Instruction manual of lubrication system
REV DATE DESCRIPTION DRWN CHKD APPN
DRAWING TITLE
SCALE REV
DOCUMENT No.
A
(WBG)B2620C-000152ASM
Manufacturer: Dongfang Turbine Co.,Ltd.
Manufacturer DOC. NO.: VA1-DEC-00100-M-M1D- MAN -2010 REV:A
DOC NO. (WBG)B2620C-000152ASM
DESIGN NIWEI
CHECK YURONGGANG
VERIFICATION NANCHUNLEI
STD ENGINEER
REVIEW
APPROVE
Document No.: (WBG)B2620C-000152ASM Document Title: Instruction manual of lubrication system
Contents
1
Document No.: (WBG)B2620C-000152ASM Document Title: Instruction manual of lubrication system
Revision Record
0-1-2
Document No.: (WBG)B2620C-000152ASM Document Title: Instruction manual of lubrication system
0-1-2
Document No.: (WBG)B2620C-000152ASM Document Title: Instruction manual of lubrication system
switching, three 100L accumulators are supplied on the lube oil pipe, each accumulator
nitrogen-filled pressure is 0.06MPa, and is installed on operation platform.
4. Operation of oil system
Before starting the system, make sure the oil quality in the system meets the cleanness
requirement of startup operation, and the oil tank level is at the highest. When the oil tank
temperature is lower than 20℃,close the cooling water valve of the oil cooler, heat the oil
temperature to 35℃, then close the electrical heater, start the main oil pump and the fume
exhaust fan, force the lube oil system to circulate, after the oil temperature reaches 45℃, open
the cooling water valve of the oil cooler, adjust the adjustable non-return valve to keep the
main pipe oil pressure within 0.12~0.14MPa. Interlock protection is provided in auxiliary oil
pump, emergency oil pump, turning gear and oil pressure of the lube oil main pipe, when the
oil pressure of the lube oil main pipe is lower than 0.1MPa(g), warn and start the auxiliary
pump, when the lube oil main pipe oil pressure is lower than 0.07MPa, start the emergency
pump and shutdown, and stop the turning gear when the lube oil main pipe oil pressure is
lower than 0.03MPa. It must make low pressure interlock protection test every half a month.
5. Introduction of the return oil system
This system includes 3 return oil main pipes, the front bearing pedestal lube oil return oil
(Φ141.3×6.55), rear bearing pedestal lube oil(Φ114.3×6.02)and feed water pump, return to
dirty area. Installation of the return oil pipe must be toward the oil tank with a gradual slope
of not less than 1, so as to make the return oil in the pipe in a half full status, beneficial to the
oil fume of each bearing pedestal to flow to the oil tank through the space above the oil
surface, then emit to atmosphere after separation by the fume exhaust unit. After the return oil
returns to the oil tank dirty oil area, it enters the clean oil area after filtered by the strainer.
6. Lube oil temperature
This system uses ISO Vg32 turbine oil, the unit bearings require the inlet temperature to
be 40~45℃, the normal bearing return oil temperature is lower than 65℃.
7. Oil tank level
Before putting into operation, it is necessary to set the middle position of the highest oil
level and the lowest oil level to 0 according to the drawing oil level requirement(from the oil
tank 384mm), to be as the normal oil level of the oil level indicator.
During normal operation Highest oil level +89mm
Lowest oil level -114mm
Shut-down oil level -241mm
8 Oil pressure adjustments:
8.1 Setting oil system’s pressure before starting the system:
0-1-4
DocumentNo.:(WBG)B2620C-000152ASM
Document Title: Instruction manual of lubrication system
0-1-5
DocumentNo.:(WBG)B2620C-000152ASM
Document Title: Instruction manual of lubrication system
8.1.1 Open the manhole flange cover 1,2 and 3 of the oil tank manhole cover.
8.1.2 Start a main oil pump.
8.1.3 Close the oil spill valve from the manhole flange cover 3, set adjust check valve 1 ,make
the oil pressure of main pipe on the operation layer is 0.18MPa.
8.1.4 Open the oil spill valve, make oil pressure reduce to 0.15MPa.
8.1.5 Stop the main oil pump, and start the other one, set the oil pressure in 0.14±0.01MPa.
Make sure the oil pressure on the operation layer is 0.14±0.01MPa when the two main oil pump
working separately.
8.1.6 Stop main oil pump, open the DC emergency oil pump, adjust check valve2 ,set the oil
pressure on the operation layer is 0.14MPa.
8.1.7 Close flange cover .
Make the oil pressure higher than 0.14 when the system working. If the pressure is not
higher than 0.14 set it again.
9. Requirement of the oil system
9.1 Installation of the oil system must meet DL5011 – 92 “Technical code for construction and
acceptance of power construction works” (turbine unit) “Technical conditions for oil system
installation”.
9.2 Oil circulation flushing requirement of the oil system must meet DL5011-92“Technical code
for construction and acceptance of power construction works (turbine unit) “Technical conditions for
oil system flushing”.
10. Main performance index of the turbine oil
10.1 Quality requirement of the turbine oil
10.1.1 Excellent anti oxidation stability and thermal stability
10.1.2 Good viscosity temperature behavior and proper viscosity.
10.1.3 Good low temperature operation performance.
10.1.4 Good resistance to emulsification.
10.1.5 Good anti-foam performance.
10.1.6 Good antirust and anticorrosion performance.
10.1.7 Good air release performance.
0-1-6
DocumentNo.:(WBG)B2620C-000152ASM Document Title: Instruction manual of lubrication system
EPC CONTRACTOR
PROJECT TITLE
M_LOT1D-BOP OF TURBINE
CONTRACT No.
DRAWING TITLE
SUB-CONTRACTOR
DONGFANG ELECTRIC
FUNCTION
DRWN
CHKD
NAME SIGN DATE
0-1-7
APPD
0-1-1