis migrant congregatory
kingfisher Europe Marine, Wetlands
(inland)
Marine
Coastal/Supratidal,
Artificial/Terrestrial,
Congregatory
Forest, Shrubland, Full
black kite Milvus migrans LC (and
Desert, Grassland, migrant
dispersive)
Marine Intertidal,
Wetlands (inland),
Savanna
Forest, Shrubland,
graceful Not a Not
Prinia gracilis LC Savanna,
prinia migrant congregatory
Artificial/Terrestrial
corn Emberiza Grassland, Full Not
LC
bunting calandra Artificial/Terrestrial migrant congregatory
Artificial/Terrestrial,
rufous-
Cercotrichas Wetlands (inland), Full Not
tailed LC
galactotes Grassland, Forest, migrant congregatory
scrub-robin
Shrubland, Savanna
Artificial/Terrestrial,
LC; NT Congregatory
Wetlands (inland), Full
hen harrier Circus cyaneus in (and
Shrubland, Grassland, migrant
Europe dispersive)
Forest
Desert, Rocky areas (eg.
see-see Ammoperdix Not a Not
LC inland cliffs, mountain
partridge griseogularis migrant congregatory
peaks), Shrubland
Forest, Congregatory
Spanish Passer Full
LC Artificial/Terrestrial, (and
sparrow hispaniolensis migrant
Shrubland, Grassland dispersive)
Caves and Subterranean
Habitats (non-aquatic),
Eurasian Not a Not
Bubo bubo LC Forest, Grassland,
eagle-owl migrant congregatory
Shrubland,
Artificial/Terrestrial
Eurasian
Streptopelia Artificial/Terrestrial, Not a Not
collared- LC
decaocto Shrubland migrant congregatory
dove
cattle egret Bubulcus ibis LC Forest, Wetlands Full Congregatory
(inland), Grassland, migrant (and
Artificial/Terrestrial dispersive)
Marine Intertidal, Desert,
Menetries's Full Not
Sylvia mystacea LC Shrubland, Savanna,
warbler migrant congregatory
Artificial/Terrestrial
Marine Intertidal,
white Artificial/Terrestrial, Full Not
Motacilla alba LC
wagtail Grassland, Wetlands migrant congregatory
(inland), Desert
APPENDIX 5
STAKEHOLDER ENGAGEMENT MATERIALS
PowerPoint Presentation
Khor Mor 250
Expansion
Project
Objectives of Meeting
• The Operator will work with RSK and Hatch during the undertaking
of the ESIA.
Khor Mor Existing Gas Processing Facility
Objectives:
• Potential for the Project to impact the physical environment (e.g. air, water), socio-economic environment
(e.g. people, economy) and the ecological environment (e.g. flora, fauna)
• Impacts with high or moderate significance warrant mitigation measures to reduce them to as low as
reasonably practicable (ALARP) and maximise any potential benefits
• Approach taken to identify and incorporate mitigation measures for the Project is based on the best
practice hierarchy of decisions and measures in order of priority, as follows:
o Avoid at source/reduce at source
o Abate on site
o Abate off-site/at receptor
o Repair or remedy
• Mitigation measures identified in the ESIA will be implemented via an Environmental and Social
Management Plan (ESMP) during Project implementation
Stakeholder Engagement
• Objectives:
Objective:
2. The SPD will investigate your grievance. Additional information may be requested from yourself (or other
individuals, where relevant) at this time.
3. The findings of the investigation and a proposed resolution will be discussed with you.
4. If you accept the resolution, it will be implemented as quickly as possible. If you reject the resolution, your
grievance will be escalated to an Appeals Committee for review and eventual resolution.
5. Following implementation of the resolution, you will be notified by the SPD and the grievance will be
officially closed out.
Note that further details on reporting grievances will be provided to community leaders.
Description of the ESIA report
• Baseline characteristics of the socio-economic and natural environment within the expected
area of influence
• Mitigation measures
• Undertaking of the ESIA and preparation of the draft ESIA report – August 2019
to December 2019
• Disclosure of the draft ESIA report and submission of the final ESIA report –
January 2020
Q&A
Posters
KHOR MOR 250 EXPANSION PROJECT
Pearl Petroleum operates the 482000 483000 484000 485000
Legend:
3889000
KM 10 Flowline
into:
3887000
• Natural gas
Document Path: P:\180000 - Middle East\182279 Crescent Kurdistan EIA\01 - GIS\LPG Site.mxd
• Liquified Petroleum Gas (LPG)
Kor Mor Expansion
The gas is used in power © Crown copyright, All rights reserved. 2019
Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS User Community
National Geographic, Esri, Garmin, HERE, UNEP-WCMC, USGS, NASA, ESA, METI, NRCAN, GEBCO, NOAA, increment P Corp.
stations in Chemchemal,
Sulaymaniyah and Erbil to
produce more efficient, cleaner
electricity.
3886000
The Khor Mor 250 Expansion Project is a
natural extension to the existing facility at
Khor Mor.
The Project involves the construction
of a new gas processing facility inside
the existing site, alongside new
flowlines from new gas wells near the
facility. There will also be new
supporting infrastructure outside the
site boundary.
Once completed, the Project will increase
production at the site, contributing
further to the region’s energy supply and
providing local employment and services
opportunities in the Kurdistan Region of
Iraq.
What are the key components?
STAKEHOLDER ENGAGEMENT
We would like to hear from you if you have
any questions.
Following implementation, you will be The Appeals Committee will propose additional
notified by the SPD and your grievance will actions or an alternative resolution. If you do not
be officially closed. END agree, you are entitled to take legal action and
the final decision will be taken by the arbitrator
or courts.
END
Background Information Document (BID)
Project Information
Khor Mor 250 Expansion
The Khor Mor 250 Expansion Project is a
Project natural extension to the existing facility at Khor
Background Information Document Mor. The existing facility extracts hydrocarbon
from the Khor Mor Reservoir, which is then
Pearl Petroleum was founded in 2009 and is separated into natural gas, Liquified
jointly owned by five shareholders, the largest Petroleum Gas (LPG) and condensate. Natural
being Dana Gas and Crescent Petroleum. The gas is transported from the existing facility to
company operates major gas fields in power stations in Chemchemal, Sulaymaniyah
Kurdistan (Chemchemal, Khor Mor and Block and Erbil. The site currently has a total of seven
19/20) production wells; four are located within the
site boundary and three are located outside
Environmental and Social Impact
the site boundary.
Assessment (ESIA)
The Khor Mor 250 Expansion Project involves
the construction of a new gas processing In line with national legislation and
facility within the existing site boundary, international standards, an ESIA of the Khor
alongside new flowlines (from new production Mor 250 Expansion Project will be
wells to the new processing facility) and new undertaken.
supporting infrastructure outside the site The ESIA will require completion of various
boundary. studies and engagement with stakeholders
In addition, the Project will include the to ensure it meets international standards.
following components: The ESIA will identify potential impacts, both
o new well flowlines positive and negative, and recommend
o a Central Control Building and actions to manage potential significant
Laboratory negative impacts and maximise positive
o new site utilities and power generation benefits.
The company is planning to expand its existing o construction workshops, yards, offices Stakeholder engagement is an important
gas facility – Khor Mor – located close to the and accommodation camp. part of the ESIA process and a national
village of Khor Mor in the governorate of Once completed, the Project will increase the requirement. Stakeholder engagement
Sulaymaniyah in the Kurdistan Region of Iraq. production of gas and liquid products at the involves sharing Project information with
site, contributing further to the region’s stakeholders. Engagement meetings will
The Project will involve the design,
energy supply through more efficient, cleaner provide an opportunity for stakeholders to
procurement and construction of a new gas
electricity generation and providing local ask questions and make comments about
processing facility capable of processing and
employment and services opportunities in the the Project, and to listen and respond to
producing natural gas and liquid products.
Kurdistan Region of Iraq. their concerns via the ESIA process.
The ESIA Process How will you be involved?
Scoping
The aim of this phase is to identify the scope of the ESIA, the
study area, available information and high-level potential
impacts that need to be further evaluated during the ESIA.
Baseline Studies
Project contribution
between 25% and 50%
of AAQS and predicted
Project contribution between
Project contribution environmental
50% and 100% of AAQS and
between 25% and 50% of concentration > 100% of
Project contribution < 25% predicted environmental
Un-degraded AAQS and predicted AAQS or Project
of AAQS (see Project concentration > 100% of
airshed environmental contribution between
standards for air quality) AAQS or predicted
concentration < 100% of 50% and 100% of AAQS
Air quality environmental concentration >
AAQS and predicted
100% of AAQS
environmental
concentration < 100% of
AAQS
Daytime noise
levels (Leq 1hr All daytime
<65 65-70 >70-75 >75
dBA) during exposure periods
construction
Night-time noise
levels (Leq 1hr All daytime
<50 50-55 >55-60 >60
dBA) during exposure periods
construction
Daytime noise Noise <40 40-45 >45-50 >50
levels (Leq 1hr disturbance
1 This concerns conventional air pollutants with local and / or regional impact. GHGs are handled differently, as per the overview of methodology in the body of the report.
Impact magnitude rating
Receptor Impact type
Slight Low Medium High
dBA) during impact
operation magnitude
Amenity impact
<5 5-10 >10-15 >15
magnitude
Noise
Night-time noise disturbance
<35 35-40 >40-45 >45
levels (Leq 1hr impact
dBA) during magnitude
operation Amenity impact
<5 5-10 >10-15 >15
magnitude
25% to 50% of soils
Less than 25% of soils More than 50% of soils
Disturbance of soils with disturbed have a
disturbed have a medium or disturbed have a medium or
low erosion potential in medium or high erosion
Soil erosion high erosion potential and high erosion potential and are
landscapes with slopes potential and are in
are in landscapes with in landscapes with slopes 4%
<4% landscapes with slopes
slopes 4% to 30% to 30%
4% to 30%
Clearly evident (i.e.
perceptible and readily
No perceptible or readily Major (i.e. order of magnitude)
Riparian erosion Perceptible change in measurable) change
measurable change from change from baseline riparian
(see also Surface baseline riparian erosion from baseline riparian
baseline riparian erosion erosion rates, and affecting a
Water) rates erosion rates, but
Soil rates large geographic area
affecting a small
geographic area
Loss of land/soils Less than 25% of the soils Between 25% to 50% of Greater than 50% of the soils
No impact to soils that are
used for impacted are used for the soils impacted are impacted are used for
used for agriculture
agriculture agriculture used for agriculture agriculture
Alteration of chemical Increase in concentration of Degradation of soil Degradation of soil quality
composition of soil by organic or inorganic quality providing providing ongoing
adding toxic material, compounds or other ongoing contamination contamination source and/or
Soil quality
slight increase in total contaminants in soil source and/or resulting resulting in high risk to
contaminative potential. presenting a minor risk to in high risk to potential potential receptors.
Concentrations not environmental, biological receptors, including Concentrations exceeding
Impact magnitude rating
Receptor Impact type
Slight Low Medium High
exceeding guideline and human (site users only) local community. investigation levels.
values. receptors. Concentrations Effects are widespread.
Concentrations exceeding exceeding investigation
investigation levels. levels.
Effects confined within the Effects extend beyond
Project footprint or to a the area of disturbance
small, isolated location(s) to the surrounding area
outside the Project area. but are contained within
the general area.
Alteration of existing profiles
Changes to site profiles or Earthworks altering great enough (>±3 m) to
Changes to site profiles or
elevations (<±0.5 m), profiles and elevations impact neighbouring land (e.g.
elevations (<±1 m), and/or
and/or compaction or (<±3 m); and/or drainage flows onto
Topography and compaction or disturbance
disturbance of surface placement of hard-stand neighbouring land),
drainage of surface soils / placement
soils / placement of hard- or poorly managed subsidence, and/or placement
characteristics of hard-stand not resulting
stand not resulting in drainage system of hard-stand and/or poorly
in measurable alteration to
measurable alteration to resulting in alteration of managed drainage system
drainage characteristics
drainage characteristics drainage characteristics resulting in alteration of
drainage characteristics
Addition of foundation
Addition of foundation Addition of foundation
materials, reworking or
materials, reworking or materials, reworking or Mining or exploitation of
Subsurface removal of soils altering
removal of soils altering a removal of soils altering a geological formations (e.g.
lithology a shallow high-
shallow low-sensitivity shallow medium-sensitivity quarrying activities).
sensitivity geological
geological succession. geological succession.
succession.
Groundwater quality
Groundwater quality Groundwater quality
impacts are likely to Groundwater quality impacts
impacts are likely to be impacts are likely to be well
Groundwater result in occasional are likely to routinely or
well within ambient ranges within ambient ranges or
quality and exceedances of ambient permanently exceed ambient
Hydrogeology or Iraq standards and Iraq standards and
spatial extent ranges or Iraq standards ranges or Iraq standards over
isolated in extent (i.e. localised in extent (i.e. 1 to
and extend area-wide large areas (i.e. >100ha)
<1ha) 10ha)
(i.e. 10 to 100ha)
Duration Short-term, localised Short-term, localised effects Localised effects on Severe effects on groundwater
Impact magnitude rating
Receptor Impact type
Slight Low Medium High
effects on groundwater on groundwater quality, but groundwater quality that quality that are likely to be long
quality, but likely to be which are likely to return to are likely to be lasting (e.g. months or more)
highly transitory (e.g. equilibrium conditions within reasonably long lasting or permanent, and/or give rise
lasting a matter of hours) a short timeframe (i.e. (e.g. weeks or months) to indirect ecological and/or
and well within natural hours or days at most) and/or give rise to socio-economic impacts
fluctuations indirect ecological
and/or socio-economic
impacts
There are known or
There are known or
expected groundwater There are known or expected
There are no known or expected groundwater
users within the likely groundwater users within the
Groundwater expected groundwater users within the likely area
area of influence of likely area of influence of
Resource and users within the likely area of influence of Project
Project abstraction Project abstraction boreholes,
Availability of influence of Project abstraction boreholes, but
boreholes, and their and their supplies will be
abstraction boreholes. their supplies may not be
supplies may be affected by the Project
reduced by the Project.
reduced by the Project
Changes to surface
Changes to surface water
water features (e.g.
Changes to surface water features (e.g. reworking or
Changes to surface water reworking or removal of
features (e.g. reworking or removal of soil or structures,
features (e.g. reworking or soil or structures,
removal of soil or addition of access roads and
removal of soil or addition of access roads
structures, addition of tracks, increased traffic)
structures, addition of and tracks, increased
Surface water access roads and tracks, leading to widespread (i.e.
access roads and tracks, traffic) leading to area-
features increased traffic) not >100ha) alteration of surface
increased traffic) leading to wide (i.e. 10 to 100ha)
leading to measurable water bodies, changes to
localised (i.e. 1 to 10ha) changes to preferential
Surface water changes in the surface preferential flow pathways and
changes in flow pathways flow pathways during
water system (i.e. rivers, regime during the rainy
during the rainy season the rainy season, or
streams or canals) season, or resulting in large
resulting in diversion
scale re- diversion works
works
Decrease in surface water Decrease in surface water Decrease in surface Decrease in surface water flow
flow downstream of project flow downstream of project water flow downstream downstream of project asset is
Flow Rate asset not discernible by asset is likely to be of project asset is likely to cause users to use
local users at any time of discernible by local users sufficient to cause less water than they normally
the year. but is unlikely to cause complaints from local use and to seek one or more
Impact magnitude rating
Receptor Impact type
Slight Low Medium High
users to use less water than users but is unlikely to supplementary sources of
they normally use at any cause users to use less water to make up the deficit
time of year. water than they would during the dry season.
normally use or to seek
a supplementary source
of water at any time of
year.
Reduction in water
quality (suspended
Reduction in water quality sediment, turbidity,
(suspended sediment, colour, odour and taste) Reduction in water quality
turbidity, colour, odour and downstream of project (suspended sediment,
Reduction in water quality
taste) downstream of asset is sufficient to turbidity, colour, odour and
(suspended sediment,
project asset is likely to be cause complaints from taste) downstream of project
turbidity, colour, odour and
discernible by local users local users but is asset is likely to cause users
taste) downstream of
Surface water but is unlikely to cause unlikely to cause users to use less water than they
project asset not
quality users to use less water than to use less water than normally use and to seek
discernible by local users
they normally use or to they would normally use supplementary sources of
at any time of year.
seek supplementary or to seek water to make up the deficit at
Concentrations not sources of water at any supplementary sources all times of the year.
exceeding Iraq standards time of year. of water at any time of Concentrations exceeding Iraq
Concentrations not year. standards
exceeding Iraq standards Concentrations
exceeding Iraq
standards
Minor disruption of Moderate disruption of Affects an entire population or
behaviour or species behaviour or species species in sufficient magnitude
Disruption of behaviour or
interactions not impacting interactions to cause a decline in
species interactions that is
overall health/integrity of Affects a portion of a abundance and/or change in
Biodiversity Flora and fauna barely detectable with
the population of the population and may distribution beyond which
respect to natural
species. bring about a change in natural recruitment
variability
Affects a specific group of abundance and/or (reproduction, immigration
localised individuals within distribution over one or from unaffected areas) would
Impact magnitude rating
Receptor Impact type
Slight Low Medium High
a population over a short more generation, but not return that population or
time period (one generation does not threaten the species, or any population or
or less), but does not affect integrity of that species dependent upon it, to
other trophic levels or the population or any its former level within several
population itself population dependent generations
on it Introduction of alien invasive
species
Minor shift away from
baseline conditions. Direct Post-development Post-development character,
or indirect impacts will be character, composition, composition, and/or attributes
discernible but underlying and/or attributes of of baseline habitat will be
Disruption of habitat is character composition baseline habitat will be fundamentally changed and
barely detectable with and/or attributes of baseline partially changed but the the overall integrity of the
Habitats condition will be similar to overall integrity of the habitat or species within it are
respect to natural
variability pre development habitat is not threatened threatened
circumstances or patterns. Approximately 5 to 20% Approximately 20 to 100% of a
Approximately 1 to 5% of a of a habitat is within the habitat is within the Project
habitat affected within the Project AOI AOI
Project AOI
Change in classification
Protected areas No change in status of of protected area or
Delisting of protected area or
or proposed N/A protected area or proposed proposed protected area
proposed protected area
protected areas protected area to a lower level of
protection
The Project results in a The Project results in a The Project results in the loss
small reduction in the moderate reduction in of all or a significant proportion
availability or functionality of the availability or of the availability or
Disruption of ecosystem functionality of an ecosystem
the ecosystem service, functionality of the
Ecosystem service is barely service, and/or has
and/or has implications for ecosystem service,
services detectable with respect to implications for the majority of
a small number of people and/or has implications
natural variability people within the Project AOI
relative to the population for a substantial number
within the Project AOI of people relative to the The long-term viability of the
There is a perceptible population within the service is threatened
Impact magnitude rating
Receptor Impact type
Slight Low Medium High
difference from baseline Project AOI
conditions. Does not threaten the
long-term viability of the
service.
Job creation, although Unfulfilled expectations of job
significant, falls short of creation leading to
local expectations, demonstrations, sabotage, and
Job creation benefits are contributing to contributing to social unrest
Local job creation meets,
barely detectable to community
Job creation but does not exceed local Significant generation of local
stakeholders in dissatisfaction; or local
expectations employment, resulting in long-
surrounding communities job creation improves
income levels, but not term local economic
for all sections of the improvement and community
population benefits
Site security and Dissatisfaction regarding Potential safety hazard Minor accident, Severe injury or fatal accident,
community safety site security and (unattended plant, unfenced attributed by the attributed by the community
community safety is barely equipment dump, etc.) community (with or (with or without justification) to
2 ILO guidelines hold that children over twelve years of age may, outside the hours fixed for school attendance, be employed on light work which is not such as to prejudice
their attendance at school or their capacity to benefit from the instruction there given.
Impact magnitude rating
Receptor Impact type
Slight Low Medium High
detectable within causing community anxiety without justification) to the Project
stakeholders in lack of due care on the
surrounding communities part of the Project
Some degradation of
None or very limited
archaeological or other
impacts to archaeological or
cultural heritage Permanent or irreversible loss
other cultural heritage
resources or degradation of critical
resources, to the extent that
Negligible or slight the asset(s) is marginally Clear modification of archaeological or other cultural
changes to the setting of altered critical resources so that heritage resources
Archaeology and
Archaeology an archaeological or the archaeological or Comprehensive changes to
cultural heritage Impacts limited to non-
cultural heritage asset or cultural heritage asset is the setting of an
critical resources
group of assets Considerable changes archaeological or cultural
Minor changes to the heritage asset or group of
to the setting of an
setting of an archaeological assets
archaeological or
or cultural heritage asset or
cultural heritage asset or
group of assets
group of assets
Notes
AAQS = ambient air quality standards
Un-degraded airshed: baseline < AAQS.
Degraded airshed: baseline > AAQS and/or ecologically sensitive habitats.
Leq 1hr = equivalent continuous sound pressure level over a one-hour period.
Amenity impact magnitude: incremental increase above background levels (L eq 1 hour – L90 1 hour) where background noise level is greater than 30 dB(A) L90 during the night and
35 dB(A) L90 during the daytime.
Impact magnitude for operational noise is based on sensitive receptors in predominantly residential or rural areas. Where residential areas are located within
commercial/industrial districts or on the main road, a relaxation to the operational phase impact magnitude of 10 dB(A) will apply e.g. worker’s camps. This follows the principles
of Kurdistan local standards (add cross reference).
‘<’ = less than.
‘>’ = greater than.
Table A6.2: Sensitivity criteria for the potential environmental and social impacts/receptors
Sensitivity criteria
Receptor/impact
Low Medium High
Receptors where people or habitats are
Receptors where sensitivity to air Receptors moderately sensitive to air
particularly susceptible to air pollution, e.g.
Air quality pollution is minimal, e.g. industrial areas pollution, where it may cause some
residential areas, schools, healthcare clinics
and desert. disturbance, e.g. agricultural areas.
and ecologically sensitive areas.
Receptors where people or habitats are
Receptors where sensitivity to Receptors moderately sensitive to noise,
particularly susceptible to noise, e.g. residential
Noise distraction or disturbance from noise is where it may cause some distraction or
areas, schools, healthcare clinics and
minimal, e.g. industrial areas, desert. disturbance, e.g. agricultural areas.
ecologically sensitive areas.
Soils with medium and/or high erosion potential
Soils with medium and/or high erosion
that drain to water resources that support
potential that drain to water resources
economically important or ecologically
Soils with low erosion potential, and/or that support diverse aquatic habitats or
significant aquatic species or provide essential
Soil erosion are resistant to compaction and are a locally important source of potable
habitat for those species or are a locally
scarring. water for communities living nearby,
important source of potable water for
and/or the surface is prone to
communities living nearby, and/or are sensitive
compaction and scarring.
to compression.
Flat sloped, shallow and/or well Riparian zones with medium slopes and Steep riparian zones with limited or no
Riparian erosion
vegetated riparian zones some vegetation vegetation
Soils that are suitable for agricultural
Soils that are not suitable for agriculture, Soils that are used for agricultural production or
Loss of land/soils use, but are used for grazing and limited
i.e. desert soils of low fertility without are located in an area that is regionally
used for agriculture subsidence agriculture, or are located in
available water supply important for agricultural production
an area not intended for agricultural use
Soils of moderate geological, ecological
Soils of no geological, ecological or Soils of important geological, economic or
or economic value, and/or soils that
Soil quality economic value, and/or soils that have ecological value, and/or soils that have the
have the ability to recover only over
the ability to recover quickly ability to recover only over many seasons.
multiple seasons.
The groundwater resource has little to The groundwater resource has local The groundwater resource has local
Hydrogeology no role in terms of supply services for importance in terms of supply, but there importance in terms of supply, with no suitable
local communities is ample capacity and/or adequate technically or economically feasible
opportunity for alternative sources of alternatives, or is important at a regional or
Sensitivity criteria
Receptor/impact
Low Medium High
comparable quality trans-boundary watershed level for supply
Water non-potable for humans but
Water non-potable and unsuitable for
suitable for irrigation and watering Water is used for industrial, irrigation, watering
irrigation or watering livestock
livestock livestock or potable uses
Surface waters No use for navigation or industry
Water used for navigation, industry or Supports human needs
Water supply meets local needs and agriculture and human needs Area lacking water resources
there is no shortfall of resources
Water supply does not meet local needs
Regionally significant populations of globally
Species are globally common but are
threatened or endangered species (i.e. listed
Species are not protected or listed rare in Iraq, or important to ecosystem
as Vulnerable, Endangered or Critically
functioning (e.g. predator / prey
Species are abundant / common and Endangered species by IUCN), which are or
Flora and fauna species), or a species that is under
not critical for ecosystem functions are likely to be found within the Project AOI,
threat or has a declining population
Areas of little or no vegetation and are likely affected by the Project
Species listed as Near Threatened by
Species important to ecosystem functioning,
IUCN.
such as predator or prey species
Sites designated for protection at national or
Habitats that are suffering significant international level
decline at a national or regional level Habitats recognised as intact or unique (e.g.
Sites of local biodiversity value that are
not intact, fragile or unique. May include Areas of high species or habitat true deserts, fragile soils, wetlands) or areas
wildlife corridors diversity, or ‘naturalness’ recognised by NGOs as having high
Habitats that are capable of unassisted environmental value (e.g. Key Biodiversity
Habitats that recover quickly following Areas)
disturbance (i.e. habitats comprising recovery to natural conditions following
Habitats disturbance, although this may require Habitats that are unlikely to return to natural
species that readily re-colonise
disturbed areas) several years (e.g. reed beds and other conditions without some intervention (such as
habitats where growing conditions are re-seeding or planting), but which are capable
Habitats that can be classified as favourable) of assisted recovery (including most semi-
‘modified’ in accordance with IFC deserts)
Performance Standard 6 (IFC, 2012) Habitats that can be classified as
‘natural’ in accordance with IFC Habitats that can be classified as ‘critical’ in
Performance Standard 6 (IFC, 2012) accordance with IFC Performance Standard 6
(IFC, 2012)
Ecosystem services The ecosystem service is of low The ecosystem service has moderate The ecosystem service is of high importance to
importance to beneficiaries (local, importance to beneficiaries and beneficiaries and has moderate replaceability
Sensitivity criteria
Receptor/impact
Low Medium High
regional and global) or is of moderate moderate replaceability (some spatial (some spatial alternatives); is of moderate
importance but with many spatial alternatives), high importance to importance to beneficiaries and has few or no
alternatives available beneficiaries and many spatial spatial alternatives; or is essential to
alternatives, or low importance and few beneficiaries but has many spatial alternatives
to no spatial alternatives
Households with adequate employment
/ income to meet their basic needs,
enjoying a standard of living above the Households with inadequate income to Households with inadequate income and
Employment local average meet basic needs, and/or one or more without an individual in regular or sufficient
members actively seeking work employment
Households with no individuals actively
seeking work
Low income or unemployed persons with no
Middle to high-income persons or Middle-income persons or families with access, or severely limited access, to services
families limited access to goods / services
Local communities Vulnerable households
Persons with ample access to goods Nomads and semi-nomads who pass
and services through the Project AOI Nomads and semi-nomads who utilise the
Project AOI to maintain their livelihood
Occupants of well-established, existing
households, not members of any Periodically employed persons and Highly vulnerable or sensitive populations or
Social cohesion marginalised group, permanently minority groups with no legal right to minority groups who perceive themselves as
employed, and with sufficient resources occupy their land/ homes targets of discrimination
to maintain livelihoods and security
Owners and employees of businesses whose
Owners and employees of well- Owners and employees of small and markets will be displaced or expanded by
established businesses with secure medium-sized enterprises with a secure increased Project activity
contracts associated with the Project or market position Any people or businesses subject to
Project-dependent services, fully able to Businesses with an indirect interest, but involuntary relocation or economic
Local economy, maintain their market presence, or not a wholly dependent relationship to displacement
markets and prices enterprises without any direct interest in the Project Businesses which lose oilfield contracts on
oil-field-related business Middle-income household residents which they have been reliant, or which win
Well-paid or relatively wealthy residents, Producers or consumers of produce significant new contracts on the Project
able to withstand price fluctuations likely to be subject to price fluctuations New businesses created to take advantage of
increased opportunities afforded by the Project
Sensitivity criteria
Receptor/impact
Low Medium High
Marginalised people reliant on livelihoods
unconnected to the oil industry, such as
herders and producers of raw materials which
are marketed remotely from the site, whose
produce will not be subject to price inflation
Poor households, i.e. those living below the
national poverty line
Physical resources
Individuals or households with access to
and infrastructure Households which partially rely on
their own adequate and reliable facilities Households wholly dependent on affected
(e.g. utilities, affected infrastructure, including
(e.g. transport, electricity, private public infrastructure for the supply of services
transport network, transport, recreation, electricity and/or
education) and are not directly affected or utilities
educational, education.
by changes to these utilities
recreational)
Road users
Limited number of alternative routes
(including Convenient alternative routes available No alternative route easily available
available
pedestrians)
The Project AOI includes locally or
The Project AOI does not include known The Project AOI includes internationally
nationally recognized, environmentally
Reputation culturally, environmentally or politically recognized, environmentally or politically
or politically significant or sensitive
significant or sensitive areas significant or sensitive areas
areas
Expat workers, highly-paid workers,
temporary migrant workers with little or Full-time local employees (including
Workers Low paid/casual/occasional workers
no long- term direct interest in the contractors)
Project
Unemployed, seeking work on the Project
Recruitment Those already employed or not seeking Project employees, seeking work for
methods employment family members or friends Tribal, ethnic or minority group members who
perceive discrimination
Archaeological and cultural heritage Archaeological and cultural heritage Nationally and internationally significant
assets of local importance assets or regional importance archaeological and cultural heritage
Archaeology and
Archaeological and cultural heritage Archaeological and cultural heritage monuments protected by the Kurdistan
cultural heritage
assets compromised by poor assets with potential to contribute to government, Iraqi federal law and/or
preservation, and/or poor survival of regional research objectives international conventions
Sensitivity criteria
Receptor/impact
Low Medium High
contextual associations Area where archaeological or other Undesignated sites of the quality and
Archaeological and cultural heritage cultural heritage resources are present, importance to be designated
assets of limited value, but with potential and/or area where chance of Assets that can contribute significantly to
to contribute to local research objectives disturbance of previously unknown or acknowledged national research objectives
unrecorded buried archaeology is
Areas of negligible or low potential for Area where significant or important
moderate
previously unrecorded buried archaeological or other cultural heritage
archaeology resources are present, and/or area where
chance of disturbance of previously unknown
or unrecorded archaeology is high
APPENDIX 7
AIR QUALITY MODEL ASSUMPTIONS
The US Environmental Protection Agency (USEPA) AERMOD or CALPUFF models are
used for evaluating the possible impacts of point source air emissions. This allows for
assessing impact in a wider range of local meteorological conditions and also factors in
the influence of terrain on dispersion. To perform the modeling study, USEPA
recommends that equivalent emission parameters, referred to as ‘Pseudo-parameters’
have to be estimated for stack height, diameter and exit velocity. Pseudo-parameters
account for hot, turbulent and buoyant plume.
These parameters do not necessarily have any physical relevance; however, they are
calculated so as to simulate the movement of the exhaust plume as would be from a
point source. The pseudo parameters calculated in this study and which was used for
modeling are:
1) Effective Stack height
The effective stack height is the total height of the flare, including flame and nominal
(physical) height of the flare. The following equation is used to estimate effective height:
Where:
Hs = Physical stack height above ground
Heff = Effective stack height
QT = Total heat available from combustion in Joules/s,
F = % heat lost by radiation (a function of molecular weight of the flared gas stream)
Qn = Net heat release
2) Effective exit velocity
Effective exit velocity is the velocity of the plume following combustion and is calculated
as a representative value at the flame tip. Exit velocity of the plume is dependent on the
‘lift rate’ of the exhaust gases caused by the heat from combustion. While there is no
specific threshold on gas exit velocity, the USEPA and other regulators have suggested a
minimum gas exit velocity of 20m/s to provide sufficient momentum and prevent stack tip
downwash.
3) Effective stack diameter
The effective stack diameter considers that the size of the flame and exhaust gases are
potentially larger than original inner diameter or flare nozzle tip. Effective diameter is
therefore calculated using the following formula:
Where:
Deff = effective diameter at the flame tip (m)
Veff = effective exit velocity (m/s)
Fb, actual = Heat released by combustion (m4/s3)
The calculated pseudo-parameters which were used as inputs to the modeling study, are
presented in Table A7.1 below.
HP Flare
1 (with LT 100.1 38.75 20 1273 64.30 97.63 349.87 50.95
Flare)
LLP
3 29.27 2.77 20 1273 0.12 0 0.68 0.04
Flare
Receptors
Receptors were placed in a nested grid as described in Table A7.2 below (see also
Figure A7.1). Receptors were placed to a distance of 50 km from the facility. Terrain
elevations were extracted and assigned to the model domain from the SRTM 30 digital
elevation model. Sensitive receptors were jointly identified with the client and are listed in
the table below. Terrain elevations were processed and assigned to the receptors using
AERMAP.
0-200 20
200-500 50
500-1000 100
1000-2000 200
2000-5000 500
5000-10000 1000
10000-20000 1000
20000-50000 5000
Figure A7.1 Nested receptor grid
APPENDIX 8
COMMITMENTS REGISTER
Table A8.1 Environmental commitments register
Further evaluation during the detailed engineering phase including re-run of the air quality model with detailed design specifications to confirm compliance with the
ENV01 Operations Pearl Petroleum
Project Standards.
ENV02 Consider alternative treatments of sour gas and evaluate compliance solutions during the detailed design phase. Operations Pearl Petroleum
ENV03 Undertake a quantitative impact assessment to evaluate the drawdown impact on local water users. Construction Pearl Petroleum
ENV04 Develop a Water Management Plan to ensure future sustainable management of water resources. Construction Pearl Petroleum
ENV05 Ensure that an abstraction permit is obtained from local authorities. Construction Pearl Petroleum
ENV06 Undertake refuelling at designated areas according to industry guidelines. Construction Pearl Petroleum
ENV07 Store chemicals and hydrocarbons within secondary containment and according to Good International Industrial Pratices (GIIP). Construction Pearl Petroleum
ENV08 Adopt quiet working methods, where reasonably practicable, using plant with lower noise and vibration emissions. Construction Pearl Petroleum
ENV09 Avoid or limit noisy construction activities during the night-time period. Construction Pearl Petroleum
ENV10 Use acoustic screens and/or enclosures for static items of plant which generate noise levels that have the potential to cause disturbance. Construction Pearl Petroleum
ENV11 Carry out regular inspections of noise mitigation measures to ensure integrity is maintained at all times. Construction Pearl Petroleum
ENV12 Provide briefings for all site-based personnel so that noise issues are understood, and mitigation measures are adhered to. Construction Pearl Petroleum
ENV13 Produce a Biodiversity Management Plan (to include bio-security and bio-restoration). Construction Pearl Petroleum
ENV14 Undertake a preconstruction survey for important plant species in areas identified as potential habitat in particular along flowlines where routes are likely to be re-surveyed. Construction EPC Contractor
ENV15 Evaluate practical alternatives to avoid or reduce impacts to the important plant species if these species are identified within areas subject to land disturbing activities. Construction EPC Contractor
ENV16 Prohibit the collection of natural resources, such as plant materials for firewood, food or medicine. Construction EPC Contractor
Use appropriate technique (seed harvesting/cutting/translocation) to move individual plants from the construction footprint if the individual cannot be avoided during land
ENV17 Construction EPC Contractor
disturbing activities.
ENV18 Undertake site clearance with due consideration to main breeding season. Construction EPC Contractor
Establish a 10 m buffer zone, if possible and practical, around the burrow or nest where no construction may occur until monitoring indicates that the species has left the
ENV19 Construction EPC Contractor
nest/burrow.
ENV20 Evaluate alternatives to relocate the species, if sensitive species active nest or burrow cannot be avoided; and seek approval from regulator. Construction EPC Contractor
ENV21 Prohibit deliberate disturbance of killing of fauna by site workers - any unintentional killing or injury of species to be reported and tracked internally. Construction EPC Contractor
ENV22 Limit vegetation removal to the extent possible. Construction EPC Contractor
ENV23 Consider animal bypass around flowline construction zones, as deemed necessary. Construction EPC Contractor
Restore habitats in temporary workspaces after construction activities are complete including returning the segregated topsoil to the site and restore ecology with native
ENV24 Construction EPC Contractor
species.
ENV25 Reduce the time between construction and reinstatement for works undertaken in sensitive habitats to the extent possible. Construction EPC Contractor
Ensure that the Waste Management Plan (WMP) provides for avoidance of waste storage or other waste management procedures that reduce potential forage by nuisance
ENV26 Construction EPC Contractor
species.
ENV27 Undertake toolbox talks with staff to educate them on what species are likely to be present on-site and on correct actions to be taken if any animals are encountered. Construction EPC Contractor
ENV28 Limit office operations to daylight hours, where possible. Operations EPC Contractor
ENV29 Develop and implement a Lighting Plan (LP) for the new and existing faculties to limit spread by using directional lighting, hoods, etc. and only light the working areas. Operations EPC Contractor
Discussion should be held with the Ministry of Natural Resources and other parties regarding the fate of buried pipelines which are sometimes left in place subsequent to
ENV30 Construction Pearl Petroleum
decommissioning by agreement of all parties.
ENV31 This risk will be further reduced by recycling and reuse of materials/equipment where possible offsite. Construction Pearl Petroleum
Table A8.2 Social commitments register
Construction
SOC01 Prioritise the sourcing of goods and services from local and regional businesses, providing required quality and delivery timescales can be met. Pre-commissioning Pearl Petroleum
Decommissioning
Construction
SOC02 Support the development and capacity building of local and regional businesses, either directly or as part of government of sector-wide initiatives. Pre-commissioning Pearl Petroleum
Operations
Construction
Compile an annual environmental and social performance report, made available to stakeholders, which details how local and regional businesses have been prioritised in
SOC03 Pre-commissioning Pearl Petroleum
the sourcing of goods and services and provided with capacity building support.
Operations
Construction
Prior to construction, undertake a benchmarking exercise to gather data on the average price of local basic good and services; use the data to monitor changes in the cost of
SOC04 Pre-commissioning Pearl Petroleum
goods and services against baseline conditions.
Operations
Construction
Implement a comprehensive Social Monitoring Plan that includes monitoring socio-economic changes in local communities (e.g. in living standards, household well-being
SOC05 Pre-commissioning Pearl Petroleum
and other daily necessities) through regular community meetings and through regular price surveys.
Operations
Construction
Undertake targeted engagement with vulnerable people should local price inflation become an issue. Design and implement additional support measures (e.g. the provision
SOC06 Pre-commissioning Pearl Petroleum
of goods to vulnerable people) on a case-by-case basis with support from third parties (e.g. development agencies) as appropriate.
Operations
Construction
Extend the existing Community Grievance Management Procedure to the KM250A Project to ensure that Project affected communities and other stakeholders have
SOC07 Pre-commissioning Pearl Petroleum
unrestricted access and opportunity to raise concerns and grievances related to the Project.
Operations
Pearl Petroleum
Develop an Influx Management Strategy (including a 'no hiring at the gate' policy), providing clear information on the scale, scope and process of accessing Project-related
SOC08 Construction
employment and business opportunities.
EPC Contractor
Provide information on the Project’s recruitment strategy and key messages about the scale, scope and process of accessing Project-related employment and business
SOC09 Construction Pearl Petroleum
opportunities to local communities to ensure that stakeholder expectations are suitably managed.
Pearl Petroleum
SOC10 Include similar information and messages in the worker codes of conduct in order to ensure that accurate information is conveyed to interested parties. Construction
EPC Contractor
SOC11 Ensure that the Social Monitoring Plan (see SOC05) includes monitoring changes in population size and the arrival of economic migrants . Construction Pearl Petroleum
Work with, and where feasible support, local authorities in planning for and managing the spatial changes (e.g. in land use) and increasing demands on infrastructure and
SOC12 Construction Pearl Petroleum
services that occur as the local area surrounding the Project grows.
Construction
SOC13 Prioritise employment of people from local communities, followed by people from other parts of the Kurdistan Region. Pre-commissioning Pearl Petroleum
Operations
Construction
State the proportion of workers who will be hired from local communities and/or the wider region in order to maximise their employment opportunities. Pre-commissioning EPC Contractor
Operations
SOC14
Construction
Oversee Contractors’ recruitment activities to ensure adherence to local hiring requirements. Pre-commissioning Pearl Petroleum
Operations
Construction
Give information about the Project’s recruitment strategy and key messages about the scale, scope and process of accessing Project-related employment and business
SOC15 Pre-commissioning Pearl Petroleum
opportunities to local communities to ensure that stakeholder expectations are suitably managed.
Operations
Pearl Petroleum
Construction
EPC Contractor
At the end of employment, formally recognise workers’ involvement in the Project through the provision of references and/or certificates outlining workers’ job role(s), the Pearl Petroleum
SOC16 Pre-commissioning
duration of their employment and other details (e.g. training undertaken) as appropriate.
EPC Contractor
Pearl Petroleum
Operations
EPC Contractor
Construction
As part of the tendering process, include training and competency development in order to support capacity building amongst the Project workforce and within the Project
SOC17 Pre-commissioning EPC Contractor
supply chain, and provide formal recognition of this training for workers (e.g. through references and/or certifications) where possible.
Operations
Construction
Provide on-the-job training to the Project workforce in order to enable workers to gain new or improved skills and provide formal recognition of this training (e.g. through
SOC18 Pre-commissioning Pearl Petroleum
references and/or certifications) to workers where possible.
Operations
Construction
SOC19 Ensure that the proportion of foreign workers is reduced and replaced by personnel who come from local communities and other parts of Kurdistan. Pre-commissioning Pearl Petroleum
Operations
Construction
Gather data on average incomes associated with the public and private sector to benchmark wage levels in the local area; use the data to benchmark wage levels in the Pre-commissioning
SOC20 Pearl Petroleum
local area (this should be coordinated with SOC05).
Operations
Construction
SOC21 Ensure that the Social Monitoring Plan (see SOC05) includes sources of employment and changes in wage levels. Pre-commissioning Pearl Petroleum
Operations
Construction
Review the existing process for recruitment to ensure that it is able to cope with an increase in the number of jobs available as a result of the Project; make changes to the
SOC22 Pre-commissioning Pearl Petroleum
existing process as appropriate.
Operations
Construction
Where appropriate, develop a Local Community Employment Plan (LCEP), which will become part of the existing Local Goods and Services Plan, prioritising the
EPC Contractor
employment of people from local communities, followed by people from other parts of the Kurdistan Region.
Pre-commissioning
SOC23
Construction
Oversee contractors’ recruitment activities to ensure adherence to local hiring requirements. Pearl Petroleum
Pre-commissioning
Construction
Pre-commissioning
Manage overall relationship with local communities through a range of strategies, including regular engagement and ongoing social investment. Include long-term capacity
SOC24 Pearl Petroleum
building and skills development programmes in the latter. Operations
Decommissioning
Construction
In the Local Community Employment Plan (see SOC23), include provisions to ensure that Project employment opportunities for local people reflect engagement with local
SOC25 Pre-commissioning EPC Contractor
authorities and are perceived to be equitably distributed across the communities through ongoing engagement with village Anjuman.
Operations
Construction
Internally review existing systems for managing conflict, for example grievances and road blocks, to ensure that they are sufficiently robust to manage conflicts which may
SOC26 Pre-commissioning Pearl Petroleum
arise as a result of the Project; make changes to existing systems as appropriate.
Operations
Construction
SOC27 Develop retrenchment plans with the aim of ensuring social cohesion and reducing the impacts of the termination of employment contracts. Pre-commissioning EPC Contractor
Decommissioning
Pearl Petroleum
Construction
EPC Contractor
During the recruitment process, and for the duration of their employment, ensure transparency with workers regarding the temporary nature of their employment on the Pearl Petroleum
SOC28 Project and regularly remind workers of this fact. Clearly state the duration of workers’ employment in their employment contracts and discuss with workers the need to Pre-commissioning
prepare for the termination of their employment contracts. See also SOC22 and SOC23. EPC Contractor
Pearl Petroleum
Decommissioning
Other contractor
Construction
Pre-commissioning
Select contractors through a robust pre-qualification and due diligence process and include standards on labour and working conditions, aligned with those prescribed by the
SOC29 Pearl Petroleum
International Finance Corporation (IFC), in all contractual documents.
Operations
Decommissioning
Approve contractors' worker grievance procedures (which should align with the existing Worker Grievance Management Procedure). Pre-commissioning Pearl Petroleum
Hold regular meetings (e.g. toolbox talks) with Project personnel, including contractor and sub-contractor employees, to ensure that workers are satisfied with their Pre-commissioning Pearl Petroleum
SOC31
employment and workplace; provide opportunities for workers to raise concerns and report problems at these meetings.
Operations Pearl Petroleum
As part of the worker induction process, explain to employees (including sub-contractor employees) their legal rights and entitlements alongside the content of their Pre-commissioning EPC Contractor
SOC32
employment contracts.
Operations Other contractor
Where appropriate and feasible, oblige each contractor to be transparent on their supply chain. Undertake a risk-based screening assessment to prioritise the types of goods Pre-commissioning Pearl Petroleum
SOC33
and services to be procured; subject these goods and services to an audit against national and regional regulatory requirements and international standards.
Develop and implement contractor Health and Safety Plans and Work Management Procedures that align with the existing Pearl Petroleum Occupational Health and Safety Pre-commissioning EPC Contractor
Plan.
Decommissioning Other contractor
SOC34
Construction Pearl Petroleum
Approve contractors' Health and Safety Plans and Work Management Procedures; undertake auditing to ensure contractor compliance with these plans and procedures. Pre-commissioning Pearl Petroleum
Pearl Petroleum
Construction
EPC Contractor
Pearl Petroleum
Pre-commissioning
EPC Contractor
Develop and implement Occupational Health and Safety (OHS) training programmes that are culturally and linguistically appropriate; update training programmes based on
SOC35
changes in the scope of work being undertaken, incident statistics and regulatory requirements.
Operations Pearl Petroleum
Pearl Petroleum
Decommissioning
Other contractor
Construction
EPC Contractor
Ensure that remuneration is justified and adequate for the level of expertise and experience provided; include details of remuneration in employment contracts with workers
SOC36 Pre-commissioning
(including sub-contractor workers).
Decommissioning Other contractor
Ensure that no Project land take will occur unless the process of the corresponding KRG agency has been completed such that timely compensation is paid to Project-
SOC37 affected persons (PAPs), including land users (e.g. livestock rearers). Pearl Petroleum to prevent access to land by Project personnel (including Pearl Petroleum staff, Construction Pearl Petroleum
contractors and sub-contractors) if there is no consent or agreement in place. See also SOC38.
Develop and implement a Livelihood Restoration Plan (LRP) to address the short- and long-term economic impacts from temporary and permanent (life of Project) loss of
access to land. Include, in the LRP, a gap analysis of the differences between international standards and regional processes, principles of land access, an entitlements
SOC38 matrix based on a mitigation and compensation framework, details of the valuation of assets and establishment of compensation rates, Construction Pearl Petroleum
the land access procedure, provisions for vulnerable people, Management of Change Procedure and monitoring and evaluation. Integrate the LRP (where relevant and
appropriate to do so) with the Rental Value and Compensation Committee's own activities.
Support the Livelihood Restoration Plan (LRP) by stakeholder engagement with the Project affected people (PAPs) to ensure that the livelihood restoration strategy is clearly
SOC39 Construction Pearl Petroleum
explained and accepted, that the approach to legacy issues is clear and that PAPs understand that they are all treated equally. See also SOC38.
Monitor the Livelihood Restoration Plan (LRP) for a period of up to five years following implementation to assess the effectiveness of livelihood restoration measures;
SOC40 Construction Pearl Petroleum
implement corrective actions, as appropriate. See also SOC38.
Agree a cut-off date with the Government prior to the commencement of survey activities for the Livelihood Restoration Plan (LRP) and clearly communicate the cut-off date
SOC41 Construction Pearl Petroleum
to the Project affected people. See also SOC38.
SOC42 Develop and implement land entry, exit and reinstatement procedures on third party lands, including information to affected land owners and land users. See also SOC38. Construction EPC Contractor
SOC43 Seek to support the efforts of local authorities in resolving existing conflicts over land in the Project area. Construction Pearl Petroleum
Undertake regular meetings with village Anjuman and local communities, including the Project affected people (PAPs), to ensure that information about the Project’s land
SOC44 Construction Pearl Petroleum
acquisition and compensation strategy is clearly communicated and that stakeholder concerns are effectively addressed. See also SOC05.
SOC45 Undertake pre-construction surveys to identify any watering wells and pasture land to which access must be maintained. Construction EPC Contractor
Leave gaps in soil stacks and pipe stings along the right of way to ensure that access to watering wells and pasture land is maintained. Provide crossing points across open
SOC46 Construction EPC Contractor
trenches and welded pipes as necessary.
In the event that loss of access to watering wells and/or pasture land is unavoidable, provide alternative water supplies and pasture land/appropriate compensation in line
SOC47 Construction Pearl Petroleum
with the Livelihood Restoration Plan (LRP). See also SOC38.
Identify risks in health and safety plans and work management procedures and, within this, include provisions to ensure community safety, including safety barriers (e.g.
SOC48 Construction EPC Contractor
fences) around open excavations to prevent local communities and livestock from falling into trenches.
Pearl Petroleum
Post culturally appropriate safety signage and information in local communities and near to work sites to raise awareness about risks to the safety of persons
SOC49 Construction
and livestock.
EPC Contractor
Develop and implement a community safety awareness campaign in local communities with a particular focus on high-risk groups (e.g. children), potentially involving school
SOC50 Construction Pearl Petroleum
visits to raise awareness on road safety risks.
Where appropriate, develop a work-specific Traffic Management Plan (TMP) that aligns with the Pearl Petroleum Traffic Management Plan and that identifies sensitive social
SOC51 receptors along transportation routes and outlines mitigation measures (e.g. speed limit restrictions, vehicle maintenance activities, awareness campaigns, recruitment of Construction EPC Contractor
traffic wardens) to reduce the risk of road traffic accidents occurring.
Construction
Develop and implement Workers’ Codes of Conduct (that aligns with the Pearl Petroleum Worker and Security Code of Conduct), inclusive of training for all Project EPC Contractor
personnel on local customs, culture and tradition, interacting with local communities, expected behaviour and the Community Grievance Management Procedure. Deliver Pre-commissioning
training as part of the worker induction process and ensure that compliance with workers' codes of conduct is a contractual requirement for all employees.
Decommissioning Other contractor
SOC52
Construction
Decommissioning
Construction
Prohibit the out-of-hours movement of non-local workers (from other parts of Kurdistan or further afield) for reasons not related to work, in accordance with construction
SOC53 Pre-commissioning Pearl Petroleum
camp rules.
Decommissioning
Construction
Review established arrangements for security provision at the existing facility to ensure that they are sufficiently robust to manage security issues which may arise as a result
SOC54 Pre-commissioning Pearl Petroleum
of the Project; make changes to existing arrangements, as appropriate.
Decommissioning
Construction
Pre-commissioning
SOC55 Ensure that training for Project security personnel includes rules of engagement and human rights (e.g. the Voluntary Principles of Security and Human Rights). Pearl Petroleum
Operations
Decommissioning
Construction
Undertake regular meetings with village Anjuman and local communities to ensure that information about the Project is clearly communicated and that stakeholder
SOC56 Pre-commissioning Pearl Petroleum
concerns are effectively addressed.
Operations
Construction
Ensure that the Social Monitoring Plan (see SOC05) provides for monitoring relations between local communities and the Project and any changes in perceptions Pre-commissioning
SOC57 Pearl Petroleum
towards Pearl Petroleum.
Operations
Decommissioning
Construction
Pre-commissioning
Provide local communities with regular updates on the Project through community meetings; integrate reporting to local communities within the overarching
SOC58 Pearl Petroleum
Stakeholder Engagement Plan (SEP) implemented at the existing facility. See also SOC03 and SOC24.
Operations
Decommissioning
Review the KM250A Project Stakeholder Engagement Plan (SEP) periodically to ensure that information on Project activities such as the potential for non-routine flaring
SOC59 Operations Pearl Petroleum
events to occur occasionally is included; make updates to the SEP, as appropriate.
Construction
Pre-commissioning
Include provisions in contractor Health and Safety Plans to ensure the fitness of workers (e.g. pre-deployment medical screenings which includes tests for communicable
SOC60 EPC Contractor
diseases) during the recruitment process.
Operations
Decommissioning
Construction
EPC Contractor
SOC61 Include health and hygiene training for all employees, including sub-contractor employees, in health and safety plans to minimise the spread of communicable diseases. Pre-commissioning
Construction
Pre-commissioning
SOC62 Identify the risks to public health associated with their scope of work in Health and Safety Plans and detail mitigation measures as appropriate. Pearl Petroleum
Operations
Decommissioning
Undertake a pre-construction survey to assess the condition of roads to be used by the Project (including but not limited to traffic signage, bridges and Pearl Petroleum
SOC63 Construction
other road infrastructure). EPC Contractor
Undertake a post-construction survey covering all of the areas surveyed pre-construction to assess the condition of roads and road-related infrastructure Pearl Petroleum
SOC64 Construction
used by the Project; close out any actions (e.g. repairs) arising from the post-construction survey in a timely manner.
EPC Contractor
Construction
SOC65 Include in In Traffic Management Plan(s) (TMPs) (see SOC51) any necessary restrictions on vehicle movements to defined access routes and demarcated work areas. EPC Contractor
Operations
Construction
As part of the worker induction process, communicate that medical assistance to all employees (including sub-contractor employees) is provided by the Project; prohibit EPC Contractor
SOC66 Pre-commissioning
workers from using local health services at this time.
Decommissioning Other contractor
Construction
SOC67 Monitor water supplies in local communities against baseline conditions; integrate this monitoring into monitoring plans implemented at the existing facility. Pearl Petroleum
Operations
Construction
SOC68 Develop and implement water efficiency training programmes in local communities with the aim of promoting sustainable water consumption. Pearl Petroleum
Operations
Pearl Petroleum
Undertake pre-construction surveys to identify community infrastructure (e.g. bridges, electricity pylons, power lines) which will need to be upgraded, moved or potentially
SOC69 Construction
damaged by the Project.
EPC Contractor
Communicate any planned activities which may affect community infrastructure (e.g. bridges, electricity pylons, power lines) to local authorities and affected
SOC70 Construction Pearl Petroleum
communities in a timely manner; ensure that information provided stakeholders includes (but is not limited to) the nature, timing and duration of the planned activities.
SOC71 Repair any damage to community infrastructure in a timely manner. Construction EPC Contractor
Construction
Request permission from the Erbil Directorate of Roads and Bridges to implement any road diversion; provide prior notification to the public and appropriate road signage
SOC72 Operations Pearl Petroleum
before any road diversions.
Decommissioning
Construction
SOC73 Seek to avoid diversions during peak hours or creating blockages or diversions during peak activities on weekends. Operations Pearl Petroleum
Decommissioning
Construction
SOC74 Monitor the physical condition of the road on an as needed basis in order to raise concerns and work with the local governments to make repairs. Operations Pearl Petroleum
Decommissioning
Construction
Provide targeted assistance, where possible and appropriate, to vulnerable groups identified in the KM250A Project Stakeholder Engagement Plan (SEP) to ensure that they Pre-commissioning
SOC75 Pearl Petroleum
have equal access to Project-related information and equal opportunities to raise questions and concerns.
Decommissioning
Construction
Ensure that recruitment processes for the Project are based on the skills required for the role with no discrimination according to age, sexuality or gender, ethnicity, religion
SOC76 Pre-commissioning Pearl Petroleum
and/or political opinion.
Operations
Construction
SOC77 Continue to provide illiterate persons with additional support when applying for jobs on the Project. Pre-commissioning Pearl Petroleum
Operations
Construction
Develop and implement a gender inclusion strategy (as part of the existing Pearl Petroleum Social Performance Standard) containing various measures to promote the
inclusion of women in the Project. Consider including recruitment targets for women for contractors and sub-contractors, provisions to ensure women feel safe in the
SOC78 Pre-commissioning Pearl Petroleum
workplace and in Project accommodation and provisions to ensure that women are fairly engaged with during the recruitment process. Where appropriate and feasible, work
in partnership with third parties (e.g. development agencies) to develop and implement the gender inclusion strategy.
Operations
Construction
Assess the potential risks that may be associated with women’s participation in the Project and identify measures to mitigate these risks in the short-, medium- and long-term
SOC79 Pre-commissioning Pearl Petroleum
as part of the gender inclusion strategy. Consider targeted engagements with men to raise awareness about the benefits associated with women's involvement in the Project.
Operations
SOC80 Undertake a comprehensive survey to establish the vulnerability of flowline land owners and land users as part of the Livelihood Restoration Plan (LRP) (see also SOC38). Construction Pearl Petroleum
Based on the results of the survey, specify in the Livelihood Restoration Plan (LRP) additional support measures to ensure that vulnerable people are not disadvantaged
SOC81 Construction Pearl Petroleum
during the Project land acquisition and compensation process (see also SOC38).
Construction
Ensure that the KM250A Project Stakeholder Engagement Plan (SEP) provides special measures, where possible and appropriate, to ensure that women have equal access Pre-commissioning
SOC82 Pearl Petroleum
to Project-related information and equal opportunities to raise questions and concerns.
Operations
Develop and implement a targeted community information campaign on hydrotesting to ensure that local communities understand the noise, water and any other impacts
SOC83 Pre-commissioning Pearl Petroleum
associated with this exercise.
Seek to maximise the Project's contribution to the development of Kurdistan's oil and gas sector and regional economic growth through, for example, considering
SOC84 Operations Pearl Petroleum
opportunities to work with universities as part of its Social Investment Programmes.
Develop a draft plan for providing transition training to allow skilled employees to better access employment in other sectors; evaluate the level of interest in such training
SOC85 Operations Pearl Petroleum
amongst workers prior to the finalisation and implementation of the plan.
SOC86 Where the Project affects the livelihood activities of crop farmers, provide appropriate compensation in line with the Livelihood Restoration Plan (LRP). Operations Pearl Petroleum
Post culturally appropriate safety warnings and information in local communities and near to Project infrastructure to raise awareness about the risks of
SOC87 Operations Pearl Petroleum
interfering or tampering with Project infrastructure.
SOC88 Develop and implement community safety awareness campaigns in local communities with the aim of discouraging interference or tampering with Project infrastructure. Operations Pearl Petroleum
Develop and implement measures to reduce the impact of night-time non-routine flaring, for example installation of glazed windows or shades for residences with a clear
SOC89 Operations Pearl Petroleum
view of flare flames.
Develop and implement programmes which promote the long-term sustainability and independence of communities. Consider the avoidance of dependency will in
SOC90 Decommissioning Pearl Petroleum
the design of all Social Investment Programmess (SIPs) and consider planning for the end of Pearl Petroleum interventions from the outset.
SOC91 Consider technical solutions to sharing costs and accountability for the provision of power and water. Decommissioning Pearl Petroleum
SOC92 Consider prioritising social investment that diversifies the local economy and reduces local communities' reliance on Pearl Petroleum at Khor Mor. Decommissioning Pearl Petroleum
SOC93 Consider skills and training to support regional development priorities. Decommissioning Pearl Petroleum
Consider strategic engagement structures, such as community committees and participatory monitoring, to build community capacity to manage
SOC94 Decommissioning Pearl Petroleum
their development.
SOC95 Consider leveraging its operations at Khor Mor to encourage other development actors to engage in the area. Decommissioning Pearl Petroleum
SOC96 Consider working in partnership with third parties (e.g. development agencies) to implement its Social Investment Programmes (SIPs). Decommissioning Pearl Petroleum