Introduction
Quality Assurance
3. Under item 6 in Section 17(1) of the BO, a condition will be imposed, when
giving approval of plans, that precast concrete elements should be manufactured by a
factory with ISO 9000 quality assurance certification.
Qualified Supervision
6. Under item 6 in Section 17(1) of the BO, a condition will be imposed, when
giving approval of plans, that qualified supervision should be provided by the RSE and
the RC for the fabrication, erection and examination of precast concrete elements.
10. In addition, the RSE and the Authorized Signatory (AS) of the RC should
inspect and carry out audit checks to the precast concrete factory at least once every
month. Under Regulation 10 of the B(A)R, a requirement will be imposed, when giving
approval of plans, that a copy of the RSE’s audit reports of the precast concrete factory
and a copy of the AS’s audit reports of the precast concrete factory duly endorsed by the
RSE should be submitted to the Buildings Department for record purpose. The RSE and
AS’s audit reports should respectively also cover the qualified supervisions by the
structural quality control supervisor of RSE’s stream and the quality control co-ordinator
of AS’s stream. Minimum requirements of the audit checks are detailed in Appendix A.
/11. …..
-3-
12. For good practices in the design, construction and quality control of precast
concrete works, reference should be made to the recommendations and guidelines given
in the Code of Practice for Precast Concrete Construction issued by the Buildings
Department.
13. For precast concrete elements not affecting the stability of the parent
structure, such as the precast concrete façade or staircase, a separate RSE may be
appointed to prepare the design and to supervise the production and erection of such
precast concrete elements. In such situation, the specified Forms BA4 and BA5 notifying
the appointment of a separate RSE and the scope of works for which he/she is
responsible are required to be submitted together with the plans for approval. The project
RSE shall also notify the Building Authority in writing that he/she is fully aware of the
appointment of a separate RSE and the demarcation of responsibilities. Upon completion
of the precast concrete construction works, the separate RSE so appointed is required to
certify the satisfactory completion of the works in accordance with Regulation 25(3) of
the B(A)R.
15. The separate RSE shall be responsible for the supervision of the production
and erection of the precast concrete elements, including the connection between the
precast concrete elements and the parent structure, i.e. ties, anchor plates, cast-in embeds
etc., except in the event where such associated works have been installed in the parent
structure prior to his/her appointment. For such cases, the structural details and layout of
the pre-installed parts should be given in the superstructure plans submitted for approval
by the project RSE who shall then be responsible for the supervision of the installation of
such parts. The separate RSE should refer to the pre-installed connection details when
designing the precast concrete elements and should co-ordinate with the project RSE for
any necessary amendment if different connection details are to be used.
16. The separate RSE shall ensure that the conditions and requirements of the
quality assurance and qualified supervision as stipulated in paragraphs 3 to 5 and 6 to 11
above respectively are complied with. He/she shall also be responsible for the
submission of the documents required in paragraph 4 above.
/17. …..
-4-
( AU Choi-kai )
Building Authority
Ref. : BD GR/1-125/54
The audit checks carried out by the RSE and the AS at the precast concrete
factory should include the following works items:.
( 07/2012)
Appendix B
(PNAP APP-143)
The audit checks on the precast concrete elements delivered to the building site
carried out by the RSE as an alternative to the audit check on precast concrete elements
at the precast concrete factory as specified in Appendix A should comply with the
requirements specified in paragraph 2 below.
2. The rate of sampling for the audit checks shall be at least 1% of the precast
concrete elements with a minimum of one per every 20 batches of delivery to the
building site. The audit check for each sample of the precast concrete element should
include the following works items
5 Others z Any other items considered essential by the RSE for the
project.
Remarks :
Tests for compressive strength of concrete cores should be carried out in accordance with
the method specified in CS1:2010, by a laboratory accredited under HOKLAS for the
particular test concerned. Test results should be reported on a HOKLAS Endorsed
Certificate and submitted within 60 days of the delivery of the precast concrete elements
to the building site.
( 07/2012)